CN103276645A - Precast pile, beam and slab renovation technology for diseases of existing line tunnel base - Google Patents
Precast pile, beam and slab renovation technology for diseases of existing line tunnel base Download PDFInfo
- Publication number
- CN103276645A CN103276645A CN2013101692467A CN201310169246A CN103276645A CN 103276645 A CN103276645 A CN 103276645A CN 2013101692467 A CN2013101692467 A CN 2013101692467A CN 201310169246 A CN201310169246 A CN 201310169246A CN 103276645 A CN103276645 A CN 103276645A
- Authority
- CN
- China
- Prior art keywords
- slab
- tunnel
- beams
- piles
- precast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention discloses a precast pile, beam and slab renovation technology for diseases of an existing line tunnel base. The technology is used for reinforcing and renovating of a tunnel which is large in base disease range and serious in disease condition. Piles, beams and slabs are prefabricated outside a hole, restrained beams are used for erecting lines overhead, drilling is conducted, precast piles are embedded, cement slurry is poured, the beams are erected on the piles, the slabs are paved, and railway ballast is backfilled. According to the precast pile, beam and slab renovation technology for the diseases of the existing line tunnel base, the piles, the beams and the slabs are all prefabricated outside the hole, the aspects of materials, dimensions, maintenance and the like are all guaranteed, end product quality is high, and durability is achieved. The pile, beam and slab prefabricating technology is adopted, concentrated batch production can be achieved, the construction time inside the hole can be reduced, the time limit for a project is shortened, and an operation influence is reduced. After the precast piles, the beams and the slabs are constructed, later period maintenance is relatively easy. The precast pile, beam and slab renovation technology has the advantages of being practical, rapid, safe, easy to renovate and thorough in disease treatment.
Description
Affiliated technical field
The present invention relates to the constructing tunnel field, be specially adapted to the tunnel on a large scale, serious bottom disease regulation problem.
Background technology
The railway tunnel bottom is the underlying structure of track, and the solid of underlying structure firmly is the most important condition that guarantees the track kilter.The existing line tunnel bottom is because a little less than the structure durability design of thin, Drainage Design is unreasonable, construction technology defective, of poor quality, the routine servicing maintenance is not in place, and tunnel bottom is subjected to train nature and the human factor effect of aspect such as power, groundwater erosion repeatedly, substrate occur cracking, damaged, sink, to both sides outside, squeeze and burst and become muddy when a thaw sets in, emit phenomenon such as mud.These diseases all can cause the gauge deviation, rail and joint breaking.If things go on like this, railway operation and passenger's comfortableness is caused adverse effect, when serious even jeopardize traffic safety.How realizing existing line tunnel bottom disease is renovated safely and fast effectively is the current important topic that needs to be resolved hurrily.
For stablizing bedding, eliminate the unfavorable variation of track.At present tunnel bottom disease regulation method is mainly contained: railway roadbed is overhauled, the railway roadbed substrate is changed and filled out, railway roadbed substrate pressure drop etc.
Railway roadbed is overhauled: workload is bigger, repairs slowlyer, and disturbance is bigger, influences the normal operation of train, causes enormous economic loss.
The railway roadbed substrate is changed and filled out: the characteristics of this method are that construction is simple, fast, normal operation influence to train is little, but there is bigger limitation in it, specifically, when the base layer thickness will of substrate is big, it is also relatively large to change the amount of filling out, and the substrate slope excavation also will be taked corresponding supporting measure, from economy and these two words that the aspect is taken all factors into consideration of safety, adopt this method just to seem not too suitable to the darker tunnel of basal layer, and this method is applicable to that the substrate argillic horizon degree of depth is the tunnel of 2.0-5.0m.
Railway roadbed substrate mud jacking: this grouting reinforcement technique mainly refers to build on the ground earlier the slip casting platform, and by holing until the degree of depth of designing requirement downwards outside the position of platform.Insert Grouting Pipe then and in the mode of static pressure grouting consolidation process is carried out in substrate.This method construction is simple, convenient, fast, can effectively improve the intensity on stratum, but consolidation effect is relatively poor on the location that lithic drainage is grown.
After tunnel defect taked above reinforcement measure, through long-term observation, development speed to tunnel defect has had certain alleviation, reinforcement measure plays a role, but tunnel defect does not obtain basic solution, crack quantity can continue to increase, and the width of crack occurrence is also strengthening lentamente, and the length of its cracking also has development.After several years, tunnel defect can be had a relapse, and haves no alternative but and need renovate once again, influences traffic, increases the tunnel maintenance expense.
Along with developing rapidly of China Transportation Industry, the quantity of operation tunnel is also more and more.Because tunnel structure is disguised strong, adds the restriction of existing detection means, the order of severity of tunnel defect and development trend can only deeply exposing along with the regulation construction gradually.Therefore, the long term growth of domestic railway operation must make disease management develop to systematization, standardization direction from existing blindness and local surprise from the existing disease of thorough radical cure tunnel, forms scientific and reasonable tunnel substrate disease regulation worker law system.
Summary of the invention
In view of all drawbacks of existing method, the objective of the invention is to solve the existing line tunnel on a large scale, effective construction difficult problem safely and fast under the disease situation of serious bottom, and reduce the duration in the work progress as far as possible, reduce the influence to operation.
The objective of the invention is to realize by following means.
1) size as required, prefabricated required stake, the prefabricated finished product of Liang Heban in the hole;
2) adopting the restained beam overhead wire, cut slotting according to the riding position of beam to renovating the subbasal soil layer in tunnel, is that beam is prepared placement space;
3) 2) the basis on, the arrangement requirement by stake in slotting is vertically holed, basement rock 40cm is at least goed deep in boring, cleans the stake hole subsequently and imbeds preformed pile, the operation of being in the milk;
4) treat that preformed pile fills after the intensity of slurries reaches 10Mpa, precast beam is erected on the stake, spread precast plate, recover railway ballast and circuit.
It is prefabricated that the present invention requires stake, Liang Heban to adopt outside the hole, and aspects such as material, size and maintenance are all guaranteed, and the end product quality height is durable in use.Adopt stake beam slab prefabricating technique, practicable concentrated batch process can reduce the in-cavity construction time, the reduction of erection time, reduces the influence to operation.After the preformed pile beam slab applied, later maintenance was relatively easy.Preformed pile beam slab regulation technology has practicality, quick, safe, easy reparation, disease management characteristics completely.
Adopt method of the present invention, have the following advantages:
(1) concentrate prefabricated production outside stake, beam and the firm and hard capable hole, quality is secure, reduces the disease recurrence rate, has higher throughput rate and operation degree of freedom.
Facts have proved that (2) after the employing preformed pile beam slab regulation technology, rail level is stable, recovery is fast, it is few that curing time reaches workload less, has good practicality and economic benefit, has broad application prospects.
(3) it is simple to have a job practices, and the efficiency of construction height is repaired workablely again, to advantages such as environmental disturbances are little, is applicable to the regulation of existing line tunnel bottom disease engineering.
Description of drawings
Fig. 1 is beam of the present invention and stake layout schematic diagram
Fig. 2 is Ι among Fig. 1-Ι cross section arrangement diagram
Fig. 3 is II-II sectional drawing among Fig. 2
Fig. 4 is III-III sectional drawing among Fig. 3
Fig. 5 is IV-IV sectional drawing among Fig. 3.
Illustrate: 1 is beam (girder construction) among the figure, and 2 is stake (pilework), and 3 is plate (plated construction), and 4. metallic gasket is the tunnel bottom disease management measure structure that patent content adds, and remainder is original engineering structures in the railway tunnel.
Reference numeral explanation: 1 beam, 2,3 plates, 4 metallic gaskets, 5 substrate fillers, 6 tunnel inverts, 7 Tunnel Second Lining, 8 cable channels and ditch 9, railway ballast structure, 11 grooves.
The specific embodiment
The invention will be further described below in conjunction with accompanying drawing:
(1) according to the requirement of tunnel substrate disease regulation, prefabricated production cylinder pile, Liang Heban, beam as shown in Figure 4, plate is as shown in Figure 5.
(2) adopt the restained beam overhead wire, as shown in Figure 1, according to the riding position requirement of girder construction 2, underlying structure is carried out slotting 11 earlier, groove 11 is vertical with track.According to the placement requirement of pilework 2, carry out bore operation at beam in slotting.
(3) as shown in Figure 2, clean the stake hole and imbed preformed pile 2, the space around the operation compaction pile that is in the milk;
(4) after the intensity for the treatment of the filling slurries of preformed pile and hole wall reaches 10Mpa, place metal caul 4 at the stake top, precast beam is erected in the stake that is placed with metal caul, as shown in Figure 3.
(5) lay precast plate 3 at beam, recover railway ballast, remove restained beam and circuit.
Obviously, those skilled in the art also can make other applications in basic scheme of the present invention enforcement changes, and the variation that these are done according to spirit of the present invention all should be included in the present invention's scope required for protection.
Claims (1)
1. existing line tunnel substrate disease preformed pile beam slab regulation technology is used for the comparatively serious tunnel reinforcement regulation of the big disease of substrate disease scope, and its working procedure comprises the steps:
1) size as required, prefabricated required stake, the prefabricated finished product of Liang Heban in the hole;
2) adopting the restained beam overhead wire, cut slotting according to the riding position of beam to renovating the subbasal soil layer in tunnel, is that beam is prepared placement space;
3) 2) the basis on, the arrangement requirement by stake in slotting is vertically holed, basement rock 40cm is at least goed deep in boring, cleans the stake hole subsequently and imbeds preformed pile, the operation of being in the milk;
Treat that preformed pile fills after the intensity of slurries reaches 10Mpa, precast beam is erected on the stake, spread precast plate, recover railway ballast and circuit.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310169246.7A CN103276645B (en) | 2013-05-09 | 2013-05-09 | Precast pile, beam and slab renovation technology for diseases of existing line tunnel base |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310169246.7A CN103276645B (en) | 2013-05-09 | 2013-05-09 | Precast pile, beam and slab renovation technology for diseases of existing line tunnel base |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103276645A true CN103276645A (en) | 2013-09-04 |
CN103276645B CN103276645B (en) | 2015-04-22 |
Family
ID=49059251
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310169246.7A Expired - Fee Related CN103276645B (en) | 2013-05-09 | 2013-05-09 | Precast pile, beam and slab renovation technology for diseases of existing line tunnel base |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103276645B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103510532A (en) * | 2013-09-26 | 2014-01-15 | 西南交通大学 | Railway tunnel bottom defect treatment technology based on assembly type beam slab pile |
CN105821729A (en) * | 2016-04-05 | 2016-08-03 | 上海同罡建筑工程有限公司 | Track board lifting device and method |
CN105863667A (en) * | 2016-05-06 | 2016-08-17 | 西南交通大学 | Novel bottom structure suitable for water-rich soft rock overloaded railway tunnel |
CN106049195A (en) * | 2016-05-27 | 2016-10-26 | 中铁三局集团有限公司 | Method for strengthening subgrade basement of existing high speed railway line |
CN111321636A (en) * | 2020-03-25 | 2020-06-23 | 福建工程学院 | Beam structure and method for rapidly and in-situ treating railway tunnel bottom plate diseases |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10333613A1 (en) * | 2003-07-24 | 2005-02-24 | Keller Grundbau Gmbh | Process to enhance railway line soil load bearing characteristics by insertion of concrete columns |
JP2005344475A (en) * | 2004-06-07 | 2005-12-15 | Railway Technical Res Inst | Method of repairing base course and base course |
CN101413235A (en) * | 2008-11-25 | 2009-04-22 | 中国第一冶金建设有限责任公司 | Method for reinforcing railway before paving railway rail construction under underground way bridge |
CN101440622A (en) * | 2008-12-17 | 2009-05-27 | 何志红 | CFG pile, pipe pile embankment reinforcement system and construction method thereof |
KR20090084054A (en) * | 2008-01-31 | 2009-08-05 | 한국철도기술연구원 | Structure of concrete track reinforced by piled raft foundation and its constructing and maintaining method |
CN201538934U (en) * | 2009-06-29 | 2010-08-04 | 中铁二院工程集团有限责任公司 | Collapsible loess tunnel foundation basic structure of high-speed railway |
CN102031736A (en) * | 2010-06-12 | 2011-04-27 | 中铁十六局集团有限公司 | Construction technology for under-passing existing line under complicated geological condition |
CN102071607A (en) * | 2011-01-26 | 2011-05-25 | 北京中铁瑞威基础工程有限公司 | Railroad bed repair method without affecting existing running conditions |
CN202595591U (en) * | 2012-05-11 | 2012-12-12 | 中铁第四勘察设计院集团有限公司 | Micro steel pipe pile network structure for tunnel cavern roadbed in karst region |
CN202865708U (en) * | 2012-11-19 | 2013-04-10 | 房士杰 | Railway aerial fixing device |
-
2013
- 2013-05-09 CN CN201310169246.7A patent/CN103276645B/en not_active Expired - Fee Related
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10333613A1 (en) * | 2003-07-24 | 2005-02-24 | Keller Grundbau Gmbh | Process to enhance railway line soil load bearing characteristics by insertion of concrete columns |
JP2005344475A (en) * | 2004-06-07 | 2005-12-15 | Railway Technical Res Inst | Method of repairing base course and base course |
KR20090084054A (en) * | 2008-01-31 | 2009-08-05 | 한국철도기술연구원 | Structure of concrete track reinforced by piled raft foundation and its constructing and maintaining method |
CN101413235A (en) * | 2008-11-25 | 2009-04-22 | 中国第一冶金建设有限责任公司 | Method for reinforcing railway before paving railway rail construction under underground way bridge |
CN101440622A (en) * | 2008-12-17 | 2009-05-27 | 何志红 | CFG pile, pipe pile embankment reinforcement system and construction method thereof |
CN201538934U (en) * | 2009-06-29 | 2010-08-04 | 中铁二院工程集团有限责任公司 | Collapsible loess tunnel foundation basic structure of high-speed railway |
CN102031736A (en) * | 2010-06-12 | 2011-04-27 | 中铁十六局集团有限公司 | Construction technology for under-passing existing line under complicated geological condition |
CN102071607A (en) * | 2011-01-26 | 2011-05-25 | 北京中铁瑞威基础工程有限公司 | Railroad bed repair method without affecting existing running conditions |
CN202595591U (en) * | 2012-05-11 | 2012-12-12 | 中铁第四勘察设计院集团有限公司 | Micro steel pipe pile network structure for tunnel cavern roadbed in karst region |
CN202865708U (en) * | 2012-11-19 | 2013-04-10 | 房士杰 | Railway aerial fixing device |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103510532A (en) * | 2013-09-26 | 2014-01-15 | 西南交通大学 | Railway tunnel bottom defect treatment technology based on assembly type beam slab pile |
CN105821729A (en) * | 2016-04-05 | 2016-08-03 | 上海同罡建筑工程有限公司 | Track board lifting device and method |
CN105863667A (en) * | 2016-05-06 | 2016-08-17 | 西南交通大学 | Novel bottom structure suitable for water-rich soft rock overloaded railway tunnel |
CN106049195A (en) * | 2016-05-27 | 2016-10-26 | 中铁三局集团有限公司 | Method for strengthening subgrade basement of existing high speed railway line |
CN111321636A (en) * | 2020-03-25 | 2020-06-23 | 福建工程学院 | Beam structure and method for rapidly and in-situ treating railway tunnel bottom plate diseases |
Also Published As
Publication number | Publication date |
---|---|
CN103276645B (en) | 2015-04-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103147442B (en) | Ultra-deep foundation pit press-grouting pile and prestressed anchor combined supporting construction method | |
CN103556579B (en) | A kind of comprehensive grouting pressurize adds the box culvert pushing construction method of pipe curtain supporting | |
CN105696427B (en) | The construction method and its road structure of a kind of consolidation process newly built railway karst foundation | |
CN108547641B (en) | Substrate reinforcing system of heavy-duty railway tunnel in water-rich weak stratum and construction method thereof | |
CN103276645B (en) | Precast pile, beam and slab renovation technology for diseases of existing line tunnel base | |
CN111577334B (en) | Operating tunnel inverted arch repairing method | |
EA027027B1 (en) | Method for forming a retaining wall | |
CN109610881A (en) | Prestressed girder underpins disconnected column construction method in a kind of existing tier building transformation | |
CN103835217A (en) | Method for prevention and treatment on damage and depression of pavement around inspection well | |
CN103711056B (en) | Steel tool-type temporary construction road and construction method thereof | |
CN105926391B (en) | A kind of curb method for widening of existing railway roadbed | |
CN111663385A (en) | Construction method for completing rapid restoration of settlement of integral ballast bed in skylight period | |
CN103510532A (en) | Railway tunnel bottom defect treatment technology based on assembly type beam slab pile | |
CN108035379B (en) | Comprehensive pipe gallery and construction method thereof | |
CN103195060B (en) | Soft soil foundation prestressing bolt anchorage structure and uses thereof | |
CN112080972A (en) | Method for repairing road surface by adopting grouting to reinforce roadbed | |
CN107841908A (en) | For eliminating the road structure of the high embankment lateral variation sedimentation in high-speed railway abrupt slope | |
CN102733406B (en) | Railway construction method of solid concrete roadbed in large-size industrial plant | |
CN111379253A (en) | Construction method for high-speed railway expanded cement slurry post-grouting discrete material pile composite foundation | |
CN204533812U (en) | A kind of slurry-water balance type jacking construction system | |
CN108360570A (en) | Bituminous paving inspection shaft gug construction method | |
CN117345283A (en) | Method for repairing deformation and uplift of surrounding rock of sedimentary rock tunnel substrate and reconstruction structure | |
CN103669347B (en) | Underwater anchor rod construction method | |
CN102644266B (en) | Method utilizing fracture anchor rod piles for reinforcing soft soil stratum pavements in abutment areas | |
CN105220582A (en) | Based on Disease Treatment method at the bottom of the solid concrete roabed of combined support and slip casting template and tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150422 |
|
CF01 | Termination of patent right due to non-payment of annual fee |