CN209429487U - A kind of scaffold of architectural engineering - Google Patents
A kind of scaffold of architectural engineering Download PDFInfo
- Publication number
- CN209429487U CN209429487U CN201822201769.6U CN201822201769U CN209429487U CN 209429487 U CN209429487 U CN 209429487U CN 201822201769 U CN201822201769 U CN 201822201769U CN 209429487 U CN209429487 U CN 209429487U
- Authority
- CN
- China
- Prior art keywords
- wall
- scaffold
- jack
- firm banking
- link block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000003466 welding Methods 0.000 claims 1
- 230000000694 effects Effects 0.000 abstract description 4
- 230000003993 interaction Effects 0.000 abstract description 3
- 238000010276 construction Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000003831 deregulation Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000009966 trimming Methods 0.000 description 1
Landscapes
- Load-Engaging Elements For Cranes (AREA)
Abstract
The utility model discloses a kind of scaffolds of architectural engineering, including firm banking and pedal, the quantity of the firm banking is four, and the bottom outer wall of firm banking is provided with the first jack, the inner wall of first jack is provided with supporting leg, and the bottom outer wall of supporting leg is provided with universal wheel, the opposite side outer wall of the firm banking is provided with first support bar, and the quantity of first support bar is four, the top exterior walls of the firm banking are provided with the first link block, and first the top exterior walls of link block be provided with the second jack, the bottom interior wall middle position of second jack is provided with the first internal core rod.The height of the utility model adjusting pedal, it is easy to operate, realize quickly fixed and disassembly pedal effect, support is fixed to scaffold in advance using the interaction of link block and internal core rod, position of the threaded rod in threaded hole is adjusted, is carried out using junction of the fixed ring to scaffold sufficiently fixed.
Description
Technical field
The utility model relates to construction engineering technical field more particularly to a kind of scaffolds of architectural engineering.
Background technique
Scaffold refer to construction site be worker operation and solving vertically and horizontally transport and the various brackets set up, work as building
Object is often arranged scaffold in the outside of building, allows construction personnel to stand and walk with this in construction or trimming.
Currently, the problem of the existing universal installing and dismounting difficulty of scaffold, expends a large amount of manpowers and wastes time, into
When two scaffold connections of row, people will only be fixed at the top of junction, and the bottom of junction is not carried out effectively
Fixing process causes the fixed effect of scaffold junction poor, and after the installation of existing scaffold, is difficult de-regulation foot hand
The height of frame pedal, it is inconvenient for operation, it is not convenient to use.
Utility model content
Purpose of the utility model is to solve disadvantages existing in the prior art, and a kind of architectural engineering proposed is used
Scaffold.
To achieve the goals above, the utility model adopts the technical scheme that
A kind of scaffold of architectural engineering, including firm banking and pedal, the quantity of the firm banking are four, and
The bottom outer wall of firm banking is provided with the first jack, and the inner wall of first jack is provided with supporting leg, and supporting leg
Bottom outer wall is provided with universal wheel, and the opposite side outer wall of the firm banking is provided with first support bar, and first
The quantity of strut is four, and the top exterior walls of the firm banking are provided with the first link block, and the top of the first link block
Outer wall is provided with the second jack, and the bottom interior wall middle position of second jack is provided with the first internal core rod, and second inserts
The inner wall in hole is provided with lateral column, and the opposite side outer wall of the lateral column is provided with the connecting rod equidistantly distributed, and connects
The top exterior walls of bar are provided with the second link block, and the top exterior walls of second link block are provided with third jack, and third
The bottom interior wall middle position of jack is provided with the second internal core rod, and the side outer wall of the lateral column is provided with ladder, and ladder
Quantity is two, and the opposite side top exterior walls of the lateral column are provided with second support bar, and the quantity of second support bar is
Four.
The two sides of the pedal are provided with groove as a further solution of the present invention, and the shape of groove is
The inner wall side of " convex " font, groove is provided with grapple.
The bottom that the pedal is located at groove as a further solution of the present invention, is provided with sliding slot, and sliding slot
Inner wall be provided with pull rod, the side outer wall of pull rod and the side outer wall of grapple weld, the one of the side outer wall of pull rod and groove
Side inner wall is provided with spring.
The top side outer wall of the grapple and bottom side outer wall are all provided with as a further solution of the present invention,
It is equipped with bearing block, and the outer wall of bearing block and the inner wall of groove are slidably connected.
The top two sides outer wall and the second link block of first link block as a further solution of the present invention,
Top two sides outer wall be provided with fixed ring, and the two sides outer wall of fixed ring is provided with surrounding edge.
The middle position of the surrounding edge is provided with threaded hole, and threaded hole as a further solution of the present invention,
Inner wall be provided with threaded rod, the outer wall side of threaded rod is provided with nut.
The utility model has the following beneficial effects:
1. through pedal, connecting rod, groove, pull rod, sliding slot, bearing block and the grapple of setting, using pull rod in sliding slot
Sliding, and grapple is adjusted in the position of inside grooves, so that pedal be unloaded from scaffold, and pedal can be mounted on next
In a connecting rod, so that the height of pedal is adjusted, it is easy to operate, quickly fixed and disassembly pedal effect is realized, when people or object
Grade is contradicted using junction of the bearing block to grapple and pedal when on pedal, avoids the phenomenon that bending grapple hair
It is raw;
2. by the first link block, internal core rod, fixed ring, surrounding edge and the threaded rod of setting, by the connection bottom of scaffold
End is plugged in jack, and support is fixed to scaffold in advance using the interaction of link block and internal core rod, convenient for subsequent
Fixed operation adjusts position of the threaded rod in threaded hole, to be carried out using junction of the fixed ring to scaffold sufficiently solid
It is fixed;
3. the supporting leg of universal wheel to be directly plugged on to the movement for carrying out scaffold in jack, nothing by the jack of setting
Universal wheel need to be directly anchored on scaffold, the connecting rod quantity of setting be it is multiple, the two sides of scaffold can also be prevented
Shield.
Detailed description of the invention
Fig. 1 be the utility model proposes a kind of architectural engineering scaffold structural schematic diagram;
Fig. 2 be the utility model proposes a kind of architectural engineering scaffold side structure schematic view;
Fig. 3 be the utility model proposes a kind of architectural engineering scaffold groove and grapple structural schematic diagram;
Fig. 4 be the utility model proposes a kind of architectural engineering scaffold fixed ring structural schematic diagram.
In figure: 1 firm banking, 2 universal wheels, 3 first support bars, 4 pedals, 5 first jacks, 6 first link blocks, 7 lateral columns,
8 connecting rods, 9 second support bars, 10 grapples, 11 ladders, 12 first internal core rods, 13 grooves, 14 pull rods, 15 bearing blocks, 16 springs,
17 fixed rings, 18 surrounding edges, 19 threaded rods, 20 threaded holes.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.
Referring to Fig.1-4, a kind of scaffold of architectural engineering, including firm banking 1 and pedal 4, the quantity of firm banking 1
It is four, and the bottom outer wall of firm banking 1 is provided with the first jack 5, the inner wall of the first jack 5 is plugged with supporting leg, and
The bottom outer wall of supporting leg passes through fastening bolt and is connected with universal wheel 2, and the opposite side outer wall of firm banking 1 is welded with
One support rod 3, and the quantity of first support bar 3 is four, the top exterior walls of firm banking 1 are welded with the first link block 6, and
The top exterior walls of first link block 6 are provided with the second jack, and the bottom interior wall middle position of the second jack is welded in first
Core bar 12, and the inner wall of the second jack is plugged with lateral column 7, the opposite side outer wall of lateral column 7, which is welded with, to be equidistantly distributed
Connecting rod 8, and the top exterior walls of connecting rod 8 are welded with the second link block, the top exterior walls of the second link block are provided with third
Jack, and the bottom interior wall middle position of third jack is welded with the second internal core rod, the side outer wall of lateral column 7 is welded with ladder
11, and the quantity of ladder 11 is two, the opposite side top exterior walls of lateral column 7 are welded with second support bar 9, and the second support
The quantity of bar 9 is four.
In the utility model, the two sides of pedal 4 are provided with groove 13, and the shape of groove 13 is " convex " font, groove 13
Inner wall side be plugged with grapple 10, the bottom that pedal 4 is located at groove 13 is provided with sliding slot, and the inner wall of sliding slot is slidably connected
There is a pull rod 14, the side outer wall of pull rod 14 and the side outer wall of grapple 10 weld, and the one of the side outer wall of pull rod 14 and groove 13
Side inner wall is welded with spring 16, and the top side outer wall and bottom side outer wall of grapple 10 are welded with bearing block 15, and load-bearing
The outer wall of block 15 and the inner wall of groove 13 are slidably connected, the top two sides outer wall of the first link block 6 and the top of the second link block
Two sides outer wall is welded with fixed ring 17, and the two sides outer wall of fixed ring 17 is welded with surrounding edge 18, the middle position of surrounding edge 18
It is provided with threaded hole 20, and the inner thread of threaded hole 20 is connected with threaded rod 19, the outer wall side of threaded rod 19 is threadedly coupled
There is nut.
Working principle: in use, lateral column 7 is plugged in the second jack in the first link block 6 by user, first is utilized
Support is fixed to scaffold bottom end in advance in the interaction of link block 6 and the first internal core rod 12, and user adjusts screw thread again
Position of the bar 19 in threaded hole 20, to carry out sufficiently fixed, raising foot hand using junction of the fixed ring 17 to scaffold
The connective stability of frame, user is slided in sliding slot using pull rod 14, and adjusts position of the grapple 10 inside groove 13, from
And unload pedal 4 from scaffold, user grapple 10 can be mounted in next connecting rod 8 again, to adjust pedal 4
Highly, quickly fixed and disassembly pedal 4 effect is realized.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not
It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this
Novel technical solution and its utility model design are subject to equivalent substitution or change, should all cover the protection model in the utility model
Within enclosing.
Claims (6)
1. a kind of scaffold of architectural engineering, including firm banking (1) and pedal (4), which is characterized in that the firm banking
(1) quantity is four, and the bottom outer wall of firm banking (1) is provided with the first jack (5), first jack (5) it is interior
Wall is provided with supporting leg, and the bottom outer wall of supporting leg is provided with universal wheel (2), and opposite the one of the firm banking (1)
Side outer wall is provided with first support bar (3), and the quantity of first support bar (3) is four, the top of the firm banking (1)
Outer wall is provided with the first link block (6), and the top exterior walls of the first link block (6) are provided with the second jack, and described second inserts
The bottom interior wall middle position in hole is provided with the first internal core rod (12), and the inner wall of the second jack is provided with lateral column (7), institute
The opposite side outer wall for stating lateral column (7) is provided with the connecting rod (8) equidistantly distributed, and the top exterior walls of connecting rod (8) are equal
It is provided with the second link block, the top exterior walls of second link block are provided with third jack, and the bottom interior wall of third jack
Middle position is provided with the second internal core rod, and the side outer wall of the lateral column (7) is provided with ladder (11), and the quantity of ladder (11)
It is two, the opposite side top exterior walls of the lateral column (7) are provided with second support bar (9), and the number of second support bar (9)
Amount is four.
2. a kind of scaffold of architectural engineering according to claim 1, which is characterized in that the two sides of the pedal (4)
It is provided with groove (13), and the shape of groove (13) is " convex " font, the inner wall side of groove (13) is provided with grapple (10).
3. a kind of scaffold of architectural engineering according to claim 2, which is characterized in that the pedal (4) is located at recessed
The bottom of slot (13) is provided with sliding slot, and the inner wall of sliding slot is provided with pull rod (14), the side outer wall and grapple of pull rod (14)
(10) side outer wall welding, the side outer wall of pull rod (14) and the side inner wall of groove (13) are provided with spring (16).
4. a kind of scaffold of architectural engineering according to claim 3, which is characterized in that the top of the grapple (10)
Side outer wall and bottom side outer wall are provided with bearing block (15), and the outer wall of bearing block (15) and the inner wall of groove (13) are sliding
Dynamic connection.
5. a kind of scaffold of architectural engineering according to claim 4, which is characterized in that first link block (6)
Top two sides outer wall and the top two sides outer wall of the second link block be provided with fixed ring (17), and two sides of fixed ring (17)
Outer wall is provided with surrounding edge (18).
6. a kind of scaffold of architectural engineering according to claim 5, which is characterized in that the centre of the surrounding edge (18)
Position is provided with threaded hole (20), and the inner wall of threaded hole (20) is provided with threaded rod (19), the outer wall side of threaded rod (19)
It is provided with nut.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201822201769.6U CN209429487U (en) | 2018-12-26 | 2018-12-26 | A kind of scaffold of architectural engineering |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201822201769.6U CN209429487U (en) | 2018-12-26 | 2018-12-26 | A kind of scaffold of architectural engineering |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN209429487U true CN209429487U (en) | 2019-09-24 |
Family
ID=67973731
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201822201769.6U Expired - Fee Related CN209429487U (en) | 2018-12-26 | 2018-12-26 | A kind of scaffold of architectural engineering |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN209429487U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115306127A (en) * | 2022-08-10 | 2022-11-08 | 济南市市政工程建设集团有限公司 | Installation equipment and method for movable full-hall construction support |
| CN116181047A (en) * | 2023-04-26 | 2023-05-30 | 仪征市恒盛机械有限公司 | A building construction platform that is easy to disassemble |
-
2018
- 2018-12-26 CN CN201822201769.6U patent/CN209429487U/en not_active Expired - Fee Related
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115306127A (en) * | 2022-08-10 | 2022-11-08 | 济南市市政工程建设集团有限公司 | Installation equipment and method for movable full-hall construction support |
| CN115306127B (en) * | 2022-08-10 | 2024-04-19 | 济南市市政工程建设集团有限公司 | Installation equipment and method for movable full-hall construction support |
| CN116181047A (en) * | 2023-04-26 | 2023-05-30 | 仪征市恒盛机械有限公司 | A building construction platform that is easy to disassemble |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN209429487U (en) | A kind of scaffold of architectural engineering | |
| CN213626572U (en) | Tool type external cantilever operation platform | |
| CN112723094B (en) | An integrated wall-attached device based on synchronous climbing of a light steel platform | |
| CN204676865U (en) | A kind of building scaffold | |
| CN211548680U (en) | A scaffolding for building construction | |
| CN208072912U (en) | A kind of Easy opened scaffold that construction site auxiliary is built | |
| CN107461029B (en) | Lower hanging beam pouring forming device based on hydraulic climbing formwork system setting | |
| CN207568478U (en) | A kind of convenient step ladder for being suitable for a variety of highly safe operations | |
| CN201284559Y (en) | Fastener type steel pipe scaffold template stand | |
| CN206636157U (en) | A steel structure suitable for construction site assembly | |
| CN206205407U (en) | It is a kind of can flexible combination multi-functional scaffold | |
| CN214615326U (en) | Scaffolding for building construction | |
| CN209369715U (en) | A kind of oilfield servicing step ladder | |
| CN214989509U (en) | Integrated wall-attached device based on synchronous climbing of light steel platform | |
| CN203701552U (en) | Attached scaffold for lifted through worm, gear and screw rod | |
| CN206591797U (en) | A kind of scaffold for building | |
| CN210798251U (en) | But scaffold of automatically regulated height | |
| CN206158136U (en) | But decorate facade construction mobile scaffold | |
| CN207260537U (en) | A kind of scaffold for construction | |
| CN220167444U (en) | Building engineering is with climbing frame | |
| CN204059903U (en) | Large area is encorbelmented the construction bearing platform of building | |
| CN210067401U (en) | Positioning Adjustment Device for Climbing Scaffolding | |
| CN219241250U (en) | Safety construction frame | |
| CN211286559U (en) | Scaffold for building construction | |
| CN204152174U (en) | A kind of scaffold being convenient to dismounting and expansion |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190924 Termination date: 20201226 |