CN214313983U - But quick overhaul's mechatronic equipment - Google Patents

But quick overhaul's mechatronic equipment Download PDF

Info

Publication number
CN214313983U
CN214313983U CN202120069917.2U CN202120069917U CN214313983U CN 214313983 U CN214313983 U CN 214313983U CN 202120069917 U CN202120069917 U CN 202120069917U CN 214313983 U CN214313983 U CN 214313983U
Authority
CN
China
Prior art keywords
equipment
pressure spring
switch board
groove
distribution cabinet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120069917.2U
Other languages
Chinese (zh)
Inventor
邹海飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Yuanyue Technology Co ltd
Original Assignee
Hangzhou Yuanyue Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Yuanyue Technology Co ltd filed Critical Hangzhou Yuanyue Technology Co ltd
Priority to CN202120069917.2U priority Critical patent/CN214313983U/en
Application granted granted Critical
Publication of CN214313983U publication Critical patent/CN214313983U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Patch Boards (AREA)

Abstract

The utility model discloses a but mechatronics equipment of quick maintenance, which comprises a power distribution cabinet, be provided with the intermediate layer in the switch board, the inside dry layer that is provided with of intermediate layer has seted up the layer of ventilating on the upper and lower two sides of intermediate layer, and the intermediate layer below is seted up flutedly, is provided with the toolbox in the recess, and the handle is installed to the front end of toolbox, the spacing groove has been seted up on the inner wall about the switch board, installs equipment fixing mechanism in the switch board. Through the equipment installation mechanism of design pull formula, made things convenient for the installation and the maintenance of equipment to be provided with pressure spring and time pressure spring and carry out the shock attenuation to the equipment fixing board in equipment safety mechanism. Through designing the centre gripping of placing the drier and the recess of accomodating the toolbox in the switch board, make things convenient for the maintainer in time to maintain equipment to carry out drying protection through dry layer to switch board inside and toolbox, avoid weing.

Description

But quick overhaul's mechatronic equipment
Technical Field
The utility model relates to a mechatronic equipment correlation technique field specifically is a but mechatronic equipment of fast overhaul.
Background
The existing distribution cabinet is a final-stage device of a distribution system, and comprises a power distribution cabinet, a lighting distribution cabinet and a metering cabinet. The power distribution cabinet is a general name of a motor control center. The power distribution cabinet is used in the occasions with dispersed loads and less loops; the motor control center is used for occasions with concentrated loads and more loops. They distribute the power of a certain circuit of the upper-level distribution equipment to the nearby loads.
When the existing power distribution cabinet is provided with equipment, most internal equipment mounting plates are fixedly arranged in the power distribution cabinet, so that the existing equipment is inconvenient to mount, and internal moisture is caused when seasons change or water enters the power distribution cabinet, so that internal wires are short-circuited to cause danger; and equipment is fixed in switch board including, and the space is narrow and small difficult maintenance. Accordingly, those skilled in the art have provided a mechatronic device that can be quickly serviced to address the problems set forth in the background above.
Disclosure of Invention
An object of the utility model is to provide a but mechatronics equipment of quick maintenance to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
the utility model provides a but mechatronics equipment of overhaul fast, includes the switch board, be provided with the intermediate layer in the switch board, the inside dry layer that is provided with of intermediate layer has seted up the layer of ventilating on the upper and lower two sides of intermediate layer, and the intermediate layer below is seted up flutedly, is provided with the toolbox in the recess, and the handle is installed to the front end of toolbox, the spacing groove has been seted up on the inner wall about the switch board, installs equipment fixing mechanism in the switch board, including joint board, equipment fixing board, spacing post, last pressure spring, lower pressure spring, limiting plate in the equipment fixing mechanism, the catching groove has been seted up on equipment fixing board.
As a further aspect of the present invention: the pillar is installed to the switch board bottom, and the stopper is installed to the switch board front end.
As a further aspect of the present invention: the limiting block is connected with a sliding door, a handle is mounted on the front end face of the sliding door, and a sliding groove is formed in the rear end face of the sliding door.
As a further aspect of the present invention: the sliding groove is in sliding clamping connection with the limiting block.
As a further aspect of the present invention: the equipment mounting plate is sleeved with the limiting column in a sliding mode, and the equipment mounting plate is sleeved with the limiting plate in a sliding mode.
As a further aspect of the present invention: go up pressure spring and spacing post upper portion cup joint, go up pressure spring's bottom and equipment fixing plate fixed connection.
As a further aspect of the present invention: the lower pressure spring is sleeved with the lower part of the limiting column, and the upper end of the lower pressure spring is fixedly connected with the equipment mounting plate.
As a further aspect of the present invention: the clamping plate is in sliding clamping connection with the limiting groove.
Compared with the prior art, the beneficial effects of the utility model are that:
1. through the equipment installation mechanism of design pull formula, made things convenient for the installation and the maintenance of equipment to be provided with pressure spring and time pressure spring and carry out the shock attenuation to the equipment fixing board in equipment safety mechanism.
2. Through designing the centre gripping of placing the drier and the recess of accomodating the toolbox in the switch board, make things convenient for the maintainer in time to maintain equipment to carry out drying protection through dry layer to switch board inside and toolbox, avoid weing.
Drawings
Fig. 1 is a schematic structural diagram of a mechatronic device capable of being overhauled quickly.
FIG. 2 is a schematic view of an installation structure of an apparatus installation mechanism in a mechatronic apparatus capable of quick maintenance.
FIG. 3 is a schematic diagram of a cross-sectional side view of an apparatus mounting mechanism of a mechatronic apparatus capable of being quickly overhauled.
In the figure: 1. a power distribution cabinet; 2. a sliding door; 3. a chute; 4. a handle; 5. a limiting block; 6. a limiting groove; 7. an interlayer; 8. a ventilation layer; 9. a groove; 10. a tool box; 11. a handle; 12. drying the layer; 13. a pillar; 14. an equipment mounting mechanism; 15. a clamping and connecting plate; 16. an equipment mounting plate; 17. a limiting column; 18. an upper pressure spring; 19. a lower pressure spring; 20. a limiting plate; 21. and (6) buckling grooves.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Please refer to fig. 1-3, in the embodiment of the present invention, a mechatronics device capable of fast overhaul, including a power distribution cabinet 1, pillar 13 is installed at the bottom of power distribution cabinet 1, stopper 5 is installed at the front end of power distribution cabinet 1, sliding door 2 is connected to stopper 5, handle 4 is installed on the front end face of sliding door 2, sliding chute 3 is opened on the rear end face of sliding door 2, sliding chute 3 and stopper 5 are slidably connected, an interlayer 7 is provided in power distribution cabinet 1, a drying layer 12 is provided inside interlayer 7, a ventilation layer 8 is opened on the upper and lower faces of interlayer 7, a groove 9 is opened below interlayer 7, a tool box 10 is provided in groove 9, handle 11 is installed at the front end of tool box 10, a limiting groove 6 is opened on the left and right inner walls of power distribution cabinet 1, a clamping plate 15 is slidably connected with limiting groove 6, a device installation mechanism 14 is installed in power distribution cabinet 1, a clamping plate 15 is included in device installation mechanism 14, Equipment mounting panel 16, spacing post 17, go up pressure spring 18, down pressure spring 19, limiting plate 20, seted up catching groove 21 on equipment mounting panel 16, equipment mounting panel 16 cup joints with spacing post 17 slip, and equipment mounting panel 16 cup joints with limiting plate 20 slip, it cup joints with spacing post 17 upper portion to go up pressure spring 18, goes up pressure spring 18's bottom and equipment mounting panel 16 fixed connection, and down pressure spring 19 cup joints with spacing post 17 lower part, and down pressure spring 19's upper end and equipment mounting panel 16 fixed connection.
The utility model discloses a theory of operation is:
be provided with intermediate layer 7 in this switch board 1, install drying layer 12 in intermediate layer 7, the filler in drying layer 12 is the drier to the layer of ventilating 8 has been seted up to upper and lower both sides at intermediate layer 7, the electronic component that causes for preventing 1 inside of switch board from weing damages and toolbox 10 is inside to weing and causes the unable use of instrument.
The groove 9 is arranged below the interlayer 7, the pull-out tool box 10 is arranged in the groove 9, tools used for maintenance are placed in the tool box 10, maintenance workers can conveniently maintain equipment in the power distribution cabinet 1, the time for taking the tools back and forth is saved, the maintenance efficiency is improved, the equipment mounting mechanism 14 arranged in the power distribution cabinet 1 is in sliding clamping connection with the limiting groove 6 in the power distribution cabinet 1 through the clamping plate 15 in the mechanism, the equipment mounting mechanism 14 can be taken out for equipment mounting and maintenance, the inconvenience in maintenance caused by insufficient space in the power distribution cabinet 1 is avoided, the equipment mounting plate 16 in the equipment mounting mechanism 14 can move in a certain range up and down through the limiting plate 20 and the limiting column 17, the upper pressure spring 18 and the lower pressure spring 19 are arranged at the upper part and the lower part of the sleeving connection of the equipment mounting plate 16 and the limiting column 17, and when the power distribution cabinet 1 is impacted by external force, the equipment on the equipment mounting plate 16 in the equipment is damped, and the equipment is prevented from being damaged by large impact force.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (8)

1. An electromechanical integrated device capable of being overhauled quickly, which comprises a power distribution cabinet (1) and is characterized in that, an interlayer (7) is arranged in the power distribution cabinet (1), a drying layer (12) is arranged in the interlayer (7), ventilation layers (8) are arranged on the upper surface and the lower surface of the interlayer (7), a groove (9) is arranged below the interlayer (7), a tool box (10) is arranged in the groove (9), a handle (11) is arranged at the front end of the tool box (10), spacing groove (6) have been seted up on the inner wall about switch board (1), install equipment fixing mechanism (14) in switch board (1), including joint board (15), equipment mounting panel (16), spacing post (17), go up pressure spring (18), holding down spring (19), limiting plate (20) in equipment fixing mechanism (14), catching groove (21) have been seted up on equipment mounting panel (16).
2. The quick-overhaul electromechanical integrated equipment according to claim 1, wherein a support (13) is installed at the bottom of the power distribution cabinet (1), and a limiting block (5) is installed at the front end of the power distribution cabinet (1).
3. The electromechanical integrated equipment capable of being overhauled quickly according to claim 2, characterized in that the limiting block (5) is connected with a sliding door (2), a handle (4) is installed on the front end face of the sliding door (2), and a sliding groove (3) is formed in the rear end face of the sliding door (2).
4. The quick-overhaul electromechanical integrated device according to claim 3, wherein the sliding groove (3) is slidably clamped with the limiting block (5).
5. The quick-overhaul electromechanical integrated device according to claim 1, wherein the device mounting plate (16) is slidably sleeved with the limiting column (17), and the device mounting plate (16) is slidably sleeved with the limiting plate (20).
6. The quick-overhaul electromechanical integrated device according to claim 1, wherein the upper pressure spring (18) is sleeved with the upper part of the limiting column (17), and the bottom end of the upper pressure spring (18) is fixedly connected with the device mounting plate (16).
7. The quick-overhaul electromechanical integrated device according to claim 1, wherein the lower pressure spring (19) is sleeved with the lower portion of the limiting column (17), and the upper end of the lower pressure spring (19) is fixedly connected with the device mounting plate (16).
8. The quick-overhaul electromechanical integrated device according to claim 1, wherein the clamping plate (15) is slidably clamped with the limiting groove (6).
CN202120069917.2U 2021-01-12 2021-01-12 But quick overhaul's mechatronic equipment Expired - Fee Related CN214313983U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120069917.2U CN214313983U (en) 2021-01-12 2021-01-12 But quick overhaul's mechatronic equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120069917.2U CN214313983U (en) 2021-01-12 2021-01-12 But quick overhaul's mechatronic equipment

Publications (1)

Publication Number Publication Date
CN214313983U true CN214313983U (en) 2021-09-28

Family

ID=77824254

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120069917.2U Expired - Fee Related CN214313983U (en) 2021-01-12 2021-01-12 But quick overhaul's mechatronic equipment

Country Status (1)

Country Link
CN (1) CN214313983U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113984132A (en) * 2021-10-26 2022-01-28 四川科宏石油天然气工程有限公司 Automatic measurement sledge of gas field water transportation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113984132A (en) * 2021-10-26 2022-01-28 四川科宏石油天然气工程有限公司 Automatic measurement sledge of gas field water transportation

Similar Documents

Publication Publication Date Title
CN214313983U (en) But quick overhaul's mechatronic equipment
US20060226318A1 (en) Installation bracket with level
CN213638347U (en) Combined integrated circuit board
CN208117775U (en) A kind of multi-action computer maintenance platform
CN109434783B (en) Multifunctional device for electromechanical installation of construction engineering
CN219583134U (en) Device for preparing inorganic fireproof plate by adopting steel slag tailings and desulfurized gypsum
CN207293961U (en) A kind of crane power control cabinet
CN219041341U (en) Bus duct of environment-friendly fire-fighting power supply and distribution trunk system
CN215954115U (en) Remote intelligent control device with protection structure
CN211321736U (en) Wall-hanging regulator cubicle easy to assemble
CN213169534U (en) Mainboard turnover disc with shock-absorbing function
CN217820810U (en) Portable ammeter calibration device
CN219707713U (en) Photovoltaic board conveyer that barrier property is good
CN214852349U (en) PCBA mainboard with anti-interference structure
CN213278761U (en) High-low voltage control cabinet convenient to overhaul hidden circuit
CN212968679U (en) Distribution box
CN214504272U (en) Miniature box device for computer network security
CN217116731U (en) Optical fiber laser communication cabinet
CN219221699U (en) One-key outbound call device
CN212968728U (en) Waterproof shock attenuation power cabinet
CN211500281U (en) Safe case fixed in installation
CN218335077U (en) Lean on wall chute installing support
CN221042399U (en) Power equipment monitoring devices
CN220274094U (en) Dampproofing circuit board of start-up power
CN210040940U (en) Switch board convenient to remove transportation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210928

CF01 Termination of patent right due to non-payment of annual fee