- CN214365437U CN214365437U CN202022779161.9U CN202022779161U CN214365437U CN 214365437 U CN214365437 U CN 214365437U CN 202022779161 U CN202022779161 U CN 202022779161U CN 214365437 U CN214365437 U CN 214365437U
- Authority
- CN
- China
- Prior art keywords
- inclined rod
- shelves
- enclose
- balancing weight
- stand
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 40
- 239000010959 steel Substances 0.000 claims abstract description 40
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 14
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 abstract description 6
- 230000000694 effects Effects 0.000 abstract description 5
- 238000009434 installation Methods 0.000 abstract description 4
- 238000004519 manufacturing process Methods 0.000 abstract description 4
- 238000003466 welding Methods 0.000 abstract description 4
- 238000010276 construction Methods 0.000 abstract description 3
- 229910052742 iron Inorganic materials 0.000 abstract description 3
- 238000003780 insertion Methods 0.000 description 6
- 230000037431 insertion Effects 0.000 description 6
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 3
- 238000005034 decoration Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000010079 rubber tapping Methods 0.000 description 1
- 230000007306 turnover Effects 0.000 description 1
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model discloses a shelves fixing device is enclosed temporarily to instrument formula belongs to construction technical field, including the concrete balancing weight, enclose shelves stand and U-shaped steel bar card, the setting can be dismantled on the concrete balancing weight to the one end of U-shaped steel bar card, and the setting can be dismantled on enclosing the shelves stand to the other end, and the concrete balancing weight with enclose the setting of shelves stand subaerially at same level, enclose the shelves stand and enclose the direct setting of shelves stand and enclose the shelves thing. The utility model discloses simple manufacture, the transportation is convenient, and the regularization can have enough to meet the need the use many times, and the cost of input is less, and the installation is firm, and difficult variant installs and removes the convenience, is particularly suitable for being used for the interim fender that encloses that needs frequently to install and remove, and the workman's transport of being convenient for encloses and adopts the iron wire to tie up into a whole between the fender coexistence post, then with reinforcing bar U-shaped card on the welding encloses the steel pipe of fender stand lower extreme and the hole of concrete counter weight, plays the fixed effect of enclosing the fender.
Description
Technical Field
The utility model relates to a construction technical field especially relates to an instrument formula encloses shelves fixing device temporarily.
Background
In municipal road extension, reconstruction engineering, often use temporarily to enclose the shelves, the fixed traditional way of enclosing the shelves temporarily at present is mostly: the lower end of the enclosure upright post is inserted into the concrete counterweight or fixed with the ground by adopting an expansion screw, then an angle steel inclined strut is additionally arranged at the upright post for reinforcement, the upper end of the angle steel inclined strut is fixed with the upright post by using a self-tapping screw, and the lower end of the angle steel inclined strut is fixed with the ground by adopting an expansion screw. Because the temporary enclosure in the municipal road extension and reconstruction project needs to be frequently assembled and disassembled for turnover, the traditional fixing method brings great inconvenience to construction, and the remained expansion screw is not easy to take out after the enclosure is disassembled, so that the appearance is influenced.
SUMMERY OF THE UTILITY MODEL
The to-be-solved technical problem of the utility model is, to the not enough of prior art existence, provide a low-cost input, simple manufacture, the installation is firm, installs and removes convenient instrument formula and encloses shelves fixing device temporarily. The utility model discloses the input cost is low, simple manufacture, and the installation is firm, installs and removes the convenience, is particularly suitable for being arranged in the interim rail that needs frequently to install and remove among the town road engineering.
The utility model provides a shelves fixing device is enclosed temporarily to instrument formula, includes the concrete balancing weight, encloses a shelves stand and U-shaped steel bar card, the setting can be dismantled on the concrete balancing weight to the one end of U-shaped steel bar card, and the setting can be dismantled on enclosing a shelves stand to the other end, and the concrete balancing weight with enclose a shelves stand setting subaerially at same level, enclose a shelves stand and enclose and be provided with between the shelves stand and enclose a shelves thing.
Furthermore, one side of the enclosure upright post is provided with two steel pipes, the two steel pipes are horizontally welded and fixed on the enclosure upright post, one ends of the two U-shaped steel bar clamps are sleeved in the two steel pipes, and the two U-shaped steel bar clamps form a V-shaped structure.
Furthermore, two reserved holes are formed in the upper end of the concrete balancing weight, and the other ends of the two U-shaped steel bar clamps are sleeved into the two reserved holes.
Furthermore, a detachable inclined rod device is arranged between the upper end of the enclosure stand column and the concrete balancing weight, one end of the inclined rod device can be detachably arranged on the enclosure stand column, and the other end of the inclined rod device can be detachably arranged on the concrete balancing weight.
Furthermore, the inclined rod device comprises an inclined rod reserved hole, an inclined rod bottom inserting rod, an inclined rod top sleeve and an inclined rod top inserting rod, the inclined rod top sleeve is arranged at a position above the middle of the enclosing upright post and is arranged on the same side with the steel pipe, the inclined rod bottom inserting rod and the inclined rod top inserting rod are vertically arranged at two ends of the inclined rod, the inclined rod top inserting rod is sleeved in the inclined rod top sleeve, the inclined rod reserved hole is formed in the concrete balancing weight, and the inclined rod bottom inserting rod is sleeved in the inclined rod reserved hole.
Furthermore, the included angle between the inclined rod and the enclosure upright post is 30-60 degrees.
The counterweight made of concrete, the steel pipe welded with the enclosure upright post and the U-shaped buckle made of steel bars. The concrete counter weight is equipped with two holes that run through from the top surface to the bottom surface (for guaranteeing that the counter weight performance is firm, the hole makes eccentric settings to enclosing shelves pole setting one side slightly), and the bottom both sides are equipped with the recess, and the workman's transport of being convenient for adopts the iron wire to tie up into a whole between the two stands of enclosing shelves, then blocks the reinforcing bar U-shaped card on the hole of welding steel pipe and concrete counter weight of enclosing the shelves stand lower extreme, plays the effect of fixed fender that encloses.
The utility model adopts the above technical scheme, the utility model discloses following technological effect has:
the utility model discloses simple manufacture, the transportation is convenient, and the regularization can have enough to meet the need the use many times, and the cost of input is less, and the installation is firm, and difficult variant installs and removes the convenience, is particularly suitable for being used for the interim fender that encloses that needs frequently to install and remove, and the workman's transport of being convenient for encloses and adopts the iron wire to tie up into a whole between the fender coexistence post, then with reinforcing bar U-shaped card on the welding encloses the steel pipe of fender stand lower extreme and the hole of concrete counter weight, plays the fixed effect of enclosing the fender.
Drawings
Fig. 1 is a plan view of the tool type temporary enclosure fixing device of the present invention.
Fig. 2 is a vertical view of the tool-type temporary enclosure fixing device of the present invention.
Fig. 3 is a top view of the concrete weight of fig. 2.
Fig. 4 is a cross-sectional view of the concrete weight of fig. 2.
Fig. 5 is an elevation view of the steel pipe and rail upright shown in fig. 2.
FIG. 6 is a schematic view of the U-shaped reinforcing bar clip shown in FIG. 2
Fig. 7 is a schematic view of the structure of the supporting rod at the upper end of the utility model.
Reference numbers in the figures: 1-concrete balancing weight; 2-reserving holes; 3-enclosure upright posts; 4-a steel pipe; 5-U-shaped steel bar clamps; 6-reserving holes in the diagonal rods; 7-inserting a rod at the bottom of the inclined rod; 8-a diagonal rod; 9-inclined rod top sleeve; 10-inserting rod at the top of the diagonal rod.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clear, preferred embodiments are described in detail. It should be understood, however, that the numerous specific details set forth in the specification are merely set forth to provide a thorough understanding of one or more aspects of the present invention, which may be practiced without these specific details.
The utility model provides a shelves fixing device is enclosed temporarily to instrument formula, as shown in fig. 1-6, includes concrete balancing weight 1, encloses shelves stand 3 and U-shaped reinforcing bar card 5, the one end of U-shaped reinforcing bar card 5 can be dismantled and set up on concrete balancing weight 1, and the other end can be dismantled and set up on enclosing shelves stand 3, and concrete balancing weight 1 and enclose shelves stand 3 set up same level subaerially, enclose to be provided with between shelves stand 3 and the enclosure stand 3 and enclose shelves thing. The counterweight made of concrete, the steel pipe welded with the enclosure upright post and the U-shaped buckle made of steel bars. The counterweight is formed by prefabricating concrete, two through holes are formed from the top surface to the bottom surface, grooves are formed in two sides of the bottom, workers can carry the counterweight conveniently, the steel pipe is welded at the lower end of the enclosure upright post, and the U-shaped steel bars are clamped and inserted in the holes of the steel pipe and the concrete counterweight, so that the enclosure is fixed. The U-shaped reinforcing steel bar clamp 5 is formed by bending reinforcing steel bars. The concrete balancing weight 1 plays a role in fixing a heavy object, and the U-shaped steel bar clamp 5 is used as a rigid detachable connecting piece.
The embodiment of the utility model provides an in, one side of enclosing shelves stand 3 is provided with two steel pipes 4, and two 4 horizontal welded fastening of steel pipe are on enclosing shelves stand 3, and in two steel pipes 4 were emboliaed to the one end of two U-shaped reinforcing bar cards 5, two U-shaped reinforcing bar cards 5 constituted "V" style of calligraphy structures. Two U-shaped reinforcing bar clamps 5 form horizontal "V" structure, then constitute triangular structure with concrete balancing weight 1 to better fix enclosure stand 3. The inner diameters of the two steel pipes 4 are larger than the outer diameter of the U-shaped reinforcing steel bar clamp 5.
The embodiment of the utility model provides an in, the upper end of concrete balancing weight 1 is provided with two and reserves hole 2, and the other end of two U-shaped reinforcing bar cards 5 embolias in two reservation holes 2. The reserved hole 2 is used as a fixed U-shaped steel bar clamp 5, the bottom of the reserved hole is provided with a leakage structure, and the bottom of the concrete balancing weight 1 is smaller than the upper end of the reserved hole, so that less materials can be used.
The embodiment of the utility model provides an in, as shown in FIG. 7, be provided with detachable slope lever apparatus between the upper end of enclosing a grade stand 3 and concrete balancing weight 1, slope lever apparatus one end can be dismantled and set up on enclosing a grade stand 3, and the setting can be dismantled on concrete balancing weight 1 to the other end. The inclined rod device comprises an inclined rod reserved hole 6, an inclined rod bottom insertion rod 7, an inclined rod 8, an inclined rod top sleeve 9 and an inclined rod top insertion rod 10, wherein the inclined rod top sleeve 9 is arranged at a position above the middle of the enclosing upright post 3 and is arranged on the same side with the steel pipe 4, the inclined rod bottom insertion rod 7 and the inclined rod top insertion rod 10 are vertically arranged at two ends of the inclined rod 8, the inclined rod top insertion rod 10 is sleeved in the inclined rod top sleeve 9, the inclined rod reserved hole 6 is arranged on the concrete balancing weight 1, and the inclined rod bottom insertion rod 7 is sleeved in the inclined rod reserved hole 6. The included angle between the inclined rod 8 and the enclosure upright post 3 is 30-60 degrees. The down tube bottom inserted bar 7, down tube 8 and down tube top inserted bar 10 all use the steel reinforcement welding to form, enclose the upper end of shelves stand 3 through the down tube 8 is fixed to make the bottom and the upper end of enclosing shelves stand 3 all be connected with concrete balancing weight 1 and become an overall structure, better to the fixed effect of enclosing shelves stand 3, all can directly dismantle simultaneously, easy to assemble and dismantle.
The foregoing is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, a plurality of modifications and decorations can be made without departing from the principle of the present invention, and these modifications and decorations should also be regarded as the protection scope of the present invention.
Claims (6)
1. The utility model provides a shelves fixing device is enclosed temporarily to instrument formula which characterized in that: including concrete balancing weight (1), enclose shelves stand (3) and U-shaped reinforcing bar card (5), the one end of U-shaped reinforcing bar card (5) can be dismantled and set up on concrete balancing weight (1), and the other end can be dismantled and set up on enclosing shelves stand (3), and concrete balancing weight (1) and enclose shelves stand (3) and set up subaerially at same level, enclose shelves stand (3) and enclose and be provided with between shelves stand (3) and enclose the shelves thing.
2. The tool type temporary enclosure fixing device of claim 1, wherein: one side of enclosing the shelves stand (3) is provided with two steel pipes (4), and two steel pipes (4) horizontal welded fastening are on enclosing shelves stand (3), and in two steel pipes (4) were emboliaed to the one end of two U-shaped reinforcing bar cards (5), two U-shaped reinforcing bar cards (5) constitute "V" style of calligraphy structure.
3. The tool type temporary enclosure fixing device of claim 2, wherein: the upper end of the concrete balancing weight (1) is provided with two reserved holes (2), and the other ends of the two U-shaped steel bar clamps (5) are sleeved into the two reserved holes (2).
4. The tool type temporary fence fixing device as claimed in claim 3, wherein: enclose and be provided with detachable slope lever apparatus between the upper end of shelves stand (3) and concrete balancing weight (1), slope lever apparatus one end can be dismantled and set up on enclosing shelves stand (3), and the setting can be dismantled on concrete balancing weight (1) to the other end.
5. The tool type temporary enclosure fixing device of claim 4, wherein: the inclined rod device comprises an inclined rod reserved hole (6), an inclined rod bottom inserting rod (7), an inclined rod (8), an inclined rod top sleeve (9) and an inclined rod top inserting rod (10), wherein the inclined rod top sleeve (9) is arranged at a position above the middle of the enclosure upright post (3) and is arranged on the same side with the steel pipe (4), the inclined rod bottom inserting rod (7) and the inclined rod top inserting rod (10) are vertically arranged at two ends of the inclined rod (8), the inclined rod top inserting rod (10) is sleeved in the inclined rod top sleeve (9), the inclined rod reserved hole (6) is arranged on the concrete balancing weight (1), and the inclined rod bottom inserting rod (7) is sleeved in the inclined rod reserved hole (6).
6. The tool type temporary enclosure fixing device of claim 5, wherein: the included angle between the inclined rod (8) and the enclosure upright post (3) is 30-60 degrees.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022779161.9U CN214365437U (en) | 2020-11-26 | 2020-11-26 | Temporary fence fixing device of tool type |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022779161.9U CN214365437U (en) | 2020-11-26 | 2020-11-26 | Temporary fence fixing device of tool type |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214365437U true CN214365437U (en) | 2021-10-08 |
Family
ID=77978658
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202022779161.9U Expired - Fee Related CN214365437U (en) | 2020-11-26 | 2020-11-26 | Temporary fence fixing device of tool type |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214365437U (en) |
-
2020
- 2020-11-26 CN CN202022779161.9U patent/CN214365437U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208605206U (en) | A kind of highway soft rock tunnel bilayer arch supporting construction device | |
CN206971689U (en) | Support operating platform that is detachable and recycling | |
CN214365437U (en) | Temporary fence fixing device of tool type | |
CN204040450U (en) | A kind of for angle connector in tools type section steel builder's jack | |
CN203755466U (en) | Rusted reinforced concrete frame plane joint strengthening device | |
CN207453461U (en) | Supporting frame | |
CN214798565U (en) | Cable rolling dismounting device | |
CN202031309U (en) | Suspending operation platform for structural concrete constructions | |
CN104453243A (en) | Erection device and method for steadily feeding cast-in-place concrete beam into mold | |
CN212223933U (en) | Assembly type building foundation brick moulding bed capable of being used circularly | |
CN202248819U (en) | Light wood structural construction scaffold | |
CN106544960A (en) | Tie with reinforcing bar support and reinforcing bar binding construction method | |
CN208215308U (en) | Suspension type station | |
CN206153467U (en) | Shield structure section of jurisdiction steel reinforcement cage rack for manufacturing | |
CN107476200B (en) | Full-hall support staggered overlapping structure and method | |
CN215055585U (en) | Concrete frame structure face limit safety device | |
CN202105885U (en) | Field assembled steel pipe straightening frame | |
CN220058983U (en) | Quick-dismantling horizontal safety protection device | |
CN207436464U (en) | Gate-type scaffold with can dismantle protector | |
CN207577319U (en) | A kind of steel-bar auxiliary processing device | |
CN212201423U (en) | Building reinforcing platform | |
CN213114325U (en) | Support mounting structure of cantilever beam bridge | |
CN215523190U (en) | Lamp bracket on concrete column | |
CN221504188U (en) | Tool type pump pipe rack | |
CN214144612U (en) | Height-adjustable simple split heads for building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20211008 |