CN214364341U - Integrated furred ceiling for green building - Google Patents

Integrated furred ceiling for green building Download PDF

Info

Publication number
CN214364341U
CN214364341U CN202120110781.5U CN202120110781U CN214364341U CN 214364341 U CN214364341 U CN 214364341U CN 202120110781 U CN202120110781 U CN 202120110781U CN 214364341 U CN214364341 U CN 214364341U
Authority
CN
China
Prior art keywords
keel
false keel
plate
buckle
adhesive tape
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120110781.5U
Other languages
Chinese (zh)
Inventor
罗辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Mingcheng Investment Co ltd
Original Assignee
Shenzhen Wancheng Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Wancheng Construction Engineering Co ltd filed Critical Shenzhen Wancheng Construction Engineering Co ltd
Priority to CN202120110781.5U priority Critical patent/CN214364341U/en
Application granted granted Critical
Publication of CN214364341U publication Critical patent/CN214364341U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a green integrated furred ceiling for building relates to green building technical field, including the buckle, the top of buckle is connected with the false keel, and the top of false keel is connected with the main joist, the outside of main joist is connected with the couple, and the top welding of couple has the connecting rod, the spread groove has been seted up at the both ends of false keel, and the internal connection of spread groove has the connector, the one end of connector is connected with extension fossil fragments, and the both sides set up threaded hole of connector, the internally mounted of screw hole has fixing bolt. The utility model discloses in, extra long fossil fragments are installed at the both ends of false keel to this product for personnel can adjust the length of false keel, when needs transport the false keel, personnel can dismantle the fixing bolt of false keel both sides get off, can take off the both ends of extra long fossil fragments from the false keel, take off the back, personnel can transport it, reduce the length of false keel, can avoid the false keel to receive the damage when transporting.

Description

Integrated furred ceiling for green building
Technical Field
The utility model relates to a green building technical field especially relates to an integrated furred ceiling for green building.
Background
The green building evaluation is to follow the principle of local conditions, combine the characteristics of climate, environment, resources, economy, culture and the like of the region where the building is located, and comprehensively evaluate the performances of safety, durability, health, comfort, convenient life, resource conservation, environmental livability and the like in the whole life cycle of the building.
Current integrated furred ceiling for green building can't adjust the length of fossil fragments, if the length of fossil fragments is short excessively, can lead to follow-up unable buckle of installing, fossil fragments overlength can cause the damage to it when transporting it, if the bottom surface of buckle is by the scratch, after the installation, can influence the pleasing to the eye of furred ceiling.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving current green for building integrated furred ceiling, can't adjust the length of fossil fragments, if the length of fossil fragments is short excessively, can lead to follow-up unable buckle of installing, fossil fragments overlength can cause the damage to it when transporting it, if the bottom surface of buckle is by the scratch, after the installation, can influence the pleasing to the eye shortcoming of furred ceiling, and the integrated furred ceiling for green building that provides.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a green integrated furred ceiling for building, includes the buckle, the top of buckle is connected with the false keel, and the top of false keel is connected with the main joist, the outside of main joist is connected with the couple, and the top welding of couple has the connecting rod, the spread groove has been seted up at the both ends of false keel, and the internal connection of spread groove has the connector, the one end of connector is connected with extra long fossil fragments, and the both sides of connector set up threaded hole, the internally mounted of screw hole has fixing bolt, the sticky tape is installed to the bottom of buckle, and the bottom of sticky tape installs the thread gluing area, the bottom of sticky tape is connected with the shock attenuation board, and the bottom of shock attenuation board installs the spring bracket, the bottom plate is installed to the bottom of spring bracket, the top of connecting rod is connected with the wall body.
Preferably, the connecting rod is connected with the main keel through the hook, and the main keel is parallel to the wall body.
Preferably, the lengthened keel and the auxiliary keel form a dismounting structure through a fixing bolt, and the outer diameter of the fixing bolt is consistent with the inner diameter of the threaded hole.
Preferably, the damping plate is connected with the adhesive tape through the adhesive tape, and the adhesive tape is connected with the buckle plate through the adhesive tape.
Preferably, the bottom plate and the damping plate form a telescopic structure through the spring frame, and the bottom plate and the damping plate are parallel.
Preferably, the lengthened keel is connected with the connecting groove through the connector, and the outer diameter of the connector is consistent with the inner diameter of the connecting groove.
To sum up, owing to adopted above-mentioned technical scheme, the beneficial effects of the utility model are that:
1. the utility model discloses in, extra long fossil fragments are installed at the both ends of false keel to this product for personnel can adjust the length of false keel, when needs transport the false keel, personnel can dismantle the fixing bolt of false keel both sides get off, can take off the both ends of extra long fossil fragments from the false keel, take off the back, personnel can transport it, reduce the length of false keel, can avoid the false keel to receive the damage when transporting.
2. The utility model discloses in, the shock attenuation board is installed in the bottom of buckle to this product, when transporting the buckle, if the buckle bottom receives the heavy object striking, the heavy object can strike on the bottom plate, and the bottom plate can stretch out and draw back through spring frame and shock attenuation board, reduces its impact to protect the buckle, prevent that the buckle from receiving the damage, after installing the buckle, personnel can dismantle the shock attenuation board from the buckle through the sticky tape, can avoid the shock attenuation board to influence the use of buckle.
3. The utility model discloses in, the thread gluing area is installed at the top of shock attenuation board to this product, with the shock attenuation board after dismantling from the buckle, the personnel can take off the sticky tape from the shock attenuation board through the thread gluing area, can retrieve the shock attenuation board, when using once more, only need to pass through the thread gluing area with new sticky tape and install on the shock attenuation board, can pass through the sticky tape with the shock attenuation board and install again on the buckle for the shock attenuation board can recycle, reduce the loss of material, thereby protect the environment.
Drawings
Fig. 1 is a schematic view of the front structure of the integrated ceiling of the present invention;
fig. 2 is a schematic front sectional structural view of the center keel of the present invention;
fig. 3 is a schematic diagram of a front sectional structure of the middle buckle plate of the present invention.
Illustration of the drawings:
1. buckling the plate; 2. a wall body; 3. a main keel; 4. a false keel; 5. a connecting rod; 6. hooking; 7. lengthening a keel; 8. fixing the bolt; 9. a connector; 10. connecting grooves; 11. a threaded hole; 12. sticking a tape; 13. a hook and loop fastener; 14. a damper plate; 15. a spring holder; 16. a base plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts belong to the protection scope of the present invention.
Referring to fig. 1-3, an integrated ceiling for green building comprises a buckle plate 1, a wall body 2, a main keel 3, a false keel 4, a connecting rod 5, a hook 6, an elongated keel 7, a fixing bolt 8, a connecting head 9, a connecting groove 10, a threaded hole 11, an adhesive tape 12, an adhesive tape 13, a damping plate 14, a spring frame 15 and a bottom plate 16, wherein the top of the buckle plate 1 is connected with the false keel 4, the top of the false keel 4 is connected with the main keel 3, the outer side of the main keel 3 is connected with the hook 6, the connecting rod 5 is welded on the top of the hook 6, the connecting groove 10 is arranged at two ends of the false keel 4, the connecting head 9 is connected inside the connecting groove 10, the elongated keel 7 is connected at one end of the connecting head 9, the threaded hole 11 is arranged at two sides of the connecting head 9, the fixing bolt 8 is arranged inside the threaded hole 11, the adhesive tape 12 is arranged at the bottom of the buckle plate 1, and the adhesive tape 13 is arranged at the bottom of the adhesive tape 12, the bottom of the magic tape 13 is connected with a damping plate 14, the bottom of the damping plate 14 is provided with a spring frame 15, the bottom of the spring frame 15 is provided with a bottom plate 16, and the top of the connecting rod 5 is connected with the wall body 2.
As shown in fig. 1, the connecting rods 5 are connected with the main keel 3 through the hooks 6, the main keel 3 and the wall 2 are parallel, and the connecting rods 5 are installed at the bottom of the wall 2.
As shown in fig. 1 and 2, the lengthened keel 7 and the auxiliary keel 4 form a dismounting structure through the fixing bolt 8, the outer diameter of the fixing bolt 8 is consistent with the inner diameter of the threaded hole 11, the fixing bolts 8 at two sides of the auxiliary keel 4 are dismounted, the lengthened keel 7 can be taken down from two ends of the auxiliary keel 4, and after the lengthened keel is taken down, a person can transport the lengthened keel.
As shown in fig. 3, the damping plate 14 is connected with the adhesive tape 12 through the adhesive tape 13, the adhesive tape 13 is connected with the buckle plate 1 through the adhesive tape 12, the damping plate 14 is detached from the buckle plate 1 through the adhesive tape 12, the damping plate 14 can be prevented from influencing the use of the buckle plate 1, and after the damping plate 14 is detached from the buckle plate 1, a person can take down the adhesive tape 12 from the damping plate 14 through the adhesive tape 13, and the damping plate 14 can be recovered.
As shown in fig. 3, the bottom plate 16 forms a telescopic structure with the damping plate 14 through the spring frame 15, and the bottom plate 16 is parallel to the damping plate 14, if the bottom of the buckle 1 is impacted by a heavy object, the heavy object will impact on the bottom plate 16, and the bottom plate 16 will be telescopic with the damping plate 14 through the spring frame 15, so as to reduce the impact force.
As shown in fig. 2, the elongated keel 7 is connected to the connecting groove 10 through the connector 9, and the outer diameter of the connector 9 is the same as the inner diameter of the connecting groove 10, and the connecting groove 10 is opened at both ends of the cross keel 4.
The working principle is as follows: when the auxiliary keel 4 is required to be transported, a person can disassemble the fixing bolts 8 at two sides of the auxiliary keel 4, the lengthened keel 7 can be taken down from two ends of the auxiliary keel 4, the person can transport the auxiliary keel after the auxiliary keel is taken down, when the buckle plate 1 is transported, if the bottom of the buckle plate 1 is impacted by a heavy object, the heavy object can impact on the bottom plate 16, the bottom plate 16 can stretch and contract with the damping plate 14 through the spring frame 15 to reduce the impact force of the damping plate and prevent the buckle plate 1 from being damaged, after the buckle plate 1 is installed, the person can disassemble the damping plate 14 from the buckle plate 1 through the adhesive tape 12, the installation of the buckle plate 1 can be completed, after the damping plate 14 is disassembled from the buckle plate 1, the person can take the adhesive tape 12 off from the damping plate 14 through the adhesive tape 13 to recycle the damping plate 14, when the auxiliary keel is used again, only the new adhesive tape 12 needs to be installed on the damping plate 14 through the adhesive tape 13, the damping plate 14 can be remounted on the pinch plate 1 through the adhesive tape 12, so that the damping plate 14 can be recycled.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The integrated ceiling for the green building comprises a buckle plate (1) and is characterized in that a false keel (4) is connected to the top of the buckle plate (1), a main keel (3) is connected to the top of the false keel (4), a hook (6) is connected to the outer side of the main keel (3), a connecting rod (5) is welded to the top of the hook (6), connecting grooves (10) are formed in two ends of the false keel (4), a connecting head (9) is connected to the inside of each connecting groove (10), one end of each connecting head (9) is connected with an elongated keel (7), threaded holes (11) are formed in two sides of each connecting head (9), fixing bolts (8) are installed inside the threaded holes (11), adhesive tapes (12) are installed at the bottom of the buckle plate (1), adhesive tapes (13) are installed at the bottoms of the adhesive tapes (12), and damping plates (14) are connected to the bottoms of the adhesive tapes (13), and the bottom of shock attenuation board (14) is installed spring frame (15), bottom plate (16) are installed to the bottom of spring frame (15), the top of connecting rod (5) is connected with wall body (2).
2. The integrated suspended ceiling for green buildings according to claim 1, wherein the connecting rod (5) is connected with the main keel (3) through a hook (6), and the main keel (3) is parallel to the wall body (2).
3. The integrated suspended ceiling for green buildings according to claim 1, characterized in that the lengthened keel (7) and the auxiliary keel (4) form a detachable structure through the fixing bolt (8), and the outer diameter of the fixing bolt (8) is consistent with the inner diameter of the threaded hole (11).
4. The integrated suspended ceiling for green buildings according to claim 1, wherein the damping plate (14) is connected with the adhesive tape (12) through the adhesive tape (13), and the adhesive tape (13) is connected with the buckle plate (1) through the adhesive tape (12).
5. The integrated suspended ceiling for green buildings according to claim 1, wherein the bottom plate (16) and the damping plate (14) form a telescopic structure through the spring frame (15), and the bottom plate (16) and the damping plate (14) are parallel.
6. The integrated suspended ceiling for green buildings according to claim 1, wherein the lengthened keel (7) is connected with the connecting groove (10) through the connecting head (9), and the outer diameter of the connecting head (9) is consistent with the inner diameter of the connecting groove (10).
CN202120110781.5U 2021-01-15 2021-01-15 Integrated furred ceiling for green building Active CN214364341U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120110781.5U CN214364341U (en) 2021-01-15 2021-01-15 Integrated furred ceiling for green building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120110781.5U CN214364341U (en) 2021-01-15 2021-01-15 Integrated furred ceiling for green building

Publications (1)

Publication Number Publication Date
CN214364341U true CN214364341U (en) 2021-10-08

Family

ID=77956235

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120110781.5U Active CN214364341U (en) 2021-01-15 2021-01-15 Integrated furred ceiling for green building

Country Status (1)

Country Link
CN (1) CN214364341U (en)

Similar Documents

Publication Publication Date Title
CN211817331U (en) Anti-bearing structure of furred ceiling
CN214364341U (en) Integrated furred ceiling for green building
CN111335517A (en) Inferior gram force board is used in curtain assembly
CN109083323A (en) A kind of install convenient and the movable villa furred ceiling composite plate with pooling feature
CN109339235A (en) A kind of skyscraper thin walled steel structure convenient for improving stability
CN210104961U (en) Shockproof building frame structure
CN209538473U (en) It is a kind of convenient for fixed curtain wall
CN214246573U (en) Can dismantle fast and climb a net
CN212317170U (en) Recyclable steel member splicing structure for green building
CN103938784B (en) The mounting structure of furred ceiling
CN208749166U (en) A kind of truss structure
CN209817475U (en) Connecting structure of safety protection net attached to lifting scaffold
CN211572173U (en) Curtain wall
CN207582669U (en) A kind of high strength steel constructional device
CN215167531U (en) Mounting structure of building decorative plate
CN111217274A (en) A hang in midair hoist that is used for assembled buckling restrained steel plate wall quick, high-efficient assembly
CN221219103U (en) Secondary rigid conversion layer structure for battery workshop
CN220814488U (en) Special-shaped furred ceiling installation design structure in large space
CN211578285U (en) Vertical lamp house of installing on iron tower
CN220978531U (en) Ceiling fossil fragments hoisting structure
CN212247959U (en) Demolish safety warning device for job site
CN217053975U (en) Hanging piece structure of flat lamp
CN215172790U (en) Fixing base for round steel with grid structure
CN212174315U (en) A hang in midair hoist that is used for anti-buckling steel plate wall quick, high-efficient assembly
CN213773077U (en) Underground parking garage entry limit for height subassembly

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20240421

Address after: 518000, Unit 2, Building 2-5, Bihu Rose Garden, No. 234 Jixiang Middle Road, Ziwei Community, Longcheng Street, Longgang District, Shenzhen City, Guangdong Province, China, Shop 210

Patentee after: Shenzhen Mingcheng Investment Co.,Ltd.

Country or region after: China

Address before: 518000 room 804-805, block 12, Huating phase II, manjinghua joy lane, Longgang street, Longgang District, Shenzhen City, Guangdong Province

Patentee before: SHENZHEN WANCHENG CONSTRUCTION ENGINEERING CO.,LTD.

Country or region before: China

TR01 Transfer of patent right