CN214994621U - Ready-package steel construction based on building energy saving technology - Google Patents

Ready-package steel construction based on building energy saving technology Download PDF

Info

Publication number
CN214994621U
CN214994621U CN202120487919.3U CN202120487919U CN214994621U CN 214994621 U CN214994621 U CN 214994621U CN 202120487919 U CN202120487919 U CN 202120487919U CN 214994621 U CN214994621 U CN 214994621U
Authority
CN
China
Prior art keywords
block
steel
wall
jack
threaded rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120487919.3U
Other languages
Chinese (zh)
Inventor
吕玉祥
郝尚旭
韩东营
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhou Jinhong
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202120487919.3U priority Critical patent/CN214994621U/en
Application granted granted Critical
Publication of CN214994621U publication Critical patent/CN214994621U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model relates to a building ready-package steel construction technical field especially relates to a ready-package steel construction based on building energy saving technology, including first connection steel and second connection steel, the second connection steel sets up in the top of first connection steel, and the outer wall of first connection steel is provided with fixed establishment. This ready-package steel construction based on building energy-saving technology, when connecting, peg graft the inserted block of second connection steel bottom and the first connecting block at first connection steel top center, use the threaded rod to run through the inside second jack of seting up of first connecting block and the first jack of seting up in the inserted block this moment, and because the inner wall of first jack and second jack seted up respectively with threaded rod outer wall assorted screw thread, consequently the threaded rod can pass through first jack and second jack through rotatory mode, and with the central nut inner wall threaded connection in first connecting block right side, this structural connection is convenient, when dismantling, only need take out the threaded rod alright dismantle.

Description

Ready-package steel construction based on building energy saving technology
Technical Field
The utility model relates to a building ready-package steel construction technical field specifically is a ready-package steel construction based on building energy saving technology.
Background
The building on the market at present adopts concrete placement to form mostly, when removing, can produce many smoke and dust, cause the pollution to the urban air, can produce many building rubbish simultaneously, steel construction building steel sheet or shaped steel have replaced reinforced concrete, higher intensity and better shock resistance have, when building the shed, the component of steel construction can batch production preparation, the field installation, can shorten the time limit for a project, and simultaneously, because the reuse of steel, can reduce building rubbish, more green, therefore the wide application is in industrial building and civil engineering.
And present steel construction environmental protection building, the place of fixing is dead connection basically, consequently need be with the help of a large amount of appurtenance when demolising, wastes time and energy to be not convenient for retrieve after demolising.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a ready-package steel construction based on building energy saving technology to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a ready-package steel construction based on building energy saving technology, includes first connection steel and second connection steel, the second connection steel sets up in the top of first connection steel, the outer wall of first connection steel is provided with fixed establishment.
The fixing mechanism comprises a supporting block, a fixing block, a connecting bolt, a first connecting block, an inserting block, a connecting plate, a first inserting hole, a second inserting hole and a threaded rod, the supporting block is fixedly connected to the front top of the first connecting steel, the fixing block is fixedly connected to the front bottom of the second connecting steel, the connecting bolt is arranged inside the fixing block, the first connecting block is fixedly connected to the center of the front top of the first connecting steel, the inserting block is arranged inside the first connecting block, the connecting plate is fixedly connected to the top of the inserting block, the first inserting hole is arranged inside the inserting block, the second inserting hole is arranged inside the first connecting block, and the threaded rod is arranged inside the first connecting block.
Preferably, the supporting blocks are distributed on the left and right sides of the front top of the first connecting steel and the left and right sides of the front top of the second connecting steel, and the fixing blocks are distributed on the left and right sides of the front bottom of the second connecting steel and the left and right sides of the front bottom of the first connecting steel, so that the first connecting steel and the second connecting steel can be conveniently fixed.
Preferably, the connecting bolt penetrates through the fixing block and the supporting block, the penetrating inner wall of the supporting block is provided with threads matched with the outer wall of the connecting bolt, the connecting bolt penetrates through the supporting block conveniently through rotation, the penetrating inner wall of the fixing block is provided with threads matched with the outer wall of the connecting bolt, the connecting bolt penetrates through the fixing block conveniently through rotation, the connecting bolt is in threaded connection with the fixing block and the supporting block through threads, and the supporting block is fixedly connected with the fixing block through the connecting bolt and used for fixing the first connecting steel and the second connecting steel.
Preferably, first link block distributes in the positive top center of first connection steel and the positive top center of second connection steel, the spout has been seted up to first link block inside, the outer wall and the spout inner wall sliding connection of inserted block conveniently take out the inserted block, spout and second jack intercommunication make the threaded rod can run through first link block, one side fixed connection that the inserted block was kept away from to the connecting plate is in the bottom center of second connection steel, the connecting plate distributes in the bottom center of first connection steel and the bottom center of second connection steel, first jack and second jack intercommunication, the use screw rod of being convenient for carries out through connection to first jack and second jack.
Preferably, the inner wall of first jack seted up with threaded rod outer wall assorted screw thread, make things convenient for the threaded rod to run through first jack through the rotation, the inner wall of second jack seted up with threaded rod outer wall assorted screw thread, make things convenient for the threaded rod to run through the second jack through the rotation, the threaded rod passes through screw thread and first link and inserted block threaded connection, the right side center fixedly connected with nut of first link, the outer wall right-hand member and the nut inner wall threaded connection of threaded rod play support and limiting displacement to the threaded rod, avoid long-time use back threaded rod to produce and rock.
Preferably, the inside of first connecting steel is provided with coupling mechanism, coupling mechanism includes first connecting hole, second connecting block, second connecting hole and third connecting block, first connecting hole is seted up in the inside bottom center of first connecting steel, the second connecting block sets up in the inside of second connecting steel, the second connecting hole is seted up in the inside bottom center of second connecting steel, third connecting block fixed connection is in the steel top center is connected to the second, and grafting between second connecting block and the second connecting hole also can provide certain holding power to this structure.
Preferably, the bottom of the second connecting block is fixedly connected with the center of the top of the first connecting steel, the second connecting block is inserted into the second connecting hole, and when the second connecting block needs to be detached, a lot of time does not need to be consumed to detach the first connecting steel and the second connecting steel.
Compared with the prior art, the beneficial effects of the utility model are that:
1. this ready-package steel construction based on building energy-saving technology, when connecting, peg graft the inserted block of second connection steel bottom and the first link at first connection steel top center, just tentatively accomplished being connected between first connection steel and the second connection steel, use the threaded rod to run through the inside second jack of seting up of first link and the first jack of seting up in the inserted block this moment, and because the inner wall of first jack and second jack seted up respectively with threaded rod outer wall assorted screw thread, consequently, the threaded rod can pass through first jack and second jack through rotatory mode, and with the central nut inner wall threaded connection in first link right side, this structural connection is convenient, when dismantling, only need take out the threaded rod alright dismantle.
2. This ready-package steel construction based on building energy-saving technology, accomplish the back of being connected at inserted block and first connecting block, the top of supporting shoe and the bottom laminating of fixed block, use connecting bolt to run through supporting shoe and fixed block, because the supporting shoe is seted up by the inner wall that runs through with connecting bolt outer wall assorted screw thread with the fixed block, consequently, connecting bolt can be through rotatory mode, link together supporting shoe and fixed block, accomplish first connecting steel and second and be connected being connected between the steel, when dismantling, only need take out connecting bolt and threaded rod alright demolish this structure, grafting between second connecting block and the second connecting hole also can provide certain holding power to this structure simultaneously.
Drawings
FIG. 1 is a perspective view of the overall structure of the present invention;
FIG. 2 is a front partial sectional view of the overall structure of the present invention;
FIG. 3 is an enlarged view of the structure at A in FIG. 2;
fig. 4 is the front internal schematic view of the overall structure of the present invention.
In the figure: 1. first connection steel; 2. a second connecting steel; 3. a fixing mechanism; 301. a support block; 302. a fixed block; 303. a connecting bolt; 304. a first connection block; 305. inserting a block; 306. a connecting plate; 307. a first jack; 308. a second jack; 309. a threaded rod; 4. a connecting mechanism; 401. a first connection hole; 402. a second connecting block; 403. a second connection hole; 404. and a third connecting block.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: the utility model provides a ready-package steel construction based on building energy saving technology, includes first connection steel 1 and second connection steel 2, and second connection steel 2 sets up in the top of first connection steel 1, and the outer wall of first connection steel 1 is provided with fixed establishment 3.
The fixing mechanism 3 comprises a supporting block 301, a fixing block 302, a connecting bolt 303, a first connecting block 304, an inserting block 305, a connecting plate 306, a first inserting hole 307, a second inserting hole 308 and a threaded rod 309, wherein the supporting block 301 is fixedly connected to the top of the front surface of the first connecting steel 1, the supporting block 301 is distributed on the left and right sides of the top of the front surface of the first connecting steel 1 and the left and right sides of the top of the front surface of the second connecting steel 2, the fixing block 302 is fixedly connected to the bottom of the front surface of the second connecting steel 2, the fixing block 302 is distributed on the left and right sides of the bottom of the front surface of the second connecting steel 2 and the left and right sides of the bottom of the front surface of the first connecting steel 1, so that the first connecting steel 1 and the second connecting steel 2 can be fixed conveniently, the connecting bolt 303 is arranged inside the fixing block 302, the connecting bolt 303 penetrates through the fixing block 302 and the supporting block 301, the penetrating inner wall of the supporting block 301 is provided with threads matched with the outer wall of the connecting bolt 303, so that the connecting bolt 303 can penetrate through the supporting block 301 by rotation, the inner wall of the fixing block 302 penetrated is provided with threads matched with the outer wall of the connecting bolt 303, so that the connecting bolt 303 penetrates through the fixing block 302 by rotating, the connecting bolt 303 is in threaded connection with the fixing block 302 and the supporting block 301 by threads, the supporting block 301 is fixedly connected with the fixing block 302 by the connecting bolt 303 and is used for fixing the first connecting steel 1 and the second connecting steel 2, the first connecting block 304 is fixedly connected with the center of the top of the front surface of the first connecting steel 1, the first connecting block 304 is distributed at the center of the top of the front surface of the first connecting steel 1 and the center of the top of the front surface of the second connecting steel 2, a chute is arranged in the first connecting block 304, a nut is fixedly connected with the center of the right side of the first connecting block 304, the inserting block 305 is arranged in the first connecting block 304, the outer wall of the inserting block 305 is in sliding connection with the inner wall of the chute, the inserting block 305 is convenient to take out, the disassembling difficulty of the structure is reduced, the connecting plate 306 is fixedly connected with the top of the inserting block 305, one side of the connecting plate 306, which is far away from the insert block 305, is fixedly connected to the bottom center of the second connecting steel 2, the connecting plate 306 is distributed at the bottom center of the first connecting steel 1 and the bottom center of the second connecting steel 2, the first jack 307 is arranged inside the insert block 305, the inner wall of the first jack 307 is provided with a thread matched with the outer wall of the threaded rod 309, the convenient threaded rod 309 penetrates through the first jack 307 through rotation, the second jack 308 is arranged inside the first connecting block 304, the inner wall of the second jack 308 is provided with a thread matched with the outer wall of the threaded rod 309, the convenient threaded rod 309 penetrates through the second jack 308 through rotation, the chute is communicated with the second jack 308, the first jack 307 is communicated with the second jack 308, the threaded rod 309 is conveniently used for penetrating connection of the first jack 307 and the second jack 308, the threaded rod 309 can penetrate through the first connecting block 304, the threaded rod 309 is arranged inside the first connecting block 304 and is in threaded connection with the first connecting block 304 and the insert block 305 through threads, the right end of the outer wall of the threaded rod 309 is in threaded connection with the inner wall of the nut, the threaded rod 309 is supported and limited, the threaded rod 309 is prevented from shaking after long-time use, when in connection, the insert block 305 at the bottom of the second connecting steel 2 is inserted into the first connecting block 304 at the center of the top of the first connecting steel 1, so that the connection between the first connecting steel 1 and the second connecting steel 2 is preliminarily completed, at the moment, the threaded rod 309 penetrates through the second jack 308 arranged in the first connecting block 304 and the first jack 307 arranged in the insert block 305, and the inner walls of the first jack 307 and the second jack 308 are respectively provided with threads matched with the outer wall of the threaded rod 309, so that the threaded rod 309 can pass through the first jack 307 and the second jack 308 in a rotating manner and is in threaded connection with the inner wall of the nut at the center of the right side of the first connecting block 304, the structure is convenient to connect, and when in disassembly, the structure can be disassembled only by taking out the threaded rod 309, after the insertion block 305 is connected with the first connecting block 304, the top of the supporting block 301 is attached to the bottom of the fixing block 302, the connecting bolt 303 penetrates through the supporting block 301 and the fixing block 302, and the inner wall, through which the supporting block 301 and the fixing block 302 penetrate, is provided with threads matched with the outer wall of the connecting bolt 303, so that the connecting bolt 303 can connect the supporting block 301 and the fixing block 302 together in a rotating mode, connection between the first connecting steel 1 and the second connecting steel 2 is completed, and when the structure is disassembled, the connecting bolt 303 and the threaded rod 309 only need to be taken out, so that the structure can be disassembled.
The inside of first connecting steel 1 is provided with coupling mechanism 4, coupling mechanism 4 includes first connecting hole 401, second connecting block 402, second connecting hole 403 and third connecting block 404, first connecting hole 401 is seted up in the inside bottom center of first connecting steel 1, second connecting block 402 sets up in the inside of second connecting steel 2, the bottom of second connecting block 402 and the top center fixed connection of first connecting steel 1, second connecting hole 403 is seted up in the inside bottom center of second connecting steel 2, third connecting block 404 fixed connection is in the top center of second connecting steel 2, second connecting block 402 pegs graft with second connecting hole 403, when needs dismantle, need not consume many times and dismantle first connecting steel 1 and second connecting steel 2, peg graft between second connecting block 402 and the second connecting hole 403 also can provide certain holding power to this structure.
When in use, the insertion block 305 at the bottom of the second connecting steel 2 is inserted into the first connecting block 304 at the center of the top of the first connecting steel 1, so that the connection between the first connecting steel 1 and the second connecting steel 2 is primarily completed, at this time, the threaded rod 309 is used to penetrate through the second insertion hole 308 formed in the first connecting block 304 and the first insertion hole 307 formed in the insertion block 305, and the inner walls of the first insertion hole 307 and the second insertion hole 308 are respectively provided with threads matched with the outer wall of the threaded rod 309, so that the threaded rod 309 can pass through the first insertion hole 307 and the second insertion hole 308 in a rotating manner and is in threaded connection with the inner wall of the nut at the right side center of the first connecting block 304, after the insertion block 305 is connected with the first connecting block 304, the top of the supporting block 301 is attached to the bottom of the fixing block 302, the connecting bolt 303 is used to penetrate through the supporting block 301 and the fixing block 302, and the inner wall of the supporting block 301 and the fixing block 302 are provided with threads matched with the outer wall of the connecting bolt 303, therefore, the connecting bolt 303 can connect the supporting block 301 and the fixing block 302 together in a rotating manner, and the connection between the first connecting steel 1 and the second connecting steel 2 is completed.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a ready-package steel construction based on building energy saving technology, includes first connecting steel (1) and second connecting steel (2), its characterized in that: the second connecting steel (2) is arranged at the top of the first connecting steel (1), and the outer wall of the first connecting steel (1) is provided with a fixing mechanism (3);
the fixing mechanism (3) comprises a supporting block (301), a fixing block (302), a connecting bolt (303), a first connecting block (304), an inserting block (305), a connecting plate (306), a first inserting hole (307), a second inserting hole (308) and a threaded rod (309), the supporting block (301) is fixedly connected to the top of the front face of the first connecting steel (1), the fixing block (302) is fixedly connected to the bottom of the front face of the second connecting steel (2), the connecting bolt (303) is arranged inside the fixing block (302), the first connecting block (304) is fixedly connected to the center of the top of the front face of the first connecting steel (1), the inserting block (305) is arranged inside the first connecting block (304), the connecting plate (306) is fixedly connected to the top of the inserting block (305), the first inserting hole (307) is arranged inside the inserting block (305), the second inserting hole (308) is arranged inside the first connecting block (304), the threaded rod (309) is arranged inside the first connecting block (304).
2. The quick-assembly steel structure based on the building energy-saving technology is characterized in that: the supporting blocks (301) are distributed on the left and right sides of the top of the front face of the first connecting steel (1) and the left and right sides of the top of the front face of the second connecting steel (2), and the fixing blocks (302) are distributed on the left and right sides of the bottom of the front face of the second connecting steel (2) and the left and right sides of the bottom of the front face of the first connecting steel (1).
3. The quick-assembly steel structure based on the building energy-saving technology is characterized in that: the supporting block fixing device is characterized in that the connecting bolt (303) penetrates through the fixing block (302) and the supporting block (301), the penetrating inner wall of the supporting block (301) is provided with threads matched with the outer wall of the connecting bolt (303), the penetrating inner wall of the fixing block (302) is provided with threads matched with the outer wall of the connecting bolt (303), the connecting bolt (303) is in threaded connection with the fixing block (302) and the supporting block (301) through the threads, and the supporting block (301) is fixedly connected with the fixing block (302) through the connecting bolt (303).
4. The quick-assembly steel structure based on the building energy-saving technology is characterized in that: first connecting block (304) distribute in first connecting steel (1) positive top center and the positive top center of second connecting steel (2), the spout has been seted up to first connecting block (304) inside, the outer wall and the spout inner wall sliding connection of inserted block (305), spout and second jack (308) intercommunication, one side fixed connection in the bottom center of second connecting steel (2) that inserted block (305) was kept away from in connecting plate (306), connecting plate (306) distribute in the bottom center of first connecting steel (1) and the bottom center of second connecting steel (2), first jack (307) and second jack (308) intercommunication.
5. The quick-assembly steel structure based on the building energy-saving technology is characterized in that: the inner wall of first jack (307) seted up with threaded rod (309) outer wall assorted screw thread, the inner wall of second jack (308) seted up with threaded rod (309) outer wall assorted screw thread, threaded rod (309) pass through screw thread and first connecting block (304) and inserted block (305) threaded connection, the right side center fixedly connected with nut of first connecting block (304), the outer wall right-hand member and the nut inner wall threaded connection of threaded rod (309).
6. The quick-assembly steel structure based on the building energy-saving technology is characterized in that: the inside of first connecting steel (1) is provided with coupling mechanism (4), coupling mechanism (4) are including first connecting hole (401), second connecting block (402), second connecting hole (403) and third connecting block (404), first connecting hole (401) are seted up in the inside bottom center of first connecting steel (1), second connecting block (402) set up in the inside of second connecting steel (2), second connecting hole (403) are seted up in the inside bottom center of second connecting steel (2), third connecting block (404) fixed connection is in second connecting steel (2) top center.
7. The quick-assembly steel structure based on the building energy-saving technology is characterized in that: the bottom of the second connecting block (402) is fixedly connected with the center of the top of the first connecting steel (1), and the second connecting block (402) is inserted into the second connecting hole (403).
CN202120487919.3U 2021-03-08 2021-03-08 Ready-package steel construction based on building energy saving technology Active CN214994621U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120487919.3U CN214994621U (en) 2021-03-08 2021-03-08 Ready-package steel construction based on building energy saving technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120487919.3U CN214994621U (en) 2021-03-08 2021-03-08 Ready-package steel construction based on building energy saving technology

Publications (1)

Publication Number Publication Date
CN214994621U true CN214994621U (en) 2021-12-03

Family

ID=79156036

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120487919.3U Active CN214994621U (en) 2021-03-08 2021-03-08 Ready-package steel construction based on building energy saving technology

Country Status (1)

Country Link
CN (1) CN214994621U (en)

Similar Documents

Publication Publication Date Title
CN201162344Y (en) Wide-face combined steel formwork
CN211037295U (en) Quick-release wall for assembly type building construction
CN214994621U (en) Ready-package steel construction based on building energy saving technology
CN210086553U (en) Dry-type connected precast concrete wall and foundation connection node
CN213174309U (en) Quick-release wall for assembly type building construction
CN201045219Y (en) Simple partition in house
CN212104034U (en) Prefabricated combined underground continuous wall
CN214531913U (en) A template structure for dysmorphism structure is chosen board and is pour
CN205063526U (en) Assembled enclosure with preparation of building rubbish
CN211228873U (en) Building steel structure connecting piece
CN208857997U (en) A kind of attachment device of green assembled architecture light steel wall
CN211081119U (en) Bearing support for construction building
CN209799347U (en) Adjustable aluminum alloy composite building template
CN110552426A (en) Building steel structure connecting piece
CN209924583U (en) Plug-in connection type movable enclosing wall
CN217924878U (en) Quick connecting structure between aluminum alloy template and water supply pipe pressure tank
CN213774446U (en) Template for building engineering convenient to dismantle
CN216766252U (en) Cross-floor and cross-column rod piece structure in steel structure assembly type house
CN214574609U (en) Assembled building reinforced concrete member
CN220928671U (en) Outer frame tie point fixing tool at gable
CN210887575U (en) Connecting joint of hidden bracket frame assembly type concrete beam column
CN220790217U (en) Connection structure of double-deck curtain
CN113668722B (en) Light thermal insulation board made of fly ash
CN219118407U (en) Connection structure of energy-saving environment-friendly building board
CN215631681U (en) Plugging mold for grouting of assembled PC wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhou Jinhong

Inventor after: Cao Haikun

Inventor after: Yang Zhong

Inventor after: Li Long

Inventor after: Lv Yuxiang

Inventor after: Hao Shangxu

Inventor after: Han Dongying

Inventor before: Lv Yuxiang

Inventor before: Hao Shangxu

Inventor before: Han Dongying

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240415

Address after: Room 386, JT Gate, No. 3-8 Postal Road, Lindian Town, Lindian County, Daqing City, Heilongjiang Province, 166300

Patentee after: Zhou Jinhong

Country or region after: China

Address before: 272100 No. 402, unit 1, building 1, building 4, Xianying Road, Rencheng District, Jining City, Shandong Province

Patentee before: Lv Yuxiang

Country or region before: China