CN214580186U - Hydroelectric engineering earthwork is filled out and is dug observation device - Google Patents

Hydroelectric engineering earthwork is filled out and is dug observation device Download PDF

Info

Publication number
CN214580186U
CN214580186U CN202120094759.6U CN202120094759U CN214580186U CN 214580186 U CN214580186 U CN 214580186U CN 202120094759 U CN202120094759 U CN 202120094759U CN 214580186 U CN214580186 U CN 214580186U
Authority
CN
China
Prior art keywords
fixedly connected
wall
sleeve
spring
spacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120094759.6U
Other languages
Chinese (zh)
Inventor
罗晹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huizhou Kaiyu Construction Engineering Co ltd
Original Assignee
Huizhou Kaiyu Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huizhou Kaiyu Construction Engineering Co ltd filed Critical Huizhou Kaiyu Construction Engineering Co ltd
Priority to CN202120094759.6U priority Critical patent/CN214580186U/en
Application granted granted Critical
Publication of CN214580186U publication Critical patent/CN214580186U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Cultivation Receptacles Or Flower-Pots, Or Pots For Seedlings (AREA)

Abstract

The utility model provides a hydroelectric engineering earthwork is filled out and is dug observation device relates to engineering observation technical field, the utility model discloses an organism, alignment jig and connecting device, the organism is located the top of alignment jig, the lower fixed surface of alignment jig is connected with the regulation pole, the lower fixed surface of adjusting the pole is connected with the support frame, the lower fixed surface of support frame is connected with the bracing piece, the cover is established and sliding connection has the position sleeve on the bracing piece, connecting device is located the upper surface setting of alignment jig, connecting device includes the adapter sleeve, the adapter sleeve is connected with the lower fixed surface of organism, the fixed fixture block that four symmetries of inner wall fixedly connected with of adapter sleeve set up. The utility model provides an installation of present most of equipment to the organism and dismantle the process comparatively loaded down with trivial details, need assist with the help of professional instrument for the dismouting operation has certain requirement to maintainer's experience of working, increases the maintenance cost of equipment, influences the problem of equipment normal use.

Description

Hydroelectric engineering earthwork is filled out and is dug observation device
Technical Field
The utility model relates to an engineering observation technical field especially relates to a hydroelectric engineering earthwork is filled out and is dug observation device.
Background
The earthwork engineering in the construction of water conservancy and hydropower engineering comprises excavation engineering and filling engineering, wherein a part of the earthwork is excavated by various construction methods to form a building with the specification required by design or to vacate space to sit a building foundation, the engineering is called excavation, and the earthwork is piled into the building according to a certain shape, a certain size and a certain mass by various construction methods.
Most of existing equipment are relatively complicated in installation and disassembly processes of the machine body, and need to be assisted by means of professional tools, so that the disassembly and assembly operation has certain requirements on the working experience of maintenance personnel, the maintenance cost of the equipment is increased, the subsequent maintenance of the equipment is not facilitated, and the improvement is needed.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a hydroelectric engineering earthwork digging observation device.
In order to achieve the above purpose, the utility model adopts the following technical scheme: a hydroelectric engineering earth and stone square filling and digging observation device comprises a machine body, an adjusting frame and a connecting device, wherein the machine body is positioned above the adjusting frame, the lower surface of the adjusting frame is fixedly connected with an adjusting rod, the lower surface of the adjusting rod is fixedly connected with a supporting frame, the lower surface of the supporting frame is fixedly connected with a supporting rod, the supporting rod is sleeved and connected with a positioning sleeve in a sliding way, the connecting device is arranged on the upper surface of the adjusting frame and comprises a connecting sleeve which is fixedly connected with the lower surface of the machine body, the inner wall of the connecting sleeve is fixedly connected with four symmetrically arranged fixed clamping blocks, the inner wall of the connecting sleeve is inserted and connected with a pressing block in a sliding way, one end of the pressing block, far away from the fixed clamping block, is fixedly connected with a sliding pressing plate, the sliding pressing plate is fixedly connected with the surface of the connecting sleeve through a fixed spring, and a tightening strap is sleeved on the sliding pressing plate and connected with the sliding pressing plate in a sliding mode.
Preferably, one side sliding connection that the alignment jig is close to the adapter sleeve has the stopper of four symmetry settings, fixed surface is connected with the locating lever on the alignment jig, one side fixed connection locating lever that the alignment jig is close to the stopper, the locating lever and the inner wall sliding connection of stopper.
Preferably, four equal fixedly connected with pressure spring in the one side that the stopper is close to each other, the fixed surface of adapter sleeve is connected with four spacing framves that the symmetry set up, sliding pressure plate and tightening strap all with the inner wall sliding connection of spacing frame.
Preferably, the lower surface of support frame is provided with stabilising arrangement, stabilising arrangement includes stabilizing spring, stabilizing spring and the inner wall fixed connection of position sleeve, stabilizing spring keeps away from the one end and the bracing piece fixed connection of position sleeve inner wall, the position sleeve is close to the spacing fixture block of the one end fixedly connected with of bracing piece, the inner wall fixedly connected with rack of bracing piece.
Preferably, the inner wall of the locating sleeve is connected with a limiting plate in a sliding mode, a limiting groove is formed in the surface of the limiting plate, a connecting rod is fixedly connected to one side, close to the rack, of the limiting plate, one end, far away from the limiting plate, of the connecting rod is fixedly connected with a rotating gear, and the rotating gear is meshed with the rack and connected with the rack.
Preferably, the limiting plate is far away from the one end fixedly connected with knob of connecting rod, the spacing spring that two symmetries of inner wall fixedly connected with of limiting plate set up, the one end fixedly connected with baffle of knob is kept away from to spacing spring, one side fixedly connected with fixture block that spacing spring was kept away from to the baffle, the inner wall sliding connection of fixture block and spacing fixture block.
Compared with the prior art, the utility model has the advantages and positive effects that,
1. in the utility model, by arranging the connecting device, when in use, the machine body is inserted into the mounting frame, the limit block slides along the inner wall of the connecting sleeve, under the extrusion of the fixed clamping block, the limit block gathers inwards, the compression spring deforms under stress to generate elasticity, when the limit block passes through the fixed clamping block, the compression spring drives the limit block to expand outwards and to abut against the inner wall of the connecting sleeve, the installation of the machine body is completed, the opening of the tightening band is kneaded, the tightening band extrudes the sliding pressure plate to enable the sliding pressure plate to slide towards the direction close to the connecting sleeve, the fixing spring deforms under stress to generate elasticity, the press block slides towards one end close to the limit block, the limit block gathers inwards after being extruded, the machine body is separated from the adjusting frame at the moment, the tightening band is loosened, the fixing spring drives the sliding pressure plate and the press block to slide outwards, the compression spring drives the limit block to reset, and the disassembly and assembly of the machine body are completed, most of equipment is comparatively loaded down with trivial details to the installation and the dismantlement process of organism at present, need assist with the help of professional instrument for the dismouting operation has certain requirement to maintainer's working experience, increases the maintenance cost of equipment, is unfavorable for the subsequent maintenance of equipment, and the easy-to-use nature of above-mentioned problem and improve equipment has effectively been avoided in the application of this device.
2. In the utility model, through the arrangement of the stabilizing device, when the equipment is used, the knob is firstly pinched, the two pressing plates move towards the center, the clamping block on the baffle plate slides along the inner wall of the limiting clamping block until the clamping block is separated, the knob is pulled out at the moment, the connecting rod and the rotating gear move along the limiting clamping block until the limiting plate is separated from the limiting clamping block, the supporting frame is placed on uneven ground, the supporting rod slides on the inner wall of the positioning sleeve, the supporting frame is adjusted to be in a horizontal state by rotating the knob under the action of the rotating gear and the rack, the knob is inserted into the positioning sleeve at the moment, the limiting clamping block slides on the inner wall of the limiting plate until the limiting clamping block is completely jointed, the supporting frame is fixed in the limiting clamping block, the equipment is convenient to be stably used, most of the equipment at present have requirements on a use place, the flat ground needs to be searched or created for use, and the use conditions are harsh, the use efficiency of the equipment is influenced, the normal use of the equipment is not facilitated, the problems are effectively avoided and the stability of the equipment is improved by the application of the device.
Drawings
FIG. 1 is a schematic perspective view of a hydroelectric engineering earthwork excavation observation device provided by the present invention;
FIG. 2 is a schematic structural view of the connecting device of the earth and rock excavation observation device in the hydropower engineering of the present invention;
FIG. 3 is a schematic view of a part of the structure of FIG. 2 in the earth and rock excavation observation device of the present invention;
FIG. 4 is a schematic structural view of a stabilizing device in the earth and rock excavation observation device in the hydroelectric engineering;
fig. 5 is the utility model provides a partial structure schematic diagram of fig. 4 among hydroelectric engineering earth and stone side cut-out observation device.
Illustration of the drawings: 1. a support frame; 2. an adjusting bracket; 3. adjusting a rod; 4. a connecting device; 41. connecting sleeves; 42. fixing the fixture block; 43. briquetting; 44. a sliding platen; 45. tightening the binding belt; 46. a limiting block; 47. a compression spring; 48. positioning a rod; 5. a stabilizing device; 51. a rack; 52. a limiting clamping block; 53. a rotating gear; 54. a connecting rod; 55. a baffle plate; 56. a limiting plate; 57. a stabilizing spring; 58. a limiting spring; 6. a support bar; 7. a positioning sleeve; 8. a body.
Detailed Description
In order to make the above objects, features and advantages of the present invention more clearly understood, the present invention will be further described with reference to the accompanying drawings and examples. It should be noted that the embodiments and features of the embodiments of the present application may be combined with each other without conflict.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention, however, the present invention may be practiced in other ways than those specifically described herein, and therefore the present invention is not limited to the limitations of the specific embodiments of the present disclosure.
Embodiment 1, as shown in fig. 1-5, a hydroelectric engineering earthwork is filled and excavated observation device, including organism 8, alignment jig 2 and connecting device 4, organism 8 is located above alignment jig 2, the lower fixed surface of alignment jig 2 is connected with adjusts pole 3, the lower fixed surface of adjusting pole 3 is connected with support frame 1, the lower fixed surface of support frame 1 is connected with bracing piece 6, the bracing piece 6 is sleeved and slidably connected with position sleeve 7.
The specific arrangement and function of the connecting means 4 and the stabilizing means 5 will be described in detail below.
As shown in fig. 1 and fig. 3, the connecting device 4 is disposed on the upper surface of the adjusting frame 2, the connecting device 4 includes a connecting sleeve 41, the connecting sleeve 41 is fixedly connected to the lower surface of the machine body 8, four symmetrically disposed fixing blocks 42 are fixedly connected to the inner wall of the connecting sleeve 41, a pressing block 43 is inserted and slidably connected to the inner wall of the connecting sleeve 41, a sliding pressure plate 44 is fixedly connected to one end of the pressing block 43 away from the fixing blocks 42, the sliding pressure plate 44 is fixedly connected to the surface of the connecting sleeve 41 through a fixing spring, a tightening strap 45 is sleeved and slidably connected to the sliding pressure plate 44, four symmetrically disposed limiting blocks 46 are slidably connected to one side of the adjusting frame 2 close to the connecting sleeve 41, a positioning rod 48 is fixedly connected to the upper surface of the adjusting frame 2, a positioning rod 48 is fixedly connected to one side of the adjusting frame 2 close to the limiting blocks 46, the positioning rod 48 is slidably connected to the inner wall of the limiting blocks 46, and a pressing spring 47 is fixedly connected to one side of the four limiting blocks 46 close to each other, the surface of the connecting sleeve 41 is fixedly connected with four symmetrically arranged limiting frames, and the sliding pressure plate 44 and the tightening belt 45 are both connected with the inner wall of the limiting frames in a sliding manner.
The whole connecting device 4 achieves the effects that through the arrangement of the connecting device 4, when in use, the machine body 8 is inserted into the mounting frame, the limiting block 46 slides along the inner wall of the connecting sleeve 41, the limiting block 46 gathers inwards under the extrusion of the fixed clamping block 42, the compression spring 47 deforms under force to generate elasticity, when the limiting block 46 passes through the fixed clamping block 42, the compression spring 47 drives the limiting block 46 to expand outwards and abut against the inner wall of the connecting sleeve 41, the installation of the machine body 8 is completed, the opening of the binding belt 45 is kneaded and tightened, the binding belt extrudes the sliding pressure plate 44 to enable the sliding pressure plate to slide towards the connecting sleeve 41, the fixed spring deforms under force to generate elasticity, the pressing block 43 slides towards one end close to the limiting block 46, the limiting block 46 gathers inwards after extrusion, the machine body 8 is separated from the adjusting frame 2, the tightening binding belt 45 is loosened, and the fixed spring drives the sliding pressure plate 44 and the pressing block 43 to slide outwards, pressure spring 47 drives stopper 46 and resets, accomplishes organism 8's dismouting, and most of equipment are comparatively loaded down with trivial details to organism 8's installation and dismantlement process at present, need assist with the help of professional instrument for the dismouting operation has certain requirement to maintainer's experience, increases the maintenance cost of equipment, is unfavorable for the follow-up maintenance of equipment, and the easy-to-use nature of above-mentioned problem and improve equipment has effectively been avoided in the application of this device.
As shown in fig. 1 and 5, the lower surface of the supporting frame 1 is provided with a stabilizing device 5, the stabilizing device 5 comprises a stabilizing spring 57, the stabilizing spring 57 is fixedly connected with the inner wall of the positioning sleeve 7, the end of the stabilizing spring 57 far away from the inner wall of the positioning sleeve 7 is fixedly connected with the supporting rod 6, the end of the positioning sleeve 7 near the supporting rod 6 is fixedly connected with a limiting fixture block 52, the inner wall of the supporting rod 6 is fixedly connected with a rack 51, the inner wall of the positioning sleeve 7 is slidably connected with a limiting plate 56, the surface of the limiting plate 56 is provided with a limiting groove, one side of the limiting plate 56 near the rack 51 is fixedly connected with a connecting rod 54, the end of the connecting rod 54 far away from the limiting plate 56 is fixedly connected with a rotating gear 53, the rotating gear 53 is meshed with the rack 51, the end of the limiting plate 56 far away from the connecting rod 54 is fixedly connected with a knob, the inner wall of the limiting plate 56 is fixedly connected with two symmetrically arranged limiting springs 58, one end of the limiting spring 58 far away from the knob is fixedly connected with a baffle 55, one side of the baffle 55 far away from the limiting spring 58 is fixedly connected with a fixture block, and the fixture block is connected with the inner wall of the limiting fixture block 52 in a sliding manner.
The whole ground stabilizing device 5 has the effects that by arranging the stabilizing device 5, when the equipment is used, the knob is firstly pinched, then the two pressing plates move towards the center, then the clamping blocks on the baffle 55 slide along the inner walls of the limiting clamping blocks 52 until the clamping blocks are separated from the clamping grooves, then the knob is pulled out, then the connecting rod 54 and the rotating gear 53 move along until the limiting plate 56 is separated from the limiting clamping blocks 52, then the support frame 1 is placed on uneven ground, then the supporting rod 6 slides on the inner walls of the positioning sleeves 7, the support frame 1 is adjusted to be in a horizontal state under the action of the rotating gear 53 and the rack 51, at the moment, the knob is inserted into the positioning sleeves 7, then the limiting clamping blocks 52 slide on the inner walls of the limiting clamping blocks 56 until the complete joint is realized, the support frame 1 is fixed in the limiting clamping blocks 52, the stable use of the equipment is convenient, most of the equipment has requirements on use sites at present, the flat ground needs to be found or created for use, the use conditions are harsh, the use efficiency of the equipment is affected, the normal use of the equipment is not facilitated, the problems are effectively avoided and the stability of the equipment is improved.
The above description is only a preferred embodiment of the present invention, and is not intended to limit the present invention in other forms, and any person skilled in the art may use the above-mentioned technical contents to change or modify the equivalent embodiment into equivalent changes and apply to other fields, but any simple modification, equivalent change and modification made to the above embodiments according to the technical matters of the present invention will still fall within the protection scope of the technical solution of the present invention.

Claims (6)

1. The utility model provides a hydroelectric engineering earth and stone side is filled out and is dug observation device, includes organism (8), alignment jig (2) and connecting device (4), its characterized in that: the machine body (8) is positioned above the adjusting frame (2), the adjusting rod (3) is fixedly connected to the lower surface of the adjusting frame (2), the supporting frame (1) is fixedly connected to the lower surface of the adjusting rod (3), the supporting rod (6) is fixedly connected to the lower surface of the supporting frame (1), the positioning sleeve (7) is sleeved and slidably connected to the supporting rod (6), the connecting device (4) is positioned on the upper surface of the adjusting frame (2), the connecting device (4) comprises a connecting sleeve (41), the connecting sleeve (41) is fixedly connected to the lower surface of the machine body (8), four symmetrically-arranged fixing clamping blocks (42) are fixedly connected to the inner wall of the connecting sleeve (41), a pressing block (43) is inserted and slidably connected to the inner wall of the connecting sleeve (41), and a sliding pressing plate (44) is fixedly connected to one end, far away from the fixing clamping block (42), of the pressing block (43), the sliding pressure plate (44) is fixedly connected with the surface of the connecting sleeve (41) through a fixed spring, and a tightening belt (45) is sleeved and connected on the sliding pressure plate (44) in a sliding mode.
2. The hydroelectric engineering earthwork excavation observation device according to claim 1, which is characterized in that: one side sliding connection that alignment jig (2) is close to adapter sleeve (41) has stopper (46) that four symmetries set up, fixed surface is connected with locating lever (48) on alignment jig (2), one side fixedly connected with locating lever (48) that alignment jig (2) are close to stopper (46), locating lever (48) and the inner wall sliding connection of stopper (46).
3. The hydroelectric engineering earthwork excavation observation device according to claim 2, which is characterized in that: four equal fixedly connected with pressure spring (47) in one side that stopper (46) are close to each other, the surperficial fixed connection of adapter sleeve (41) has the spacing of four symmetry settings, sliding pressure plate (44) and tighten up band (45) all with the inner wall sliding connection of spacing.
4. The hydroelectric engineering earthwork excavation observation device according to claim 1, which is characterized in that: the lower surface of support frame (1) is provided with stabilising arrangement (5), stabilising arrangement (5) are including stabilising spring (57), stabilising spring (57) and the inner wall fixed connection of position sleeve (7), the one end and bracing piece (6) fixed connection of position sleeve (7) inner wall are kept away from to stabilising spring (57), position sleeve (7) are close to spacing fixture block (52) of one end fixedly connected with of bracing piece (6), the inner wall fixedly connected with rack (51) of bracing piece (6).
5. The hydroelectric engineering earthwork excavation observation device according to claim 4, which is characterized in that: the locating sleeve (7) inner wall sliding connection has limiting plate (56), the spacing groove has been seted up on the surface of limiting plate (56), one side fixedly connected with connecting rod (54) that limiting plate (56) are close to rack (51), the one end fixedly connected with rotating gear (53) of limiting plate (56) are kept away from in connecting rod (54), rotating gear (53) are connected with rack (51) meshing.
6. The hydroelectric engineering earthwork excavation observation device according to claim 5, which is characterized in that: the one end fixedly connected with knob that connecting rod (54) was kept away from to limiting plate (56), two symmetrical spacing springs (58) that set up of inner wall fixedly connected with of limiting plate (56), one end fixedly connected with baffle (55) of knob are kept away from to spacing spring (58), one side fixedly connected with fixture block that spacing spring (58) were kept away from to baffle (55), the inner wall sliding connection of fixture block and spacing fixture block (52).
CN202120094759.6U 2021-01-13 2021-01-13 Hydroelectric engineering earthwork is filled out and is dug observation device Expired - Fee Related CN214580186U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120094759.6U CN214580186U (en) 2021-01-13 2021-01-13 Hydroelectric engineering earthwork is filled out and is dug observation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120094759.6U CN214580186U (en) 2021-01-13 2021-01-13 Hydroelectric engineering earthwork is filled out and is dug observation device

Publications (1)

Publication Number Publication Date
CN214580186U true CN214580186U (en) 2021-11-02

Family

ID=78368704

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120094759.6U Expired - Fee Related CN214580186U (en) 2021-01-13 2021-01-13 Hydroelectric engineering earthwork is filled out and is dug observation device

Country Status (1)

Country Link
CN (1) CN214580186U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114576494A (en) * 2022-03-03 2022-06-03 合肥筑平建筑工程咨询有限公司 Building engineering cost on-site mapping device based on BIM technology

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114576494A (en) * 2022-03-03 2022-06-03 合肥筑平建筑工程咨询有限公司 Building engineering cost on-site mapping device based on BIM technology
CN114576494B (en) * 2022-03-03 2023-10-24 上海沪港建设咨询有限公司 Building engineering cost on-site mapping device based on BIM technology

Similar Documents

Publication Publication Date Title
CN214580186U (en) Hydroelectric engineering earthwork is filled out and is dug observation device
CN205888892U (en) Polisher convenient to it is fixed
CN108952008A (en) Insert-type steel pipe concrete column and construction method
CN206844715U (en) A kind of novel building ergonomic support device
CN211850870U (en) Novel building engineering formwork supports device
CN209856510U (en) Pipeline supporting equipment for building construction
CN111622574A (en) Electric power construction equipment of fixed wire pole
CN214786169U (en) Rain-proof cover of building site
CN213175687U (en) Bolt connection type support frame with annular structure
CN209368825U (en) A kind of solid mechanical device of stake for building
CN210331590U (en) Suspension type hydraulic basketball stand
CN215165647U (en) Steel cushion box structure for building support
CN206554537U (en) A kind of support beam frame of construction
CN209687872U (en) A kind of reassembling type stage mounting rack
CN213205710U (en) Underground portable support for coal mine safety
CN218540463U (en) Debris flow protective net capable of buffering unloading force
CN216277936U (en) Coal mine stope face supporting construction
CN218907575U (en) Marine large-scale floating airbag composite set
CN220668608U (en) Fixing device for water conservancy pipeline installation
CN210032852U (en) Auxiliary device is fixed in installation of chemical tower ware
CN218565066U (en) Engineering construction support connecting device
CN218466565U (en) Civil engineering stake fixed bolster
CN218093086U (en) Quick installation base for mine hydraulic supporting equipment
CN213627626U (en) Novel end support hydraulic frame
CN220847536U (en) Self-extension pile body and enclosing assembly pile foundation formed by same

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211102