CN214579291U - Hydraulic pipeline for hydraulic engineering - Google Patents

Hydraulic pipeline for hydraulic engineering Download PDF

Info

Publication number
CN214579291U
CN214579291U CN202120942351.XU CN202120942351U CN214579291U CN 214579291 U CN214579291 U CN 214579291U CN 202120942351 U CN202120942351 U CN 202120942351U CN 214579291 U CN214579291 U CN 214579291U
Authority
CN
China
Prior art keywords
base
fixedly connected
hydraulic engineering
hydraulic
fixed frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120942351.XU
Other languages
Chinese (zh)
Inventor
黄志凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202120942351.XU priority Critical patent/CN214579291U/en
Application granted granted Critical
Publication of CN214579291U publication Critical patent/CN214579291U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a water conservancy pipeline for hydraulic engineering, which comprises a pipe body, the both sides fixedly connected with buffer of body, buffer's below is provided with the base, buffer is corresponding with the base, the utility model relates to a hydraulic engineering technical field. This a water conservancy pipeline for hydraulic engineering, reached and set up the base in the below of body, the staff of being convenient for carries out the preinstallation with base and foundation ditch, set up corresponding cushion below the base, adjust the position of base, hoist the body again, improve body installation effectiveness, set up buffer, make the body at the in-process with pedestal mounting, certain shock-absorbing capacity has, improve the protection to the body, the setting is led positive pole and is led positive piece, improve body installation accuracy, set up strutting arrangement, be convenient for consolidate the base, prevent that the base from sliding, make things convenient for the staff to carry out the installation of body, and the work efficiency is improved, and the purpose of user demand is satisfied.

Description

Hydraulic pipeline for hydraulic engineering
Technical Field
The utility model relates to a hydraulic engineering field, more specifically say, relate to a water conservancy pipeline for hydraulic engineering.
Background
Hydraulic engineering is an engineering built for controlling and allocating surface water and underground water in nature to achieve the purposes of removing harmful substances and benefiting. In carrying out the hydraulic engineering work progress, often need use water conservancy pipeline to carry out the drainage to water. At present, current hydraulic engineering pipeline structure is single, and the staff of not being convenient for hoists, when installing, and the staff of not being convenient for supports the regulation to the pipeline, influences the installation effect of pipeline, and then influences drainage efficiency, can't satisfy the user demand.
SUMMERY OF THE UTILITY MODEL
1. Technical problem to be solved
Aiming at the problems that the existing hydraulic engineering pipeline in the prior art is single in structure, inconvenient for workers to hoist and mount, inconvenient for workers to support and adjust the pipeline when in installation, and influences the installation effect of the pipeline, further influences the drainage efficiency, and cannot meet the use requirement, the utility model aims to provide a hydraulic pipeline for hydraulic engineering, which can realize that a pipe body, a buffer device and a base form a whole, the base is arranged below the pipe body, so that the base and a foundation pit can be pre-installed by the workers conveniently, the corresponding cushion block is arranged below the base, the position of the base is adjusted, the pipe body is hoisted, the installation efficiency of the pipe body is improved, the buffer device is arranged, the pipe body has certain buffer performance in the installation process with the base, the protection of the pipe body is improved, and a guide rod and a guide block are arranged, improve body installation accuracy, set up strutting arrangement, be convenient for consolidate the base, prevent that the base from sliding, make things convenient for the staff to carry out the installation of body, improve work efficiency, satisfy the user demand.
2. Technical scheme
In order to solve the above problems, the utility model adopts the following technical proposal.
The utility model provides a water conservancy pipeline for hydraulic engineering, includes the body, the both sides fixedly connected with buffer of body, buffer's below is provided with the base, buffer is corresponding with the base.
Preferably, buffer includes fixed frame, fixed frame and body fixed connection, the inside of fixed frame is provided with spacing frame, the inner wall fixedly connected with supporting spring of spacing frame, spacing frame passes through supporting spring fixedly connected with supporting shoe, the bottom fixedly connected with motion pole of supporting shoe, motion pole and fixed frame sliding connection, the motion pole is located the outside one end fixedly connected with extrusion piece of fixed frame, the extrusion piece is corresponding with the both sides top of base.
Preferably, the top of the fixing frame is fixedly connected with a lifting lug.
Preferably, the inner wall of the base is provided with a rubber pad.
Preferably, the top fixedly connected with of base leads the positive pole, the lateral wall fixedly connected with of fixed frame leads positive piece, it is corresponding with leading the positive pole to lead positive piece.
Preferably, both sides fixedly connected with strutting arrangement of base, strutting arrangement includes the link, link and base lateral wall fixed connection, link threaded connection has the threaded rod, the top fixedly connected with turning block of threaded rod, the bottom fixedly connected with baffle of threaded rod, the bottom fixedly connected with stock of baffle.
3. Advantageous effects
Compared with the prior art, the utility model has the advantages of: the base is arranged below the pipe body, so that a worker can conveniently pre-install the base and a foundation pit, the corresponding cushion blocks are arranged below the base, the position of the base is adjusted, the pipe body is hoisted, the installation efficiency of the pipe body is improved, the buffer device is arranged, the pipe body has certain buffer performance in the process of being installed with the base, the protection of the pipe body is improved, the buffer device is arranged, when the base is installed, the pipe body is installed again, the extrusion blocks are contacted with the two sides of the base and extruded, the extrusion blocks are driven to move upwards, the motion rods are driven to move, the support blocks are driven to move, the elastic potential energy of the support springs is increased, the pipe body has certain buffer performance in the installation process, the protection of the pipe body is improved, the lifting lugs are arranged at the top of the fixing frame, and the hoisting of the worker is facilitated, the inner wall of the base is provided with a rubber pad to improve the protection of the pipe body, the top of the base is provided with a guide rod corresponding to the guide block to improve the installation precision of the pipe body, so that workers can conveniently install the pipe body, the support device is arranged to improve the installation stability of the base, the rotating block is rotated to drive the threaded rod to rotate and drive the baffle plate to move downwards, so that the anchor rod exceeds the base, the ground can be conveniently clamped, the installation stability of the base is improved, the installation stability of the pipe body is further improved, the pipe body, the buffer device and the base are integrated, the base is arranged below the pipe body, so that the workers can conveniently pre-install the base and the foundation pit, the corresponding cushion blocks are arranged below the base, the position of the base is adjusted, the pipe body is hoisted, the installation efficiency of the pipe body is improved, the buffer device is arranged, so that the pipe body has certain buffer performance in the installation process of the base, the improvement is to the protection of body, sets up and leads positive pole and lead positive piece, improves body installation accuracy, sets up strutting arrangement, is convenient for consolidate the base, prevents that the base from sliding, makes things convenient for the staff to carry out the installation of body, improves work efficiency, satisfies user demand's purpose.
Drawings
Fig. 1 is a schematic view of the overall external structure of the present invention;
FIG. 2 is a schematic view of the overall internal structure of the present invention;
fig. 3 is a schematic view of a part of an enlarged structure of fig. 2 according to the present invention.
The reference numbers in the figures illustrate:
1. a pipe body; 2. a buffer device; 21. a fixing frame; 22. a limiting frame; 23. a support spring; 24. a support block; 25. a motion bar; 26. extruding the block; 3. lifting lugs; 4. a base; 5. a rubber pad; 6. a guide rod; 7. a guide block; 8. a support device; 81. a connecting frame; 82. a threaded rod; 83. rotating the block; 84. a baffle plate; 85. an anchor rod.
Detailed Description
The drawings in the embodiments of the present invention will be combined; the technical scheme in the embodiment of the utility model is clearly and completely described; obviously; the described embodiments are only some of the embodiments of the present invention; rather than all embodiments. Based on the embodiment of the utility model; all other embodiments obtained by a person skilled in the art without making any inventive step; all belong to the protection scope of the utility model.
Example 1:
referring to fig. 1-3, the present invention provides a technical solution: the utility model provides a water conservancy pipeline for hydraulic engineering, includes body 1, the both sides fixedly connected with buffer 2 of body 1, and buffer 2's below is provided with base 4, and buffer 2 is corresponding with base 4. Body 1, buffer 2 and base 4 constitute a whole, set up base 4 in the below of body 1, the staff of being convenient for carries out pre-installation with base 4 and foundation ditch, set up corresponding cushion in base 4 below, adjust the position of base 4, hoist and mount body 1 again, improve body 1 installation effectiveness, set up buffer 2 for body 1 has certain shock-absorbing capacity at the in-process of installing with base 4, the improvement is to the protection of body 1.
Example 2:
referring to fig. 3, a water conservancy pipeline for water conservancy projects is substantially the same as that in embodiment 1, and further, the buffering device 2 includes a fixing frame 21, the fixing frame 21 is fixedly connected to the pipe body 1, a limiting frame 22 is disposed inside the fixing frame 21, a supporting spring 23 is fixedly connected to an inner wall of the limiting frame 22, a supporting block 24 is fixedly connected to the limiting frame 22 through the supporting spring 23, a moving rod 25 is fixedly connected to a bottom of the supporting block 24, the moving rod 25 is slidably connected to the fixing frame 21, an extruding block 26 is fixedly connected to one end of the moving rod 25, which is located outside the fixing frame 21, and the extruding block 26 corresponds to tops of two sides of the base 4. Set up buffer 2, when base 4 installation was accomplished, install body 1 again, extrusion piece 26 contacts with base 4 both sides to extrude, drive extrusion piece 26 upward movement, drive motion pole 25 motion, drive supporting shoe 24 motion, increase supporting spring 23's elastic potential energy, make body 1 in the installation, have certain shock-absorbing capacity, improve the protection to body 1.
Example 3:
referring to fig. 3, a water conservancy pipeline for water conservancy projects is substantially the same as the embodiment 2, and further, a lifting lug 3 is fixedly connected to the top of the fixed frame 21. The top of the fixed frame 21 is provided with a lifting lug 3, so that the lifting can be conveniently carried out by workers.
Example 4:
referring to fig. 2, a water pipeline for water conservancy projects is substantially the same as that of embodiment 1, and further, a rubber pad 5 is disposed on an inner wall of a base 4. The inner wall of the base 4 is provided with a rubber pad 5, so that the protection of the pipe body 1 is improved.
Example 5:
referring to fig. 2, a water conservancy pipeline for water conservancy projects is substantially the same as that of embodiment 2, and further, a guide rod 6 is fixedly connected to the top of the base 4, a guide block 7 is fixedly connected to the side wall of the fixing frame 21, and the guide block 7 corresponds to the guide rod 6. The top of the base 4 is provided with the guide rod 6 corresponding to the guide block 7, so that the installation accuracy of the pipe body 1 is improved, and the installation by workers is facilitated.
Example 6:
referring to fig. 2, a water conservancy pipeline for water conservancy projects is substantially the same as that in embodiment 1, further, two sides of the base 4 are fixedly connected with the supporting devices 8, each supporting device 8 includes a connecting frame 81, the connecting frame 81 is fixedly connected with the side wall of the base 4, the connecting frame 81 is in threaded connection with a threaded rod 82, the top of the threaded rod 82 is fixedly connected with a rotating block 83, the bottom of the threaded rod 82 is fixedly connected with a baffle 84, and the bottom of the baffle 84 is fixedly connected with an anchor rod 85. Set up strutting arrangement 8, improve base 4 installation stability, rotate turning block 83, drive threaded rod 82 and rotate, drive baffle 84 downstream for stock 85 surpasss base 4, is convenient for carry out the joint to ground, improves base 4 installation stability, and then improves body 1 installation stability.
The above; is only a preferred embodiment of the present invention; however, the scope of protection of the present invention is not limited thereto; any person skilled in the art is within the technical scope of the present disclosure; according to the technical scheme of the utility model and the improvement conception, equivalent substitution or change is carried out; are all covered by the protection scope of the utility model.

Claims (6)

1. The utility model provides a water conservancy pipeline for hydraulic engineering, includes body (1), its characterized in that: the pipe is characterized in that buffering devices (2) are fixedly connected to two sides of the pipe body (1), a base (4) is arranged below each buffering device (2), and the buffering devices (2) correspond to the base (4).
2. A hydraulic conduit for hydraulic engineering according to claim 1, wherein: buffer (2) are including fixed frame (21), fixed frame (21) and body (1) fixed connection, the inside of fixed frame (21) is provided with spacing frame (22), the inner wall fixedly connected with supporting spring (23) of spacing frame (22), spacing frame (22) are through supporting spring (23) fixedly connected with supporting shoe (24), the bottom fixedly connected with motion pole (25) of supporting shoe (24), motion pole (25) and fixed frame (21) sliding connection, motion pole (25) are located the outside one end fixedly connected with extrusion piece (26) of fixed frame (21), extrusion piece (26) are corresponding with the both sides top of base (4).
3. A hydraulic conduit for hydraulic engineering according to claim 2, wherein: the top of the fixed frame (21) is fixedly connected with a lifting lug (3).
4. A hydraulic conduit for hydraulic engineering according to any one of claims 1 to 3, wherein: the inner wall of the base (4) is provided with a rubber pad (5).
5. A hydraulic conduit for hydraulic engineering according to claim 2, wherein: the top fixedly connected with of base (4) leads positive pole (6), the lateral wall fixedly connected with of fixed frame (21) leads positive piece (7), it is corresponding with leading positive pole (6) to lead positive piece (7).
6. A hydraulic conduit for hydraulic engineering according to claim 1, 2, 3 or 5, wherein: the utility model discloses a quick-witted support structure, including base (4), both sides fixedly connected with strutting arrangement (8) of base (4), strutting arrangement (8) are including link (81), link (81) and base (4) lateral wall fixed connection, link (81) threaded connection has threaded rod (82), the top fixedly connected with turning block (83) of threaded rod (82), the bottom fixedly connected with baffle (84) of threaded rod (82), the bottom fixedly connected with stock (85) of baffle (84).
CN202120942351.XU 2021-05-06 2021-05-06 Hydraulic pipeline for hydraulic engineering Active CN214579291U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120942351.XU CN214579291U (en) 2021-05-06 2021-05-06 Hydraulic pipeline for hydraulic engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120942351.XU CN214579291U (en) 2021-05-06 2021-05-06 Hydraulic pipeline for hydraulic engineering

Publications (1)

Publication Number Publication Date
CN214579291U true CN214579291U (en) 2021-11-02

Family

ID=78328915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120942351.XU Active CN214579291U (en) 2021-05-06 2021-05-06 Hydraulic pipeline for hydraulic engineering

Country Status (1)

Country Link
CN (1) CN214579291U (en)

Similar Documents

Publication Publication Date Title
CN214579291U (en) Hydraulic pipeline for hydraulic engineering
CN208816847U (en) A kind of cross-arm regulating device for assembled suspension and support
CN201103383Y (en) Fine adjustment balancing device of oil pumping machine
CN210288702U (en) Building waterproof board structure
CN210766881U (en) Internal mold supporting device
CN212430005U (en) Pipeline protector is used in hydraulic engineering construction
CN212616775U (en) Pipeline fixing device on scaffold is built in room
CN214879740U (en) Tower crane attachment device
CN216242671U (en) Water conservancy and hydropower engineering's drain pipe reinforcement instrument
CN212672566U (en) Hydraulic pipeline for hydraulic engineering
CN212251603U (en) Water conservancy pipeline connection changes to piece
CN211046382U (en) Cable conduit supporting hanger
CN214314281U (en) A circuit supporting structure for municipal works
CN215060025U (en) Support frame for hydraulic engineering construction
CN213174903U (en) Strutting arrangement is used in building engineering construction
CN219975639U (en) A water conservancy pipeline support frame for hydraulic engineering
CN214331709U (en) Pump station pipeline supporting and hanging device for water conservancy project
CN212986294U (en) Novel construction fire pipeline mounting structure
CN220102298U (en) A water conservancy pipeline bearing structure for hydraulic engineering
CN106410671B (en) A kind of device for aiding in changing tube type bus support porcelain vase
CN214504581U (en) Alarm for hydraulic and hydroelectric engineering construction management
CN214755285U (en) Electromechanical bridge frame capable of flexibly adjusting length and width
CN212455775U (en) Pipeline fixer for water conservancy construction
CN217501714U (en) Temporary roadway supporting device for mining engineering
CN220470830U (en) Water supply and drainage arrangement mechanism

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant