CN214695730U - Underground hydraulic structure settlement joint structure - Google Patents

Underground hydraulic structure settlement joint structure Download PDF

Info

Publication number
CN214695730U
CN214695730U CN202023271888.2U CN202023271888U CN214695730U CN 214695730 U CN214695730 U CN 214695730U CN 202023271888 U CN202023271888 U CN 202023271888U CN 214695730 U CN214695730 U CN 214695730U
Authority
CN
China
Prior art keywords
underground hydraulic
settlement joint
settlement
sleepers
hydraulic structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202023271888.2U
Other languages
Chinese (zh)
Inventor
华帅
徐小维
杜娟花
张正辉
许成勇
许周
朱伟
陈顺强
高强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Kaitong Foundation Engineering Co ltd
Original Assignee
Nanjing Kaitong Foundation Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Kaitong Foundation Engineering Co ltd filed Critical Nanjing Kaitong Foundation Engineering Co ltd
Priority to CN202023271888.2U priority Critical patent/CN214695730U/en
Application granted granted Critical
Publication of CN214695730U publication Critical patent/CN214695730U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model provides a settlement joint structure of an underground hydraulic structure. A concrete cushion layer is arranged below the underground hydraulic structure. The settlement joint structure is characterized by comprising a plurality of sleepers arranged below the concrete cushion layer, wherein the plurality of sleepers are arranged at intervals along a settlement joint; the settlement joint is positioned in the center of the sleepers; and graded broken stones are filled between adjacent sleepers. The settlement joint structure has the advantages that: (1) the construction efficiency is high, and the quality is high; (2) the construction is simple and convenient, and is simple and easy to implement; (3) the stress between adjacent plates of the settlement joint of the structure can be reduced, settlement deformation is prevented, and the engineering quality is ensured; and (4) the later maintenance cost is reduced, the settlement position is about 300 yuan/workday *2 days *5 persons, the material is saved by 3,000 yuan, and the total maintenance cost is 6,000 yuan.

Description

Underground hydraulic structure settlement joint structure
Technical Field
The utility model relates to an underground hydraulic structure subsiding crack handles technical field, concretely relates to underground hydraulic structure subsiding crack structure.
Background
With the continuous improvement of municipal infrastructure, underground structures are generally applied to town construction, and due to the problems of structural design, material selection, construction process and the like, the durability of the underground structures cannot meet the use requirement, so that the use function is influenced, and potential safety hazards exist. Through market research, it is found that leakage easily occurs at deformation joints, construction joints, post-cast strips, wall pipes (boxes), embedded parts and other parts of structures, and the concrete results are as follows:
1. the stress deformation at the settlement joint is large, and adjacent plates are easy to misplace;
2. the water stop belt at the deformation joint is not firmly fixed, and the water stop belt is easily damaged during concrete pouring and vibrating construction;
3. the water-stopping steel plate at the construction joint is not installed normally, positioned inaccurately and welded in place;
4. the joint surface of new and old concrete at the post-cast strip is not processed in place; the end of the full-length water stop screw rod is not blocked in place;
5. the traditional template has the defects of loose abutted seams and large deformation, and is easy to cause the honeycomb pitted surface on the surface of concrete.
SUMMERY OF THE UTILITY MODEL
In order to overcome the defect that the stress deformation of the settlement joint is large and the adjacent plates are easy to be dislocated, the utility model provides a settlement joint structure of an underground hydraulic building.
In order to solve the above problems, the utility model is realized according to the following technical scheme.
A settlement joint structure of an underground hydraulic structure is characterized in that a concrete cushion layer is arranged below the underground hydraulic structure and comprises a plurality of sleepers arranged below the concrete cushion layer, the sleepers are arranged at intervals along the settlement joint, the settlement joint is positioned in the center of each sleeper, and graded broken stones are filled between every two adjacent sleepers.
Further, the height of the graded broken stone is 150 mm.
Further, the spacing between adjacent sleepers is 1000 mm.
Further, the specification of the sleeper is 2000 × 150 × 200 mm.
Furthermore, a tarragon anticorrosive layer is arranged on the outer side of the sleeper.
Has the advantages that: (1) high construction efficiency and good quality.
(2) The construction is simple, the bottom is simply handed over, and the operation is easy.
(3) The stress between adjacent plate blocks of the settlement joint of the structure can be reduced, the settlement deformation is prevented, and the engineering quality is ensured.
(4) The later maintenance cost is reduced, each settlement position is about 300 yuan/work day 2 days 5 yuan 3000 yuan, 3000 yuan is saved in materials, and the total maintenance cost is 6000 yuan.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
In the figure: 1-underground hydraulic structures; 2. a concrete cushion layer; 3. crossties; 4. grading broken stone.
Detailed Description
The preferred embodiments of the present invention will be described in conjunction with the accompanying drawings, and it will be understood that they are presented herein only to illustrate and explain the present invention, and not to limit the present invention.
As shown in fig. 1, a C15 concrete cushion layer 2 is arranged below an underground hydraulic structure 1 made of C30 concrete. The middle part and the two ends of the underground hydraulic structure 1 are respectively provided with a settlement joint. And a plurality of sleepers 3 are arranged below the concrete cushion layer 2 at intervals along each settlement joint. The sleeper 3 is placed with the settlement joint as the center line.
The sleeper 3 is made of anticorrosive wood and is installed according with the design elevation. And (3) carrying out asphalt preservative treatment on the sleeper 3 when entering the field. The horizontal deviation of the sleeper 3 is not more than 50mm, and the height deviation is not more than 10 mm. Distance between sleepers: 1000mm, sleeper pitch deviation: plus or minus 50mm, sleeper specification: 2000X 150X 200mm, 150mm graded broken stone is laid between sleepers.
The utility model relates to a process flow includes: 1) material approach inspection; 2) paying off and positioning; 3) installing a sleeper; 4) leveling a broken stone cushion layer; 5) checking and accepting.

Claims (5)

1. The utility model provides an underground hydraulic structure subsiding crack structure, underground hydraulic structure below is the concrete bed course, its characterized in that, including setting up a plurality of sleeper in concrete bed course below, a plurality of sleeper sets up along subsiding crack interval, and the subsiding crack is located the center of sleeper, and it has the graded rubble to fill between the adjacent sleeper.
2. The underground hydraulic structure of claim 1, wherein the graded crushed stone has a height of 150 mm.
3. The underground hydraulic structure of claim 1, wherein the spacing between adjacent sleepers is 1000 mm.
4. The underground hydraulic structure of claim 1, wherein the crosstie specification is 2000 x 150 x 200 mm.
5. The underground hydraulic structure settlement joint structure of claim 1, wherein a tarp anticorrosive layer is provided on the outside of the crosstie.
CN202023271888.2U 2020-12-30 2020-12-30 Underground hydraulic structure settlement joint structure Expired - Fee Related CN214695730U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023271888.2U CN214695730U (en) 2020-12-30 2020-12-30 Underground hydraulic structure settlement joint structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023271888.2U CN214695730U (en) 2020-12-30 2020-12-30 Underground hydraulic structure settlement joint structure

Publications (1)

Publication Number Publication Date
CN214695730U true CN214695730U (en) 2021-11-12

Family

ID=78560686

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023271888.2U Expired - Fee Related CN214695730U (en) 2020-12-30 2020-12-30 Underground hydraulic structure settlement joint structure

Country Status (1)

Country Link
CN (1) CN214695730U (en)

Similar Documents

Publication Publication Date Title
CN101063289B (en) City-rail steel spring floating slab rail bed railroad switch construction method
CN108385455A (en) A kind of board-like Construction of Ballastless Track maintenance activity method of cast-in-place railway roadbed
CN106801517B (en) External reinforcing and reinforcing method for school shed with prefabricated porous plate brick mixed structure
CN112049143B (en) Large-sized concrete bearing platform construction method for large-sized low-temperature storage tank
CN111663385A (en) Construction method for completing rapid restoration of settlement of integral ballast bed in skylight period
CN108755394B (en) Method for reinforcing special-shaped pier column of bridge by using prestressed tendons
CN117758549A (en) Construction process of ballastless track of urban railway
EP4350074A1 (en) Prefabricated track structure for built-in pump house section in rail transportation and construction method
CN103276645A (en) Precast pile, beam and slab renovation technology for diseases of existing line tunnel base
CN214695730U (en) Underground hydraulic structure settlement joint structure
CN210288480U (en) Inspection well head reinforcing apparatus in town road pipe network engineering
CN108130825B (en) Subgrade of metro concrete replacement technique in special limiting condition
CN109024670B (en) Underground comprehensive pipe gallery protection and reinforcement system penetrating through buried high-voltage cable and reinforcement method
CN113669083B (en) Tunnel repairing structure based on load conversion and cap type and construction method thereof
CN110670420A (en) Underground excavation maintenance method for ballastless track subgrade of operation railway
CN114197303B (en) Bridge temporary expansion joint construction method
CN215104290U (en) Prefabricated plate type ballastless track structure
CN108221715A (en) A kind of renovation technique of bridge pavement
CN112813858A (en) Open type corrugated steel culvert structure and construction method thereof
CN217499915U (en) Assembled easily maintains environmental protection modulus telescoping device
CN111733715A (en) Construction method for slightly widening adjacent high-speed railway platform
CN109487669A (en) A kind of tramcar and town road level-crossing maintenance and reinforcement construction technology
CN212358403U (en) A reinforced structure for bar brick base
CN214656054U (en) Subway turnout area integral ballast bed settlement treatment tool
CN221142520U (en) Cover plate auxiliary road culvert structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211112