CN214738055U - Construction tool for pulling out concrete pipe pile on water - Google Patents

Construction tool for pulling out concrete pipe pile on water Download PDF

Info

Publication number
CN214738055U
CN214738055U CN202022857907.3U CN202022857907U CN214738055U CN 214738055 U CN214738055 U CN 214738055U CN 202022857907 U CN202022857907 U CN 202022857907U CN 214738055 U CN214738055 U CN 214738055U
Authority
CN
China
Prior art keywords
sleeve
pile
outer sleeve
concrete pipe
pipe pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022857907.3U
Other languages
Chinese (zh)
Inventor
范御华
朱珍慧
顾赛华
张佳鸣
韩照晏
周伟宽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No2 Engineering Co ltd Of Cccc Third Harbor Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
Original Assignee
No2 Engineering Co ltd Of Cccc Third Harbor Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No2 Engineering Co ltd Of Cccc Third Harbor Engineering Co ltd, CCCC Third Harbor Engineering Co Ltd filed Critical No2 Engineering Co ltd Of Cccc Third Harbor Engineering Co ltd
Priority to CN202022857907.3U priority Critical patent/CN214738055U/en
Application granted granted Critical
Publication of CN214738055U publication Critical patent/CN214738055U/en
Priority to PCT/CN2021/133600 priority patent/WO2022116916A1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides a construction tool for pulling out concrete pipe pile on water, which comprises an outer sleeve and an inner sleeve, wherein the bottom end of the outer sleeve is provided with a ring piece, the outer peripheral wall of the ring piece is fixed with the inner peripheral wall of the outer sleeve, the inner sleeve is arranged in the inner cavity of the outer sleeve, and when the top ends of the inner sleeve and the outer sleeve are clamped by the same pile clamping device, the bottom surface of the inner sleeve is contacted with the end surface of the ring piece; the top end of the inner sleeve is provided with a lifting lug, and the lifting lug is connected with a hook of the pile driving barge. The utility model discloses utilize the cooperation of interior sleeve pipe and outer tube to realize the pile pulling of concrete pipe pile on water, improve pile pulling efficiency and success rate.

Description

Construction tool for pulling out concrete pipe pile on water
Technical Field
The utility model relates to a pile field on water especially relates to a construction tool of extracting concrete pipe pile on water.
Background
The dock dismantling engineering comprises dismantling a revetment, a common platform behind the dock and two independent berthing piers, wherein PHC (prestressed high-strength concrete) pipe piles are also required to be pulled out when the revetment and the berthing piers are dismantled. The PHC pipe pile is a prestressed high-strength concrete pipe pile, which is a hollow cylindrical concrete prefabricated part manufactured by adopting a pre-tensioning and pre-stressing centrifugal forming process.
Because the wharf completion data and geological data are incomplete, particularly the completion data of two berthing piers is missing, and the pile length is unclear; in addition, when the wharf is soaked in seawater for twenty years, the welding position of the pile and the quality of the pile can cause the pile to break.
In view of the above, there is a need to provide a construction tool for pulling out concrete pipe piles on water, so as to improve pile pulling efficiency and pile pulling success rate.
SUMMERY OF THE UTILITY MODEL
The utility model provides a construction tool of concrete pipe pile on water extracts utilizes the cooperation of interior sleeve pipe and outer tube to realize concrete pipe pile on water's pile pulling, improves pile pulling efficiency and success rate.
Realize the utility model discloses the technical scheme of purpose as follows:
a construction tool for pulling out a concrete pipe pile on water comprises an outer sleeve and an inner sleeve, wherein a ring piece is arranged at the bottom end of the outer sleeve, the outer peripheral wall of the ring piece is fixed with the inner peripheral wall of the outer sleeve,
the inner sleeve is arranged in the inner cavity of the outer sleeve, and when the top ends of the inner sleeve and the outer sleeve are clamped by the same pile clamping device, the bottom surface of the inner sleeve is in contact with the end surface of the ring piece;
the top end of the inner sleeve is provided with a lifting lug, and the lifting lug is connected with a hook of the pile driving barge.
As a further improvement of the present invention, when the outer sleeve is sleeved with the inner sleeve, a gap is formed between the inner wall of the outer sleeve and the outer wall of the inner sleeve;
the inner wall of the outer sleeve is also uniformly provided with a plurality of blocking pieces around the circumferential direction, each blocking piece is positioned at the gap, and the blocking pieces ensure that the gap value is equal at any circumferential position.
The utility model discloses set up the purpose that stops, can evenly distributed after guaranteeing interior sleeve pipe and outer tube to assemble.
As a further improvement of the utility model, the blocking piece is an iron sheet, and the width of the iron sheet is slightly smaller than the gap value;
the length of the iron sheet is slightly larger than the gap value.
As a further improvement of the utility model, the blocking piece is arranged in the same plane of the outer sleeve pipe away from the top by 5 +/-3 cm.
As a further improvement, the bottom internal peripheral wall of the outer sleeve and the laminating of the bottom external peripheral wall of the inner sleeve are combined to avoid the entry of sundries between the inner sleeve and the outer sleeve during pile sinking.
As a further improvement of the utility model, the inner diameter of the inner sleeve is larger than the outer diameter of the concrete pipe pile on water;
the concrete pipe pile on water is located in the inner cavity of the inner sleeve, and the concrete pipe pile on water and soil around the concrete pipe pile on water are pulled out together by the inner sleeve.
As a further improvement of the utility model, the ring piece with still be equipped with a plurality of stiffening ribs between the outer tube, the stiffening rib is connected simultaneously the ring piece with the outer tube, in order to realize the ring piece with the more reliable connection of outer tube.
As a further improvement of the present invention, the bottom inner diameter of the outer sleeve is gradually reduced, the minimum inner diameter of the outer sleeve is consistent with the outer diameter of the outer sleeve, so as to realize the inner sleeve bottom peripheral wall is attached to the inner sleeve bottom peripheral wall.
As a further improvement, the outer tube is formed by welding a plurality of first steel pipes along the length direction, and the joints of the adjacent first steel pipes are fully welded and the stiffened plate is fixedly arranged outside the welding seam.
As a further improvement, the inner sleeve is formed by welding a plurality of second steel pipes along the length direction, and the joints, the inner wall and the outer wall of the adjacent second steel pipes are all fully welded.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses utilize the cooperation of interior sleeve pipe and outer tube to realize the pile pulling of concrete pipe pile on water, improve pile pulling efficiency and success rate.
2. The utility model discloses set up the purpose that stops, can evenly distributed after guaranteeing interior sleeve pipe and outer tube to assemble.
3. The utility model discloses an interior sleeve pipe and outer tube all adopt steel pipe welding to form, can purchase behind the steel pipe and make interior sleeve pipe and outer tube by oneself, save construction tool's purchasing cost.
4. The utility model discloses the bottom periphery wall of outer tube and the laminating of interior sheathed tube bottom periphery wall to debris get into between interior sleeve pipe and the outer tube when avoiding sinking the pile.
Drawings
Fig. 1 is a schematic structural diagram of a construction tool for pulling out an overwater concrete pipe pile;
FIG. 2 is a cross-sectional view A-A of FIG. 1;
FIG. 3 is a cross-sectional view B-B of FIG. 1;
FIG. 4 is a schematic structural view of the outer sleeve;
fig. 5 is a schematic view of the inner sleeve.
In the figure, 1, an outer sleeve; 2. an inner sleeve; 3. a ring sheet; 4. a blocking member; 5. and (7) lifting lugs.
Detailed Description
The present invention is described in detail with reference to the embodiments shown in the drawings, but it should be understood that these embodiments are not intended to limit the present invention, and those skilled in the art should understand that the functions, methods, or structural equivalents or substitutions made by these embodiments are within the scope of the present invention.
In the description of the present embodiments, it is to be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc. indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of describing the present invention and simplifying the description, but do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention.
Furthermore, the terms "first," "second," "third," and the like are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicit to a number of indicated technical features. Thus, a feature defined as "first," "second," etc. may explicitly or implicitly include one or more of that feature. In the description of the invention, the meaning of "a plurality" is two or more unless otherwise specified.
The terms "mounted," "connected," and "coupled" are to be construed broadly and may, for example, be fixedly coupled, detachably coupled, or integrally coupled; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the creation of the present invention can be understood by those of ordinary skill in the art through specific situations.
PHC tubular pile, namely prestressed high-strength concrete tubular pile. The hollow cylindrical concrete prefabricated member is prepared by adopting a pre-tensioned prestressing centrifugal forming process and steam curing at about 180 ℃ under 10 atmospheric pressures (about 1.0 Mpa), the standard section length is 10m, the diameter is 300-800 mm, and the strength grade of concrete is not less than C80.
At present, the domestic pile pulling method mainly focuses on a static pile pulling method, a high-pressure rotary spraying mud pile pulling method, a vibration immersed tube high-pressure water cutting pile pulling method, a full-rotation CD machine pile pulling method, an FECE full-rotation pile pulling method and the like. Wherein, the static pulling method directly pulls the tubular pile out of the stratum. The construction method has high requirement on the strength of the pile body and is not suitable for pulling out the prefabricated pipe pile. The high-pressure rotary-spraying slurry pile-pulling method is used for carrying out high-pressure rotary-spraying slurry on the periphery of a pile body to destroy soil bodies around the pile body. The disadvantages are that pile breakage is easily caused, the influence of stratum soil compactness is large, stratum disturbance is large, and the pile is not suitable for pulling out the precast pile. The vibration immersed tube high-pressure water cutting pile pulling method utilizes vibration to liquefy soil around a pile and penetrate into a steel tube, and is matched with high-pressure water to destroy the soil between the pile body and the steel tube, so that the side friction resistance of the pile is greatly reduced. The vibration immersed tube high-pressure water cutting pile pulling method is suitable for pile pulling on water, and the pile pulling method is used for pile pulling on land, so that the construction speed is low, and the stratum disturbance is large. The fully-rotary CD machine pile pulling is one of the most advanced methods for clearing underground obstacles at present, and has the advantages of high verticality, adaptability to various complex geologies and no noise. The hydraulic steel sleeve cutting machine has the disadvantages that the rotary cutting speed of the hydraulic steel sleeve is low, mechanical equipment needs to be balanced to press the steel sleeve by virtue of counter force, a crane is needed for walking, and the accurate positioning is difficult. The FECE full-rotation pile pulling method adopts a double-layer sleeve rotation drilling method to cut the soil body around the pile, thereby reducing the side frictional resistance of the pile. The FECE full-rotation pile pulling method has the advantages of wide application range and good construction effect, particularly for inclined piles and buildings sensitive to settlement nearby a site, but the method needs a special FECE full-rotation pile pulling machine and is high in construction cost.
Because the wharf completion data and geological data are incomplete, particularly the completion data of two berthing piers is missing, and the pile length is unclear; in addition, when the wharf is soaked in seawater for twenty years, the welding position of the pile and the quality of the pile can cause the pile to break.
Referring to fig. 1, 2, 3, 4 and 5, an embodiment of the present invention provides a construction tool for pulling out an over-water concrete pipe pile, including an outer sleeve 1 and an inner sleeve 2, wherein a ring 3 is disposed at the bottom end of the outer sleeve 1, an outer circumferential wall of the ring 3 is fixed to an inner circumferential wall of the outer sleeve 1, the inner sleeve 2 is disposed in an inner cavity of the outer sleeve 1, and when the top ends of the inner sleeve 2 and the outer sleeve 1 are clamped by a same pile clamping device, a bottom surface of the inner sleeve 2 contacts with an end surface of the ring 3; the top of interior sleeve pipe 2 is equipped with lug 5, and lug 5 is connected with pile driver's couple.
The utility model discloses a mode that double casing creeped into cuts the soil body around the PHC tubular pile, and the soil body is together pulled out together with the PHC tubular pile.
The utility model discloses outer tube 1 adopts external diameter 1000mm, and wall thickness 24 mm's steel pipe machining forms, is 12m steel pipe welded connection by 2 root length, and the junction is full weld and is polished with the abrasive machine, evenly welds 4 stiffened plates in the welding seam outside. The bottom of the outer sleeve 1 is cut into a ring plate by an iron plate with the thickness of 4cm and is welded with the outer sleeve 1, and the inner sleeve 2 can directly act on the iron ring after the iron ring is welded.
The utility model discloses interior sleeve pipe 2 adopts external diameter 908mm, and wall thickness 24 mm's steel pipe processing forms, is 12m steel pipe welded connection by 2 length, and the junction is full weld and is polished with the abrasive machine. Both the inner and outer sides need to be welded. Two lugs 5 are welded on the inner side of the inner sleeve 2, and the size is 20cm by 4 cm. After the inner and outer high pipes are processed, the inner sleeve 2 is sleeved into the outer sleeve 1, and the bottoms and the tops of the inner and outer steel pipes are ensured to be on the same plane. And the bottom of the inner and outer sleeves 1 is ensured to be attached, and when the pile is sunk, no soil can enter between the inner and outer sleeves 1.
When the inner sleeve 2 is sleeved in the outer sleeve 1, a gap is formed between the inner wall of the outer sleeve 1 and the outer wall of the inner sleeve 2; a plurality of blocking pieces 4 are uniformly arranged on the inner wall of the outer sleeve 1 around the circumferential direction, each blocking piece 4 is positioned at the gap, and the blocking pieces 4 ensure that the gap value is equal at any position in the circumferential direction. The blocking member 4 is arranged in the same plane at a distance of 5 + -3 cm from the top of the outer sleeve 1. Preferably, the blocking piece 4 is an iron sheet, and the width of the iron sheet is slightly smaller than the gap value; the length of the iron sheet is slightly larger than the gap value. 6 iron sheets are uniformly arranged in the same plane of the outer sleeve 1 away from the top by 5cm, and the size of the iron sheets is 5cm x 2cm, so that the inner sleeve 1 and the outer sleeve 1 can be uniformly distributed after being assembled.
The utility model discloses set up the purpose that blocks 4, can evenly distributed after guaranteeing interior sleeve pipe 2 and outer tube 1 to assemble.
The bottom internal perisporium of outer tube 1 and the laminating of the bottom periphery wall of interior sleeve pipe 2 to debris get into between interior sleeve pipe 2 and the outer tube 1 during the pile sinking avoided.
Specifically, the inner diameter of the inner sleeve 2 is larger than the outer diameter of the concrete pipe pile on water; the concrete pipe pile on water is located the inner chamber of interior sleeve pipe 2, and interior sleeve pipe 2 is pulled out concrete pipe pile on water together with its earth on every side.
Preferably, a plurality of reinforcing ribs are further arranged between the ring piece 3 and the outer sleeve 1, and the reinforcing ribs are simultaneously connected with the ring piece 3 and the outer sleeve 1 so as to realize more reliable connection of the ring piece 3 and the outer sleeve 1.
In some embodiments, the inner diameter of the bottom end of the outer sleeve 1 is gradually reduced, and the minimum inner diameter of the outer sleeve 1 is consistent with the outer diameter of the outer sleeve 1, so as to realize that the bottom peripheral wall of the inner sleeve 2 is jointed with the bottom peripheral wall of the inner sleeve 2. The outer sleeve 1 is formed by welding a plurality of first steel pipes along the length direction, the joint of the adjacent first steel pipes is fully welded, and a stiffened plate is fixedly arranged outside a welding line. The inner sleeve 2 is formed by welding a plurality of second steel pipes along the length direction, and the joint, the inner wall and the outer wall of the adjacent second steel pipes are all fully welded.
The construction process of the construction tool for pulling out the concrete pipe pile on water comprises the following steps:
primary standby and standby: firstly, a measurer measures the inclination and torsion angle of the PHC pipe pile of the wharf in advance. The inner and outer sleeves 1 are installed together by the pile driving boat matched with a 180T crawler crane, then the inner and outer sleeves 1 are lifted to the PHC pile position needing pile pulling by the pile driving boat, and the position and the angle of the boat are adjusted to be completely matched with the pile position according to the indication of a measurer.
And (3) steel pipe pile construction: after all the pile is ready, the inner and outer sleeves 1 are driven together by a 16Ton hydraulic impact hammer to the bottom elevation of the PHC pile of the existing wharf.
Preparing a vibratory hammer for pile sinking: after the pile sinking is completed, the vibration hammer is removed, and the inner sleeve 2 and the PHC pipe pile are lifted out together by using a lifting hook of the pile driving boat. The outer sleeve 1 is then pulled out with a vibration hammer.
Taking out the tubular pile: and after the inner sleeve 2 and the outer sleeve 1 are hung on the shore, cleaning mud between the inner sleeve 2 and the PHC pile with water, and taking out the PHC pile. And then repeating the steps to take out the next PHC tubular pile.
Pile pulling efficiency: extract concrete pipe pile's on water construction tool, its construction progress is: 1 root/4 hours. Specifically, the sleeve is positioned for 20 minutes, the inner sleeve and the outer sleeve 1 sink for 1 hour, the tubular pile is pulled out for 20 minutes, the inner sleeve 2 and the PHC pile are cleaned for 2 hours, and the outer sleeve 1 is pulled out for 20 minutes. The method improves pile-pulling success rate and efficiency.
In a special embodiment, the inner sleeve 2 is arranged in the outer sleeve 1, the pile clamping device clamps the inner sleeve 2 and the outer sleeve 1, the vibration hammer is started, the inner sleeve 2 and the outer sleeve 1 are sunk into a soil layer, vibration is stopped after the inner sleeve 2 and the outer sleeve 1 sink to the elevation depth, the pile clamping method is changed to enable the pile clamping device to only clamp the inner sleeve 2, the inner sleeve 2 is pulled up in a vibration-free state until the inner sleeve 2 and the PHC tubular pile are pulled out together, and due to the friction acting force between the soil in the inner sleeve 2 and the inner wall of the inner sleeve 2, the soil in the inner sleeve 2 cannot be poured out when the inner sleeve 2 is pulled out statically. After the inner sleeve 2 is hoisted to the shore, soil in the inner sleeve 2 is poured out, and the PHC pipe pile is poured out along with the soil. The outer sleeve 1 is clamped by a pile clamping device, and the vibration hammer is started to vibrate to pull out the outer sleeve 1.
The above list of details is only for the practical implementation of the present invention, and they are not intended to limit the scope of the present invention, and all equivalent implementations or modifications that do not depart from the technical spirit of the present invention should be included in the scope of the present invention.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (10)

1. A construction tool for pulling out a concrete pipe pile on water is characterized by comprising an outer sleeve and an inner sleeve, wherein a ring piece is arranged at the bottom end of the outer sleeve, the outer peripheral wall of the ring piece is fixed with the inner peripheral wall of the outer sleeve,
the inner sleeve is arranged in the inner cavity of the outer sleeve, and when the top ends of the inner sleeve and the outer sleeve are clamped by the same pile clamping device, the bottom surface of the inner sleeve is in contact with the end surface of the ring piece;
the top end of the inner sleeve is provided with a lifting lug, and the lifting lug is connected with a hook of the pile driving barge.
2. The construction tool for pulling out the concrete pipe pile on water according to claim 1, wherein when the inner sleeve is sleeved in the outer sleeve, a gap is formed between the inner wall of the outer sleeve and the outer wall of the inner sleeve;
the inner wall of the outer sleeve is also uniformly provided with a plurality of blocking pieces around the circumferential direction, each blocking piece is positioned at the gap, and the blocking pieces ensure that the gap is equal at any circumferential position.
3. The construction tool for pulling out the concrete pipe pile on water according to claim 2, wherein the blocking piece is an iron sheet, and the width of the iron sheet is slightly smaller than the gap value;
the length of the iron sheet is slightly larger than the gap value.
4. The construction tool for pulling out the concrete pipe pile on water as claimed in claim 2, wherein the blocking piece is arranged in the same plane with the outer sleeve being 5 ± 3cm from the top.
5. The construction tool for pulling out the concrete pipe pile on water according to claim 1, wherein the bottom inner peripheral wall of the outer sleeve is attached to the bottom outer peripheral wall of the inner sleeve, so that impurities can be prevented from entering between the inner sleeve and the outer sleeve during pile sinking.
6. The construction tool for pulling out the concrete pipe pile on water according to claim 1, wherein the inner diameter of the inner sleeve is larger than the outer diameter of the concrete pipe pile on water;
the concrete pipe pile on water is located in the inner cavity of the inner sleeve, and the concrete pipe pile on water and soil around the concrete pipe pile on water are pulled out together by the inner sleeve.
7. The construction tool for pulling out the concrete pipe pile on water according to claim 1, wherein a plurality of reinforcing ribs are further arranged between the ring piece and the outer sleeve, and the reinforcing ribs are simultaneously connected with the ring piece and the outer sleeve so as to realize more reliable connection of the ring piece and the outer sleeve.
8. The construction tool for pulling out the concrete pipe pile on water according to claim 1, wherein the inner diameter of the bottom end of the outer sleeve is gradually reduced, and the minimum inner diameter of the outer sleeve is consistent with the outer diameter of the outer sleeve so as to realize the fitting of the inner peripheral wall of the bottom of the outer sleeve and the outer peripheral wall of the bottom of the inner sleeve.
9. The construction tool for pulling out the concrete pipe pile on water according to claim 1, wherein the outer sleeve is formed by welding a plurality of first steel pipes along the length direction, the joints of the adjacent first steel pipes are fully welded, and a reinforcing plate is fixedly arranged outside the welding line.
10. The construction tool for pulling out the concrete pipe pile on water according to claim 1, wherein the inner sleeve is formed by welding a plurality of second steel pipes along the length direction, and the joint, the inner wall and the outer wall of each adjacent second steel pipe are fully welded.
CN202022857907.3U 2020-12-01 2020-12-01 Construction tool for pulling out concrete pipe pile on water Active CN214738055U (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN202022857907.3U CN214738055U (en) 2020-12-01 2020-12-01 Construction tool for pulling out concrete pipe pile on water
PCT/CN2021/133600 WO2022116916A1 (en) 2020-12-01 2021-11-26 Construction method for pulling out concrete pipe pile on water and pile pulling-out tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022857907.3U CN214738055U (en) 2020-12-01 2020-12-01 Construction tool for pulling out concrete pipe pile on water

Publications (1)

Publication Number Publication Date
CN214738055U true CN214738055U (en) 2021-11-16

Family

ID=78617722

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022857907.3U Active CN214738055U (en) 2020-12-01 2020-12-01 Construction tool for pulling out concrete pipe pile on water

Country Status (1)

Country Link
CN (1) CN214738055U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022116916A1 (en) * 2020-12-01 2022-06-09 中交第三航务工程局有限公司 Construction method for pulling out concrete pipe pile on water and pile pulling-out tool

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022116916A1 (en) * 2020-12-01 2022-06-09 中交第三航务工程局有限公司 Construction method for pulling out concrete pipe pile on water and pile pulling-out tool

Similar Documents

Publication Publication Date Title
KR100884289B1 (en) Composite type steel temporary construction and construction method thereof
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
CN112900435A (en) Construction method for pulling out concrete pipe pile on water
CN214738055U (en) Construction tool for pulling out concrete pipe pile on water
CN102359112A (en) Method for bracing foundation pit by using steel box piles
CN113605383A (en) A steel protects a section of thick bamboo is transferred in merogenesis for bored concrete pile construction
CN111472356A (en) Larsen steel sheet pile sleeve obstacle clearing and pile pulling construction method
CN108570996B (en) It builds a dam under the conditions of shallow water mud cofferdam method
CN113373925B (en) Method and device for mounting steel sheet pile in sandstone stratum by rotary drilling rig
CN103938619A (en) Construction process of tubular pile and special hole opener of construction process
CN111764819B (en) Buried drilling treatment method for collapsed hole of pile foundation in aeolian sand stratum
JP4863120B2 (en) Foundation pile
WO2022116916A1 (en) Construction method for pulling out concrete pipe pile on water and pile pulling-out tool
CN214033712U (en) Pile pulling tool for water-washed pile pulling
CN203782685U (en) Special hole forming device for construction of tubular pile
JP3871937B2 (en) Construction method for underwater frame structures
CN215367361U (en) Open caisson pile clamping breaking structure
CN212506303U (en) Partially recyclable secant pile supporting structure
CN113605378A (en) Construction method of non-pull-out type half-sleeve retaining wall cast-in-situ bored pile
JP3224008B2 (en) Underwater ground improvement method
CN107816068B (en) Construction method of underground diaphragm wall brushing concrete bypass flow detection and treatment device
JP2017190635A (en) Construction method for steel pipe pile
JP3629474B2 (en) Steel pipe sheet pile method
CN212956502U (en) Embedded rock type steel pipe pile is gone into to awl
KR100729380B1 (en) Piling method and pile connector thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant