CN214525032U CN202120686144.2U CN202120686144U CN214525032U CN 214525032 U CN214525032 U CN 214525032U CN 202120686144 U CN202120686144 U CN 202120686144U CN 214525032 U CN214525032 U CN 214525032U
Authority
CN
China
Prior art keywords
layer support
main frames
pipe
support
welded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120686144.2U
Other languages
Chinese (zh)
Inventor
王伟
夏扬帆
赵有收
高树青
魏君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Civil Engineering Co Ltd
Original Assignee
China Construction Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Civil Engineering Co Ltd filed Critical China Construction Civil Engineering Co Ltd
Priority to CN202120686144.2U priority Critical patent/CN214525032U/en
Application granted granted Critical
Publication of CN214525032U publication Critical patent/CN214525032U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The application relates to a support is deposited to pile foundation construction pipe, including bottom layer support, intermediate level support, top layer support and lift mechanism. The lifting mechanism can be independently installed on the bottom layer support, the middle layer support and the top layer support, a plurality of guide pipe bodies are placed on the bottom layer support, the middle layer support and the top layer support, the bottom layer support comprises two first main frames and two first connecting rods, the two first main frames and the two first connecting rods are welded in a square shape, and the connecting rods and the top of the first main frames are welded with a plurality of partition pipes. The utility model discloses in, through when in actual use, the user places the bottom support in subaerial earlier, then just can be very laborsaving through lifting the mechanism and place the pipe body on bottom support, intermediate level support and top layer support, also can classify the neat placing of pipe body moreover, saves occupation space, conveniently transports, also conveniently washes the pipe body.

Description

Pile foundation construction pipe storage support
Technical Field
The application relates to the field of bridge engineering construction, in particular to a pile foundation construction conduit storage support.
Background
The low pile foundation is a deep foundation consisting of piles and pile bearing platforms (bearing platforms for short) connected with the pile tops or a single pile foundation connected with the piles by the piles and the pile foundation, namely a pile foundation for short, and if the pile bodies are completely buried in the soil and the bottom surfaces of the bearing platforms are contacted with the soil body, the low pile foundation is called as a low pile foundation; if the upper part of the pile body is exposed out of the ground and the bottom of the pile cap is positioned above the ground, the pile body is called a high pile cap foundation, the building pile foundation is usually a low pile cap pile foundation, and the pile foundation is widely applied in high-rise buildings.
At present, the pile foundation fills the in-process, and the pipe of extracting is generally all scattered to place on the ground, and it is big to deposit the mode randomness, brings to transport inconvenient, occupy site area big, wash unclean scheduling problem, how reasonable planning and utilization construction site standardize the pile foundation pipe and put the mode, and the washing and the concentrated transportation of the pile foundation pipe of being convenient for are the starting point of this scheme.
SUMMERY OF THE UTILITY MODEL
In order to solve present pipe and place in disorder, occupation space is big, transports inconveniently, washes unclean technical problem, this application provides a support is deposited to pile foundation construction pipe.
The application provides a pair of support is deposited to pile foundation construction pipe adopts following technical scheme: the utility model provides a support is deposited to pile foundation construction pipe, includes bottom support, intermediate level support, top layer support and lifts the mechanism: the lifting mechanism can be independently arranged on the bottom layer bracket, the middle layer bracket and the top layer bracket, and a plurality of catheter bodies are respectively arranged on the bottom layer bracket, the middle layer bracket and the top layer bracket;
the bottom layer support comprises two main frames I and two connecting rods I, the two main frames I and the two connecting rods I are welded together in a square shape, a plurality of partition pipes I are welded at the tops of the connecting rods I and the main frames I, a bearing pipe I is welded between the two main frames I, and supporting legs are welded at two sides of the bottom of the main frames I;
the middle layer support comprises two main frames II and two connecting rods II, the two main frames II and the two connecting rods II are welded together in a square shape, a plurality of partition pipes II are welded at the tops of the connecting rods II and the main frames II, a bearing pipe II is welded between the two main frames II, and inserting pipes are welded at two sides of the bottom of each main frame II;
the top layer support comprises two third main frames and two third connecting rods, the two third main frames and the two third connecting rods are welded together in a shape like a Chinese character 'kou', a plurality of partition pipes III are welded at the tops of the three connecting rods and the three main frames, a bearing pipe III is welded between the two third main frames, and three insertion pipes III are welded on two sides of the bottoms of the three main frames.
Preferably, the second partition pipes on the second main frames are inserted into the inner cavity of the third insertion pipe, and the first partition pipes on the first main frames are inserted into the inner cavity of the insertion pipe.
Preferably, the length of the leg is less than the length of the cannula and the cannula III, and the bottom of the leg is placed on the ground.
Preferably, a single catheter body is placed between two adjacent partition pipes I, two adjacent partition pipes II and two adjacent partition pipes III.
Preferably, lift mechanism including the cover establish two fixed mounting cover on body frame one or body frame two or body frame three, one side of fixed mounting cover is run through and is provided with fastening bolt, fastening bolt's surperficial threaded connection has lock nut, fixed mounting cover through fastening bolt and lock nut fixed mounting on body frame one or body frame two or body frame three.
Preferably, one side demountable installation of fixed mounting cover has the mounting bracket, and the inboard fixedly connected with of mounting bracket rotates the axostylus axostyle, and two surperficial swing joint that rotate the axostylus axostyle have the support frame, and the surperficial threaded connection who rotates the axostylus axostyle has the installation nut.
Preferably, stop levers are welded on two sides of the top of the lifting frame.
Preferably, the first partition pipe, the second partition pipe and the third partition pipe are adjacent at equal intervals.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the utility model discloses in, through when in actual use, the user places the bottom support in subaerial earlier, then just can be very laborsaving through lifting the mechanism and place the pipe body on bottom support, intermediate level support and top layer support, also can classify the neat placing of pipe body moreover, saves occupation space, conveniently transports, also conveniently washes the pipe body.
2. The utility model discloses in through the setting of lifting mechanism, when placing the pipe body, can classify the arrangement through lifting the laborsaving quick pipe body of will organizing and place, the operation of being convenient for, the person of facilitating the use uses.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this application, serve to provide a further understanding of the application and to enable other features, objects, and advantages of the application to be more apparent. The drawings and their description illustrate the embodiments of the invention and do not limit it. In the drawings:
FIG. 1 is a schematic structural diagram of an embodiment.
FIG. 2 is a perspective assembly view of a lifting mechanism according to an embodiment.
Fig. 3 is an exploded perspective view of the first embodiment.
FIG. 4 is a perspective view of a lift mechanism according to an embodiment.
Description of reference numerals: 1. a bottom layer support; 2. a middle layer support; 3. a top layer support; 4. a catheter body; 5. a lifting mechanism; 101. a first main frame; 102. a first connecting rod; 103. a first bearing pipe; 104. a first isolating pipe; 105. a support leg; 21. a second main frame; 22. a second connecting rod; 23. a second bearing pipe; 24. a second isolating pipe; 25. inserting a tube; 31. a main frame III; 32. a third connecting rod; 33. a third bearing pipe; 34. a third isolating pipe; 35. inserting a pipe III; 51. fixing the mounting sleeve; 52. fastening a bolt; 53. locking the nut; 54. a mounting frame; 55. rotating the shaft lever; 56. a lifting frame; 57. installing a nut; 58. a stop lever.
Detailed Description
In order to make the technical solutions better understood by those skilled in the art, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only partial embodiments of the present application, but not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
It should be noted that the terms "first," "second," and the like in the description and claims of this application and in the drawings described above are used for distinguishing between similar elements and not necessarily for describing a particular sequential or chronological order. It should be understood that the data so used may be interchanged under appropriate circumstances such that embodiments of the application described herein may be used. Furthermore, the terms "comprises," "comprising," and "having," and any variations thereof, are intended to cover a non-exclusive inclusion, such that a process, method, system, article, or apparatus that comprises a list of steps or elements is not necessarily limited to those steps or elements expressly listed, but may include other steps or elements not expressly listed or inherent to such process, method, article, or apparatus.
In this application, the terms "upper", "lower", "left", "right", "front", "rear", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings. These terms are used primarily to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to a particular orientation or to be constructed and operated in a particular orientation.
Moreover, some of the above terms may be used to indicate other meanings besides the orientation or positional relationship, for example, the term "on" may also be used to indicate some kind of attachment or connection relationship in some cases. The specific meaning of these terms in this application will be understood by those of ordinary skill in the art as appropriate.
In addition, the term "plurality" shall mean two as well as more than two.
It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. The present application is described in further detail below with reference to figures 1-4.
Example (b):
combine fig. 1 to 4, this application embodiment discloses a support is deposited to pile foundation construction pipe, including bottom layer support 1, intermediate level support 2, top layer support 3 and lift mechanism 5: the lifting mechanism 5 can be independently installed on the bottom layer support 1, the middle layer support 2 and the top layer support 3, a plurality of guide pipe bodies 4 are respectively placed on the bottom layer support 1, the middle layer support 2 and the top layer support 3, the bottom layer support 1 comprises two main frames I101 and two connecting rods I102, the two main frames I101 and the two connecting rods I102 are welded together in a square shape, a plurality of partition pipes I104 are welded at the tops of the connecting rods I102 and the main frames I101, a bearing pipe I103 is welded between the two main frames I101, supporting legs 105 are welded at two sides of the bottom of the main frame I101, the middle layer support 2 comprises two main frames II 21 and two connecting rods II 22, the two main frames II 21 and the two connecting rods II 22 are welded together in a square shape, a plurality of partition pipes II 24 are welded at the tops of the connecting rods II 22 and the main frames II 21, and a bearing pipe II 23 is welded between the two main frames II 21, the insertion pipes 25 are welded on two sides of the bottom of the second main frame 21, the top layer support 3 comprises two third main frames 31 and two third connecting rods 32, the two third main frames 31 and the two third connecting rods 32 are welded together in a square shape, the connecting rods three 32 and the top of the third main frame 31 are welded with a plurality of third isolating pipes 34, the three main frames 31 are welded with three bearing pipes 33, the two sides of the bottom of the three main frames 31 are welded with the three insertion pipes 35, the second isolating pipes 24 on the two second main frames 21 are inserted into the inner cavities of the three insertion pipes 35, the first isolating pipes 104 on the two first main frames 101 are inserted into the inner cavities of the insertion pipes 25, the length of the support legs 105 is smaller than that of the insertion pipes 25 and the three insertion pipes 35, the bottom of the support legs 105 is placed, a single guide pipe body 4 is placed between the first isolating pipes 104, the second isolating pipes 24 and the third isolating pipes 34, the lifting mechanism 5 comprises two fixed installation sleeves 51 which are sleeved on the first main frames 101 or the second main frames 21 or the third main frames 31, fastening bolts 52 are arranged on one side of a fixed mounting sleeve 51 in a penetrating mode, locking nuts 53 are connected to surface threads of the fastening bolts 52, the fixed mounting sleeve 51 is fixedly mounted on a first main frame 101, a second main frame 21 or a third main frame 31 through the fastening bolts 52 and the locking nuts 53, a mounting frame 54 is detachably mounted on one side of the fixed mounting sleeve 51, rotating shaft rods 55 are fixedly connected to the inner sides of the mounting frame 54, lifting frames 56 are movably connected to the surfaces of the two rotating shaft rods 55, mounting nuts 57 are connected to the surface threads of the rotating shaft rods 55, stop rods 58 are welded to the two sides of the top of each lifting frame 56, through the arrangement of the lifting mechanism 5, when the catheter bodies 4 are placed, the catheter bodies 4 can be classified and sorted quickly through the lifting mechanism 5 in a labor-saving mode and placed well, the operation is convenient, the use is convenient for users, a first partition pipe 104, a second partition pipe 24 and a third partition pipe 34 are adjacent at equal intervals, the adjacent spacing is preferably three hundred and fifty millimeters.
In the using method and the working principle of the embodiment, during actual use, a user firstly places the bottom layer support 1 on the ground, then places the conduit body 4 on the bottom layer support 1 and between the two partition pipes one 104, so that the conduit body 4 is transversely placed on the connecting rod one 102 and the bearing pipe one 103, when placing the conduit body 4, the user can firstly sleeve the fixing and installing sleeve 51 on the main frame one 101, then insert the fastening bolt 52, screw the fastening nut 53 to lock, fix the fixing and installing sleeve 51 on the main frame one 101, then unfold and place the lifting frame 56 on the ground, then roll the conduit body 4 or carry the conduit body 4 to the lifting frame 56, and limit the conduit body 4 to fall through the blocking rod 58, then lift the lifting frame 56 upwards, lift the conduit body 4 upwards through lifting of the lifting frame 56, then along with the inclination of the lifting frame 56, the pipe body 4 just can roll to the body frame 101 and hold on the pipe 103, then adjust one by one, place pipe body 4 between two disconnected pipe 104, also place pipe body 4 according to same mode on same intermediate level support 2 and the top layer support 3, so just can be very laborsaving place pipe body 4 on bottom layer support 1, and also can arrange pipe body 4 neatly and classify, save occupation space, convenient transportation, also conveniently wash pipe body 4.
The above description is only a preferred embodiment of the present application and is not intended to limit the present application, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, improvement and the like made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims (8)

1. The utility model provides a support is deposited to pile foundation construction pipe which characterized in that, includes bottom support (1), intermediate level support (2), top layer support (3) and lifts mechanism (5): the lifting mechanism (5) can be independently arranged on the bottom layer support (1), the middle layer support (2) and the top layer support (3), and a plurality of conduit bodies (4) are respectively arranged on the bottom layer support (1), the middle layer support (2) and the top layer support (3);
the bottom layer support (1) comprises two main frames I (101) and two connecting rods I (102), the two main frames I (101) and the two connecting rods I (102) are welded together in a square shape, a plurality of partition pipes I (104) are welded at the tops of the connecting rods I (102) and the main frames I (101), a pipe bearing I (103) is welded between the two main frames I (101), and supporting legs (105) are welded at two sides of the bottom of the main frames I (101);
the middle-layer support (2) comprises two main frames II (21) and two connecting rods II (22), the two main frames II (21) and the two connecting rods II (22) are welded together in a square shape, a plurality of partition pipes II (24) are welded at the tops of the connecting rods II (22) and the main frames II (21), a bearing pipe II (23) is welded between the two main frames II (21), and inserting pipes (25) are welded at two sides of the bottom of the main frames II (21);
top layer support (3) include three (31) of two body frames and three (32) of two connecting rods, and the welding of mouth font is in the same place for three (31) of two body frames and three (32) of two connecting rods, the welding has a plurality of to cut off pipe three (34) all at the top of three (32) of connecting rod and three (31) of body frames, and the welding has the pipe three (33) of holding between three (31) of two body frames, three (35) of intubate have all been welded to the both sides of three (31) bottoms of body frames.
2. The pile foundation construction conduit storage bracket of claim 1, wherein: the second partition pipes (24) positioned on the second main frames (21) are inserted in the inner cavity of the third insertion pipe (35), and the first partition pipes (104) positioned on the first main frames (101) are inserted in the inner cavity of the insertion pipe (25).
3. The pile foundation construction conduit storage bracket of claim 2, wherein: the length of the supporting leg (105) is smaller than that of the insertion tube (25) and the insertion tube III (35), and the bottom of the supporting leg (105) is placed on the ground.
4. The pile foundation construction conduit storage bracket of claim 3, wherein: a single catheter body (4) is placed between two adjacent first partition pipes (104), two adjacent second partition pipes (24) and two adjacent third partition pipes (34).
5. The pile foundation construction conduit storage bracket of claim 4, wherein: lifting mechanism (5) are including establishing two fixed mounting cover (51) on body frame one (101) or body frame two (21) or body frame three (31), one side of fixed mounting cover (51) is run through and is provided with fastening bolt (52), the surperficial threaded connection of fastening bolt (52) has lock nut (53), fixed mounting cover (51) are through fastening bolt (52) and lock nut (53) fixed mounting on body frame one (101) or body frame two (21) or body frame three (31).
6. The pile foundation construction conduit storage bracket of claim 5, wherein: one side demountable installation of fixed mounting cover (51) has mounting bracket (54), the inboard fixedly connected with of mounting bracket (54) rotates axostylus axostyle (55), and the surface swing joint of two rotation axostylus axostyles (55) has lift frame (56), the surperficial threaded connection who rotates axostylus axostyle (55) has installation nut (57).
7. The pile foundation construction conduit storage bracket of claim 6, wherein: stop levers (58) are welded on two sides of the top of the lifting frame (56).
8. The pile foundation construction conduit storage bracket of claim 7, wherein: the first partition pipe (104), the second partition pipe (24) and the third partition pipe (34) are adjacent at equal intervals.
CN202120686144.2U 2021-04-06 2021-04-06 Pile foundation construction pipe storage support Expired - Fee Related CN214525032U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120686144.2U CN214525032U (en) 2021-04-06 2021-04-06 Pile foundation construction pipe storage support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120686144.2U CN214525032U (en) 2021-04-06 2021-04-06 Pile foundation construction pipe storage support

Publications (1)

Publication Number Publication Date
CN214525032U true CN214525032U (en) 2021-10-29

Family

ID=78272089

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120686144.2U Expired - Fee Related CN214525032U (en) 2021-04-06 2021-04-06 Pile foundation construction pipe storage support

Country Status (1)

Country Link
CN (1) CN214525032U (en)

Similar Documents

Publication Publication Date Title
CN214525032U (en) Pile foundation construction pipe storage support
CN209976522U (en) Well site operation greasy dirt collection device and collecting equipment
CN205577188U (en) Collect heat preservation, decorative layer and template in exterior wall cladding of an organic whole system
CN207212391U (en) A kind of cloth bench-table car for Tunnel Blasting dust dedusting
CN211229428U (en) Building assembled scaffold
CN86203954U (en) Wall bearing self-lifting scaffold
CN212897721U (en) Prefabricated assembled building skirt protection network
CN215042676U (en) Vehicle rinse-system that leaves at building construction site
CN214031879U (en) A aeration tank for municipal sewage treatment
CN219411432U (en) Building decoration curtain wall mounting structure
CN213301395U (en) Water level monitoring device for hydraulic engineering
CN210002877U (en) Back ridge external corner active diagonal pulling device in aluminum alloy template system
CN211225836U (en) Detachable self-adaptive inclinometer pipe mounting device
CN218515399U (en) Shoe rack with good stability and convenient to splice
CN217064782U (en) Supporting framework for planting greenhouse
CN220267152U (en) Suspension type household wall construction operation platform
CN214834584U (en) Scaffold for building engineering
CN2133627Y (en) Lifted scaffold using on bums and holes position of high-building
CN212957977U (en) Safety enclosure for civil and industrial building construction
CN213654166U (en) Novel modular scaffold frame for building goes up and down device
CN217925049U (en) Anti-seismic reinforcing structure for bearing wall of raw soil house
CN213774368U (en) Scaffold for building engineering
CN214823387U (en) Desk carrier
CN218023160U (en) Reinforcing steel bar background easy-to-drag support
CN210948459U (en) Engineering maintenance ladder for water conservancy and hydropower

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211029