CN215062753U - Bent room of integrated temperature humidity control pipe-line system - Google Patents

Bent room of integrated temperature humidity control pipe-line system Download PDF

Info

Publication number
CN215062753U
CN215062753U CN202120778575.1U CN202120778575U CN215062753U CN 215062753 U CN215062753 U CN 215062753U CN 202120778575 U CN202120778575 U CN 202120778575U CN 215062753 U CN215062753 U CN 215062753U
Authority
CN
China
Prior art keywords
pipe
room
bent room
line system
bent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120778575.1U
Other languages
Chinese (zh)
Inventor
廖俊杰
胡光忠
王平
宾秋月
朱文昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan University of Science and Engineering
Original Assignee
Sichuan University of Science and Engineering
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan University of Science and Engineering filed Critical Sichuan University of Science and Engineering
Priority to CN202120778575.1U priority Critical patent/CN215062753U/en
Application granted granted Critical
Publication of CN215062753U publication Critical patent/CN215062753U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Air Conditioning Control Device (AREA)

Abstract

The utility model relates to a temperature and humidity control of fermentation with bent room to a bent room of integrated temperature and humidity control pipe-line system is disclosed, it is including bent room, temperature and humidity control pipe-line system includes that one arranges in the outside regulation pipe-line system who nevertheless communicates with bent room inner space in bent room, including centrifugal fan, heater, humidifier, air-supply line and play tuber pipe in the regulation pipe-line system, but regulation pipe-line system and bent room inner space intercommunication are closed major loop, wherein the export of humidifier is provided with first normally closed motorised valve, be provided with second normally closed motorised valve on the air-supply line, be provided with the third normally closed motorised valve on the play tuber pipe, be connected with first normally open motorised valve on the major loop between air-supply line and the play tuber pipe. The control and the maintenance of each part in the pipeline system can be adjusted outside. The utility model provides high bent room's leakproofness and heat insulating ability, energy saving and consumption reduction shortens the fermentation cycle, improves the daqu fermentation effect.

Description

Bent room of integrated temperature humidity control pipe-line system
Technical Field
The utility model relates to a bent room, especially a pipe-line system of humiture that can adjust bent room.
Background
The Daqu is used as a leaven for fermenting and brewing Daqu liquor and plays a very key role in the brewing process of the white liquor. The yeast contains rich microorganisms and active enzymes, is mixed into grain lees cooled to contain starch after being cooked and gelatinized at high temperature, participates in the fermentation process, and generates special fragrance. The different fermentation temperatures of the yeast can cause the different amount of microorganisms which influence the body odor type in the yeast blocks. According to different fermentation temperatures, the yeast can be roughly divided into high-temperature yeast, medium-temperature yeast and low-temperature yeast. Wherein, the low-temperature yeast has abundant acetic acid bacteria, and the metabolite ethyl acetate generated by acetic acid bacteria fermentation is the main fragrant substance of the fen-flavor liquor; the medium-temperature yeast is rich in caproic acid bacteria, and the fermentation metabolite ethyl caproate is a main fragrant substance of the strong aromatic Chinese spirits; the ingredients in the high-temperature yeast are complex, ethyl acetate and ethyl lactate in the fermentation metabolites are prominent, and the content of the composite acid is high.
In the process of yeast fermentation, the traditional yeast room has a plurality of problems in the production process: (1) because the yeast blocks are stored in the yeast room for a long time, in order to increase the storage amount and improve the fermentation effect, the yeast blocks are generally stacked in a layered stacking mode and covered with straws and the like. However, in the storage process, due to the concentrated stacking, under the action of microorganisms, the temperature rise is fast, the unevenness is large, the temperature and the humidity are not easy to control, and the quality of finished koji is directly influenced; (2) the koji chamber cannot accurately monitor and regulate the temperature and the humidity according to the fermentation condition. The fermentation of the yeast blocks is easy to occur when the temperature is higher in summer, and the fermentation period of the yeast blocks is prolonged when the temperature is too low in winter; (3) because the difference can appear in its humiture because the difference of spatial position among the bent piece fermentation process, traditional bent room leads to the fermentation of bent piece inhomogeneous easily because can't carry out uniform control to inside humiture in real time.
For improving the intelligent degree of humiture regulation and control in the bent room, in the chinese utility model patent of CN103397793B 'an intelligent fermentation bent room' of 12 months 17 days authorization announcement in 2014, an internally mounted has introduced a bent room of air-conditioning air-blower, air-conditioning blast pipe, air-conditioning exhaust pipe, through installing humiture detection subassembly conduction humiture signal to control system on the removal goods shelves, control system controls air-conditioning air-blower, air-conditioning blast pipe, heating or humidification device in air-conditioning exhaust pipe and the wind channel again, realize rising temperature as required, humidification or cooling, dehumidification. The device mainly arranges governing system inside bent room, has occupied the space in the bent room, has reduced the fermentation output in the bent room of unit volume, in case the system trouble in addition, disturbs the humiture environment in the bent room easily when getting into the maintenance, leads to fermentation quality to descend failure even, causes the loss.
SUMMERY OF THE UTILITY MODEL
In order to make the most of the effective use of the space in the bent room, the unexpected interference brought by the adjustment system trouble of humiture in the bent room is avoided, the utility model aims to solve the technical problem that a bent room of integrated humiture regulation pipe-line system is provided.
The utility model provides a technical scheme that its technical problem adopted is: integration temperature and humidity control pipe-line system's bent room, including bent room, temperature and humidity control pipe-line system includes one arranges in the outside regulation pipe-line system who nevertheless communicates with bent room inner space of bent room, including centrifugal fan in the regulation pipe-line system, a heater, the humidifier, the air-supply line reaches the play tuber pipe, but regulation pipe-line system and bent room inner space intercommunication are closed major loop, wherein the export of humidifier is provided with first normally closed motorised valve, be provided with the second normally closed motorised valve on the air-supply line, be provided with the third normally closed motorised valve on the play tuber pipe, be connected with first normally open motorised valve on the main loop between air-supply line and the play tuber pipe. The control and the maintenance of each part in the pipeline system can be adjusted outside.
The main loop is sequentially provided with the following components according to the airflow direction: the air inlet pipe, the centrifugal fan, the heater, the humidifier, the bent room, the air outlet pipe and the first normally open electric valve are arranged, the air flow can be controlled to be heated and humidified necessarily and then enter the bent room, air exhaust is smooth, and control of internal and external circulation of a main loop is facilitated.
The heater is an electric heater, and automatic control is convenient to carry out.
The bent room is a skid-mounted bent room which is installed on the same bottom plate together with the adjusting pipeline system, and the adjusting pipeline system and the bent room are integrally installed and arranged, so that the operation and the maintenance are convenient.
In order to realize the automatic adjustment of the temperature and the humidity of the bending room, a temperature sensor and a humidity sensor are arranged in the bending room, a main control module is arranged outside the bending room, and the main control module is respectively connected with each electric valve, the centrifugal fan, the heater, the humidifier, the temperature sensor and the humidity sensor on the adjusting pipeline system.
The temperature sensor and the humidity sensor are arranged in a layered mode according to the height of the bending room, and at least two layers are arranged on each layer. Can judge the uniformity of temperature and humidity in the koji room, and the main control module correspondingly sends out control signals for regulating all parts of the pipeline system according to the requirements of the temperature and the humidity corresponding to the fermentation process.
The adjusting pipeline system is connected with the curved room through at least two branch pipes respectively, and the plurality of interfaces are convenient for rapid air circulation so as to be beneficial to rapidly adjusting the temperature and the humidity according to the fermentation requirement.
The pipe orifice positions of the branch pipes communicated with the bent room are uniformly distributed along the length direction of the bent room, so that the temperature and the humidity of each position in the bent room can be uniformly controlled conveniently, and the temperature difference and the humidity difference of each position in the bent room can be reduced as much as possible.
The humidifier is an ultrasonic humidifier, and is convenient to carry out automatic control.
And a second normally-open electric valve is connected on a main loop between the humidifier and the bending room, so that the humidifier is convenient to overhaul.
The utility model has the advantages that: the temperature and humidity regulation of the yeast room is completed by an integrated temperature and humidity regulation pipeline system, the sealing property and the heat preservation property of the yeast room are improved, the energy is saved, the consumption is reduced, the fermentation period is shortened, the fermentation effect of the yeast is improved, and the production efficiency of the yeast and the quality of the finished yeast products are improved.
Drawings
Fig. 1 is a schematic diagram of the present invention.
Fig. 2 is a schematic structural diagram of the present invention.
Fig. 3 is a top view of fig. 2.
Fig. 4 is a left side view of fig. 3.
Fig. 5 is a schematic view of the arrangement positions of the temperature sensor and the humidity sensor in fig. 2.
Fig. 6 is a schematic diagram of embodiment 2 of the present invention.
The arrows in fig. 1 and 6 indicate the direction of the air flow.
Labeled as: 1-a yeast block, 2-a yeast room, 3-a first normally closed electric valve, 4-a humidifier, 5-a heater, 6-a centrifugal fan, 7-a first normally open electric valve, 8-a second normally closed electric valve, 9-a third normally closed electric valve, 10-a bottom plate, 11-an air inlet pipe, 12-an air outlet pipe, 13-a branch pipe, 14-a second normally open electric valve, and 15-a temperature and humidity monitoring point.
Detailed Description
The present invention will be further explained with reference to the drawings and examples.
Example 1:
as shown in fig. 1, fig. 2, fig. 3 and fig. 4, the bent room of integrated temperature and humidity control pipe-line system, including bent room 2, temperature and humidity control pipe-line system includes one and arranges in bent outside of the room but with the regulation pipe-line system of bent room inner space intercommunication, including centrifugal fan 6, heater 5, humidifier 4, air-supply line 11 and air-out pipe 12 in the regulation pipe-line system, but regulation pipe-line system passes through air-supply line 11 and air-out pipe 12 and the intercommunication of bent room inner space for closed main loop, arranges following each part in proper order according to the air current flow direction on the main loop: the air inlet pipe 11, centrifugal fan 6, heater 5 (the heater is electric heater), humidifier 4 (the humidifier is the supersound humidifier), bent room 2, go out tuber pipe 12, first normally open motorised valve 7, wherein the export of humidifier 4 is provided with first normally closed motorised valve 3, the air inlet pipe 11 is the first house steward that is provided with second normally closed motorised valve 8, it is the second house steward that is provided with third normally closed motorised valve 9 to go out tuber pipe 12, first house steward and second house steward are equallyd divide and are connected with bent room 2 through at least two branch pipes 13 respectively, first house steward and second house steward are arranged in parallel with the bottom surface of bent room 2, the mouth of pipe position that each branch pipe 13 and bent room 2 communicate is located below half the height of bent room 2, along the length direction evenly distributed of bent room 2, be connected with first normally open motorised valve 7 on the main return circuit between air inlet pipe 11 and the play tuber pipe 12.
Bent room 2 is for installing the bent room of sled dress formula on same bottom plate 10 together with adjusting pipe-line system, be provided with temperature sensor and humidity transducer in bent room 2, bent room 2 is provided with main control module outward, main control module respectively with adjust pipe-line system on first normally closed motorised valve 3, first normally open motorised valve 7, second normally open motorised valve 8, third normally open motorised valve 9, centrifugal fan 6, heater 5, humidifier 4, temperature sensor and humidity transducer are connected, as shown in fig. 5, temperature sensor and humidity transducer have all arranged the three-layer according to bent room height layering, there are five on every layer, can each temperature sensor and humidity transducer sampling mean value as main control module's input parameter with the automatic control of decision-making to other equipment. The specific automatic control process can refer to the Chinese utility model patent with the publication number of CN210181497U which has been issued by the same applicant as the automatic control system for the skid-mounted curved house.
The operation is as follows.
And (3) a heating link: as shown in fig. 1, fig. 3 and fig. 4, when the heating operation is performed, the first normally open electric valve 7 of the main loop is kept open, the second normally closed electric valve 8 and the third normally closed electric valve 9 are kept normally closed, the centrifugal fan 6 continuously rotates, the heater 5 is powered on, air enters the electric heater from the pipeline to be heated, the heated air enters the curved room 2, the continuous circulation heating is performed, the loop air realizes the internal circulation, the air flowing through the cavity is continuously heated and is discharged into the curved room 2, and the function of the internal circulation heating of the curved room is realized.
And (3) a humidifying step: as shown in fig. 1, 3 and 4, when the humidification operation is performed, the first normally open electric valve 7 of the main circuit is kept open, the second normally closed electric valve 8 and the third normally closed electric valve 9 are kept normally closed, the first normally closed electric valve 3 at the outlet of the humidifier 4 is opened, the electric heater is electrified to normally heat, 100% humidity air discharged from the humidifier 4 is mixed with hot air flowing through the electric heater, the humidity of the air in the pipeline is increased by adjusting the temperature of the electric heater and the wind speed of the centrifugal fan 6, the air in the pipeline is mixed with the air in the bending room 2, and the temperature and humidity condition of the mixed air can be adjusted to the condition required by the bending room.
And (3) cooling: as shown in fig. 1, 3 and 4, the first normally open electric valve 7 of the main circuit is closed, the first normally closed electric valve 3, the second normally closed electric valve 8 and the third normally closed electric valve 9 are simultaneously opened, the external circulation pipeline system of the curved chamber is started, air with lower temperature enters the curved chamber 2 through the air inlet pipe 11, the air is heated to proper temperature through the electric heater and passes through the working humidifier 4, the air with proper temperature and humidity is discharged into the curved chamber 2, and high-temperature air in the curved chamber 2 is discharged through the exhaust pipe 12, so that the purpose of cooling is achieved.
And (3) a dampness reducing link: as shown in fig. 1, 3 and 4, the first normally open electric valve 7 of the main circuit is closed, the first normally closed electric valve 3 is closed, the second normally closed electric valve 8 and the third normally closed electric valve 9 are simultaneously opened, the humidifier 4 is closed, the external circulation pipeline system of the koji room is started, air with lower temperature enters the system through the air inlet pipe 11, the air is heated to proper temperature through the electric heater, air with proper temperature and humidity is discharged into the koji room, and high-temperature air in the koji room is discharged through the air outlet pipe 12, so that the purpose of reducing humidity is achieved.
Example 2:
as shown in fig. 6, a second normally open electric valve 14 is connected to the main circuit between the humidifier 4 and the bending chamber 2, and the rest of the structure is the same as that of embodiment 1.
The first normally open electric valve 7 and the second normally open electric valve 14 can be selectively or emergently closed, the third normally closed electric valve 9 is opened, the adjusting pipeline system is overhauled, and the influence on the fermentation process due to overhauling is reduced.

Claims (10)

1. Bent room of integrated temperature humidity control pipe-line system, including bent room (2), characterized by: temperature and humidity control pipe-line system includes one and arranges in bent room outside but with the regulation pipe-line system of bent room inner space intercommunication, including centrifugal fan (6) among the regulation pipe-line system, heater (5), humidifier (4), air-supply line (11) and play tuber pipe (12), it is closed main loop with bent room inner space intercommunication to adjust pipe-line system, wherein the export of humidifier (4) is provided with first normally closed motorised valve (3), be provided with second normally closed motorised valve (8) on air-supply line (11), be provided with third normally closed motorised valve (9) on the play tuber pipe, be connected with first normally open motorised valve (7) on air-supply line (11) and the main loop between the play tuber pipe (12).
2. The curved room of the integrated temperature and humidity regulation pipeline system according to claim 1, which is characterized in that: the main loop is sequentially provided with the following components according to the airflow direction: the air conditioner comprises an air inlet pipe (11), a centrifugal fan (6), a heater (5), a humidifier (4), a bent room (2), an air outlet pipe (12) and a first normally open electric valve (7).
3. The bent room of integrated humiture regulation pipe-line system of claim 1 or 2, characterized by: the heater (5) is an electric heater.
4. The bent room of integrated humiture regulation pipe-line system of claim 1 or 2, characterized by: the bent house (2) is a skid-mounted bent house which is arranged on the same bottom plate (10) together with the adjusting pipeline system.
5. The bent room of integrated humiture regulation pipe-line system of claim 1 or 2, characterized by: be provided with temperature sensor and humidity transducer in bent room (2), bent room (2) is provided with main control module outward, and main control module is connected with each motorised valve (3, 7, 8, 9), centrifugal fan (6), heater (5), humidifier (4), temperature sensor and humidity transducer on the regulation pipe-line system respectively.
6. The curved room of the integrated temperature and humidity regulation pipeline system of claim 5, which is characterized in that: the temperature sensor and the humidity sensor are arranged in a layered mode according to the height of the bending room, and at least two layers are arranged on each layer.
7. The bent room of integrated humiture regulation pipe-line system of claim 1 or 2, characterized by: the adjusting pipeline system is respectively connected with the bent room (2) through at least two branch pipes (13).
8. The curved room of the integrated temperature and humidity regulation pipeline system of claim 7, which is characterized in that: the pipe orifice positions of the branch pipes (13) communicated with the curved chamber (2) are uniformly distributed along the length direction of the curved chamber (2).
9. The bent room of integrated humiture regulation pipe-line system of claim 1 or 2, characterized by: the humidifier is an ultrasonic humidifier.
10. The curved room of the integrated temperature and humidity regulation pipeline system of claim 2, which is characterized in that: and a second normally open electric valve (14) is connected on a main loop between the humidifier (4) and the bending room (2).
CN202120778575.1U 2021-04-15 2021-04-15 Bent room of integrated temperature humidity control pipe-line system Active CN215062753U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120778575.1U CN215062753U (en) 2021-04-15 2021-04-15 Bent room of integrated temperature humidity control pipe-line system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120778575.1U CN215062753U (en) 2021-04-15 2021-04-15 Bent room of integrated temperature humidity control pipe-line system

Publications (1)

Publication Number Publication Date
CN215062753U true CN215062753U (en) 2021-12-07

Family

ID=79105928

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120778575.1U Active CN215062753U (en) 2021-04-15 2021-04-15 Bent room of integrated temperature humidity control pipe-line system

Country Status (1)

Country Link
CN (1) CN215062753U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116515573A (en) * 2023-06-02 2023-08-01 山西今盛环境工程有限公司 Distiller's yeast block culture system and culture method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116515573A (en) * 2023-06-02 2023-08-01 山西今盛环境工程有限公司 Distiller's yeast block culture system and culture method

Similar Documents

Publication Publication Date Title
CN102306044B (en) Automatic control refrigeration system for high-density computer room and method thereof
CN202769866U (en) Intelligent air humidifier
CN201947892U (en) Ventilation type constant-temperature-and-humidity tank for tea leaf fermentation
CN215062753U (en) Bent room of integrated temperature humidity control pipe-line system
CN205448633U (en) Fu brick golden flower ferment storehouse intelligence control system
CN211746640U (en) Realize constant temperature and humidity automated control's black tea fermentation room
CN208964892U (en) A kind of bean cotyledon koji making disc machine
CN204811686U (en) High temperature oven of stainless steel structure
CN112889547A (en) Energy-saving planting room using waste heat of data center
CN205455861U (en) Garlic fermenting installation
CN110777055A (en) High-efficient incubator of biological medicine
CN201758628U (en) Air circulation system of micro vegetable factory
CN105018342A (en) Pot-type mouldy bran culture system capable of controlling mouldy bran culture process precisely
CN202269202U (en) Pre-treatment ventilation system for edible fungus culture warehouse
CN110004051B (en) Composite system for black garlic fermentation and green garlic preparation based on heat pump
CN201752186U (en) Roof structure of high-capacity growing room used for vertically planting edible mushrooms
CN110012737B (en) Intelligent potato control raw material warehouse
CN201926079U (en) Intelligent energy-saving central air-conditioning device
CN209923347U (en) Multifunctional energy-saving black garlic fermentation system
CN205213520U (en) A constant temperature system for pork tripe mushroom factory cultivation in winter
CN209804802U (en) Lead-acid storage battery pole plate curing chamber
CN218969239U (en) Feeding complex enzyme fermentation system with temperature and humidity regulation function
CN201752196U (en) Oxygen supply system of high-capacity growing room used for vertically planting edible mushrooms
CN216874834U (en) Multipurpose semi-automatic tea leaf withering test bed
CN215757409U (en) Clean constant-temperature constant-humidity biochemical culture room

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant