CN215105154U - Steel dam gate with silt clearance structure - Google Patents

Steel dam gate with silt clearance structure Download PDF

Info

Publication number
CN215105154U
CN215105154U CN202120870151.8U CN202120870151U CN215105154U CN 215105154 U CN215105154 U CN 215105154U CN 202120870151 U CN202120870151 U CN 202120870151U CN 215105154 U CN215105154 U CN 215105154U
Authority
CN
China
Prior art keywords
gate
steel dam
silt
bevel gear
gate body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120870151.8U
Other languages
Chinese (zh)
Inventor
潘小兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangzhou Songtian Hydraulic Machinery Co ltd
Original Assignee
Yangzhou Songtian Hydraulic Machinery Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangzhou Songtian Hydraulic Machinery Co ltd filed Critical Yangzhou Songtian Hydraulic Machinery Co ltd
Priority to CN202120870151.8U priority Critical patent/CN215105154U/en
Application granted granted Critical
Publication of CN215105154U publication Critical patent/CN215105154U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Barrages (AREA)

Abstract

The utility model discloses a steel dam gate with a silt cleaning structure, which comprises a gate body, wherein the gate body is connected with a gate hoist when in work, and is placed at a required position; the waterproof motor is fixedly arranged on the back of the gate body; the cross bar is fixedly arranged on the surface of the bump; and the jacking block is connected with the cross rod through the upright post. This steel dam gate with silt clearance structure is when needs clearance silt, start waterproof motor, waterproof motor passes through the connecting axle this moment and drives first bevel gear rotatory, first bevel gear drives second bevel gear rotatory, the overlap joint post is rotatory under second bevel gear's effect this moment, the overlap joint post drives the disc rotation, the lug removes in the inside of recess this moment, and the horizontal pole is under the effect of spacing pipe and lug, reciprocating linear motion is done on the horizontal direction, the inner wall of the gate body that strikes that the horizontal pole can be once, make silt become soft, convenient clearance.

Description

Steel dam gate with silt clearance structure
Technical Field
The utility model relates to a steel dam gate technical field specifically is a steel dam gate with silt clearance structure.
Background
The steel dam gate is widely applied to the industries of irrigation, hydroelectric generation and the like, can effectively improve the natural environment and improve the grade of the natural environment of a city, for example, the steel dam gate with the publication number of CN202658585U, the decorative plate is additionally arranged on the back surface of the gate leaf to shield the longitudinal beam exposed on the back surface of the gate leaf, so that the whole body on the back surface of the gate leaf is a flat surface, the problems of oxidation, rusting, corrosion and the like on the back surface of the steel dam gate are effectively prevented, the service life of the steel dam gate can be prolonged, and the back surface of the steel barium dam gate is flat and beautiful.
However, the silt on the surface of the gate is inconvenient to remove, and after the gate is used for a long time, the silt in water can be accumulated on the surface of the gate of the steel dam, so that the resistance of the gate of the steel dam is increased when the gate of the steel dam is opened and closed, and the working efficiency of the gate of the steel dam is influenced.
Aiming at the problems, innovative design is urgently needed on the basis of the original steel dam gate.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a steel dam gate with silt clearance structure to the inconvenient silt of self surface of cleaing away that proposes in solving above-mentioned background art, after long-time the use, the surface at the steel dam gate can be piled up to the silt of aquatic, and the resistance when having increased steel dam gate switch has influenced the work efficiency's of steel dam gate problem.
In order to achieve the above object, the utility model provides a following technical scheme: a steel dam gate with silt clearance structure, includes:
the gate body is connected with the gate hoist when working, the gate body is placed at a required position, and the hoist controls the up-and-down movement of the gate body to achieve the purpose of water discharging and storing;
the waterproof motor is fixedly arranged on the back of the gate body;
the lapping column is movably arranged inside the gate body, a disc is fixedly arranged at the tail end of the lapping column, and a lug is movably arranged inside the disc;
the cross bar is fixedly arranged on the surface of the bump;
and the jacking block is connected with the cross rod through the upright post.
Preferably, the tail end of the waterproof motor is fixedly provided with a connecting shaft, the other side of the connecting shaft is fixedly provided with a first bevel gear, when the waterproof motor is started, the waterproof motor drives the connecting shaft to rotate, and the connecting shaft drives the first bevel gear to rotate.
Preferably, the surface of the overlapping column is fixedly provided with a second bevel gear corresponding to the first bevel gear, the first bevel gear rotates to drive the second bevel gear to rotate, and the overlapping column also rotates at the moment.
Preferably, the surface of the disc is provided with an oval groove, the inner wall of the disc is attached to the outer wall of the lug, the disc is driven to rotate when the lap joint column rotates, and the disc drives the lug to move through the groove.
Preferably, the inside screw thread of gate body installs spacing pipe, and the horizontal axis of spacing pipe and the horizontal axis of overlap joint post are on a straight line, and lug and horizontal pole are reciprocating linear motion in the horizontal direction under the effect of spacing pipe and disc.
Preferably, the cross rod penetrates through the limiting pipe.
Preferably, the top blocks are distributed on the surface of the upright post at equal intervals, and the upright post drives the top blocks to synchronously move when the cross rod makes reciprocating linear motion in the horizontal direction.
Compared with the prior art, the beneficial effects of the utility model are that: the steel dam gate with the silt cleaning structure;
1. when the steel dam gate with the silt cleaning structure needs to clean silt, the waterproof motor is started, the waterproof motor drives the first bevel gear to rotate through the connecting shaft, the first bevel gear drives the second bevel gear to rotate, the lapping column rotates under the action of the second bevel gear, the lapping column drives the disc to rotate, the protruding block moves in the groove, the cross rod makes reciprocating linear motion in the horizontal direction under the action of the limiting pipe and the protruding block, and the cross rod can knock the inner wall of the gate body one time and time to soften the silt and facilitate cleaning;
2. this steel dam gate with silt clearance structure when the horizontal pole is reciprocal linear motion in the horizontal direction, the horizontal pole passes through the stand and drives the synchronous reciprocal linear motion of being of a plurality of kicking blocks in the horizontal direction, and the inner wall of gate body is also strikeed to the kicking block, makes the silt of gate body surface become soft, and soft silt is driven easily under the impact of rivers, has reduced the resistance of steel dam gate during operation, has improved work efficiency.
Drawings
FIG. 1 is a schematic front view of the present invention;
FIG. 2 is a schematic side sectional view of the gate body of the present invention;
FIG. 3 is a schematic view of the connection structure of the second bevel gear and the lap joint column of the present invention;
FIG. 4 is a schematic view of the connection structure of the lap post and the disc of the present invention;
fig. 5 is an enlarged schematic view of a portion a in fig. 2 according to the present invention.
In the figure: 1. a gate body; 2. a waterproof motor; 3. a connecting shaft; 4. a first bevel gear; 5. a second bevel gear; 6. a lap joint column; 7. a disc; 8. a groove; 9. a bump; 10. a cross bar; 11. a limiting pipe; 12. a column; 13. and (7) a top block.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-5, the present invention provides a technical solution: a steel dam gate with silt clearance structure, includes:
the gate comprises a gate body 1, wherein the gate body 1 is connected with a gate hoist when working, and the gate body 1 is placed at a required position;
the waterproof motor 2 is fixedly arranged on the back of the gate body 1;
the gate comprises a lap joint column 6, wherein the lap joint column 6 is movably arranged inside a gate body 1, a disc 7 is fixedly arranged at the tail end of the lap joint column 6, and a lug 9 is movably arranged inside the disc 7;
the cross rod 10 is fixedly arranged on the surface of the bump 9;
the top block 13, the top block 13 is connected with the cross bar 10 through the upright post 12.
The tail end of the waterproof motor 2 is fixedly provided with a connecting shaft 3, the other side of the connecting shaft 3 is fixedly provided with a first bevel gear 4, the surface of the lapping column 6 is fixedly provided with a second bevel gear 5 corresponding to the first bevel gear 4, the surface of the disc 7 is provided with an oval groove 8, and the inner wall of the disc 7 is attached to the outer wall of the lug 9.
When needs clearance silt, start waterproof motor 2, waterproof motor 2 drives first bevel gear 4 through connecting axle 3 this moment and rotates, first bevel gear 4 drives second bevel gear 5 rotatoryly, overlap joint post 6 is rotatory under second bevel gear 5's effect this moment, overlap joint post 6 drives disc 7 rotatoryly, lug 9 removes at recess 8's inside this moment, and horizontal pole 10 is at spacing pipe 11, lug 9 and disc 7's effect down, do reciprocal linear motion in the horizontal direction, the inner wall of striking gate body 1 that horizontal pole 10 can be once, make the silt of 1 surface of gate body become soft, convenient clearance.
Spacing pipe 11 is installed to the inside screw thread of gate body 1, and the horizontal axis of spacing pipe 11 and the horizontal axis of overlap joint post 6 are on a straight line, and horizontal pole 10 runs through in the inside of spacing pipe 11, and kicking block 13 is at the surface of stand 12 equidistant distribution.
When horizontal pole 10 is reciprocal linear motion in the horizontal direction, horizontal pole 10 drives the synchronous reciprocal linear motion of being in the horizontal direction of a plurality of kicking blocks 13 through stand 12, and the inner wall of gate body 1 also can be strikeed to kicking block 13, makes the silt of 1 surface of gate body become soft, and soft silt is clear away easily under the impact of rivers, has reduced the resistance of steel dam gate during operation, has improved work efficiency.
The working principle is as follows: when using this steel dam gate with silt clearance structure, according to fig. 1-5, when the staff started waterproofing motor 2, first bevel gear 4, second bevel gear 5 and overlap joint post 6 are rotatory, disc 7 is rotatory this moment, lug 9 and horizontal pole 10 are under spacing pipe 11's effect, only be reciprocating linear motion in the horizontal direction, horizontal pole 10 passes through stand 12 and drives kicking block 13 and also be reciprocating linear motion in the horizontal direction, horizontal pole 10 and kicking block 13 can strike the inner wall of gate body 1, make the silt of gate body 1 surface become soft, soft silt, easily by rivers clear away.
The above is the operation of the whole device, and the details which are not described in detail in this specification are well known to those skilled in the art.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a steel dam gate with silt clearance structure which characterized in that includes:
the gate body is connected with the gate hoist when working and is placed at a required position;
the waterproof motor is fixedly arranged on the back of the gate body;
the lapping column is movably arranged inside the gate body, a disc is fixedly arranged at the tail end of the lapping column, and a lug is movably arranged inside the disc;
the cross bar is fixedly arranged on the surface of the bump;
and the jacking block is connected with the cross rod through the upright post.
2. The steel dam gate with silt cleaning structure of claim 1, wherein: the terminal fixed mounting of waterproof motor has the connecting axle, and the other one side fixed mounting of connecting axle has first bevel gear.
3. The steel dam gate with silt cleaning structure of claim 2, wherein: and a second bevel gear corresponding to the first bevel gear is fixedly arranged on the surface of the lapping column.
4. The steel dam gate with silt cleaning structure of claim 1, wherein: oval grooves are formed in the surface of the disc, and the inner wall of the disc is attached to the outer wall of the protruding block.
5. The steel dam gate with silt cleaning structure of claim 1, wherein: the inside screw thread of gate body installs spacing pipe, and the horizontal axis of spacing pipe and the horizontal axis of overlap joint post are on a straight line.
6. The steel dam gate with silt cleaning structure of claim 5, wherein: the cross rod penetrates through the limiting pipe.
7. The steel dam gate with silt cleaning structure of claim 6, wherein: the top blocks are distributed on the surface of the upright post at equal intervals.
CN202120870151.8U 2021-04-26 2021-04-26 Steel dam gate with silt clearance structure Expired - Fee Related CN215105154U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120870151.8U CN215105154U (en) 2021-04-26 2021-04-26 Steel dam gate with silt clearance structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120870151.8U CN215105154U (en) 2021-04-26 2021-04-26 Steel dam gate with silt clearance structure

Publications (1)

Publication Number Publication Date
CN215105154U true CN215105154U (en) 2021-12-10

Family

ID=79272088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120870151.8U Expired - Fee Related CN215105154U (en) 2021-04-26 2021-04-26 Steel dam gate with silt clearance structure

Country Status (1)

Country Link
CN (1) CN215105154U (en)

Similar Documents

Publication Publication Date Title
CN112792064A (en) Pipeline maintenance cleaning robot
CN215105154U (en) Steel dam gate with silt clearance structure
CN204564687U (en) Revolving drilling rod washing facility
CN111804091B (en) Based on construction site dust suppression device
CN205056525U (en) Window belt cleaning device under water
CN210529641U (en) River course gate for hydraulic engineering with safeguard function
CN211596707U (en) Slag dragging equipment for hydropower station
CN108221880B (en) Gate device for water conservancy
CN213274177U (en) River silt thickness detection device
CN210827357U (en) Dam with automatic cleaning function
CN210121579U (en) Gate belt cleaning device for hydraulic engineering
CN209144903U (en) A kind of urban river sediment cleaning hydraulic suction dredge
CN109296056B (en) Movable type house residence water supply and drainage pipeline pipe wall cleaning machine
CN213444332U (en) Storage tank with function of scraping residual engine oil on inner wall
CN212405331U (en) A sediment removal device for hydraulic engineering
CN215252777U (en) Leveling device for water conservancy and hydropower foundation treatment
CN216663886U (en) Unpowered high-efficiency self-cleaning highway sound barrier
CN215801359U (en) Safety device is used in hydraulic engineering construction
CN219333264U (en) Mud scraper with anti-corrosion function
CN219408722U (en) Building engineering foundation ditch detection device
CN219011345U (en) Desilting device
CN214033754U (en) Ecological bank protection engineering of water conservancy construction is with firm base
CN215364937U (en) Sludge discharge device for sewage treatment
CN212721618U (en) Water level measuring device for water conservancy monitoring
CN213349912U (en) Monitoring device for mining

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211210