CN215026257U CN202121257864.3U CN202121257864U CN215026257U CN 215026257 U CN215026257 U CN 215026257U CN 202121257864 U CN202121257864 U CN 202121257864U CN 215026257 U CN215026257 U CN 215026257U
Authority
CN
China
Prior art keywords
frame
water storage
wall
storage frame
tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202121257864.3U
Other languages
Chinese (zh)
Inventor
武立超
任立永
路文静
尹莉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Ruichuang Environmental Protection Science & Technology Co ltd
Original Assignee
Tianjin Ruichuang Environmental Protection Science & Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Ruichuang Environmental Protection Science & Technology Co ltd filed Critical Tianjin Ruichuang Environmental Protection Science & Technology Co ltd
Priority to CN202121257864.3U priority Critical patent/CN215026257U/en
Application granted granted Critical
Publication of CN215026257U publication Critical patent/CN215026257U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model belongs to the sludge treatment field especially for the fast sludge treatment sedimentation tank of sedimentation rate, including the cell body, the inside block of cell body is connected with the water storage frame, the inside top spiro union of water storage frame is fixed with a frame, top frame left side inner wall fixedly connected with baffle, the baffle is L shape structure, baffle right side wall with the shunt tubes of a plurality of parallel distribution of fixedly connected with between the inner wall of top frame right side, be fixed with a plurality of parallel distribution between baffle right side wall and the top frame right side inner wall, and with the shunt tubes of baffle intercommunication each other, sewage is let in inside the baffle, then inside the shunt tubes, and the guide plate that the guide is led to the bottom of the pool to flocculent deposit is passed to a plurality of on the shunt tubes again, can lead to the bottom of the pool fast with flocculent deposit for the sedimentation efficiency of mud, shunt sewage simultaneously, make impurity in sewage and the sewage, The sludge is dispersed to different areas inside the water storage frame, so that the floor area of the sedimentation tank can be reduced.

Description

Sludge treatment sedimentation tank with high sedimentation rate
Technical Field
The utility model relates to a sludge treatment field specifically is the fast sludge treatment sedimentation tank of sedimentation rate.
Background
Sewage is a pollutant generated in human activities, and sludge treatment is becoming more and more important in order to protect our global environment, wherein the sludge treatment is a process for purifying sewage to reach the water quality requirement of draining a certain water body or reusing the water body, and a sedimentation tank is one of important components in a sludge treatment system, and the sludge and impurities are removed by standing and precipitating the sewage.
Present sedimentation tank is when using, inside people directly let in sedimentation tank with sewage, then the flocculent precipitate in the sewage is in the inside sediment that naturally stews of sedimentation tank under the rivers effect, consequently the flocculent precipitates completely, need longer flow length, the area that leads to the sedimentation tank is great, sewage is the water pipe through fixed position, let in sedimentation tank inside at fixed position, be close to the sewage in water pipe area and be in the state that flows fast all the time, the sewage of keeping away from the water pipe area is in static state, the slower meeting that flocculent impurity deposits in the sewage reduces treatment effect.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a sludge treatment sedimentation tank that sedimentation rate is fast to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
the sludge treatment sedimentation tank with the high sedimentation rate comprises a tank body, wherein a water storage frame is connected in the tank body in a clamping manner, a top frame is fixedly connected to the top end of the inside of the water storage frame in a threaded manner, a partition plate is fixedly connected to the inner wall of the left side of the top frame and is of an L-shaped structure, a plurality of parallel-distributed shunt pipes are fixedly connected between the right side wall of the partition plate and the inner wall of the right side of the top frame, the liquid inlet ends of the shunt pipes are mutually communicated with the partition plate, a plurality of leakage holes are formed in the outer wall of each shunt pipe, and a guide plate for guiding flocculent sediments to the bottom of the tank is fixedly mounted in each leakage hole; the top frame inner wall bottom fixedly connected with card frame, card frame block is connected inside the water storage frame, the equal threaded connection in water storage frame left and right sides wall top has the bolt, the bolt spiro union is fixed inside the card frame.
As a further aspect of the present invention: the cell body with water storage frame right side wall all sets up corresponding water drainage tank, two water drainage tank all is located top frame below.
As a further aspect of the present invention: the bottom of the drainage groove is an inclined plane.
As a further aspect of the present invention: the bottom of cell body is equipped with the siphon blow off pipe, the top of siphon blow off pipe is equipped with a plurality of blow off pipe branch pipes, the blow off pipe branch pipe runs through cell body, water storage frame, and with cell body, water storage frame sealing connection.
As a further aspect of the present invention: two grooves are formed in the outer side wall of the water storage frame, and the two bolts are located inside the two grooves respectively.
As a further aspect of the present invention: the outer wall of the clamping frame is provided with two fixing holes which are symmetrically distributed, and the two bolts are respectively fixed in the two fixing holes in a threaded manner.
As a further aspect of the present invention: the top end of the top frame is fixedly connected with four lifting lugs which are distributed in a rectangular shape.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses in, cell body internally mounted has fixed water storage frame and top frame together, top frame left side inner wall is fixed with the baffle of L shape, be fixed with a plurality of parallel distribution between baffle right side wall and the top frame right side inner wall, and the shunt tubes that communicates each other with the baffle, in operation, sewage is let in inside the baffle, then it is inside to shunt a plurality of shunt tubes, a plurality of that passes on the shunt tubes again will flocculate the guide plate that deposits to the bottom of the pool direction, can lead flocculent precipitate to the bottom of the pool fast, accelerate the precipitation efficiency of mud, shunt sewage simultaneously, make impurity in sewage and the sewage, mud disperses the different regions of water storage frame inside, can reduce the area of sedimentation tank.
2. The utility model discloses in, the card frame block of top frame inner wall bottom is inside the water storage frame, when the installation, can carry out positioning work to the top frame, then come to fix the top frame at the water storage frame top through two bolts, the installation is dismantled efficiently, the card frame can also block the gap between water storage frame and the top frame simultaneously, can prevent the condition that sewage leaked, the top frame, adopt the disconnect-type design between water storage frame and the cell body, the workman can take out water storage frame and top frame from the cell body is inside alone, and the split is come and is carried out the cleaning work of mud and impurity, workman's operating space has been increased, cleaning effect and efficiency have been improved.
Drawings
FIG. 1 is a schematic view of a sludge treatment sedimentation tank with a high sedimentation rate;
FIG. 2 is a schematic diagram of a top view of a top frame of a sludge treatment sedimentation tank with a high sedimentation rate;
FIG. 3 is a schematic structural view of a top frame in a sludge treatment sedimentation tank with a high sedimentation rate;
fig. 4 is an enlarged schematic view of a portion a in fig. 1.
In the figure: 1. a tank body; 2. a water storage frame; 21. a bolt; 22. a groove; 3. a top frame; 31. a partition plate; 311. a screen frame; 32. a shunt tube; 321. a leak hole; 322. a baffle; 33. clamping a frame; 331. a fixing hole; 34. lifting lugs; 4. a water discharge tank; 5. a siphon blow-off pipe; 51. a sewage branch pipe.
Detailed Description
Referring to fig. 1-4, in the embodiment of the present invention, a sludge treatment sedimentation tank with a high sedimentation rate comprises a tank body 1, a water storage frame 2 is connected to the inside of the tank body 1 in a clamping manner, a top frame 3 is fixed to the top end of the inside of the water storage frame 2 in a threaded manner, a partition plate 31 is fixedly connected to the inner wall of the left side of the top frame 3, the partition plate 31 is in an L-shaped structure, a plurality of parallel distribution flow dividing pipes 32 are fixedly connected between the right side wall of the partition plate 31 and the inner wall of the right side of the top frame 3, the liquid inlet end of the flow dividing pipes 32 is mutually communicated with the partition plate 31, a plurality of leakage holes 321 are formed in the outer wall of the flow dividing pipes 32, a flow guide plate 322 for guiding flocculent sediments to the bottom of the tank is fixedly installed in the leakage holes 321, a clamping frame 33 is fixedly connected to the bottom of the inner wall of the top frame 3, the clamping frame 33 is connected to the inside of the water storage frame 2 in a clamping manner, bolts 21 are screwed to the tops of the left and right side walls of the storage frame 2, a siphon 5 is arranged at the bottom of the tank body 1, the top of siphon blow off pipe 5 is equipped with a plurality of blow off pipe branch pipes 61, and blow off pipe branch pipe 61 runs through cell body 1, water storage frame 2 to with cell body 1, water storage frame 2 sealing connection.
In fig. 1, 2 and 3: the inside of the pool body 1 is provided with a water storage frame 2 and a top frame 3, the top frame 3 is fixed at the top of the water storage frame 2 by two bolts 21 in a screwed way, the installation and the disassembly are convenient, the firmness after the installation of the top frame 3 and the stability in use are improved, the left inner wall of the top frame 3 is fixed with an L-shaped partition plate 31, a plurality of shunt tubes 32 which are distributed in parallel are fixed between the right side wall of the partition plate 31 and the right inner wall of the top frame 3, and the shunt tubes 32 are communicated with the partition plate 31, when the pool works, sewage is introduced into the partition plate 31 and then shunted into the shunt tubes 32, and then passes through a plurality of guide plates which are arranged on the shunt tubes 32 and guide flocculent precipitates to the pool bottom, so that the flocculent precipitates can be quickly guided to the pool bottom, the precipitation efficiency of the sludge is accelerated, after the sludge is precipitated, the sewage is sucked and discharged by a siphon blow-off pipe 5 at the bottom through a sewage discharge branch pipe 51, the discharge work of sewage is convenient, the sewage discharge work can also lead impurities and the sludge in the water and the sludge to be dispersed to different areas inside the water storage frame 2, the condition that a large amount of sludge and impurities are accumulated in the same area can be reduced, and the treatment effect can be improved.
In fig. 1: corresponding water drainage tank 4 has all been seted up with 2 right side walls of water storage frame to cell body 1, two water drainage tank 4 all are located frame 3 below, after the sediment of stewing, the liquid level of the sewage of the top removes water drainage tank 4 departments on the water storage frame 2, sewage can pass water storage frame 2 and the water drainage tank 4 on the cell body 1 and outwards discharge to next treatment facility in, continue to carry out the treatment of sewage, conveniently carry out the discharge work of sewage, water drainage tank 4 bottom is the inclined plane, can improve drainage effect.
In fig. 1, 3 and 4: the bottom of the inner wall of the top frame 3 is fixed with a clamping frame 33, the clamping frame 33 is clamped in the water storage frame 2, when the water storage frame is installed, the top frame 3 can be positioned, the top frame 3 is stably installed on the top of the water storage frame 2, so that the fixing work of the top frame 3 and the water storage frame 2 is carried out, the installation effect and the efficiency are improved, the clamping frame 33 can also block a gap between the water storage frame 2 and the top frame 3, the condition of sewage leakage can be prevented, the outer wall of the clamping frame 33 is provided with two symmetrically distributed fixing holes 331, the two bolts 21 are respectively fixed in the two fixing holes 331 in a screwed mode, after the top frame 3 is positioned on the top of the water storage frame 2, the two bolts 21 are sequentially screwed inwards, namely the two bolts 21 can respectively enter the two fixing holes 331, the bolts 21 are tightly connected in the fixing holes 331 by screwing the bolts 21, and the top frame 3 is further fixed on the top of the water storage frame 2 through the bolts 21, the mounting and dismounting efficiency is high, the connection strength between the top frame 3 and the water storage frame 2 is improved, the outer side wall of the water storage frame 2 is provided with two grooves 22, two bolts 21 are respectively positioned in the two grooves 22, the bolts 21 can completely enter the corresponding grooves 22 after mounting, the outer wall of the water storage frame 2 can be positioned on a plane, the mounting and dismounting work of the water storage frame 2 cannot be influenced, the water storage frame 2 and the top frame 3 can be placed in the pool body 1 after the top frame 3 and the water storage frame 2 are mounted together, then sewage is led in for standing and precipitating work of the sewage, after the work is finished, the top frame 3 can be pulled upwards to take the top frame 3 and the water storage frame 2 out of the pool body 1, then the top frame 3 can be taken down for cleaning work of sludge and impurities, the operation is simple, a separation type design is adopted between the top frame 3, the water storage frame 2 and the pool body 1, a worker can independently take the water storage frame 2 and the top frame 3 out of the pool body 1, and the split is come and is carried out the cleaning work of mud and impurity, make things convenient for the workman to clear up the work, workman's operating space has been increased, workman's the operation degree of difficulty has been reduced, cleaning effect and efficiency have been improved, after the clearance is accomplished, install back water storage frame 2 top with frame 3, then put back water storage frame 2 and top frame 3 inside the cell body 1, can continue to carry out the precipitation work of sewage, 3 top fixedly connected with four lugs 34 that are the rectangular distribution of top frame, the workman can be through mutually supporting between hoisting accessory and lug 34, come top frame 3 and water storage frame 2 to take out from cell body 1 is inside, can improve work efficiency.
The utility model discloses a theory of operation is: during operation, sewage is let in inside the baffle 31, then shunt to inside a plurality of shunt tubes 32, pass the guide plate that a plurality of on shunt tubes 32 will flocculate and deposit to the bottom of the pool direction again, can lead to the bottom of the pool fast flocculent precipitate, accelerate the precipitation efficiency of mud, after the mud deposits, attract the discharge through blowdown branch pipe 51 by siphon blow off pipe 5 of bottom, conveniently carry out the discharge work of sewage, can also make impurity and mud in the sewage disperse to the different regions inside water storage frame 2, can reduce mud, the condition that the impurity is piled up in same region in a large number, can improve the treatment effect, after the work is accomplished, upwards pull the roof frame 3 can take out roof frame 3 and water storage frame 2 from the inside of cell body 1, then take off bolt 21, and upwards pull roof frame 3 and take off roof frame 3, carry out the work of clearing up of mud and impurity, roof frame 3, Adopt the disconnect-type design between water storage frame 2 and the cell body 1, the workman can take out water storage frame 2 and top frame 3 from cell body 1 inside alone to the split is come and is carried out the cleaning work of mud and impurity, makes things convenient for the workman to clear up the work, has increased workman's operating space, has improved clearance effect and efficiency.
The above-mentioned, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (7)

1. The sludge treatment sedimentation tank with the high sedimentation rate comprises a tank body (1) and is characterized in that a water storage frame (2) is connected to the inside of the tank body (1) in a clamping manner, a top frame (3) is fixedly connected to the top end inside the water storage frame (2) in a screw connection manner, a partition plate (31) is fixedly connected to the inner wall of the left side of the top frame (3), the partition plate (31) is of an L-shaped structure, a plurality of parallel-distributed shunt tubes (32) are fixedly connected between the right side wall of the partition plate (31) and the inner wall of the right side of the top frame (3), the liquid inlet ends of the shunt tubes (32) are mutually communicated with the partition plate (31), a plurality of leakage holes (321) are formed in the outer wall of the shunt tubes (32), and a guide plate (322) for guiding flocculent sediments to the bottom of the tank is fixedly installed in the leakage holes (321);
top frame (3) inner wall bottom fixedly connected with card frame (33), card frame (33) block is connected inside water storage frame (2), the equal threaded connection in water storage frame (2) left and right sides wall top has bolt (21), bolt (21) spiro union is fixed inside card frame (33).
2. The sludge treatment sedimentation tank with the high sedimentation rate according to claim 1, wherein the right side walls of the tank body (1) and the water storage frame (2) are provided with corresponding drainage grooves (4), and the two drainage grooves (4) are both positioned below the top frame (3).
3. The sedimentation tank for sludge treatment with high sedimentation rate according to claim 2, wherein the bottom of the drainage tank (4) is a slope.
4. The sludge treatment sedimentation tank with the high sedimentation rate according to claim 1, wherein a siphon sewage pipe (5) is arranged at the bottom of the tank body (1), a plurality of sewage pipe branch pipes (61) are arranged at the top of the siphon sewage pipe (5), and the sewage pipe branch pipes (61) penetrate through the tank body (1) and the water storage frame (2) and are hermetically connected with the tank body (1) and the water storage frame (2).
5. The sludge treatment sedimentation tank with the high sedimentation rate as claimed in claim 1, wherein two grooves (22) are formed in the outer side wall of the water storage frame (2), and the two bolts (21) are respectively positioned in the two grooves (22).
6. The sludge treatment sedimentation tank with the high sedimentation rate as claimed in claim 1, wherein the outer wall of the clamp frame (33) is provided with two symmetrically distributed fixing holes (331), and the two bolts (21) are respectively fixed inside the two fixing holes (331) in a threaded manner.
7. The sludge treatment sedimentation tank with the high sedimentation rate according to claim 1, wherein four lifting lugs (34) are fixedly connected to the top end of the top frame (3) and are distributed in a rectangular shape.
CN202121257864.3U 2021-06-07 2021-06-07 Sludge treatment sedimentation tank with high sedimentation rate Expired - Fee Related CN215026257U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121257864.3U CN215026257U (en) 2021-06-07 2021-06-07 Sludge treatment sedimentation tank with high sedimentation rate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121257864.3U CN215026257U (en) 2021-06-07 2021-06-07 Sludge treatment sedimentation tank with high sedimentation rate

Publications (1)

Publication Number Publication Date
CN215026257U true CN215026257U (en) 2021-12-07

Family

ID=79207897

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121257864.3U Expired - Fee Related CN215026257U (en) 2021-06-07 2021-06-07 Sludge treatment sedimentation tank with high sedimentation rate

Country Status (1)

Country Link
CN (1) CN215026257U (en)

Similar Documents

Publication Publication Date Title
CN215026257U (en) Sludge treatment sedimentation tank with high sedimentation rate
CN217961414U (en) Vertical-flow sedimentation tank exhaust water distributor
CN214344960U (en) High-efficient combination formula inclined plate settler
CN115770419A (en) Vertical inclined tube precipitation structure and application
CN214714591U (en) Along with sedimentation tank of liquid level automatic rising remove superficial mud device
CN213433109U (en) Precipitation equipment for treating wastewater
CN214319429U (en) Horizontal-flow sedimentation tank for sewage environment-friendly treatment
CN210674364U (en) Novel high-efficient water treatment solid-liquid separation device
CN212881431U (en) Sewage precipitation purification filtration system
CN212854808U (en) Small slag flushing slurry pumping pipeline filtering device
CN221479641U (en) Stepped electrochemical water treatment device
CN221358650U (en) Novel recoil device
CN215137179U (en) Novel micro-vortex high-density clarification tank
CN213467072U (en) High-efficient sedimentation tank side direction flow swash plate purifier
CN216366744U (en) Device for preventing inclined tube of inclined tube sedimentation tank from being blocked
CN219423868U (en) Sewage purification equipment for hospital
CN214436743U (en) High-efficient environmental protection sedimentation tank for sewage treatment
CN216946529U (en) Water purification unit and water purification system
CN220749458U (en) Water conservancy drainage structure
CN218686599U (en) Concrete production wastewater recovery device
CN211328325U (en) Sewage solid impurity treatment device
CN214914123U (en) Desulfurizing tower circulating liquid filter equipment
CN221601437U (en) Hydration catalyst recovery unit
CN219376394U (en) Sedimentation tank for concrete sewage treatment device
CN217757142U (en) Sewage treatment purifier of boats and ships

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211207