CN214786538U - Interim rail guard of construction is built in room convenient to dismouting - Google Patents

Interim rail guard of construction is built in room convenient to dismouting Download PDF

Info

Publication number
CN214786538U
CN214786538U CN202120489485.0U CN202120489485U CN214786538U CN 214786538 U CN214786538 U CN 214786538U CN 202120489485 U CN202120489485 U CN 202120489485U CN 214786538 U CN214786538 U CN 214786538U
Authority
CN
China
Prior art keywords
support frame
fixedly connected
protective guard
convenient
lateral wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120489485.0U
Other languages
Chinese (zh)
Inventor
陈佳盼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Sijian Construction Group Co Ltd
Original Assignee
Nantong Sijian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Sijian Construction Group Co Ltd filed Critical Nantong Sijian Construction Group Co Ltd
Priority to CN202120489485.0U priority Critical patent/CN214786538U/en
Application granted granted Critical
Publication of CN214786538U publication Critical patent/CN214786538U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Tents Or Canopies (AREA)

Abstract

The utility model discloses a temporary protective guard of construction is built in room convenient to dismouting, support frame including two symmetry settings, two the connecting block that two symmetries of the equal fixedly connected with of one side lateral wall that the support frame is close to each other set up, and the equal fixedly connected with location axle of the last lateral wall of connecting block, two be equipped with the rail guard body between the support frame, and the equal fixedly connected with connecting strip of the upper and lower both sides lateral wall of rail guard body, and the both ends of connecting strip all cup joint at the epaxial platform in location. This interim rail guard of construction is built in room convenient to dismouting through setting up locating pin and connecting strip, when needs install the device, at first with the most advanced this soil of inserting of location on the support frame inside, then through putting up the connecting strip cover on the locating pin, has realized the installation work of rail guard body like this, convenient operation, speed is very fast.

Description

Interim rail guard of construction is built in room convenient to dismouting
Technical Field
The utility model relates to a construction technical field specifically is a temporary rail guard of construction is built in room convenient to dismouting.
Background
The building engineering refers to an engineering entity formed by the construction of various building constructions and their auxiliary facilities and the installation of lines, pipelines and equipment matched with them. The house building comprises a top cover, beam columns, walls, a foundation and a building body, wherein the roof cover, the beam columns, the walls and the foundation can form an internal space, so that the requirements of people on production, living, learning, public activities and the like are met, and the house building comprises a factory building, a theater, a hotel, a shop, a school, a hospital, a house and the like; the 'auxiliary facilities' refer to water towers, bicycle sheds, pools and the like which are matched with the house building. The 'installation of lines, pipelines and equipment' refers to the installation activities of the lines, pipelines and equipment such as electricity, water supply and drainage, communication, elevators and the like which are matched with the building construction and the auxiliary facilities thereof. With the rapid development of urbanization and modern industry, more and more high-rise and super high-rise buildings stand from cities. In the house building construction process, temporary guard rails are usually arranged around a construction site, so that pedestrians are prevented from approaching the temporary guard rails, and the construction safety and the construction closure are improved.
However, the temporary guard railing for building construction in the existing house is inconvenient to disassemble and assemble, and the occupied space is large when the guard railing is not used, so that the storage effect is influenced.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a temporary protective guard of construction is built in room convenient to dismouting has solved the problem that proposes in the above-mentioned background art.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a temporary protective guard of construction is built in room convenient to dismouting, includes the support frame that two symmetries set up, two the connecting block that two symmetries of the equal fixedly connected with of one side lateral wall that the support frame is close to each other set up, and the equal fixedly connected with location axle of the last lateral wall of connecting block, two be equipped with the rail guard body between the support frame, and the equal fixedly connected with connecting strip of the upper and lower both sides lateral wall of rail guard body, and the both ends of connecting strip all cup joint at the epaxial platform in location.
Optionally, the two ends of the connecting strip are provided with positioning holes, the positioning shaft penetrates through the positioning holes, and the positioning shaft and the positioning holes are in clearance fit.
Optionally, the guard rail body is provided with a plurality of strip-shaped openings which are equidistantly arranged, and the strip-shaped openings are linearly distributed in the horizontal direction.
Optionally, the lower side wall of the support frame is fixedly connected with two symmetrically arranged positioning tips, and the positioning tips are in a circular truncated cone shape.
Optionally, the side wall of one of the support frames is provided with two symmetrically arranged positioning grooves.
Optionally, the other side wall of the supporting frame is fixedly connected with two symmetrically arranged positioning pins, and the positioning grooves are matched with the positioning pins.
(III) advantageous effects
The utility model provides a temporary protective guard of construction is built in room convenient to dismouting possesses following beneficial effect:
1. this interim rail guard of construction is built in room convenient to dismouting through setting up locating pin and connecting strip, when needs install the device, at first with the most advanced this soil of inserting of location on the support frame inside, then through putting up the connecting strip cover on the locating pin, has realized the installation work of rail guard body like this, convenient operation, speed is very fast.
2. This interim rail guard of construction is built in room convenient to dismouting through setting up constant head tank and location axle, when not using the device, inserts the location axle on one of them support frame inside the constant head tank of another support frame, has just so realized connecting between two support frames, saves the space of accomodating.
Drawings
Fig. 1 is a front perspective structure view of a temporary protective guard for building construction, which is convenient to disassemble and assemble;
fig. 2 is a structural diagram of a temporary protective guard for building construction at a position a, which is convenient for disassembly and assembly;
fig. 3 is the utility model provides a room is built and is constructed interim protective guard's rear view stereogram is convenient for dismouting.
In the figure: 1. a support frame; 2. a guard rail body; 3. positioning the tip; 4. a connecting strip; 5. a strip-shaped opening; 6. positioning pins; 7. positioning a groove; 8. connecting blocks; 9. and (5) positioning the shaft.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1 to 3, the present invention provides a technical solution: a temporary protective guard for house construction convenient to disassemble and assemble comprises two symmetrically arranged support frames 1, wherein the lower side wall of each support frame 1 is fixedly connected with two symmetrically arranged positioning tips 3, each positioning tip 3 is in a round table shape, one side wall of each support frame 1, which is close to each other, is fixedly connected with two symmetrically arranged connecting blocks 8, the upper side wall of each connecting block 8 is fixedly connected with a positioning shaft 9, a protective guard body 2 is arranged between the two support frames 1, the upper side wall and the lower side wall of each protective guard body 2 are fixedly connected with connecting strips 4, two ends of each connecting strip 4 are sleeved on the positioning shafts 9, positioning holes are formed in two ends of each connecting strip 4, each positioning shaft 9 penetrates through each positioning hole, the positioning shafts 9 and the positioning holes are in clearance fit, a plurality of strip-shaped openings 5 which are arranged at equal intervals are formed in the protective guard body 2, and the strip-shaped openings 5 are linearly distributed in the horizontal direction, inside inserting the sharp-pointed 3 of location on two support frames 1 building site soil, then through cup jointing connecting strip 4 on locating pin 6, realized the installation work of rail guard body 2 like this, convenient operation, the installation rate is very fast.
The locating slot 7 that two symmetries set up is seted up to the lateral wall of one of them support frame 1, and the locating pin 6 that two symmetries set up of the lateral wall fixedly connected with of another support frame 1, and locating slot 7 matches each other with locating pin 6, inserts the locating shaft 9 on one of them support frame 1 inside the locating slot 7 of another support frame 1, has just so realized the connection between two support frames 1, saves the space of accomodating like this.
To sum up, this temporary protective guard of construction is built in room convenient to dismouting, when needs install the device, at first insert inside the building site soil with the pointed end 3 of location on two support frames 1, then through cup jointing connecting strip 4 on locating pin 6, the installation work of protective guard body 2 has been realized like this, high durability and convenient operation, the installation rate is very fast, when not using the device, shift out two support frames 1 from inside the soil, then inside inserting the constant head tank 7 of another support frame 1 with location axle 9 on one of them support frame 1, just so realized the connection between two support frames 1, occupation space is little, the space of accomodating is saved like this.
The utility model discloses the standard part that uses all can purchase from the market, and dysmorphism piece all can be customized according to the description with the record of drawing of description, and the concrete connected mode of each part all adopts conventional means such as ripe rivet, welding among the prior art, and machinery, part and equipment all adopt among the prior art, conventional model, and circuit connection adopts conventional connected mode among the prior art, and the details are not repeated here, and the content that does not make detailed description in this description belongs to the prior art that the professional skilled person in this field knows.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides a temporary protective guard of construction is built in room convenient to dismouting, includes support frame (1) that two symmetries set up, its characterized in that: two connecting block (8) that two symmetries of the equal fixedly connected with of one side lateral wall that support frame (1) is close to each other set up, and the equal fixedly connected with location axle (9) of the last lateral wall of connecting block (8), two be equipped with rail guard body (2) between support frame (1), and the equal fixedly connected with connecting strip (4) of the upper and lower both sides lateral wall of rail guard body (2), and the both ends of connecting strip (4) all cup joint on location axle (9).
2. The room construction temporary protective guard convenient to disassemble and assemble according to claim 1, characterized in that: locating holes are formed in the two ends of the connecting strip (4), the locating shaft (9) penetrates through the locating holes, and the locating shaft (9) is in clearance fit with the locating holes.
3. The room construction temporary protective guard convenient to disassemble and assemble according to claim 1, characterized in that: the protective guard is characterized in that the protective guard body (2) is provided with a plurality of strip-shaped openings (5) which are arranged at equal intervals, and the strip-shaped openings (5) are linearly distributed in the horizontal direction.
4. The room construction temporary protective guard convenient to disassemble and assemble according to claim 1, characterized in that: the lower side wall of the support frame (1) is fixedly connected with two symmetrically arranged positioning tips (3), and the positioning tips (3) are in a round table shape.
5. The room construction temporary protective guard convenient to disassemble and assemble according to claim 1, characterized in that: the side wall of one of the support frames (1) is provided with two symmetrically arranged positioning grooves (7).
6. The room construction temporary protective guard convenient to disassemble and assemble according to claim 5, characterized in that: the other one lateral wall fixedly connected with of support frame (1) has two symmetry setting locating pin (6), constant head tank (7) and locating pin (6) match each other.
CN202120489485.0U 2021-03-08 2021-03-08 Interim rail guard of construction is built in room convenient to dismouting Active CN214786538U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120489485.0U CN214786538U (en) 2021-03-08 2021-03-08 Interim rail guard of construction is built in room convenient to dismouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120489485.0U CN214786538U (en) 2021-03-08 2021-03-08 Interim rail guard of construction is built in room convenient to dismouting

Publications (1)

Publication Number Publication Date
CN214786538U true CN214786538U (en) 2021-11-19

Family

ID=78755846

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120489485.0U Active CN214786538U (en) 2021-03-08 2021-03-08 Interim rail guard of construction is built in room convenient to dismouting

Country Status (1)

Country Link
CN (1) CN214786538U (en)

Similar Documents

Publication Publication Date Title
CN212002646U (en) Warning rail for building safety protection
CN214786538U (en) Interim rail guard of construction is built in room convenient to dismouting
CN210302162U (en) Sand pool structure of job site fire control is built in room
CN212201574U (en) Guardrail convenient to installation
CN212656659U (en) Foldable protective fence for construction site
CN216641550U (en) Overhead supporting structure and viewing room
CN207553715U (en) Communication iron tower and computer room combined type base station
CN213952887U (en) Scaffold frame for building engineering convenient to carry
CN215167770U (en) Supporting framework for architectural decoration
CN216007729U (en) Adjustable construction platform of hospital housing construction
CN217812738U (en) Building engineering guard plate convenient to carry
CN205840499U (en) A kind of recreation ground guardrail
CN213626563U (en) Concatenation formula equipment platform is used in building installation
CN215594393U (en) Integrally assembled movable house
CN211173394U (en) Building protective fence assembling structure
CN212642061U (en) Scaffold frame that engineering construction operation was used is built in room
CN215485112U (en) Prefabricated enclosure of concatenation formula
CN205296917U (en) Polygonized structure stadiums convenient to dismantle
CN219118688U (en) Construction frame for construction of building engineering high place
CN216305225U (en) Multi-use architecture decoration panel
CN217811596U (en) H-shaped steel combined base for light house
CN214498613U (en) Civil engineering rail guard
CN215760885U (en) Rail guard is used in construction of gardens ancient building
CN211421371U (en) Assembled balcony of prefabricated floor
CN218894361U (en) Outer wall frame structure for building construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant