CN214575822U - Construction equipment that steel construction abnormal shape aluminum plate cornices is encorbelmented to roofing - Google Patents

Construction equipment that steel construction abnormal shape aluminum plate cornices is encorbelmented to roofing Download PDF

Info

Publication number
CN214575822U
CN214575822U CN202022890791.3U CN202022890791U CN214575822U CN 214575822 U CN214575822 U CN 214575822U CN 202022890791 U CN202022890791 U CN 202022890791U CN 214575822 U CN214575822 U CN 214575822U
Authority
CN
China
Prior art keywords
layer overhead
overhead vehicle
aluminum plate
supporting seat
overhead trolley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022890791.3U
Other languages
Chinese (zh)
Inventor
朱宝君
代晓朋
张纪刚
刘振林
邢连杰
宋浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202022890791.3U priority Critical patent/CN214575822U/en
Application granted granted Critical
Publication of CN214575822U publication Critical patent/CN214575822U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Tents Or Canopies (AREA)

Abstract

The utility model discloses a construction equipment that steel construction abnormal shape aluminum plate that encorbelments of roofing eaves, including braced frame, lower floor's overhead vehicle is installed to braced frame's higher authority, and upper-deck overhead vehicle is installed to lower floor's overhead vehicle's higher authority, and lower floor's overhead vehicle is installed on braced frame's flower frame roof beam, installs the anticreep device below lower floor's overhead vehicle, and the anticreep device comprises limit baffle, upper fixed plate, support frame, roller bearing, supporting seat and bottom plate, and beneficial effect is: through having set up lower floor's overhead vehicle and upper strata overhead vehicle for the process of carrying out the hoist and mount removal to mounting material in the installation is more convenient, both can so that mounting material carries out lateral shifting and also can make mounting material model longitudinal movement, makes mounting material's installation lighter, also makes mounting material's welding process more accurate, has increased work efficiency.

Description

Construction equipment that steel construction abnormal shape aluminum plate cornices is encorbelmented to roofing
Technical Field
The utility model relates to a construction equipment field specifically is a construction equipment that steel construction abnormal shape aluminum plate that encorbelments of roofing eaves.
Background
At present, the construction of the aluminum plate curtain wall mostly adopts on-site assembly of parts, and due to the complexity of the overhanging steel structure roof cornice aluminum plate curtain wall and the repeated welding quality and positioning position of the keel, the welding efficiency is low, the high-altitude welding amount is large, the quality cannot be ensured, the installation efficiency of the keel and the cornice aluminum plate is low, and particularly, the installation of the cornice bottom aluminum plate is easy to cause the quality problem; by adopting the lifting device for the overhanging roof cornice aluminum plate curtain wall unit and the construction method thereof, the quality hidden troubles of infirm repeated welding and the like caused by the uncertainty of the positions of keel connection are avoided, meanwhile, the construction is simple and convenient, the operability is strong, the connection stability is high, and the construction quality is easy to ensure
Therefore, the utility model provides a construction equipment that steel construction abnormal shape aluminum plate that roofing was encorbelmented eaves is used for solving above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a construction equipment that steel construction abnormal shape aluminum plate cornices is encorbelmented to the roofing to solve the problem that provides among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a construction device for cornice of a roof overhanging steel structure special-shaped aluminum plate comprises a supporting frame, wherein a lower-layer overhead trolley is arranged on the supporting frame, an upper-layer overhead trolley is arranged on the upper surface of the lower-layer overhead trolley, the lower-layer overhead trolley is arranged on a flower frame beam of the supporting frame, an anti-falling device is arranged below the lower-layer overhead trolley, the anti-falling device comprises a limit baffle, an upper fixing plate, a supporting frame, a rolling shaft, a supporting seat and a lower fixing plate, the limit baffle is welded below the lower-layer overhead trolley, the inner side of the limit baffle is vertically welded with the upper fixing plate and the lower fixing plate, the supporting seat is arranged on the lower fixing plate, the supporting frame is vertically welded on the supporting seat and the upper fixing plate, the rolling shaft is arranged on the supporting frame, the rolling shaft can enable the lower-layer overhead trolley to be capable of reducing friction force with the flower frame beam in the process of moving installation materials, and is more labor-saving, the limit baffle can prevent the derailment phenomenon from occurring when the lower-layer overhead trolley moves on the flower shelf beam, and the safety is improved.
Preferably, the round hole has been seted up in the centre of bottom plate, and round hole department vertical welding has the set nut piece, installs the bolt in the set nut piece, through rotatory bolt, just can control the supporting seat and carry out the oscilaltion process, can adjust the supporting seat according to the actual thickness of flower frame roof beam like this for upper and lower roller bearing can be better with the laminating of flower frame roof beam, remove the in-process more save worry laborsaving, and increase the security.
Preferably, the lateral wall of supporting seat is provided with sawtooth draw runner and rectangle draw runner respectively the symmetry, and sawtooth draw runner and rectangle draw runner vertical welding respectively are on the lateral wall of supporting seat, and peg graft on the bottom plate together with the supporting seat.
Preferably, one side of sawtooth draw runner is equipped with prevents descending mechanism, prevents descending mechanism by spacing, cylindric lock and supporting shoe, and the supporting shoe vertical welding is equipped with spacing between the supporting shoe on the bottom plate, spacing passing through cylindric lock and supporting shoe swing joint, and when mounting material at the in-process that removes, if mounting material makes lower floor's built on stilts car and limit baffle descend suddenly, spacing can in time block the sawtooth draw runner, prevents to cause the incident.
Preferably, the mounting mode of the upper-layer overhead trolley and the lower-layer overhead trolley is the same as that of the lower-layer overhead trolley and the flower-shaped frame beam, steel beams are welded on the upper-layer overhead trolley, three groups of steel beams are arranged at equal intervals, and the steel beams are used for mounting the chain block, so that the mounting material can be hoisted and is convenient to move.
Preferably, a second traction rope is installed in the middle of the lower-layer overhead vehicle, and a first traction rope is installed in the middle of the upper-layer overhead vehicle.
Compared with the prior art, the beneficial effects of the utility model are that:
by arranging the lower-layer overhead vehicle and the upper-layer overhead vehicle, the process of hoisting and moving the mounting material in the mounting process is more convenient, the mounting material can be moved transversely and the type of the mounting material can be moved longitudinally, the mounting process of the mounting material is easier, the welding process of the mounting material is more accurate, and the working efficiency is improved;
through having set up limit baffle and roller bearing for lower floor's overhead vehicle and upper strata overhead vehicle can not appear the phenomenon of derailing at the in-process that removes, have increased the security in the use, simultaneously under the effect of roller bearing, less frictional force makes lower floor's overhead vehicle and upper strata overhead vehicle can relax laborsaving more at the in-process that removes.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of the present invention;
FIG. 3 is a schematic structural view of the present invention;
fig. 4 is a schematic structural diagram of the present invention.
In the figure: the support frame comprises a support frame 1, a flower shelf beam 2, a lower-layer overhead vehicle 3, a limit baffle 4, a first traction rope 5, an upper-layer overhead vehicle 6, a steel beam 7, a second traction rope 8, an upper fixing plate 9, a support frame 10, a sawtooth slide bar 11, a limit bar 1101, a cylindrical pin 1102, a support block 1103, a rolling shaft 12, a support seat 13, a lower fixing plate 14, a bolt 15, a fixing nut block 16 and a rectangular slide bar 17.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below. The embodiments of the present invention, all other embodiments obtained by a person skilled in the art without creative work, all belong to the protection scope of the present invention.
Referring to fig. 1 to 4, the present invention provides a technical solution: a construction device for cornice of a roof overhanging steel structure special-shaped aluminum plate comprises a supporting frame 1, wherein a lower-layer overhead trolley 3 is arranged on the supporting frame 1, an upper-layer overhead trolley 6 is arranged on the upper-layer overhead trolley 3, the lower-layer overhead trolley 3 is arranged on a flower shelf beam 2 of the supporting frame 1, an anti-falling device is arranged below the lower-layer overhead trolley 3 and consists of a limit baffle 4, an upper fixing plate 9, a supporting frame 10, a rolling shaft 12, a supporting seat 13 and a lower fixing plate 14, the limit baffle 4 is welded below the lower-layer overhead trolley 3, the inner side of the limit baffle 4 is vertically welded with the upper fixing plate 9 and the lower fixing plate 14, the supporting seat 13 is arranged on the lower fixing plate 14, the supporting frame 10 is vertically welded on the supporting seat 13 and the upper fixing plate 9, the rolling shaft 12 is arranged on the supporting frame 10, and the rolling shaft 12 can enable the lower-layer overhead trolley 3 to move on the flower shelf beam 2 in the process, reduce the frictional force with pergola roof beam 2 for lower floor's overhead vehicle 3 is more laborsaving at the process of removing the installation material, and limit baffle 4 can prevent that derailment phenomenon from appearing in the time of lower floor's overhead vehicle 3 removes on pergola roof beam 2, has increased the security.
The round hole has been seted up to the centre of bottom plate 14, and round hole department vertical welding has fixed nut piece 16, installs bolt 15 in the fixed nut piece 16, through rotatory bolt 15, just can control supporting seat 13 and carry out the oscilaltion process, can adjust supporting seat 13 according to the actual thickness of flower frame roof beam 2 like this for upper and lower roller bearing 12 can be better with the laminating of flower frame roof beam 2, remove the in-process more laborsaving of worrying, and increase the security.
Sawtooth sliding strips 11 and rectangular sliding strips 17 are symmetrically arranged on the side walls of the supporting seat 13 respectively, and the sawtooth sliding strips 11 and the rectangular sliding strips 17 are vertically welded on the side walls of the supporting seat 13 respectively and are inserted into the lower fixing plate 14 together with the supporting seat 13.
One side of sawtooth draw runner 11 is equipped with prevents descending mechanism, prevent descending mechanism by spacing 1101, cylindric lock 1102 and supporting shoe 1103, supporting shoe 1103 vertical welding is on bottom plate 14, be equipped with spacing 1101 between the supporting shoe 1103, spacing 1101 is through cylindric lock 1102 and supporting shoe 1103 swing joint, when mounting material at the in-process that removes, if mounting material makes lower floor's overhead vehicle 3 and limit baffle 4 descend suddenly, spacing 1101 can in time block sawtooth draw runner 11, prevent to cause the incident.
The mounting mode of the upper-layer overhead vehicle 6 and the lower-layer overhead vehicle 3 is the same as that of the lower-layer overhead vehicle 3 and the flower frame beam 2, the steel beams 7 are welded on the upper-layer overhead vehicle 6, the steel beams 7 are totally provided with three groups in an equidistant mode, and the steel beams 7 are used for mounting the chain block, so that the mounting material can be hoisted and is convenient to move.
The second traction rope 8 is installed in the middle of the lower-layer overhead vehicle 3, and the first traction rope 5 is installed in the middle of the upper-layer overhead vehicle 6.
The working principle is as follows: in the in-process of using, when needs hoist and mount mounting material, at first install chain block on girder steel 7, fix required mounting material on chain block afterwards, when needs vertically move mounting material, pulling second haulage rope 8, second haulage rope 8 will stimulate lower floor's overhead vehicle 3 and upper strata overhead vehicle 6 longitudinal movement, when needs carry out lateral shifting to mounting material, stimulate first haulage rope 5, first haulage rope 5 will make upper strata overhead vehicle 6 take mounting material to carry out lateral shifting on lower floor's overhead vehicle 3.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a construction equipment that steel construction abnormal shape aluminum plate cornices is encorbelmented to roofing, includes braced frame (1), its characterized in that: the upper surface of the supporting frame (1) is provided with a lower layer overhead trolley (3), the upper surface of the lower layer overhead trolley (3) is provided with an upper layer overhead trolley (6), the lower layer overhead trolley (3) is arranged on the flower shelf beam (2) of the supporting frame (1), the lower surface of the lower layer overhead trolley (3) is provided with an anti-falling device, the anti-falling device consists of a limit baffle (4), an upper fixing plate (9) and a supporting frame (10), roller bearing (12), supporting seat (13) and bottom plate (14) are constituteed, and limit baffle (4) welding is below lower floor's overhead vehicle (3), and the inboard vertical welding of limit baffle (4) has upper fixed plate (9) and bottom plate (14), installs supporting seat (13) on bottom plate (14), and equal vertical welding has support frame (10) on supporting seat (13) and upper fixed plate (9), installs roller bearing (12) on support frame (10).
2. The construction device for the cornice of the roof overhanging steel structure special-shaped aluminum plate, according to claim 1, is characterized in that: a round hole is formed in the middle of the lower fixing plate (14), a fixing nut block (16) is perpendicularly welded to the round hole, and a bolt (15) is installed in the fixing nut block (16).
3. The construction device for the cornice of the roof overhanging steel structure special-shaped aluminum plate, according to claim 1, is characterized in that: sawtooth sliding strips (11) and rectangular sliding strips (17) are symmetrically arranged on the side walls of the supporting seat (13) respectively, and the sawtooth sliding strips (11) and the rectangular sliding strips (17) are vertically welded on the side walls of the supporting seat (13) respectively and are inserted into the lower fixing plate (14) together with the supporting seat (13).
4. The construction device for the cornice of the roof overhanging steel structure special-shaped aluminum plate, according to claim 3, is characterized in that: one side of the sawtooth sliding strip (11) is provided with an anti-falling mechanism, the anti-falling mechanism is composed of a limiting strip (1101), a cylindrical pin (1102) and supporting blocks (1103), the supporting blocks (1103) are vertically welded on the lower fixing plate (14), the limiting strip (1101) is arranged between the supporting blocks (1103), and the limiting strip (1101) is movably connected with the supporting blocks (1103) through the cylindrical pin (1102).
5. The construction device for the cornice of the roof overhanging steel structure special-shaped aluminum plate, according to claim 1, is characterized in that: the mounting mode of upper-layer overhead trolley (6) and lower-layer overhead trolley (3) is the same as that of lower-layer overhead trolley (3) and flower stand beam (2), steel beam (7) is welded on the upper-layer overhead trolley (6), three groups of steel beams (7) are arranged at the same interval, and chain blocks are mounted on the steel beams (7).
6. The construction device for the cornice of the roof overhanging steel structure special-shaped aluminum plate, according to claim 1, is characterized in that: and a second traction rope (8) is installed in the middle of the lower-layer overhead vehicle (3), and a first traction rope (5) is installed in the middle of the upper-layer overhead vehicle (6).
CN202022890791.3U 2020-12-07 2020-12-07 Construction equipment that steel construction abnormal shape aluminum plate cornices is encorbelmented to roofing Active CN214575822U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022890791.3U CN214575822U (en) 2020-12-07 2020-12-07 Construction equipment that steel construction abnormal shape aluminum plate cornices is encorbelmented to roofing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022890791.3U CN214575822U (en) 2020-12-07 2020-12-07 Construction equipment that steel construction abnormal shape aluminum plate cornices is encorbelmented to roofing

Publications (1)

Publication Number Publication Date
CN214575822U true CN214575822U (en) 2021-11-02

Family

ID=78330630

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022890791.3U Active CN214575822U (en) 2020-12-07 2020-12-07 Construction equipment that steel construction abnormal shape aluminum plate cornices is encorbelmented to roofing

Country Status (1)

Country Link
CN (1) CN214575822U (en)

Similar Documents

Publication Publication Date Title
CN109653105B (en) Main truss system of box girder bridge cantilever construction hanging basket and use method thereof
CN211141352U (en) Combined type track dismantling device used in shield construction method
CN202245811U (en) Combined curtain wall hoisting equipment
CN212101696U (en) Novel bridge crane
CN214575822U (en) Construction equipment that steel construction abnormal shape aluminum plate cornices is encorbelmented to roofing
CN210529487U (en) Bridge and box-shaped bridge inspection device with flange plates
CN217801443U (en) Special tool for installing loop swing door
CN203383516U (en) Construction device for installing connecting beam on frame type steel structure
CN216476416U (en) Building engineering platform of unloading
CN212154108U (en) Wall-attached type anti-tilting and anti-falling support
CN210855028U (en) Portable lighting equipment overhead hoist is used in radio and television engineering
CN2209702Y (en) Saffold
CN221216935U (en) Assembled curtain wall unit body lifting device for super high-rise building reconstruction
CN211949676U (en) Steel construction track fixing device
CN219387118U (en) Single-side suspension movable working platform
CN217708658U (en) Curtain wall installation can climb roofing system of hanging
CN219690747U (en) Sliding protective shed
CN219730323U (en) Wet joint template lifting device
CN220167451U (en) Steel construction removes hanging flower basket device
CN216426527U (en) Door and window debugging frame
CN220886775U (en) Gantry type lifting equipment
CN212315359U (en) Double-main-beam hook bridge crane
CN218623229U (en) High altitude vestibule curtain bottom overhauls device
CN217734783U (en) Special-shaped outer vertical face suspension rail type movable hanging basket
CN218176710U (en) High plug-type platform of unloading of security