CN215053285U CN202120416439.8U CN202120416439U CN215053285U CN 215053285 U CN215053285 U CN 215053285U CN 202120416439 U CN202120416439 U CN 202120416439U CN 215053285 U CN215053285 U CN 215053285U
Authority
CN
China
Prior art keywords
basement
side wall
soft soil
soil area
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120416439.8U
Other languages
Chinese (zh)
Inventor
林家浩
李迎霞
胡振宇
高利
胡东卫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuhai Huafa Architectural Design Consulting Co Ltd
Original Assignee
Zhuhai Huafa Architectural Design Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuhai Huafa Architectural Design Consulting Co Ltd filed Critical Zhuhai Huafa Architectural Design Consulting Co Ltd
Priority to CN202120416439.8U priority Critical patent/CN215053285U/en
Application granted granted Critical
Publication of CN215053285U publication Critical patent/CN215053285U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model provides a soft soil area basement lateral wall outer water and electricity pipe well anti-settling device, including pre-buried a plurality of threading pipes in the basement lateral wall, set up in the landing slab of basement upper portion outer wall, with the link plate of the free end bottom surface connection of landing slab, a plurality of electric power pipes set up in the bottom of link plate, the threading pipe with the quantity of electric power pipe corresponds; the platform board with the link plate is connected and with the basement lateral wall encloses into a cavity, the water and electricity pipeline penetrates the threading pipe extremely in the cavity and the bending is placed, the water and electricity pipeline passes again the electric power pipe extremely outside the cavity. The problems that in the prior art, a hydroelectric pipeline is damaged due to ground settlement, is difficult to overhaul and has a complex structure are solved.

Description

Subsidence prevention device for basement side wall outer water and electricity pipe well in soft soil area
Technical Field
The utility model relates to a technical field is prevented subsiding by the pipeline, concretely relates to device is prevented subsiding by outer hydroelectric pipe well of soft soil area basement lateral wall.
Background
The conduit is extended into the underground chamber from the outside of the underground chamber, and is mainly used for connecting wires and cables in the underground chamber, and the wires and cables outside the underground chamber are usually stored and accommodated by using a power tube in order to prevent electric leakage, damage and the like. When electric wire, cable in the power tube insert in the threading pipe, for the convenience of the connection of electric wire, cable and accomodate the holding, an electric well has been made outside the underground chamber usually, and electric wire, cable in the power tube insert in the electric well earlier, and rethread electric well inserts in the threading pipe to make electric wire, cable insert the basement.
Many areas can appear subsiding because of geological reason on the ground, ground can make the electric power pipe sink thereupon when subsiding, and electric well and basement are because just done corresponding safeguard measure when building, can not sink thereupon, the dislocation just appears easily in the connection between electric power pipe and the electric well under this condition, make electric wire, cable damaged or broken, thereby the condition of electric leakage, outage appears, seriously influence people's production and life, and need dig a large amount of soil bodies in later stage maintenance process, thereby carry out the inspection to damaged position, when being difficult to overhaul, lead to the cost also higher, in the installation, also show the characteristics that the structure is complicated, be not convenient for installation and dismantlement.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art, the utility model provides a device is prevented subsiding by outer water and electricity pipe-well of soft soil area basement lateral wall has solved prior art normal water and electricity pipeline and has received the problem that the damage, be difficult to overhaul and the structure is complicated because of ground subsidence.
The technical scheme of the utility model is realized like this:
a settlement-preventing device for a water and electricity pipe well outside the side wall of a basement in a soft soil area comprises a plurality of threading pipes pre-embedded in the side wall of the basement, a platform plate arranged on the outer wall of the upper part of the basement and a hanging plate connected with the bottom surface of the free end of the platform plate, wherein a plurality of power pipes are arranged at the bottom end of the hanging plate, and the number of the threading pipes corresponds to that of the power pipes;
the platform board with the link plate is connected and with the basement lateral wall encloses into a cavity, and the water and electricity pipeline penetrates the threading pipe extremely in the cavity and the bending is placed, the water and electricity pipeline passes again the electric power pipe extremely outside the cavity.
Preferably, in the anti-settling device for the hydropower pipe well outside the side wall of the basement in the soft soil area, the threading pipes are uniformly distributed and embedded in the side wall of the basement;
a plurality of electric power pipe evenly distributed set up in the bottom of link plate.
Preferably, in the anti-settling device for the hydroelectric pipe well outside the side wall of the basement in the soft soil area, the threading pipe is a waterproof threading pipe;
the power tube is a waterproof power tube.
Preferably, a device is prevented subsiding by outer hydroelectric pipe well of soft soil area basement lateral wall, the landing deck with be provided with the buttress post between the basement lateral wall.
Preferably, a soft soil area basement lateral wall outer hydroelectric pipe well anti-settling device, buttress post with the inside through connection of basement lateral wall has the atress reinforcing bar.
Preferably, a device is prevented subsiding by outer hydroelectric pipe well of soft soil area basement lateral wall, the landing slab is cantilever slab or cantilever beam.
Preferably, the device is prevented subsiding by outer hydroelectric pipe well of soft soil area basement lateral wall, the cantilever plate is formed with reinforced concrete pouring.
Preferably, the settlement-preventing device for the hydroelectric pipe well outside the side wall of the basement in the soft soil area is formed by pouring reinforced concrete on the cantilever beam.
Preferably, a soft soil area basement lateral wall outer hydroelectric pipe well anti-settling device, the terminal surface of cantilever beam is provided with two piece at least atress reinforcing bars along length direction.
Preferably, the anti-settlement device for the hydroelectric pipe well outside the side wall of the basement in the soft soil area is formed by pouring concrete.
The utility model has the advantages that:
1. the utility model discloses a pre-buried a plurality of threading pipes in the basement lateral wall, as the guide access to the water and electricity pipeline, basement upper portion outer wall is connected with the landing slab, the free end bottom surface of landing slab is connected with the link plate, form the basic frame that accomodates the holding to the water and electricity pipeline from this, the bottom of link plate is provided with a plurality of power tubes, as the guide that connects out to the water and electricity pipeline, the threading pipe corresponds with the quantity of power tube, convenient maintenance and the installation of water and electricity pipeline; the platform plate is connected with the hanging plate and surrounds the basement side wall to form a cavity, so that a space for containing the water and electricity pipelines is formed, the water and electricity pipelines penetrate through the threading pipe into the cavity and are placed in a bent mode, the water and electricity pipelines are contained regularly and are effectively protected, and the water and electricity pipelines penetrate through the power pipe to the outside of the cavity to form a complete connecting route;
2. the basement is characterized in that a buttress is connected between the outer surface of the side wall of the basement and the platform plate and used as a supporting foundation of the structure, a plurality of threading pipes are uniformly distributed and embedded in the side wall of the basement, and a plurality of power pipes are uniformly distributed and arranged at the bottom end of the hanging plate, so that a good storage protection foundation is formed together, the water and electricity pipeline is convenient to install and effectively protected, and meanwhile, the basement also has the characteristic of convenience in maintenance;
3. the hanging plate is formed by pouring concrete, so that the compatibility with the material of the side wall of the underground chamber is effectively enhanced, and local materials are conveniently used, reinforced and maintained; the platform plate is selected as an overhanging plate or an overhanging beam according to the use requirement, the overhanging plate and the overhanging beam are both formed by pouring reinforced concrete, the supporting performance is improved, the uniform application is facilitated, and at least two stressed reinforcing steel bars are arranged on the end surface of the overhanging beam along the length direction, so that the overhanging beam is ensured to have good structural strength; the inside through connection of landing slab and basement lateral wall has the atress reinforcing bar, forms the connection and plays good reinforcing effect in both inside from this, strengthens the structural strength of landing slab and basement lateral wall, full play its mechanical properties.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings needed to be used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without inventive exercise.
Fig. 1 is a schematic structural view of a first embodiment of the settlement preventing device for the hydroelectric tubular well outside the side wall of the basement in the soft soil area of the utility model;
FIG. 2 is a schematic structural view of a second embodiment of the settlement preventing device for the hydroelectric tubular well outside the basement sidewall in the soft soil area of the present invention;
fig. 3 is a schematic structural view of a third embodiment of the settlement preventing device for the hydroelectric pipe well outside the basement sidewall in the soft soil area at a first viewing angle;
fig. 4 is the utility model relates to a weak soil area basement lateral wall outer hydroelectric pipe well anti-settling device's third embodiment is at the structural schematic under the second visual angle.
The attached drawings are as follows: 1-basement side wall, 1.1-basement bottom plate, 2-platform plate, 3-hanging plate, 4-threading pipe, 5-electric power pipe, 6-water and electricity pipeline, 7-cavity, 8-basement, 9-outdoor, 10-stressed steel bar, 11-buttress column, 12-cantilever beam and 13-cantilever plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
Example one
Referring to fig. 1, a settlement-preventing device for a water and electricity pipe well outside a basement side wall in a soft soil area is used for protecting a water and electricity pipeline 6, a plurality of threading pipes 4 are pre-buried in the basement side wall 1 and used for guiding and connecting in the water and electricity pipeline, a platform plate 2 is connected to the outer wall of the upper portion of the basement 7, a hanging plate 3 is connected to the bottom surface of the free end of the platform plate 2, a basic frame for containing and containing the water and electricity pipeline 6 is formed, a plurality of power pipes 5 are arranged at the bottom end of the hanging plate 3 and used for guiding and connecting out the water and electricity pipeline 6, the number of the threading pipes 4 corresponds to that of the power pipes 5, equipment maintenance and installation of the water and electricity pipeline 6 are facilitated, the platform plate 2 is connected with the hanging plate 3 and surrounds a cavity 7 with the basement side wall 1, so that a space for containing and containing the water and electricity pipeline 6 is formed, namely, a stable freely-retractable buffer zone is provided for the water and electricity pipeline 6, the threading pipes 4 penetrate into the cavity 7 and are placed in a bent way, play good switching on and accomodate the effect, when the soil body subsides, the water and electricity pipeline 6 of buckling and placing freely stretches out and draws back in cavity 7 to obtain effective buffering, thereby obtain effective protection, water and electricity pipeline 6 passes power tube 5 again to the cavity 7 outside, forms complete connecting line.
Preferably, 4 evenly distributed of a plurality of threading pipes are pre-buried in basement lateral wall 1, and 5 evenly distributed of a plurality of electric power pipe set up in the bottom of link plate 3 to form good protection basis of accomodating, when making water and electricity pipeline 6 be convenient for install and obtain effective protection, still possess the characteristics of easy access, in addition, resource space utilization has still been improved, thereby make full use of surrounding space comes to protect water and electricity pipeline 6 in order to play the effect of preventing subsiding.
More preferred, threading pipe 4 is waterproof threading pipe, and electric power pipe 5 is waterproof electric power pipe, and the invasion of external steam has effectively been kept out in the setting of waterproof function to make water and electricity pipeline 6 isolated with external steam, avoid corroding or damaging with this assurance water and electricity pipeline 6.
Preferably, according to the use requirement, the platform plate 2 is an overhanging plate or an overhanging beam, namely when the overhanging dimension D of the hanging plate is less than or equal to 800mm, the platform plate 2 is an overhanging plate; when the overhanging size D of the hanging plate is more than 800mm and less than or equal to 1500mm, the platform plate 2 adopts the cantilever beam, thereby meeting the requirements of structural strength and adaptability.
More preferred, the cantilever plate forms with reinforced concrete pouring, and the cantilever beam forms with reinforced concrete pouring, and reinforced concrete chooses for use, does benefit to the material compatibility between reinforcing platform board 2 and basement lateral wall 1, is convenient for draw materials on the spot and consolidate the maintenance, and the operation when doing benefit to the construction is unified, has still improved stable structure frame basis for the protection of holding of water and electricity pipeline 6.
Preferably, the end face of the cantilever beam is provided with at least two stressed steel bars along the length direction, so that the cantilever beam is guaranteed to have good structural strength and fully exert strong mechanical properties.
Preferentially, the hanging plate 3 is formed by pouring concrete, the compatibility of materials between the hanging plate and the side wall 1 of the basement is effectively enhanced, the structure is favorably kept in a stable state, local materials are conveniently used, the reinforcement and the maintenance are facilitated, and the operation uniformity during construction is ensured.
Example two
Referring to fig. 2, the present embodiment differs from the first embodiment only in that: according to the user demand, the landing slab is cantilever board 13, promptly when the landing slab size D of encorbelmenting is not more than 800mm, the landing slab adopts cantilever board 13, reaches the satisfaction of structural strength requirement and adaptability from this.
Preferably, the stress steel bar 10 is connected to the interior of the cantilever plate 13 and the interior of the basement side wall 1 in a penetrating manner, so that the cantilever plate 13 and the basement side wall 1 are connected to each other in the interior and play a good role in reinforcement, the structural strength of the cantilever plate 13 and the basement side wall 1 is enhanced, and the mechanical properties of the cantilever plate and the basement side wall 1 are fully exerted.
EXAMPLE III
Referring to fig. 3-4, the present embodiment differs from the first embodiment only in that: according to the use requirement, namely when the overhang size is 800mm < D1+D2Less than or equal to 1500mm or less than 800mm and less than D3+D4When the thickness is less than or equal to 1500mm, the composite material is used as a good supporting and protecting foundation, and simultaneously, the structural damage caused by overlarge pressure is prevented, so that the structural strength requirement and the adaptability are metCompliance is satisfied, in this example, D1800mm, i.e. D2≤700mm;D3=300mm,D4Is less than or equal to 1200mm, thereby meeting the actual use requirement, ensuring the stable and intact structure and playing the function of preventing sedimentation, thereby effectively protecting the water and electricity pipeline 6.
Specifically, in order to further enhance the structural strength of the device and fully exert the mechanical properties of each device, the outer surface of the basement side wall 1 is connected with a buttress column 11 which is used as a support base of the structure, the outer surface of the upper end of the buttress column 11 is connected with a cantilever plate 13, the outer surface of the buttress column 11 is connected with a cantilever beam 12, the cantilever beam 12 is positioned below the cantilever plate 13, under the support of the buttress column 11 on the cantilever beam 12, the buttress column 11 and the cantilever beam 12 have good mechanical properties, the bottom surface of the free end of the cantilever beam 12 is connected with a hanging plate 2, so as to form a basic frame for containing and accommodating the hydropower pipeline 6, the bottom end of the hanging plate 2 is provided with a plurality of power pipes 5 which are used for guiding and leading out the hydropower pipeline 6, the threading pipes 4 correspond to the number of the power pipes 5, so as to facilitate the equipment maintenance and the installation of the hydropower pipeline 6, and the cantilever beam 12 and the basement side wall 1 are connected with the device and exert good reinforcing effect by arranging the buttress column 11, the structural strength of the cantilever beam 12 and the side wall 1 of the underground chamber is enhanced, and the mechanical property of the cantilever beam is fully exerted; cantilever beam 12 is connected with cantilever board 13 and link plate 2 respectively and encloses into a cavity 7 with basement lateral wall 1, thereby form and accomodate the space of holding to water and electricity pipeline 6, provide a stable buffer area that freely stretches out and draws back promptly for water and electricity pipeline 6, water and electricity pipeline 6 penetrates through threading pipe 4 and places to buckle in the cavity 7, play good switching on and accomodate the effect, when the soil body subsides, the water and electricity pipeline 6 of placing of buckling freely stretches out and draws back in the cavity 7, and obtain effective buffering, thereby obtain effective protection, water and electricity pipeline 6 passes power pipe 5 outside cavity 7 again, form complete connecting line.
Preferably, in order to further enhance the structural strength and the bearing capacity of the cantilever beam 12, the basement bottom plate 1.1 extends outwards from the bottom of the basement side wall 1, and the buttress column 11 is arranged on the basement bottom plate 1.1 and connected with the outer surface of the basement side wall 1, so that a good bearing foundation is formed, the buttress column 11 and the cantilever beam 12 are well reinforced and supported, the strong mechanical property of the cantilever beam is fully exerted, and the requirement of effective protection of the water and electricity pipeline 6 when the soil body is settled is met.
The utility model discloses a setting up in basement lateral wall 1's outside and encorbelmenting outward and preventing subsiding the structure, bearing soil body pressure in water and electricity pipeline 6's top, basement lateral wall 1 and link plate 2 and the common cavity 7 that forms of platform board 3 provide stable freely flexible buffer for water and electricity pipeline 6 to when the soil body takes place to subside, make water and electricity pipeline 6 receive effectual protection, avoid water and electricity pipeline 6 to take place to break when the soil subsides.
It will be understood that when an element is referred to as being "secured to" or "disposed on" another element, it can be directly on the other element or be indirectly on the other element. When an element is referred to as being "connected to" another element, it can be directly connected to the other element or be indirectly connected to the other element.
It will be understood that the terms "length," "width," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like are used in an orientation or positional relationship indicated in the drawings for convenience in describing the invention and to simplify the description, and are not intended to indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and are therefore not to be considered limiting of the invention.
Furthermore, the terms "first", "second", "element i", "element ii" are used for descriptive purposes only and are not to be construed as indicating or implying a relative importance or implying a number of technical features indicated. Thus, features defined as "first", "second", "element i", "element ii" may explicitly or implicitly include one or more of such features. In the description of the present invention, "plurality" or "a plurality" means two or more unless specifically limited otherwise.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. The anti-settling device for the water and electricity pipe well outside the side wall of the basement in the soft soil area is characterized by comprising a plurality of threading pipes pre-embedded in the side wall of the basement, a platform plate arranged on the outer wall of the upper part of the basement and a hanging plate connected with the bottom surface of the free end of the platform plate, wherein a plurality of power pipes are arranged at the bottom end of the hanging plate, and the number of the threading pipes corresponds to that of the power pipes;
the platform board with the link plate is connected and with the basement lateral wall encloses into a cavity, and the water and electricity pipeline penetrates the threading pipe extremely in the cavity and the bending is placed, the water and electricity pipeline passes again the electric power pipe extremely outside the cavity.
2. The anti-settling device for the hydropower pipe well outside the basement side wall in the soft soil area according to claim 1, wherein a plurality of threading pipes are uniformly distributed and embedded in the basement side wall;
a plurality of electric power pipe evenly distributed set up in the bottom of link plate.
3. The anti-settling device for the hydropower pipe well outside the side wall of the basement in the soft soil area as claimed in claim 2, wherein the threading pipe is a waterproof threading pipe;
the power tube is a waterproof power tube.
4. The anti-settling device for the hydropower pipe well outside the side wall of the basement in the soft soil area as claimed in claim 1, wherein a buttress is arranged between the platform plate and the side wall of the basement.
5. The anti-settling device for the hydropower pipe well outside the basement side wall in the soft soil area according to claim 4, wherein stressed steel bars are connected to the buttress columns and the inner portion of the basement side wall in a penetrating mode.
6. The anti-settling device for the hydropower pipe well outside the side wall of the basement in the soft soil area as claimed in claim 1, wherein the platform plate is a cantilever plate or a cantilever beam.
7. The anti-settling device for the hydropower pipe well outside the side wall of the basement in the soft soil area as claimed in claim 6, wherein the cantilever plate is formed by pouring reinforced concrete.
8. The anti-settling device for the hydropower pipe well outside the side wall of the basement in the soft soil area as claimed in claim 6, wherein the cantilever beam is formed by pouring reinforced concrete.
9. The anti-settling device for the hydropower pipe well outside the basement side wall in the soft soil area according to claim 8, wherein at least two stressed steel bars are arranged on the end face of the cantilever beam along the length direction.
10. The anti-settling device for the hydropower pipe well outside the side wall of the basement in the soft soil area as claimed in claim 1, wherein the hanging plate is formed by pouring concrete.
CN202120416439.8U 2021-02-25 2021-02-25 Subsidence prevention device for basement side wall outer water and electricity pipe well in soft soil area Active CN215053285U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120416439.8U CN215053285U (en) 2021-02-25 2021-02-25 Subsidence prevention device for basement side wall outer water and electricity pipe well in soft soil area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120416439.8U CN215053285U (en) 2021-02-25 2021-02-25 Subsidence prevention device for basement side wall outer water and electricity pipe well in soft soil area

Publications (1)

Publication Number Publication Date
CN215053285U true CN215053285U (en) 2021-12-07

Family

ID=79253677

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120416439.8U Active CN215053285U (en) 2021-02-25 2021-02-25 Subsidence prevention device for basement side wall outer water and electricity pipe well in soft soil area

Country Status (1)

Country Link
CN (1) CN215053285U (en)

Similar Documents

Publication Publication Date Title
US7394023B2 (en) Slack cable arrangement for underground electric service conduit connected to service boxes on the sides of buildings
US4518817A (en) Buried conductor cable energy distribution system with conductor loop enclosure
CN215053285U (en) Subsidence prevention device for basement side wall outer water and electricity pipe well in soft soil area
CN218348052U (en) Anti device that floats of mucky soil layer underground piping
CN206409743U (en) The steel pipe pile-supported structure of underground utilities
US7994426B1 (en) Slack cable arrangement for underground electric service conduit connected to service boxes on the sides of buildings
CN216275828U (en) Building water and electricity pipeline stand alone type prevents subsiding well
JP2869462B2 (en) Optical cable laying method
CN213805417U (en) Protective structure for reinforcing foundation pit excavation soil body close to pile foundation
CN211597797U (en) Two-sided coincide wall window end opening horizontal electromechanical pre-buried spool protection device
CN210562123U (en) Protection architecture of ground is wall built-in fitting even
CN112575811A (en) Comprehensive pipe gallery sinking section with support and assembling method
CN215630172U (en) A bury formula rubber waterstop fixing device in for in basic slab movement joint
CN218322862U (en) Anti seepage device that subsides of outdoor cable shaft of basement
KR100753970B1 (en) Supporting apparatus using pc wire for box in weakness ground
CN210608435U (en) Service wire support watertight fittings
CN218514069U (en) Anti-sedimentation protection structure for isolation switch mechanism box
CN212742631U (en) Cable working well
CN219118255U (en) Reinforcement meter data line binding structure for uplift pile
CN220685778U (en) Landing stage that drain pipe and cable conductor combine together
CN210007309U (en) structure for outdoor slot box to enter indoor
CN216889868U (en) Underground factory building rock wall crane beam structure under unfavorable geological conditions
CN214883733U (en) Slope reinforcing device for foundation building engineering
CN206834685U (en) Light current well lines arrangement
CN217352514U (en) Underground pipeline passes through a fender pile structure

Legal Events