CN215072305U - PV string optimizer system - Google Patents

PV string optimizer system Download PDF

Info

Publication number
CN215072305U
CN215072305U CN202120956936.7U CN202120956936U CN215072305U CN 215072305 U CN215072305 U CN 215072305U CN 202120956936 U CN202120956936 U CN 202120956936U CN 215072305 U CN215072305 U CN 215072305U
Authority
CN
China
Prior art keywords
string
unit
optimizer
assembly
string optimizer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120956936.7U
Other languages
Chinese (zh)
Inventor
肖安波
曾建友
周党生
盛小军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Hopewind Electric Co Ltd
Original Assignee
Shenzhen Hopewind Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Hopewind Electric Co Ltd filed Critical Shenzhen Hopewind Electric Co Ltd
Priority to CN202120956936.7U priority Critical patent/CN215072305U/en
Application granted granted Critical
Publication of CN215072305U publication Critical patent/CN215072305U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Inverter Devices (AREA)

Abstract

The utility model discloses a PV string optimizer system, which comprises N PV string optimizers, each PV string optimizer corresponds to a PV component string, each PV component string is composed of at least two PV components connected in series, each PV string optimizer input end is independently connected with the corresponding PV component string output end for independent maximum power tracking, one PV string optimizer I to one PV string optimizer N are connected to a DC/AC inverter through the corresponding cables I to N respectively, the PV string optimizer system has the functions of maximum power point tracking and short-circuit fault disconnection protection at the same time, each PV component string carries out independent MPPT tracking, when any PV component string has a short circuit, the other PV assembly strings still work normally, the problem of parallel mismatch is avoided, and short-circuit current is continuously generated in the whole loop under the condition that short-circuit faults occur in one PV assembly string.

Description

PV string optimizer system
Technical Field
The utility model relates to a photovoltaic power generation technical field especially relates to a PV cluster optimizer system.
Background
The existing PV power optimizer is to install one power optimizer for each PV component corresponding to the connection. The technical core of the power optimizer is to realize maximum power point tracking of the PV assembly, and a loop can be cut off when short circuit and other faults exist, so that arcing and fire ignition are prevented, and the like. However, as the cost of PV modules decreases, the cost of the power optimizer is higher than the cost of PV modules, resulting in the cost of a real power plant increasing too much to be practical for mass application.
The existing collecting and distributing type collecting box firstly collects the multi-path PV strings, and then a plurality of PV strings are subjected to maximum power point tracking. The distributed combiner box can solve the problem of parallel mismatch of a plurality of PV strings, but because a plurality of PV strings are introduced into one combiner box, if the combiner box is subjected to a major fault short circuit, all PV string in the combiner box can be caused to be short-circuited. Due to the current limiting characteristic of the PV assembly, overcurrent protection cannot be performed by using a circuit breaker or a fuse, and only the whole loop can continuously generate short-circuit current until a short-circuit point generates heat to cause arc discharge and fire.
There is a need for a PV string optimizer system having both maximum power point tracking and short-circuit fault disconnection protection functions, where each PV module string performs independent MPPT tracking, when any PV module string is short-circuited, other PV module strings still operate normally, and no parallel mismatch problem occurs, and when a short-circuit fault occurs at the rear end of an automatic disconnecting switch of any PV module string, which causes an input overcurrent, the automatic disconnecting switch is automatically disconnected, so that a short-circuit fault of one PV module string is avoided, which causes the whole circuit to continuously generate a short-circuit current.
SUMMERY OF THE UTILITY MODEL
The to-be-solved technical problem of the utility model is to provide a PV cluster optimizer system, this PV cluster optimizer system has the protect function of maximum power point tracking and short-circuit fault disconnection simultaneously, each way PV subassembly cluster all carries out independent MPPT and trails, when any PV subassembly cluster of the same kind short circuit condition appears, other PV subassembly cluster still normally works, can not appear parallelly connected mismatch problem, the automatic breaking switch rear end of any PV subassembly cluster of the same kind appears the automatic breaking switch of short circuit fault under leading to the condition of input overcurrent, thereby avoid PV subassembly cluster of the same kind to appear leading to whole return circuit to continuously produce short-circuit current under the short-circuit fault condition.
In order to solve the technical problem, the utility model provides a PV cluster optimizer system, including a N PV cluster optimizer, each PV cluster optimizer corresponds a PV module cluster, and each PV module cluster comprises two at least PV module series connection, each PV cluster optimizer input independently with correspond PV module cluster output is connected and is carried out independent maximum power tracking, PV cluster optimizer one to PV cluster optimizer N be connected to the dc-to-ac converter through cable one to cable N that corresponds separately, PV module cluster one can be the same or inequality to PV module model and the quantity of arbitrary PV module cluster between the PV module cluster N.
Preferably, N PV string optimizers and corresponding N PV module strings form a first unit, the inverter in the PV string optimizers system further includes a second unit, and the second unit includes a first input fuse and a DC/AC conversion unit corresponding to each PV string optimizer; the PV string optimizers I to N are connected to corresponding input fuses I in the unit II through independent cables I to N, all input fuses in the inverter are output and converged to form a uniform direct current bus, the PV assembly strings I to N in the unit I are subjected to maximum power tracking and independent control through the PV string optimizers I to N, and the direct current bus is connected with the DC/AC conversion unit.
Preferably, the inverter in the PV string optimizer system further comprises a battery access fuse through which the energy storage battery is connected to the dc bus.
Preferably, N PV string optimizers and corresponding N PV module strings form a first unit, the inverter in the PV string optimizers system further includes a second unit, and the second unit includes a first input fuse and a DC/AC conversion unit corresponding to each PV string optimizer; the PV string optimizers I to N are connected to corresponding input fuses I in the unit II through independent cables I to N; the output of all input fuses I in the inverter is converged to form a uniform direct current bus, the PV string optimizer system further comprises a third unit, the third unit comprises M PV assembly strings which are independent respectively, and the second unit of the inverter further comprises an input fuse II and a DC/AC conversion unit, wherein the input fuse II corresponds to the PV assembly strings I to the PV assembly strings M in the third unit; and the PV assembly string I to the PV assembly string M in the unit III are directly connected in parallel after passing through the input fuse II corresponding to the unit II of the inverter.
Preferably, the PV string optimizer system further comprises a unit four and a battery access fuse, the unit four comprises a DC/DC converter for detecting the state of the energy storage battery and controlling the current and voltage for charging and discharging the energy storage battery according to the instruction of the battery management system, the DC/DC converter is connected with the DC bus through the battery access fuse, and the energy storage battery is connected with the DC/DC converter.
Preferably, each PV string optimizer comprises an automatic breaking switch K1 with short-circuit fault disconnection protection function and a DC/DC converter arranged at the rear end of the automatic breaking switch K1.
Preferably, the PV string optimizer further comprises a control unit for detecting the voltage value at the input end of the PV string optimizer and judging whether the rear end of the automatic breaking switch K1 is short-circuited.
Preferably, the control unit is connected with the automatic breaking switch K1, the input end of the PV string optimizer and the output voltage end of the PV string optimizer.
Preferably, the rear end of the automatic breaking switch K1 is provided with a boosting circuit for boosting the voltage at the output end of the PV string and connecting the boosted output voltage to the outside through an output cable.
Preferably, the automatic breaking switch K1 is connected in series with a positive wire at the input end of the PV string optimizer; or the automatic breaking switch K1 is connected in series on the negative electrode lead; or two automatic breaking switches K1 are respectively connected in series on the positive electrode lead and the negative electrode lead.
After the system is adopted, the PV string optimizer system comprises N PV string optimizers, each PV string optimizer corresponds to one PV assembly string, each PV assembly string is formed by connecting at least two PV assemblies in series, the input end of each PV string optimizer is independently connected with the output end of the corresponding PV assembly string to perform independent maximum power tracking, the PV string optimizers I to N are connected to an inverter through corresponding cables I to N, and the types and the number of PV assemblies of any PV assembly string between the PV assembly strings I to N can be the same or different; the PV assembly string optimizer system has the protection functions of maximum power point tracking and short-circuit fault disconnection, each PV assembly string carries out independent MPPT tracking, when any PV assembly string of one path is in a short-circuit condition, other PV assembly strings still work normally, the problem of parallel mismatch can not occur, when the short-circuit fault occurs at the rear end of the automatic disconnecting switch of any PV assembly string of one path, the automatic disconnecting switch is automatically disconnected under the condition that input overcurrent is caused, and therefore the situation that short-circuit fault occurs in the PV assembly strings of one path, the whole loop continuously generates short-circuit current is avoided.
Drawings
FIG. 1 is a block diagram of a prior art power optimizer connection to a PV;
FIG. 2 is a block diagram of the connection of a prior art collection and distribution header box to a PV;
FIG. 3 is a circuit diagram of the PV string optimizer of the present invention connected to a PV module string;
fig. 4 is a circuit diagram of a PV string optimizer of the present invention;
fig. 5 is a circuit diagram of a PV string optimizer system according to an embodiment of the present invention;
fig. 6 is a circuit diagram of a PV string optimizer and its photovoltaic system according to the second embodiment of the present invention;
fig. 7 shows a PV string optimizer and a photovoltaic system thereof according to a third embodiment of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Example one
Referring to fig. 3, 4 and 5, fig. 3 is a circuit diagram of the PV string optimizer and PV module string connection of the present invention, fig. 4 is a circuit diagram of the PV string optimizer of the present invention, and fig. 5 is a circuit diagram of a PV string optimizer system according to an embodiment of the present invention; the embodiment discloses a PV string optimizer system, which includes N PV string optimizers, each PV string optimizer corresponds to a PV module string, each PV module string is composed of at least two PV modules connected in series, each PV string optimizer input end is independently connected with a corresponding PV module string output end for independent maximum power tracking, each PV string optimizer includes an automatic breaking switch K1 with a short-circuit fault breaking protection function and a DC/DC converter arranged at the rear end of the automatic breaking switch K1, and PV string optimizers one to PV string optimizers N are connected to an inverter through corresponding cables one to N;
the PV component strings I to N are respectively connected into a PV string optimizer I to a PV string optimizer N through N pairs of cable bundles, and the output of all the PV string optimizers is connected into an inverter through cables I to N; each PV cluster optimizer is internally provided with an independent Maximum Power Point Tracking (MPPT) unit, the maximum power output tracking of each PV assembly cluster is carried out, each PV cluster is independently connected to the independent PV cluster optimizer to carry out the independent MPPT tracking, the problem of parallel mismatch does not exist, the PV assembly models and the number of any PV assembly cluster between the PV assembly cluster I and the PV assembly cluster N can be the same or different, and the effect of convenient use is achieved.
In this embodiment, the PV string optimizer further includes a control unit for detecting a voltage value at an input terminal of the PV string optimizer and determining whether a short circuit occurs at a rear end of the automatic disconnecting switch K1;
and the control unit is connected with the automatic breaking switch K1, the input end of the PV string optimizer and the output voltage end of the PV string optimizer.
The rear end of the automatic breaking switch K1 is provided with a boosting circuit for boosting the voltage at the output end of the PV string and connecting the boosted output voltage to the outside through an output cable.
In this embodiment, the PV string optimizer is installed with the PV string assembly, the DC/AC inverter device at the output rear end of the PV string optimizer is located at a relatively long distance from the PV string optimizer, and the output voltage Vo of the boost circuit of the PV string optimizer needs to pass through a long-distance output cable to be connected to the DC/AC inverter device at the output rear end of the PV string optimizer, where the output cable has a relatively long distance and is relatively easy to cause a short-circuit fault, and when any one of the cables from one cable to cable N is short-circuited, the control unit of the corresponding PV string optimizer detects an abnormal inductive current and triggers the automatic disconnecting switch K1 of the PV string optimizer to be disconnected, thereby playing a role in preventing the fault from being expanded.
In this embodiment, the DC/AC inverter outputs energy to the power grid to perform grid-connection control, and simultaneously adjusts the total power energy output to ensure the stability of the DC bus voltage.
In this embodiment, the main breaking switch K1 is one of a mechanical switch contactor, a relay, a semiconductor insulated gate bipolar transistor, a metal oxide semiconductor field effect transistor, and a triode.
In the embodiment, the automatic breaking switch K1 is connected in series with the positive wire of the input end of the PV string optimizer; or the automatic breaking switch K1 is connected in series on the negative electrode lead; or two automatic breaking switches K1 are respectively connected in series on the positive electrode lead and the negative electrode lead.
Example two
Referring to fig. 6, fig. 6 is a circuit diagram of a PV string optimizer and a photovoltaic system thereof according to a second embodiment of the present invention; the embodiment discloses a PV string optimizer system, wherein N PV string optimizers and corresponding N PV module strings form a first unit, an inverter in the PV string optimizer system further comprises a second unit, and the second unit comprises a first input fuse and a DC/AC conversion unit, which correspond to each PV string optimizer; the PV string optimizers one to N are connected to the corresponding input fuses one in the unit two through independent cables one to N.
In this embodiment, the PV string optimizer further includes a control unit for detecting a voltage value at an input terminal of the PV string optimizer and determining whether a short circuit occurs at a rear end of the automatic disconnecting switch K1;
and the control unit is connected with the automatic breaking switch K1, the input end of the PV string optimizer and the output voltage end of the PV string optimizer.
The rear end of the automatic breaking switch K1 is provided with a boosting circuit for boosting the voltage at the output end of the PV string and connecting the boosted output voltage to the outside through an output cable.
The PV component strings I to N are respectively connected into a PV string optimizer I to a P string optimizer N through N pairs of cables, the PV string optimizer I to the PV string optimizer N are connected to an input fuse I of the unit II through respective independent cables I to N, an independent Maximum Power Point Tracking (MPPT) unit is arranged in each PV string optimizer for carrying out power output maximization tracking on each PV component string, all input fuses in the unit II are converged to form a unified direct current bus bar, the PV component strings I to PV component strings N in the unit I are subjected to maximum power point tracking and independent control through the PV string optimizer I to the PV string optimizer N, and the direct current bus bar is connected with the DC/AC conversion unit.
In this embodiment, the PV string optimizer system further includes a battery access fuse through which the energy storage battery is connected to the dc bus.
In this embodiment, the inverter outputs energy to a power grid to perform grid-connection control, and adjusts and regulates the voltage of the dc bus bar, that is, the charging and discharging are controlled by the voltage of the energy storage battery, so as to complete the energy control of the inverter.
In this embodiment, the main breaking switch K1 is one of a mechanical switch contactor, a relay, a semiconductor insulated gate bipolar transistor, a metal oxide semiconductor field effect transistor, and a triode.
In the embodiment, the automatic breaking switch K1 is connected in series with the positive wire of the input end of the PV string optimizer; or the automatic breaking switch K1 is connected in series on the negative electrode lead; or two automatic breaking switches K1 are respectively connected in series on the positive electrode lead and the negative electrode lead.
EXAMPLE III
Referring to fig. 7, fig. 7 shows a PV string optimizer and a photovoltaic system thereof according to a third embodiment of the present invention.
The embodiment discloses a PV string optimizer system, which further includes a unit three on the basis of the PV string optimizer system of the embodiment one, an inverter in the PV string optimizer system further includes a unit two, and the unit two includes an input fuse one and a DC/AC conversion unit corresponding to each PV string optimizer; the PV string optimizers I to N are connected to corresponding input fuses I in the unit II through independent cables I to N; all input fuses I in the inverter are output and converged to form a unified direct current bus, the unit III comprises M PV assembly strings which are independent respectively, and the unit II comprises an input fuse II and a DC/AC conversion unit which correspond to the PV assembly strings I to M in the unit III; and PV assembly strings I to M in the unit III are directly connected in parallel after passing through the input fuse II corresponding to the unit II.
The PV string optimizer system further comprises a unit IV and a battery access fuse, wherein the unit IV comprises a DC/DC converter which is used for detecting the state of the energy storage battery and controlling the current and the voltage for charging and discharging the energy storage battery according to the instruction of the battery management system, the DC/DC converter is connected with the direct current bus through the battery access fuse, and the energy storage battery is connected with the DC/DC converter.
The outputs of the first unit and the third unit are connected to the input fuse of the second unit, the PV module string-to-PV voltage is independently controlled by the PV string-to-PV-string optimizer-to-PV-string-to-PV-module string-to-module-to-PV-to-module-to-PV-to-string-to-module-to-module-to-module-to-, when the PV module string is used, the model number and the number of the PV module string need to be kept consistent, otherwise, the parallel mismatch and the power generation loss are large.
And the unit four is used for charging the energy storage battery, power is taken from a direct current bus of the PV string optimizer system after passing through a fuse wire in the unit two, the value of the voltage of the direct current bus, namely the input voltage of the DC/DC unit, is determined by a DC/AC inverter in the unit two, the unit four comprises a DC/DC converter which is used for detecting the state of the energy storage battery and controlling the current and the voltage for charging and discharging the energy storage battery according to the instruction of a battery management system, the DC/DC converter is connected with the direct current bus through the battery access fuse wire, and the energy storage battery is connected with the DC/DC converter.
In the embodiment, part of the PV component strings are directly connected in parallel, and part of the PV component strings are connected after passing through the independent PV string optimizer, so that the problem of serious power generation loss caused by great terrain difference in some occasions in reality is well solved.
After the system is adopted, the PV string optimizer system comprises N PV string optimizers, each PV string optimizer corresponds to one PV assembly string, each PV assembly string is formed by connecting at least two PV assemblies in series, the input end of each PV string optimizer is independently connected with the output end of the corresponding PV assembly string to perform independent maximum power tracking, the PV string optimizers I to N are connected to an inverter through corresponding cables I to N, and the types and the number of PV assemblies of any PV assembly string between the PV assembly strings I to N can be the same or different; the PV assembly string optimizer system has the protection functions of maximum power point tracking and short-circuit fault disconnection, each PV assembly string carries out independent MPPT tracking, when any PV assembly string of one path is in a short-circuit condition, other PV assembly strings still work normally, the problem of parallel mismatch can not occur, when the short-circuit fault occurs at the rear end of the automatic disconnecting switch of any PV assembly string of one path, the automatic disconnecting switch is automatically disconnected under the condition that input overcurrent is caused, and therefore the situation that short-circuit fault occurs in the PV assembly strings of one path, the whole loop continuously generates short-circuit current is avoided.
It should be understood that the above is only a preferred embodiment of the present invention, and the scope of the present invention is not limited thereto, and all the equivalent structures or equivalent flow changes made by the contents of the specification and the drawings or directly or indirectly applied to other related technical fields are also included in the scope of the present invention.

Claims (10)

1. A PV string optimizer system is characterized by comprising N PV string optimizers, each PV string optimizer corresponds to one PV assembly string, each PV assembly string is formed by connecting at least two PV assemblies in series, each PV string optimizer input end is independently connected with the corresponding PV assembly string output end for independent maximum power tracking, one PV string optimizer to one PV string optimizer N are connected to an inverter through corresponding cables from one PV assembly string to the other PV assembly string, and the types and the number of PV assemblies of any PV assembly string from the one PV assembly string to the PV assembly string N can be the same or different.
2. The PV string optimizer system of claim 1, wherein N PV string optimizers and corresponding N PV module strings form a first unit, wherein the inverter in the PV string optimizer system further comprises a second unit comprising a first input fuse corresponding to each PV string optimizer, a DC/AC conversion unit; the PV string optimizers I to N are connected to corresponding input fuses I in the unit II through independent cables I to N, all input fuses in the inverter are output and converged to form a uniform direct current bus, the PV assembly strings I to N in the unit I are subjected to maximum power tracking and independent control through the PV string optimizers I to N, and the direct current bus is connected with the DC/AC conversion unit.
3. The PV string optimizer system of claim 2, wherein the inverter in the PV string optimizer system further comprises a battery access fuse through which the energy storage battery is connected to the dc bus.
4. The PV string optimizer system of claim 1, wherein N PV string optimizers and corresponding N PV module strings form a first unit, wherein the inverter in the PV string optimizer system further comprises a second unit comprising a first input fuse corresponding to each PV string optimizer, a DC/AC conversion unit; the PV string optimizers I to N are connected to corresponding input fuses I in the unit II through independent cables I to N; the output of all input fuses I in the inverter is converged to form a uniform direct current bus, the PV string optimizer system further comprises a third unit, the third unit comprises M PV assembly strings which are independent respectively, and the second unit of the inverter further comprises an input fuse II and a DC/AC conversion unit, wherein the input fuse II corresponds to the PV assembly strings I to the PV assembly strings M in the third unit; and the PV assembly string I to the PV assembly string M in the unit III are directly connected in parallel after passing through the input fuse II corresponding to the unit II of the inverter.
5. The PV string optimizer system according to claim 4 further comprising a unit four including a DC/DC converter for detecting the state of the energy storage battery and controlling the amount of current and voltage to be charged and discharged to and from the energy storage battery according to the instructions of the battery management system, wherein the DC/DC converter is connected to the DC bus via the battery access fuse, and wherein the energy storage battery is connected to the DC/DC converter.
6. The PV string optimizer system according to claim 1, wherein each PV string optimizer comprises an automatic disconnect switch K1 with short-circuit fault disconnect protection and a DC/DC converter disposed at the back end of the automatic disconnect switch K1.
7. The PV string optimizer system of claim 6, wherein the PV string optimizer further comprises a control unit that detects PV string optimizer input voltage values and determines whether a short circuit occurs at the back end of the automatic disconnect switch K1.
8. The PV string optimizer system according to claim 7, wherein the control unit is connected to an automatic disconnect switch K1, a PV string optimizer input, a PV string optimizer output voltage terminal.
9. The PV string optimizer system according to claim 6, wherein the automatic disconnect switch K1 is provided at the back end with a voltage boosting circuit for boosting the voltage at the output end of the PV string and connecting the boosted output voltage to the outside through an output cable.
10. The PV string optimizer system according to claim 6, wherein the automatic disconnect switch K1 is connected in series on the positive conductor at the input of the PV string optimizer; or the automatic breaking switch K1 is connected in series on the negative electrode lead; or two automatic breaking switches K1 are respectively connected in series on the positive electrode lead and the negative electrode lead.
CN202120956936.7U 2021-05-06 2021-05-06 PV string optimizer system Active CN215072305U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120956936.7U CN215072305U (en) 2021-05-06 2021-05-06 PV string optimizer system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120956936.7U CN215072305U (en) 2021-05-06 2021-05-06 PV string optimizer system

Publications (1)

Publication Number Publication Date
CN215072305U true CN215072305U (en) 2021-12-07

Family

ID=79198454

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120956936.7U Active CN215072305U (en) 2021-05-06 2021-05-06 PV string optimizer system

Country Status (1)

Country Link
CN (1) CN215072305U (en)

Similar Documents

Publication Publication Date Title
US20230208354A1 (en) Direct current combiner box, inverter, photovoltaic system, and protection method
US11942775B2 (en) High voltage battery cluster, and overcurrent protection circuit and switch box thereof
US11342752B2 (en) Energy storage system and multi-stage short circuit protection system thereof
EP3961854B1 (en) Protection device and protection method for photovoltaic power generation system, and photovoltaic power generation system
EP4007108A1 (en) Battery cluster management device and battery energy storage system
CN113508506B (en) Photovoltaic power generation system, photovoltaic inverter and direct current collection flow box
US12051905B2 (en) Power system
CN104242811A (en) Photovoltaic power supply system
US12074444B2 (en) Power system
Zhao et al. Research on demonstration project of Zhangbei flexible DC grid
CN215072305U (en) PV string optimizer system
CN108418193B (en) Fault power supply recovery method and system combining reclosing and low voltage ride through
CN113131858A (en) PV string optimizer system
CN210693533U (en) Open-circuit protection device for storage battery pack of transformer substation
WO2020146999A1 (en) Pv power converter and control method and pv power plant using the same
Li et al. Continuous operation of LVDC source/load under DC faults in MMC-DC distribution systems
Li et al. A protection method for microgrids based on information sharing
CN219394439U (en) Direct current shunt box and photovoltaic power generation system
CN218449471U (en) Photovoltaic overvoltage protection device and inverter
Klein et al. Post-Fault Power Flow Control for Multi-Terminal Bipolar HVDC Systems Connecting Offshore Wind Farms
CN118412834A (en) DC-DC converter, photovoltaic inverter and direct current combiner box
Zafar et al. Fault analysis for DC Bus-integrated energy storage system, electric vehicle supply equipment, and photo voltaic systems
Zhaozhao et al. Research on the Scheme of Flexible DC Connection of Regional New Energy to the Power Grid
CN117748709A (en) Spare power automatic switching method and system based on distributed buffer resistor
CN116826674A (en) Light Chu Chongqun direct-current micro-grid interelectrode fault protection method adopting adaptive control mode switching

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant