CN214513503U CN202120570457.1U CN202120570457U CN214513503U CN 214513503 U CN214513503 U CN 214513503U CN 202120570457 U CN202120570457 U CN 202120570457U CN 214513503 U CN214513503 U CN 214513503U
Authority
CN
China
Prior art keywords
water supply
supply pipe
tower crane
dust
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120570457.1U
Other languages
Chinese (zh)
Inventor
王嘉伟
周岩
张彦芝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202120570457.1U priority Critical patent/CN214513503U/en
Application granted granted Critical
Publication of CN214513503U publication Critical patent/CN214513503U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model discloses a dust fall processing device for construction engineering, which comprises a tower crane and a reservoir, wherein the tower crane and the reservoir are both fixedly arranged on the ground, a water pipe is arranged in the reservoir and is connected with a vertical water supply pipe, a water pump and a solenoid valve are sequentially arranged on the water pipe, the top end of the vertical water supply pipe is connected with a horizontal water supply pipe, and a plurality of high-pressure nozzles are arranged on the horizontal water supply pipe; a control cabinet is arranged on one side of the tower crane, and the water pump and the electromagnetic valve are electrically connected with the control cabinet; by arranging the water supply pipe and the high-pressure nozzle on the tower crane, flying fog can be formed during use, dust particles and impurities in the air can be adsorbed, the concentration of the particles in the air of a construction site can be reduced by more than 80%, and meanwhile, after the tower crane is sprayed at high altitude for a period of time, the ground is in a wet state, so that the dust is effectively inhibited from being lifted again; and the temperature of a construction site can be effectively reduced at high temperature in summer, generally by 3-5 ℃, the probability of artificial heatstroke is reduced, and the extremely hot working environment of the construction site is effectively improved.

Description

Dust fall processing apparatus for building engineering
Technical Field
The utility model relates to a building engineering auxiliary assembly technical field, specific theory especially relates to a dust fall processing apparatus for building engineering.
Background
With the continuous acceleration of urban modern construction, a large number of construction sites inevitably appear in cities, and various construction sites cause severe influence on the surrounding environment, firstly, dust pollution is caused, a large amount of dust is generated in the construction sites, and if the construction sites fly upwards, a layer of thick dust covers the whole city; in addition, in the middle of these dusts, there are a large number of substances harmful to human body, will cause the influence for city resident's health, in order to avoid these problems, generally live the fixed building of building site among the prior art or all around subaerial and be equipped with a large amount of water jet equipment, the water jet that utilizes water jet equipment plays the dust fall, the dust removal effect, but current water jet equipment adopts the mode of fixed mounting mostly, so can not angle of adjustment carry out the dust fall when using and handle, just need to install multiunit water jet equipment and just can carry out the dust fall when falling the dust to the area on a large scale and handle, from this has increased many costs for the dust fall operation.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a dust fall processing apparatus for building engineering to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a dust fall processing device for constructional engineering comprises a tower crane and a water storage tank, wherein the tower crane and the water storage tank are both fixedly arranged on the ground, a water pipe is arranged in the water storage tank and is connected with a vertical water supply pipe, a water pump and an electromagnetic valve are sequentially arranged on the water pipe, the top end of the vertical water supply pipe is connected with a horizontal water supply pipe, the vertical water supply pipe is arranged on a vertical tower body of the tower crane, the horizontal water supply pipe is arranged on a cantilever of the tower crane, and a plurality of high-pressure nozzles are arranged on the horizontal water supply pipe;
one side of tower crane is provided with the switch board, water pump, solenoid valve with switch board electric connection.
Preferably, the vertical water supply pipe and the horizontal water supply pipe are connected by a universal rotary joint.
Preferably, still be provided with dust sensor and wireless transmission spare on the tower crane, the dust sensor with be electric connection between the wireless transmission spare, be provided with the wireless receiving subassembly in the switch board.
Preferably, the control cabinet comprises a control system taking a PLC as a control core.
Has the advantages that: compared with the prior art, the beneficial effects of the utility model are that: the water supply pipe and the high-pressure nozzle are arranged on the tower crane, flying fog can be formed during use, dust particles and impurities in the air can be adsorbed, the concentration of the particles in the air of a construction site can be reduced by more than 80% under the condition that the wind speed in the site is lower than that of secondary wind, and meanwhile, after the tower crane is sprayed at high altitude for a period of time, the ground forms a wet state, so that the dust is effectively inhibited from being lifted again; and the temperature of a construction site can be effectively reduced at high temperature in summer, generally by 3-5 ℃, the probability of artificial heatstroke is reduced, and the extremely hot working environment of the construction site is effectively improved.
Drawings
Fig. 1 is the utility model provides a dust fall processing apparatus for building engineering's overall structure schematic diagram.
In the drawings: the device comprises a tower crane 1, a water storage tank 2, a water pump 3, an electromagnetic valve 4, a vertical water supply pipe 5, a horizontal water supply pipe 6, a high-pressure nozzle 7, a dust sensor 8, a wireless transmission part 9 and a control cabinet 10.
Detailed Description
In order to make the above objects, features and advantages of the present invention more clearly understood, the present invention will be further described with reference to the accompanying drawings and examples. It should be noted that the embodiments and features of the embodiments of the present application may be combined with each other without conflict.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention, however, the present invention may be practiced in other ways than those specifically described herein, and therefore the present invention is not limited to the limitations of the specific embodiments of the present disclosure.
Examples
Referring to the attached drawings, in the embodiment of the present invention, a dust settling treatment device for building engineering includes a tower crane 1 and a reservoir 2, wherein the tower crane 1 and the reservoir 2 are both fixed on the ground, a water pipe is arranged in the reservoir 2 and connected to a vertical water supply pipe 5, a water pump 3 and a solenoid valve 4 are sequentially installed on the water pipe, a horizontal water supply pipe 6 is connected to the top end of the vertical water supply pipe 5, the vertical water supply pipe 5 is arranged on a vertical tower body of the tower crane 1, the horizontal water supply pipe 6 is arranged on a cantilever of the tower crane 1, and a plurality of high pressure nozzles 7 are arranged on the horizontal water supply pipe 6;
one side of tower crane 1 is provided with switch board 10, water pump 3, solenoid valve 4 with switch board 10 electric connection.
Further, the vertical water supply pipe 5 and the horizontal water supply pipe 6 are connected by a universal swivel joint.
Further say, still be provided with dust sensor 8 and wireless transmission 9 on the tower crane 1, dust sensor 8 with be electric connection between the wireless transmission 9, be provided with the wireless receiving subassembly in the switch board 10.
Further, the control cabinet 10 includes a control system using a PLC as a control core.
The use process comprises the following steps:
when the water-saving dust-settling device is used, water in the water storage tank 2 finally forms water mist above a construction area through the high-pressure nozzle 7 through the water pump 3, the vertical water supply pipe 5 and the horizontal water supply pipe 6, and dust can be effectively settled; the dust sensor 8 can detect the concentration of dust in the air and transmit the detection structure into the control cabinet 10 through the wireless transmission piece 9, and the controller in the control cabinet 10 controls the existence and the size of the spray according to the dust concentration.
In the process, the water supply pipe and the high-pressure nozzle are arranged on the tower crane, flying fog can be formed in a construction area within 360 degrees in use, dust particles and impurities in the air can be adsorbed, the concentration of particulate matters in the air of a construction site can be reduced by more than 80% under the condition that the wind speed in the site is lower than that of secondary wind, and meanwhile, after the tower crane is sprayed at high altitude for a period of time, the ground forms a wet state, so that the dust is effectively prevented from being lifted again; in addition, the temperature of a construction site can be effectively reduced at high temperature in summer, generally by 3-5 ℃, the probability of artificial heatstroke is reduced, and the extremely hot working environment of the construction site is effectively improved; the application has the advantages of simple structure, strong practicability and simple operation and is worth popularizing.
The above is only the preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, without departing from the concept of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicability of the patent. It is to be understood that the terms indicating an orientation or positional relationship are based on the orientation or positional relationship shown in the drawings and are used only for convenience in describing the present invention and for simplicity in description, and do not indicate or imply that the referenced devices or elements must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.

Claims (4)

1. The utility model provides a dust fall processing apparatus for building engineering which characterized in that: the tower crane water supply device comprises a tower crane (1) and a water storage tank (2), wherein the tower crane (1) and the water storage tank (2) are fixedly arranged on the ground, a water pipe is arranged in the water storage tank (2) and is connected with a vertical water supply pipe (5), a water pump (3) and an electromagnetic valve (4) are sequentially arranged on the water pipe, the top end of the vertical water supply pipe (5) is connected with a horizontal water supply pipe (6), the vertical water supply pipe (5) is arranged on a vertical tower body of the tower crane (1), the horizontal water supply pipe (6) is arranged on a cantilever of the tower crane (1), and a plurality of high-pressure nozzles (7) are arranged on the horizontal water supply pipe (6);
one side of tower crane (1) is provided with switch board (10), water pump (3), solenoid valve (4) with switch board (10) electric connection.
2. The dust fall processing apparatus for the construction engineering according to claim 1, characterized in that: the vertical water supply pipe (5) and the horizontal water supply pipe (6) are connected through a universal rotary joint.
3. The dust fall processing apparatus for the construction engineering according to claim 1, characterized in that: still be provided with dust sensor (8) and wireless transmission spare (9) on tower crane (1), dust sensor (8) with be electric connection between wireless transmission spare (9), be provided with the wireless receiving subassembly in switch board (10).
4. The dust fall processing apparatus for the construction engineering according to claim 1, characterized in that: the control cabinet (10) comprises a control system which takes a PLC as a control core.
CN202120570457.1U 2021-03-19 2021-03-19 Dust fall processing apparatus for building engineering Expired - Fee Related CN214513503U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120570457.1U CN214513503U (en) 2021-03-19 2021-03-19 Dust fall processing apparatus for building engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120570457.1U CN214513503U (en) 2021-03-19 2021-03-19 Dust fall processing apparatus for building engineering

Publications (1)

Publication Number Publication Date
CN214513503U true CN214513503U (en) 2021-10-29

Family

ID=78263774

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120570457.1U Expired - Fee Related CN214513503U (en) 2021-03-19 2021-03-19 Dust fall processing apparatus for building engineering

Country Status (1)

Country Link
CN (1) CN214513503U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115301026A (en) * 2022-08-10 2022-11-08 安徽建工集团股份有限公司总承包分公司 Hanging type dust removal system and hanging type dust removal method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115301026A (en) * 2022-08-10 2022-11-08 安徽建工集团股份有限公司总承包分公司 Hanging type dust removal system and hanging type dust removal method

Similar Documents

Publication Publication Date Title
CN103433242B (en) Transformer station's dry ice cleaning vehicle
CN214513503U (en) Dust fall processing apparatus for building engineering
CN201617771U (en) High-rise building outer wall surface cleaning robot
CN201855766U (en) Automatic spray system of open train
CN204436530U (en) A kind of vehicle exhaust dust removal apparatus
CN208036640U (en) A kind of flame device and unmanned plane based on unmanned plane
CN206883881U (en) High ferro prefabricated case beam automatic intelligent shower water curing system
CN212440549U (en) Spraying watering lorry based on magnetized water dust removal technology
CN216574625U (en) Unmanned aerial vehicle dry ice cleaning system suitable for electrified decontamination of power equipment
CN208950632U (en) A kind of infrared automatic dust suppression device by water spray of mining wireless
CN207126289U (en) A kind of miniature dedusting environment friendly dolly
CN106594916A (en) Urban comprehensive dust removing, haze reducing and air conditioning system
CN206008319U (en) A kind of solar energy watering drop haze system
CN105737269A (en) Urban haze machine
CN205730723U (en) A kind of depositing dust with dust sensing removes device
CN211274003U (en) Movable wet dust-removing working device
CN209748049U (en) Wind-force machine of removing obstacles
CN108854356A (en) A kind of city housing-group removes haze system
CN218130744U (en) Movable spray dust removal device
CN211913145U (en) Integrated water mist dust removal device
CN213433610U (en) Portable high-pressure water mist spraying dust device
CN214809425U (en) Penetrate fog ware and dust suppression device
CN214604392U (en) Intelligent robot for maintaining support in intelligent pipe gallery
CN210097257U (en) Full-automatic outer frame spraying dustproof system
CN218459022U (en) Humidification dust fall shallow

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211029