CN214947344U - Municipal administration green drainage pipe - Google Patents

Municipal administration green drainage pipe Download PDF

Info

Publication number
CN214947344U
CN214947344U CN202120310031.2U CN202120310031U CN214947344U CN 214947344 U CN214947344 U CN 214947344U CN 202120310031 U CN202120310031 U CN 202120310031U CN 214947344 U CN214947344 U CN 214947344U
Authority
CN
China
Prior art keywords
pipe
aperture
settling tank
holes
tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120310031.2U
Other languages
Chinese (zh)
Inventor
杨可
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Biao Rui Construction Engineering Co ltd
Original Assignee
Yunnan Biao Rui Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Biao Rui Construction Engineering Co ltd filed Critical Yunnan Biao Rui Construction Engineering Co ltd
Priority to CN202120310031.2U priority Critical patent/CN214947344U/en
Application granted granted Critical
Publication of CN214947344U publication Critical patent/CN214947344U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sink And Installation For Waste Water (AREA)

Abstract

The utility model relates to the technical field of drainage pipelines, in particular to a municipal green drainage pipeline, which comprises a settling tank, wherein a settling tank is arranged in the middle of the settling tank, communicating pipes are embedded on two side surfaces of the settling tank, a first limiting ring is arranged on the outer wall of the circumference on each communicating pipe, an inserting pipe is also arranged at the end part of each communicating pipe, a third limiting ring is also arranged on the outer wall of the circumference of each inserting pipe, a drainage pipe is also arranged at the other end of each inserting pipe, second limiting rings are arranged at the positions, close to the two ends, on the outer wall of the circumference of the drainage pipe, and a box cover is arranged at the top of the settling tank; this municipal administration green drainage pipe, the cooperation of setting tank and precipitation tank, be convenient for will deposit through the particulate matter in the drain pipe, prevent to accumulate and block up drainage pipe, the drain pipe with communicating pipe through the pipe aggregate erection of pegging graft, convenient quick installation combination uses, setting tank top cooperation case lid protects the setting tank is inside, avoids external environment to the influence that causes of inside, prevents that external dust granule from getting into inside, causes to block up the influence.

Description

Municipal administration green drainage pipe
Technical Field
The utility model relates to a drainage pipe technical field specifically is a municipal administration green drainage pipe.
Background
Rainwater and sewage pipelines under municipal roads, namely commonly called as 'sewer pipelines', are generally called as municipal drainage pipelines in engineering, and different pipelines such as electric power, communication, coal gas, water supply, drainage pipelines and the like are generally arranged according to the current situation of facilities under the municipal roads;
general municipal administration green drainage pipe, single structure, difficult combined use, and long-time use, drainage pipe blocks up easily, can not deposit the particulate matter in drainage pipe, is not convenient for clear up the use to the particulate matter of inside.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a municipal administration green drainage pipe to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
a municipal green environment-friendly drainage pipeline comprises a settling tank, wherein a settling tank is arranged in the middle of the settling tank, communicating pipes communicated with the interior are embedded in the two side faces of the settling tank near the middle positions, first annular grooves are formed in the end parts of the communicating pipes, a first limiting ring is arranged on the outer wall of the circumference of one end of each communicating pipe, which is far away from the settling tank, a plurality of first through holes are formed in the first limiting ring, an inserting pipe is further arranged at the end part of each communicating pipe, a third limiting ring is further arranged on the outer wall of the circumference of the inserting pipe, a third through hole is further formed in the position, corresponding to the first through hole, of the third limiting ring, a drainage pipe is further arranged at the other end of the inserting pipe, second annular grooves are formed in the two end parts of the drainage pipe, second limiting rings are arranged on the outer wall of the circumference of the drainage pipe near the two end parts, and second through holes are further formed in the positions, corresponding to the third through holes, of the second limiting rings, and a second fastening bolt is arranged in the second through hole, and a box cover is arranged at the top of the settling box.
Preferably, round holes are formed in the edge of the upper surface of the box cover close to the middle of the box cover, first fastening bolts are arranged in the round holes, and threaded holes are formed in the upper surface of the settling box and in positions corresponding to the round holes.
Preferably, the width of case lid and the width looks adaptation of setting tank, the aperture of round hole and the aperture looks adaptation of screw hole, the aperture of screw hole and the diameter looks adaptation of first fastening bolt, first fastening bolt passes the round hole to with screw hole threaded connection.
Preferably, communicating pipe and settling tank butt fusion are fixed, first spacing ring and communicating pipe be the integrated into one piece structure, first perforation is the equidistant distribution of annular.
Preferably, the second spacing ring is the integrated into one piece structure with the drain pipe, the second is perforated and is the annular equidistant distribution, the fenestrate aperture of second and second fastening bolt's diameter looks adaptation, set the nut on the second fastening bolt tip.
Preferably, the third limiting ring and the inserting pipe are of an integrally formed structure, the third through holes are distributed in an annular shape at equal intervals, the aperture of the third through hole is matched with the aperture of the second through hole, and the aperture of the third through hole is matched with the aperture of the first through hole.
Preferably, the width of the insertion pipe is matched with the width of the first limiting ring, the width of the insertion pipe is also matched with the width of the second limiting ring, and the insertion pipe is respectively in insertion fit with the first limiting ring and the second limiting ring.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses the cooperation of setting tank and precipitation tank is convenient for will deposit through the particulate matter in the drain pipe, prevents to accumulate and blocks up drainage pipe, and the drain pipe is through the pipe aggregate erection of pegging graft with communicating pipe, and convenient quick installation makes up the use, and it is more convenient to let dismantle the change, and setting tank top cooperation case lid protects the setting tank is inside, avoids external environment to the influence that causes of inside, prevents that external dust granule from getting into inside, causes to block up the influence.
2. The utility model discloses grafting pipe one end and the cooperation of pegging graft of the first ring channel on communicating pipe, the cooperation of pegging graft of the second ring channel that the other end was served with the drain pipe one, the leakproofness of connection is increased, passing second perforation, third perforation and first perforation in proper order through second fastening bolt, under the cooperation of nut, fixed drain pipe, grafting pipe and communicating pipe increase holistic stability.
Drawings
FIG. 1 is a schematic view of the overall structure of the municipal green environment-friendly drainage pipeline of the present invention;
FIG. 2 is a schematic view of the exploded structure of the municipal green environmental protection drainage pipeline of the present invention;
FIG. 3 is a schematic view of the frame structure of the settling tank of the present invention;
fig. 4 is a schematic view of the structure of the drain pipe frame of the present invention.
The various reference numbers in the figures mean:
1. a settling tank; 10. a settling tank; 11. a threaded hole;
2. a box cover; 20. a circular hole; 21. a first fastening bolt;
3. a communicating pipe; 30. a first annular groove; 31. a first limit ring; 310. a first perforation;
4. a drain pipe; 40. a second annular groove; 41. a second stop collar; 410. a second perforation; 411. a second fastening bolt;
5. inserting a pipe; 50. a third limit ring; 500. and a third perforation.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and to simplify the description, but do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore should not be construed as limiting the present invention.
Furthermore, the terms "first", "second", "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, features defined as "first", "second", "third" may explicitly or implicitly include one or more of the features. In the description of the present invention, "a plurality" means at least two, e.g., two, three, etc., unless specifically limited otherwise.
Referring to fig. 1-4, the present invention provides a technical solution:
a municipal green environment-friendly drainage pipeline comprises a settling tank 1, a settling tank 10 is arranged in the middle of the settling tank 1, communicating pipes 3 communicated with the interior are embedded on two side surfaces of the settling tank 1 and close to the middle positions, first annular grooves 30 are formed on the end parts of the communicating pipes 3, first limiting rings 31 are arranged on the outer circumferential walls of the communicating pipes 3 far away from one end of the settling tank 1, a plurality of first through holes 310 are formed in the first limiting rings 31, inserting pipes 5 are further arranged at the end parts of the communicating pipes 3, third limiting rings 50 are further arranged on the outer circumferential walls of the inserting pipes 5, third through holes 500 are further formed in the third limiting rings 50 and correspond to the first through holes 310, a drain pipe 4 is further arranged at the other end of the inserting pipes 5, second annular grooves 40 are formed at two end parts of the drain pipe 4, second limiting rings 41 are further arranged at two end parts of the outer circumferential walls of the drain pipe 4 and close to the two end parts, and second through holes 410 are further formed in the second limiting rings 41 and correspond to the third through holes 500, the second through hole 410 is provided with a second fastening bolt 411, and the top of the settling tank 1 is provided with a tank cover 2.
In this embodiment, 2 upper surface edges of case lid are close to the intermediate position and all have seted up round hole 20, all are equipped with first fastening bolt 21 in the round hole 20, and threaded hole 11 is still seted up with the position that round hole 20 corresponds to 1 upper surface of setting tank, and case lid 2 is convenient for manually install fixedly under first fastening bolt 21's cooperation.
Specifically, the width of case lid 2 and the width looks adaptation of setting tank 1, the aperture of round hole 20 and the aperture looks adaptation of screw hole 11, the aperture of screw hole 11 and the diameter looks adaptation of first fastening bolt 21, first fastening bolt 21 passes round hole 20 to with 11 threaded connection of screw hole, convenient to detach changes the use, increase setting tank 1 leakproofness.
Further, communicating pipe 3 is fixed with the butt fusion of settling tank 1, and first spacing ring 31 is the integrated into one piece structure with communicating pipe 3, and first perforation 310 is the equidistant distribution of annular, increases the stability of being connected of communicating pipe 3 and settling tank 1.
Secondly, second spacing ring 41 is the integrated into one piece structure with drain pipe 4, and second perforation 410 is the annular equidistant distribution, and the aperture of second perforation 410 and the diameter looks adaptation of second fastening bolt 411, the last nut that sets of second fastening bolt 411 end, second fastening bolt 411 and nut cooperation are convenient for the composite set use.
It should be noted that the third limiting ring 50 and the inserting pipe 5 are integrally formed, the third through holes 500 are annularly and equidistantly distributed, the aperture of the third through hole 500 is matched with the aperture of the second through hole 410, and the aperture of the third through hole 500 is matched with the aperture of the first through hole 310, so that the second fastening bolt 411 can be conveniently inserted, combined and fixed.
It is worth supplementing that the width of the inserting pipe 5 is matched with the width of the first limiting ring 31, the width of the inserting pipe 5 is also matched with the width of the second limiting ring 41, the inserting pipe 5 is respectively matched with the first limiting ring 31 and the second limiting ring 41 in an inserting manner, and under the matching of the inserting pipe 5, the drainage pipe 4 and the communicating pipe 3 can be conveniently and rapidly combined to be connected with a corresponding drainage pipeline.
The municipal administration green drainage pipe of this embodiment is when using, the user is manual with the installation that precipitation tank 1 corresponds on the municipal road of the construction that needs, peg graft pipe 5 one end and peg graft with communicating pipe 3 on first ring channel 30, the other end is pegged graft with the one-ended second ring channel 40 of drain pipe 4, drain pipe 4 is connected with precipitation tank 1 through peg graft pipe 5, then manually wear 410 to penetrate second fastening bolt 411 from the second in proper order, through third perforation 500, and wear out from first perforation 310, fix at the cooperation nut, quick stable aggregate erection drain pipe 4 and precipitation tank 1, the end user is with case lid 2 and 1 fixed connection of precipitation tank, when needs clearance inside precipitate, the user is manual opens case lid 2, clear up the particulate matter inside precipitation tank 10, prevent that inside particulate matter from blockking up the pipeline.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It should be understood by those skilled in the art that the present invention is not limited by the above embodiments, and the description in the above embodiments and the description is only preferred examples of the present invention, and is not intended to limit the present invention, and that the present invention can have various changes and modifications without departing from the spirit and scope of the present invention, and these changes and modifications all fall into the scope of the claimed invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (7)

1. The utility model provides a municipal administration green drainage pipe, includes setting tank (1), its characterized in that: a settling tank (10) is arranged in the middle of the settling tank (1), communicating pipes (3) communicated with the interior are embedded on two side faces of the settling tank (1) close to the middle positions, first annular grooves (30) are formed in the end portions of the communicating pipes (3), first limiting rings (31) are arranged on the outer walls of the circumferences of the communicating pipes (3) far away from one end of the settling tank (1), a plurality of first through holes (310) are formed in the first limiting rings (31), inserting pipes (5) are further arranged at the end portions of the communicating pipes (3), third limiting rings (50) are further arranged on the outer walls of the circumferences of the inserting pipes (5), third through holes (500) are further formed in the positions, corresponding to the first through holes (310), of the third limiting rings (50), a drain pipe (4) is further arranged at the other end of the inserting pipes (5), and second annular grooves (40) are formed at two ends of the drain pipe (4), drain pipe (4) circumference outer wall is gone up and is close to both ends department and all be equipped with second spacing ring (41), second perforation (410) have still been seted up with the position that third perforation (500) correspond on second spacing ring (41), be equipped with second fastening bolt (411) in the second perforation (410), setting tank (1) top is equipped with case lid (2).
2. The municipal green environment-friendly drainage pipeline according to claim 1, wherein: round hole (20) have all been seted up near the intermediate position in case lid (2) upper surface edge, all be equipped with first fastening bolt (21) in round hole (20), threaded hole (11) are still seted up with the position that round hole (20) correspond to on settling tank (1) upper surface.
3. The municipal green environment-friendly drainage pipeline according to claim 2, wherein: the width of case lid (2) and the width looks adaptation of setting tank (1), the aperture of round hole (20) and the aperture looks adaptation of screw hole (11), the aperture of screw hole (11) and the diameter looks adaptation of first fastening bolt (21), round hole (20) are passed in first fastening bolt (21) to with screw hole (11) threaded connection.
4. The municipal green environment-friendly drainage pipeline according to claim 1, wherein: communicating pipe (3) and setting tank (1) butt fusion are fixed, first spacing ring (31) and communicating pipe (3) are the integrated into one piece structure, first perforation (310) are the equidistant distribution of annular.
5. The municipal green environment-friendly drainage pipeline according to claim 1, wherein: second spacing ring (41) and drain pipe (4) are integrated into one piece structure, second perforation (410) are the annular equidistant distribution, the aperture of second perforation (410) and the diameter looks adaptation of second fastening bolt (411), set the nut on second fastening bolt (411) end.
6. The municipal green environment-friendly drainage pipeline according to claim 1, wherein: the third limiting ring (50) and the insertion pipe (5) are of an integrally formed structure, the third through holes (500) are distributed in an annular shape at equal intervals, the aperture of the third through holes (500) is matched with the aperture of the second through holes (410), and the aperture of the third through holes (500) is matched with the aperture of the first through holes (310).
7. The municipal green environment-friendly drainage pipeline according to claim 1, wherein: the width of the insertion pipe (5) is matched with the width of the first limiting ring (31), the width of the insertion pipe (5) is also matched with the width of the second limiting ring (41), and the insertion pipe (5) is respectively matched with the first limiting ring (31) and the second limiting ring (41) in an insertion mode.
CN202120310031.2U 2021-02-03 2021-02-03 Municipal administration green drainage pipe Active CN214947344U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120310031.2U CN214947344U (en) 2021-02-03 2021-02-03 Municipal administration green drainage pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120310031.2U CN214947344U (en) 2021-02-03 2021-02-03 Municipal administration green drainage pipe

Publications (1)

Publication Number Publication Date
CN214947344U true CN214947344U (en) 2021-11-30

Family

ID=79120083

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120310031.2U Active CN214947344U (en) 2021-02-03 2021-02-03 Municipal administration green drainage pipe

Country Status (1)

Country Link
CN (1) CN214947344U (en)

Similar Documents

Publication Publication Date Title
CN214947344U (en) Municipal administration green drainage pipe
KR200389196Y1 (en) Connecting pipe using flange
CN215137632U (en) Pipeline filter equipment for building plumbing
CN206786216U (en) Used in construction drainage plough groove type pressure ring is flexibly connected HDPE plumbing installations
CN207715926U (en) A kind of novel PPR pipe
KR100772683B1 (en) Assembly type precast manhole
CN206859264U (en) A kind of multi-channel energy-saving safety manhole joint design
CN211175657U (en) Municipal administration drainage sewage pipes
CN105402499A (en) Drain pipe connecting piece and pipe connecting structure
CN212405389U (en) Municipal administration drain pipe fitting block dirty structure
KR102043705B1 (en) Easily detachable water and sewer conduit of closed type
CN211525781U (en) Building water supply and drainage pipeline convenient to install and connect
CN210318919U (en) Assembled fitment feed pipe connection structure
CN204081306U (en) Outdoor rain pipe syndeton
CN203585603U (en) FNPP-modified enhancing dual-wall corrugated pipe
KR20190074056A (en) Drain connection joint
CN207316327U (en) A kind of municipal administration supplying drainage pipeline connecting structure
CN211312753U (en) Municipal works drainage pipe
CN216475451U (en) Inspection well convenient for connecting pipelines
CN216408006U (en) Anticorrosive antiseep connecting piece of water supply and drainage pipeline
CN210216649U (en) Municipal works's water supply and drainage pipe mounting structure
CN202066547U (en) Water meter connecting pipe with plurality of branch pipes
CN211175772U (en) Novel building drain pipe connection structure
KR102469048B1 (en) Connection structure of water and sewer conduit
CN212691141U (en) Sewage pipeline connecting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant