Prior art keywords
bin
finished product
production line
valve
grout
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202023094015.9U
Other languages
Chinese (zh)
Inventor
李军枝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Hehe Building Materials Co ltd
Original Assignee
Hebei Hehe Building Materials Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Hehe Building Materials Co ltd filed Critical Hebei Hehe Building Materials Co ltd
Priority to CN202023094015.9U priority Critical patent/CN214357994U/en
Application granted granted Critical
Publication of CN214357994U publication Critical patent/CN214357994U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Filling Or Emptying Of Bunkers, Hoppers, And Tanks (AREA)

Abstract

The utility model relates to a novel finished product storehouse that grout production line was used belongs to grout material and generates equipment technical field. The device comprises a cylindrical stock bin and a support frame, wherein the lower end of the support frame is fixed with the ground, and the stock bin is fixed on the upper part of the support frame; the device also comprises a dust collecting device, wherein a plurality of bin vibrators are fixedly arranged on the surface of the outer bin wall of the bin and are distributed in different position areas on the surface of the outer bin wall; the lower part of the storage bin is a conical blanking section, the lower end of the blanking section is connected with a crushing valve, and the lower end of the crushing valve is connected with a transition cylinder; the upper part of the transition cylinder is of a rectangular cylinder structure, and the lower part of the transition cylinder is of an inverted conical cylinder structure; the lower end of the transition cylinder is connected with a discharge valve; and a dust collecting pipeline opening of the dust collecting device is arranged above the area where the baiting valve is positioned. The utility model discloses can ensure that the grout falls smoothly from the feed bin, guarantee going on of the smooth high efficiency of grout bagging-off work.

Description

Novel finished product storehouse that grout production line was used
Technical Field
The utility model relates to a novel finished product storehouse that grout production line was used belongs to grout material and generates equipment technical field.
Background
The grouting material is prepared by taking a high-strength material as an aggregate, taking cement as a bonding agent and assisting materials with high flow state, micro-expansion, segregation prevention and the like. The grouting material has good self-fluidity, rapid hardening, early strength, high strength, no shrinkage and micro-expansion; no toxicity, no harm, no aging, no pollution to water quality and surrounding environment, good self-sealing property, rust prevention and the like. The construction method has the advantages of reliable quality, cost reduction, short construction period, convenient use and the like.
Grouting materials, like cement, are powdery materials that need to be filled into bags after preparation of the finished product. Specifically, the finished grouting material is stored in a finished product bin, and then bagged through the finished product bin. In actual production, it is found that there are often cases where the grouting material adheres to the inner wall of the silo. In addition, the grout material can be the caking sometimes in the feed bin, and then causes the feed opening to block up. The existing grouting material finished product bin cannot ensure the orderly and smooth bagging work.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a novel finished product storehouse that grout production line was used.
In order to realize the purpose, the utility model discloses a technical scheme is:
a novel finished product bin for a grouting material production line comprises a cylindrical bin and a support frame, wherein the lower end of the support frame is fixed with the ground, and the bin is fixed on the upper part of the support frame; the device also comprises a dust collecting device, wherein a plurality of bin vibrators are fixedly arranged on the surface of the outer bin wall of the bin and are distributed in different position areas on the surface of the outer bin wall; the lower part of the storage bin is a conical blanking section, the lower end of the blanking section is connected with a crushing valve, and the lower end of the crushing valve is connected with a transition cylinder; the upper part of the transition cylinder is of a rectangular cylinder structure, and the lower part of the transition cylinder is of an inverted conical cylinder structure; the lower end of the transition cylinder is connected with a discharge valve; and a dust collecting pipeline opening of the dust collecting device is arranged above the area where the baiting valve is positioned.
The utility model discloses technical scheme's improvement still lies in: the bin vibrators are not on the same plane in the height direction and the circumferential direction of the bin;
the utility model discloses technical scheme's improvement still lies in: the three bin vibrators are respectively positioned at the upper part, the middle part and the lower part of the bin.
The utility model discloses technical scheme's improvement still lies in: the three bin vibrators are distributed at intervals of 120 degrees in the circumferential direction.
The utility model discloses technical scheme's improvement still lies in: a vibrator mounting seat is welded on the outer bin wall of the bin, and the bin vibrator is mounted on the vibrator mounting seat.
The utility model discloses technical scheme's improvement still lies in: the upper end of the storage bin is in a semi-closed state.
The utility model discloses technical scheme's improvement still lies in: a weighing platform is arranged corresponding to the lower end of the discharge valve.
Since the technical scheme is used, the utility model discloses the technological effect who gains has:
the utility model discloses the storage part on the upper portion of feed bin is provided with the feed bin vibrator, with feed bin vibrator fixed mounting on the outer bulkhead of feed bin, shakes to shake through the feed bin vibrator and produces the vibration to the feed bin, can ensure the smooth whereabouts of material, prevents the interior bulkhead sizing of feed bin. Simultaneously, the ejection of compact part at the lower extreme of feed bin is provided with broken valve, can be broken the grouting material of caking through broken valve, prevents to block up to guarantee that grouting material can normally fall smoothly at ejection of compact part.
The utility model discloses with the different position regions of feed bin vibrator distribution installation on outer bin wall surface, the feed bin vibrator all is not in the coplanar in the direction of height and the circumference direction of feed bin, can make each position homoenergetic of feed bin receive the vibration power of feed bin vibrator to can improve the effect of beating of feed bin vibrator.
The utility model discloses set up the vibrator mount pad in the outer storehouse wall welding of feed bin, install the feed bin vibrator on the vibrator mount pad, can be convenient for install the outer storehouse wall surface at the feed bin with the feed bin vibrator.
The utility model discloses can ensure the grout material and follow the smooth ejection of compact in the feed bin to guarantee that the bagging-off work of grout material is normal, high-efficient going on.
Drawings
FIG. 1 is a perspective view of the present invention;
FIG. 2 is a front view of the present invention;
the device comprises a material bin 1, a material bin 1-1, a blanking section 2, a support frame 3, a material bin vibrator 4, a crushing valve 5, a transition cylinder 6, a blanking valve 7 and a vibrator mounting seat.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "disposed," "connected," and the like are to be construed broadly, and for example, "connected" may be either fixedly connected or detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The utility model relates to a novel finished product storehouse that grout production line was used for store off-the-shelf grout material and carry out the bagging-off of grout material.
As shown in fig. 1, the new finished product bin comprises a cylindrical bin 1 and a support frame 2. The storage bin 1 is used for storing the processed powdery grouting material. The support frame 2 supports and fixes the storage bin 1 on the ground. The lower end of the support frame 2 is fixed with the ground, and the stock bin 1 is fixed on the upper part of the support frame 2. The lower part of the storage bin 1 is a discharging part, and the support frame 1 enables the lower part of the storage bin 1 to have sufficient working space.
As shown in fig. 1 and fig. 2, the novel finished product bin is fixedly provided with a plurality of bin vibrators 3 on the surface of the outer bin wall of the bin 1, and is used for rapping the bin wall of the bin 1, so that grouting material attached to the inner wall of the bin 1 can be shaken off, and the inner wall of the bin 1 is prevented from being stuck. In order to improve the rapping effect of the bin vibrator 3, the bin vibrator 3 is distributed and installed on different position areas of the surface of the outer bin wall, namely, the bin vibrator 3 is not on the same plane in the height direction and the circumferential direction of the bin 1, so that all positions of the bin 1 can be subjected to the vibrating force of the bin vibrator 3 as much as possible.
Specifically, three bin vibrators 3 may be provided, and the three bin vibrators 3 are respectively provided at the upper portion, the middle portion, and the lower portion of the bin 1 at the horizontal height. Meanwhile, the three bin vibrators 3 are distributed at intervals of 120 ° in the circumferential direction. Only two bin vibrators are shown in fig. 1 and 2, and at least one bin vibrator is further provided at the back surface portion. The bin vibrators 3 may also be provided in multiple numbers, for example, 4 or 5.
The utility model discloses a what play in 1 lower part of feed bin is the effect of blowing, sets up the lower part of feed bin 1 into conical unloading section 1-1 in order to improve the blowing effect, and further connects at the lower extreme of unloading section 1-1 and sets up broken valve 4. The main function of the breaking valve is to break up lumps in the material flow of the discharger, which are formed by the material in the silo due to moisture. The crushing valve is generally an electric crushing valve and is powered by a motor of the crushing valve.
The utility model is provided with a transition cylinder 5 at the lower end of the crushing valve 4, specifically, the upper part of the transition cylinder 5 is a rectangular cylinder structure, and the lower end discharge port of the crushing valve 1 is connected; the lower part of the transition cylinder 5 is of an inverted cone structure and is used for being connected with a discharge valve 6. As shown in fig. 1 and 2, a discharge valve 6 is connected to a lower end of the transition cylinder 5.
The utility model discloses be provided with feed bin vibrator 3 at the storage part of feed bin 1, ensure the smooth whereabouts of material. Meanwhile, a crushing valve 4 is arranged at the discharging part at the lower end of the storage bin 1, so that the materials can normally and smoothly fall down at the discharging part.
The utility model discloses still include dust collection device, what in fact dust collection device played is the effect of dust catcher, prevents that the dust is too much in the air in the workshop. Here, based on the dust collecting device in the workshop, the dust collecting pipeline port of the dust collecting device is additionally arranged above the area where the emptying valve 6 is located, and the dust collecting pipeline port is arranged at the position to be capable of carrying out targeted recovery on dust generated during emptying and bagging. Specifically, the dust collecting pipeline can be fixed at the lower part of the support frame and positioned above the discharge valve, and the position of a port of the dust collecting pipeline is aligned to the bagging work area.
The utility model discloses a major structure of feed bin is circular, and direct inconvenient construction of outer wall installation feed bin vibrator at the feed bin. In a specific implementation, in order to facilitate the installation of the bin vibrator 3 on the surface of the outer bin wall of the bin 1, a vibrator mounting seat 7 is generally welded on the outer bin wall of the bin 1, and then the bin vibrator 3 is installed on the vibrator mounting seat 7. The vibrator mounting seat 7 is welded on the outer wall of the storage bin.
The utility model discloses in concrete implementation, be semi-enclosed state with the upper end of feed bin 1. Or one part is closed, and the other part is opened or closed by using an openable and closable cover plate which is hinged.
The utility model discloses in concrete implementation, set up the platform of weighing at the lower extreme that corresponds baiting valve 6 usually for weigh the weight of the grout material in the wrapping bag, guarantee that the weight of the material of irritating is sufficient accurate. The weighing station is similar to a weighbridge.
The utility model discloses a set up feed bin vibrator and broken valve, can ensure the smooth ejection of compact in the grout material follow feed bin to guarantee that the bagging-off work of grout material is normal, high-efficient going on.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (7)

1. A novel finished product bin for a grouting material production line comprises a cylindrical bin (1) and a support frame (2), wherein the lower end of the support frame (2) is fixed with the ground, and the bin (1) is fixed at the upper part of the support frame (2); still include the dust collection device, its characterized in that: the surface of the outer bin wall of the bin (1) is fixedly provided with a plurality of bin vibrators (3), and the bin vibrators (3) are distributed in different position areas of the surface of the outer bin wall; the lower part of the storage bin (1) is a conical blanking section (1-1), the lower end of the blanking section (1-1) is connected with a crushing valve (4), and the lower end of the crushing valve (4) is connected with a transition cylinder (5); the upper part of the transition cylinder (5) is of a rectangular cylinder structure, and the lower part of the transition cylinder is of an inverted conical cylinder structure; the lower end of the transition cylinder (5) is connected with a discharge valve (6); and a dust collecting pipeline opening of the dust collecting device is arranged above the area where the baiting valve (6) is positioned.
2. The novel finished product storehouse of grout production line usefulness of claim 1, its characterized in that: the bin vibrator (3) is not on the same plane in the height direction and the circumferential direction of the bin (1).
3. The novel finished product storehouse of grout production line usefulness of claim 2, its characterized in that: the three bin vibrators (3) are arranged and are respectively positioned at the upper part, the middle part and the lower part of the bin (1).
4. The novel finished product storehouse of grout production line usefulness of claim 3, its characterized in that: the three bin vibrators (3) are distributed at intervals of 120 degrees in the circumferential direction.
5. The novel finished product bin for the grouting material production line according to any one of claims 1 to 4, characterized in that: a vibrator mounting seat (7) is welded on the outer bin wall of the bin (1), and the bin vibrator (3) is mounted on the vibrator mounting seat (7).
6. The novel finished product bin for the grouting material production line according to any one of claims 1 to 4, characterized in that: the upper end of the storage bin (1) is in a semi-closed state.
7. The novel finished product bin for the grouting material production line according to any one of claims 1 to 4, characterized in that: a weighing platform is arranged corresponding to the lower end of the discharge valve (6).
CN202023094015.9U 2020-12-21 2020-12-21 Novel finished product storehouse that grout production line was used Expired - Fee Related CN214357994U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023094015.9U CN214357994U (en) 2020-12-21 2020-12-21 Novel finished product storehouse that grout production line was used

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023094015.9U CN214357994U (en) 2020-12-21 2020-12-21 Novel finished product storehouse that grout production line was used

Publications (1)

Publication Number Publication Date
CN214357994U true CN214357994U (en) 2021-10-08

Family

ID=77987073

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023094015.9U Expired - Fee Related CN214357994U (en) 2020-12-21 2020-12-21 Novel finished product storehouse that grout production line was used

Country Status (1)

Country Link
CN (1) CN214357994U (en)

Similar Documents

Publication Publication Date Title
CN107098175A (en) A kind of vertical storehouse formula biomass fuel storage and induction system
US7891592B2 (en) Vibratory hopper and shredder in combination
CN214357994U (en) Novel finished product storehouse that grout production line was used
CN111891423A (en) Powder distribution system and powder distribution method
CN207258028U (en) External vibration source Powder packaging machine
CN101602409B (en) Quantitative packing machine
CN219635694U (en) Granule alloy bag-opening split-canning container
JP3678900B2 (en) Discharge method, discharge device and supply device for powder
CN213010874U (en) Powder unloading system
CN214455239U (en) Container quantitative intelligent loading system for cement packaging
KR101368686B1 (en) Powder in bags to prevent bias for bags transfer device
CN212149360U (en) Pig feed bagging machine
CN213890655U (en) Concrete mixing plant gravel bin unloader
CN112455321A (en) Structure that two kinds of fluidization in powder tank car arrange and lower ejection of compact combine together
CN218344297U (en) Detachable dual-purpose feeding temporary storage bin
CN202246213U (en) Bagged powder lime feeding device
CN212530129U (en) Powder distribution system
CN213975437U (en) Internal vibration type discharging device for batching scale bucket
CN212221757U (en) Turning plate type discharging device for ash storehouse
CN212023064U (en) Multi-functional ton bag filling funnel
CN210914477U (en) Efficient environment-friendly loading device for fragile materials
CN206984438U (en) A kind of full-automatic powder chartered plane
JPS6023712Y2 (en) Bag filling weighing device
CN221208325U (en) Novel environment-friendly agricultural material anti-blocking pulverizer
CN221070182U (en) Automatic sand and stone charging device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211008

CF01 Termination of patent right due to non-payment of annual fee