CN214615326U - Scaffolding for building construction - Google Patents

Scaffolding for building construction Download PDF

Info

Publication number
CN214615326U
CN214615326U CN202023177117.7U CN202023177117U CN214615326U CN 214615326 U CN214615326 U CN 214615326U CN 202023177117 U CN202023177117 U CN 202023177117U CN 214615326 U CN214615326 U CN 214615326U
Authority
CN
China
Prior art keywords
plate
fixed
brackets
side walls
integrally formed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202023177117.7U
Other languages
Chinese (zh)
Inventor
余红梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Tengwang Construction Engineering Co ltd
Original Assignee
Sichuan Tengwang Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Tengwang Construction Engineering Co ltd filed Critical Sichuan Tengwang Construction Engineering Co ltd
Priority to CN202023177117.7U priority Critical patent/CN214615326U/en
Application granted granted Critical
Publication of CN214615326U publication Critical patent/CN214615326U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

本实用新型公开了一种建筑工程施工用脚手架,包括顶板、连接件、底板和爬架,所述底板的底端的四角处均安装有刹车滚轮,所述底板的顶端的四角处均固定有底托,所述顶板的底端的四角处均固定有顶托,沿底板的短边方向设置的两个底托以及两个顶托之间均固定有连接件,其余两个底托以及顶托之间也固定有连接件;四个所述顶托和四个底托相向的端部均构造有与立柱适配的插槽,四个所述立柱分别贯穿四个凸柱,沿顶板的短边方向设置的两个凸柱均与竖板一体成型,其余两个凸柱均与另一个竖板一体成型,所述顶板与四个顶托焊接,四个所述底托均与底板焊接。该建筑工程施工用脚手架,方便拆卸,提高了稳定性。

Figure 202023177117

The utility model discloses a scaffolding for building engineering construction, comprising a top plate, a connecting piece, a bottom plate and a climbing frame. Brake rollers are installed at the four corners of the bottom end of the bottom plate, and bottoms are fixed at the four corners of the top end of the bottom plate. The four corners of the bottom end of the top plate are fixed with top supports, the two bottom supports arranged along the short side direction of the bottom plate and the connecting pieces are fixed between the two top supports, and the other two bottom supports and the top support are fixed. A connector is also fixed between; the opposite ends of the four top brackets and the four bottom brackets are configured with slots that are adapted to the uprights, and the four uprights pass through the four convex columns respectively, along the short side of the top plate. The two protruding columns arranged in the direction are integrally formed with the vertical plate, and the remaining two protruding columns are integrally formed with the other vertical plate. The top plate is welded with the four top brackets, and the four bottom brackets are welded with the bottom plate. The scaffolding used in the construction of the building project is convenient for disassembly and improves the stability.

Figure 202023177117

Description

Scaffold for building engineering construction
Technical Field
The utility model belongs to the technical field of the scaffold frame, concretely relates to scaffold frame for building engineering construction.
Background
Scaffolding (scaffold) is a temporary construction tool set up on the construction site for workers to handle and address vertical and horizontal transport. The high-rise building block is mainly used in places where external walls, interior decoration or high floor height cannot be directly constructed, and is mainly used for up-and-down dry work of constructors, maintenance of peripheral safety nets, high-altitude installation of components and the like. And (4) classification: 1. whether it is movable: the device is divided into a mobile device and a fixed device; 2. materials: is divided into wood, steel and rope ladders; 3. construction property: the method is divided into a building scaffold, an installation scaffold and the like. Scaffold frame for general building engineering construction adopts bolted connection, and it is comparatively inconvenient with the installation to dismantle, expends time.
Therefore, in view of the current situation, the design and production of a scaffold for construction engineering are urgently needed to meet the requirement of practical use.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a scaffold frame is used in building engineering construction to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a scaffold for building engineering construction comprises a top plate, connecting pieces, a bottom plate and a climbing frame, wherein brake rollers are mounted at four corners of the bottom end of the bottom plate, bottom supports are fixed at four corners of the top end of the bottom plate, top supports are fixed at four corners of the bottom end of the top plate, the connecting pieces are fixed between the two bottom supports and the two top supports which are arranged along the direction of the short edge of the bottom plate, and the connecting pieces are fixed between the other two bottom supports and the top supports;
the connecting piece comprises a connecting plate, inserting columns and sleeves, wherein two sliding blocks are arranged on one side of the connecting plate, which is far away from a vertical plate, a transverse rod and a sleeve are respectively fixed on the opposite side walls of the two sliding blocks, one end of the transverse rod is inserted into the sleeve, a spring is arranged in the sleeve, the side walls of the two sliding blocks, which are far away from the transverse rod, are uniformly formed with the inserting columns, and the side walls of the four jacking supports, the four bottom supports and the four upright columns are respectively provided with slots matched with the inserting columns;
the four top supports and the opposite end parts of the four bottom supports are respectively provided with slots matched with the stand columns, the four stand columns respectively penetrate through the four convex columns, the side walls of the four convex columns and the stand columns are respectively provided with screw holes matched with the locking bolts, the two convex columns arranged along the direction of the short edge of the top plate are respectively integrally formed with a vertical plate, the other two convex columns are respectively integrally formed with another vertical plate, the opposite side walls of the two vertical plates are respectively fixed with two sleeves, two support rods are arranged between the two vertical plates, two ends of one support rod are respectively connected with the two sleeves, and two ends of the other support rod are respectively connected with the other two sleeves;
a plurality of hooks are fixed at the bottom end of one of the support rods, and a climbing frame is arranged on one side of each hook.
Preferably, climb the frame and include inserted block, montant and connecting rod, two be fixed with a plurality of connecting rod between the montant, two the montant has two inserted blocks towards the equal integrated into one piece of lateral wall of vaulting pole, the top of roof and bottom plate all is constructed two and the slot of inserted block adaptation.
Preferably, two dovetail grooves are formed in one side, facing the sleeve, of the connecting plate, and sliding blocks matched with the dovetail grooves are integrally formed in the side walls, facing the connecting plate, of the two sliding blocks.
Preferably, four screw holes matched with the bolts are formed in the side walls of the sleeves, and two thread grooves matched with the bolts are formed in the side walls of the support rods.
Preferably, the top plate is welded with four top supports, and the four bottom supports are welded with the bottom plate.
The utility model discloses a technological effect and advantage: according to the scaffold for building engineering construction, a climbing frame is convenient for constructors to go up to a top plate or go from the top plate to the ground from the bottom, the four insertion blocks are used for realizing the connection of the climbing frame with the top plate and a bottom plate, the climbing frame can be separated from the top plate only by lifting the climbing frame, and the climbing frame is convenient to move and is matched with other equipment for use; the vertical plates and the convex columns are integrally formed, so that the structural strength is improved, and the overall stability is improved by the two vertical plates, the two support rods and the four connecting pieces; make the horizontal pole and the sleeve pipe phase shift of four connecting pieces, can remove the fixed to four stands, make things convenient for four stands and four tops to hold in the palm and four stands and four collet's separation, convenient transportation, make the sleeve pipe and the horizontal pole of two connecting pieces remove in opposite directions, loosen the horizontal pole of two connecting pieces after inserting the slot of four collets respectively with the bottom of four stands, spring reset can make four insert the slot that the post inserted four stand lateral walls respectively, make things convenient for four stands and four collet fixed, this scaffold for building engineering construction, convenient dismantlement, and the stability is improved.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of the connecting member of the present invention;
fig. 3 is a schematic structural view of the climbing frame of the present invention;
fig. 4 is an enlarged view of the structure a in fig. 1 according to the present invention.
In the figure: the vertical type steel plate column locking device comprises a top plate 1, a top support 2, a connecting piece 3, a connecting plate 30, an inserting column 31, a sleeve 32, a cross rod 33, a sliding block 34, a bottom plate 4, a climbing frame 5, an inserting block 50, a vertical rod 51, a connecting rod 52, a support rod 6, a sleeve 60, a convex column 7, a vertical plate 8, an upright column 9, a locking bolt 90 and a bottom support 10.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Unless defined otherwise, all references to up, down, left, right, front, back, inner and outer directions herein are to be interpreted as referring to up, down, left, right, front, back, inner and outer directions in the drawings to which the invention is applied, and all references are hereby incorporated herein by reference.
The utility model provides a scaffold for building engineering construction as shown in figures 1-4, including roof 1, connecting piece 3, bottom plate 4 and climbing frame 5, the brake gyro wheel is all installed at the four corners department of the bottom of bottom plate 4, the four corners department of the top of bottom plate 4 all is fixed with collet 10, the four corners department of the bottom of roof 1 all is fixed with top support 2, all weld connecting piece 3 between two collet 10 and two top supports 2 that set up along the minor face direction of bottom plate 4, also weld connecting piece 3 between the other two collet 10 and top supports 2;
the connecting piece 3 comprises a connecting plate 30, inserting columns 31 and sleeves 32, two sliding blocks 34 are arranged on one side of the connecting plate 30, which is far away from the vertical plate 8, a cross rod 33 and the sleeves 32 are respectively welded on the opposite side walls of the two sliding blocks 34, one end of the cross rod 33 is inserted into the sleeves 32, springs are arranged in the sleeves 32, the inserting columns 31 are integrally formed on the side walls, which are far away from the cross rod 33, of the two sliding blocks 34, and the side walls of the four jacking supports 2, the four bottom supports 10 and the four upright posts 9 are respectively provided with a slot matched with the inserting columns 31;
the opposite end parts of the four top supports 2 and the four bottom supports 10 are respectively provided with a slot matched with an upright post 9, the four upright posts 9 respectively penetrate through four convex posts 7, the side walls of the four convex posts 7 and the upright posts 9 are respectively provided with a screw hole matched with a locking bolt 90, the two convex posts 7 arranged along the short edge direction of the top plate 1 are respectively integrally formed with a vertical plate 8, the other two convex posts 7 are respectively integrally formed with another vertical plate 8, the opposite side walls of the two vertical plates 8 are respectively welded with two sleeves 60, two support rods 6 are arranged between the two vertical plates 8, two ends of one support rod 6 are respectively connected with the two sleeves 60, and two ends of the other support rod 6 are respectively connected with the other two sleeves 60;
the bottom welding of one of them vaulting pole 6 has a plurality of couple, and one side of a plurality of couple is equipped with climbs frame 5.
Specifically, climb frame 5 including inserted block 50, montant 51 and connecting rod 52, two the welding has a plurality of connecting rod 52 between montant 51, two montant 51 has two inserted blocks 50 towards the homogeneous shaping of lateral wall of vaulting pole 6, roof 1 and bottom plate 4's top all is constructed two slots with inserted block 50 adaptation, climbs frame 5 and makes things convenient for constructor to go up on roof 1 or from roof 1 to ground from top to bottom, and four inserted blocks 50 realize climbing frame 5 and be connected of roof 1 and bottom plate 4, only need to lift climbing frame 5 and can make climbing frame 5 and roof 1 separate, conveniently climb frame 5's removal and cooperate other equipment uses.
Specifically, two dovetail grooves are formed in one side of the connecting plate 30 facing the sleeve 32, and two sliding blocks 34 facing the side wall of the connecting plate 30 are integrally formed with sliding blocks matched with the dovetail grooves.
Specifically, four screw holes matched with bolts are formed in the side wall of the sleeve 60, two thread grooves matched with the bolts are formed in the side wall of the support rod 6, and the sleeve 60 and the support rod 6 are conveniently separated.
Specifically, the top plate 1 is welded with four top supports 2, and the four bottom supports 10 are all welded with the bottom plate 4.
The working principle of the scaffold for building engineering construction is that the climbing frame 5 is convenient for constructors to go up to the top plate 1 or go down to the ground from the top plate 1, the four insertion blocks 50 realize the connection of the climbing frame 5 with the top plate 1 and the bottom plate 4, the climbing frame 5 can be separated from the top plate 1 only by lifting the climbing frame 5, the climbing frame 5 is convenient to move and is matched with other equipment for use, the vertical plates 8 and the convex columns 7 are integrally formed, the structural strength is improved, the two vertical plates 8, the two support rods 6 and the four connecting pieces 3 improve the integral stability, the cross rods 6 and the sleeves 32 of the four connecting pieces 3 move oppositely, the fixation of the four stand columns 9 can be released, the four stand columns 9 and the four top supports 2 are convenient to be separated from the four bottom supports 10, the sleeves 32 and the cross rods 33 of the two connecting pieces 3 are convenient to transport, the bottom ends of the four stand columns 9 are respectively inserted into the slots of the four bottom supports 10, and then the cross rods 33 of the two connecting pieces 3 are loosened, spring return can make four insert the post 31 and insert the slot of four stand 9 lateral walls respectively, makes things convenient for four stand 9 and four collet 10 fixed, repeats above-mentioned operation, conveniently is connected four stand 9 and four collet 2.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and variations can be made in the embodiments or in part of the technical features of the embodiments without departing from the spirit and the scope of the invention.

Claims (5)

1.一种建筑工程施工用脚手架,包括顶板(1)、连接件(3)、底板(4)和爬架(5),其特征在于:所述底板(4)的底端的四角处均安装有刹车滚轮,所述底板(4)的顶端的四角处均固定有底托(10),所述顶板(1)的底端的四角处均固定有顶托(2),沿底板(4)的短边方向设置的两个底托(10)以及两个顶托(2)之间均固定有连接件(3),其余两个底托(10)以及顶托(2)之间也固定有连接件(3);1. A scaffolding for building construction, comprising a top plate (1), a connector (3), a bottom plate (4) and a climbing frame (5), characterized in that: the four corners of the bottom end of the bottom plate (4) are all installed There are brake rollers, bottom brackets (10) are fixed at the four corners of the top of the bottom plate (4), and top brackets (2) are fixed at the four corners of the bottom end of the top plate (1). A connecting piece (3) is fixed between the two bottom brackets (10) and the two top brackets (2) arranged in the short side direction, and a connecting piece (3) is also fixed between the other two bottom brackets (10) and the top bracket (2). connecting piece (3); 所述连接件(3)包括连板(30)、插柱(31)和套管(32),所述连板(30)远离竖板(8)的一侧设有两个滑块(34),两个所述滑块(34)相向的侧壁分别固定有横杆(33)和套管(32),所述横杆(33)的一端插入套管(32)内,所述套管(32)内设有弹簧,两个所述滑块(34)远离横杆(33)的侧壁均一体成型有插柱(31),四个所述顶托(2)和四个底托(10)以及四个立柱(9)的侧壁均开设有与插柱(31)适配的插槽;The connecting piece (3) includes a connecting plate (30), a post (31) and a sleeve (32), and two sliding blocks (34) are provided on the side of the connecting plate (30) away from the vertical plate (8). ), the opposite side walls of the two sliding blocks (34) are respectively fixed with a cross bar (33) and a sleeve (32), one end of the cross bar (33) is inserted into the sleeve (32), the sleeve A spring is arranged in the tube (32), and the side walls of the two sliding blocks (34) away from the cross bar (33) are integrally formed with inserting posts (31), four of the top brackets (2) and four bottoms The support (10) and the side walls of the four uprights (9) are provided with slots adapted to the posts (31); 四个所述顶托(2)和四个底托(10)相向的端部均构造有与立柱(9)适配的插槽,四个所述立柱(9)分别贯穿四个凸柱(7),四个所述凸柱(7)和立柱(9)的侧壁均开设有与锁紧螺栓(90)适配的螺孔,沿顶板(1)的短边方向设置的两个凸柱(7)均与竖板(8)一体成型,其余两个凸柱(7)均与另一个竖板(8)一体成型,两个所述竖板(8)相向的侧壁均固定有两个套筒(60),两个所述竖板(8)之间设有两个撑杆(6),其中一个撑杆(6)的两端分别与两个套筒(60)连接,另一个撑杆(6)的两端分别与另两个套筒(60)连接;The opposite ends of the four top brackets (2) and the four bottom brackets (10) are configured with slots that are adapted to the uprights (9), and the four uprights (9) pass through the four protruding columns (9). 7), the side walls of the four protruding posts (7) and the upright post (9) are provided with screw holes adapted to the locking bolts (90), and two protruding The column (7) is integrally formed with the vertical plate (8), and the remaining two convex columns (7) are integrally formed with the other vertical plate (8), and the opposite side walls of the two vertical plates (8) are fixed with Two sleeves (60), two struts (6) are arranged between the two vertical plates (8), and two ends of one strut (6) are respectively connected with the two sleeves (60), Two ends of the other strut (6) are respectively connected with the other two sleeves (60); 其中一个撑杆(6)的底端固定有若干个挂钩,若干个挂钩的一侧设有爬架(5)。Several hooks are fixed at the bottom end of one of the struts (6), and one side of the several hooks is provided with a climbing frame (5). 2.根据权利要求1所述的一种建筑工程施工用脚手架,其特征在于:所述爬架(5)包括插块(50)、竖杆(51)和连杆(52),两个所述竖杆(51)之间固定有若干个连杆(52),两个所述竖杆(51)朝向撑杆(6)的侧壁均一体成型有两个插块(50),所述顶板(1)和底板(4)的顶端均构造有两个与插块(50)适配的插槽。2. A construction scaffold according to claim 1, characterized in that: the climbing frame (5) comprises an insert block (50), a vertical rod (51) and a connecting rod (52), and the two Several connecting rods (52) are fixed between the vertical rods (51), and two insert blocks (50) are integrally formed with the side walls of the two vertical rods (51) facing the strut (6). The tops of the top plate (1) and the bottom plate (4) are both configured with two slots that are adapted to the insert blocks (50). 3.根据权利要求1所述的一种建筑工程施工用脚手架,其特征在于:所述连板(30)朝向套管(32)的一侧开设有两个燕尾槽,两个所述滑块(34)朝向连板(30)的侧壁均一体成型有与燕尾槽适配的滑块。3. A scaffolding for construction according to claim 1, characterized in that: two dovetail grooves are provided on the side of the connecting plate (30) toward the casing (32), and two sliding blocks are provided with two dovetail grooves. (34) The side walls facing the connecting plate (30) are integrally formed with sliding blocks adapted to the dovetail grooves. 4.根据权利要求1所述的一种建筑工程施工用脚手架,其特征在于:四个所述套筒(60)的侧壁均开设有与螺栓适配的螺孔,两个所述撑杆(6)的侧壁均开设有两个与螺栓适配的螺纹槽。4. A scaffolding for construction according to claim 1, characterized in that: the side walls of the four sleeves (60) are provided with screw holes adapted to the bolts, and the two braces The side walls of (6) are provided with two threaded grooves adapted to the bolts. 5.根据权利要求1所述的一种建筑工程施工用脚手架,其特征在于:所述顶板(1)与四个顶托(2)焊接,四个所述底托(10)均与底板(4)焊接。5. A kind of scaffolding for construction according to claim 1, characterized in that: the top plate (1) is welded with four top brackets (2), and the four described bottom brackets (10) are all connected to the bottom plate ( 4) Welding.
CN202023177117.7U 2020-12-25 2020-12-25 Scaffolding for building construction Expired - Fee Related CN214615326U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023177117.7U CN214615326U (en) 2020-12-25 2020-12-25 Scaffolding for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023177117.7U CN214615326U (en) 2020-12-25 2020-12-25 Scaffolding for building construction

Publications (1)

Publication Number Publication Date
CN214615326U true CN214615326U (en) 2021-11-05

Family

ID=78432140

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023177117.7U Expired - Fee Related CN214615326U (en) 2020-12-25 2020-12-25 Scaffolding for building construction

Country Status (1)

Country Link
CN (1) CN214615326U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116517385A (en) * 2023-06-05 2023-08-01 河海大学 Engineering rail guard with protective structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116517385A (en) * 2023-06-05 2023-08-01 河海大学 Engineering rail guard with protective structure
CN116517385B (en) * 2023-06-05 2025-11-07 河海大学 Engineering rail guard with protective structure

Similar Documents

Publication Publication Date Title
CN110185247A (en) Mobile outrigger platform
CN214615326U (en) Scaffolding for building construction
CN219528334U (en) Scaffold for building construction
CN215670909U (en) High security scaffold frame
CN218406331U (en) Anti-tilting scaffold
CN211473327U (en) Building external climbing type building construction operation platform
CN104278830A (en) Integral combined scaffold
CN210239090U (en) Movable operating platform
CN209429487U (en) A kind of scaffold of architectural engineering
CN205000618U (en) Novel scaffold
CN210888118U (en) Building faces limit structure post construction protection frame
CN204212388U (en) Integral combined scaffolding
CN210508314U (en) Scaffold structure for building
CN213143808U (en) Scaffold for constructional engineering
CN211775603U (en) Combined type step construction platform
CN212176492U (en) Scaffold for high-rise building construction
CN212897474U (en) Scaffold frame for municipal works
CN114197841A (en) Rectangular pipe frame structure scaffold system
CN207829428U (en) High-rise steel structure brushing Job Operations platform
CN209114850U (en) Magnesium alloy hanging basket basket body inserts connection structure
CN220620961U (en) Building construction has building construction frame of anti falling structure
CN114086752A (en) Movable cantilever platform device for roof structure
CN215631411U (en) Quick assembly disassembly scaffold frame is used in construction in room
CN217782775U (en) Scaffold for civil engineering construction
CN213926693U (en) Movable frame for building construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211105

CF01 Termination of patent right due to non-payment of annual fee