Civil engineering construction pouring template Download PDFInfo
- Publication number
- CN214302842U CN214302842U CN202120160071.3U CN202120160071U CN214302842U CN 214302842 U CN214302842 U CN 214302842U CN 202120160071 U CN202120160071 U CN 202120160071U CN 214302842 U CN214302842 U CN 214302842U
- Authority
- CN
- China
- Prior art keywords
- plate
- splint
- supporting
- shielding plate
- shielding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 28
- 238000003466 welding Methods 0.000 claims description 4
- 229910000838 Al alloy Inorganic materials 0.000 claims description 3
- 239000000956 alloy Substances 0.000 claims description 2
- 239000011229 interlayer Substances 0.000 claims 2
- 230000006378 damage Effects 0.000 abstract description 4
- 239000002699 waste material Substances 0.000 abstract description 2
- 238000009415 formwork Methods 0.000 description 4
- 239000011230 binding agent Substances 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000295 complement effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses a civil engineering construction pouring template, including shielding plate A and shielding plate B, install shielding plate B under shielding plate A, be provided with the backup pad device between shielding plate A and the shielding plate B, the backup pad device includes intermediate layer board A, supporting splint, intermediate layer board B, bolt, sheltering from splint and supporting baffle, the lower extreme of intermediate layer board A is provided with the supporting splint, the lower extreme of supporting splint is provided with intermediate layer board B, and construction worker uses the spanner to demolish the fixed screw of two sheltering from splint and supporting splint, then removes two sheltering from splint from the recess of shielding plate A and shielding plate B, then changes the shielding plate A that damages or shielding plate B after, again with both sides sheltering from splint connect shielding plate A and shielding plate B, then uses the screw to fix two sheltering from splint and supporting splint, therefore, the replacement of the shielding plate of the pouring template is completed, and the integral waste of the pouring template is avoided.
Description
Technical Field
The utility model belongs to the technical field of the building trade is relevant, concretely relates to template is pour in civil engineering construction.
Background
The pouring formwork is a temporary supporting structure, is manufactured according to design requirements, enables a concrete structure and a member to be formed according to specified positions and geometric dimensions, keeps the correct positions, and bears the self weight of the building formwork and external loads acting on the building formwork. The purpose of the template engineering is to ensure the quality and the construction safety of the concrete engineering, accelerate the construction progress and reduce the engineering cost.
The existing civil engineering construction pouring template technology has the following problems: the existing pouring template for civil engineering construction can help construction workers to quickly finish the pouring and the shape of concrete, the existing pouring template is formed by bonding through a binder at a high temperature, but the surface of the pouring template is torn down when the pouring template is disassembled, so that the integral pouring template cannot be used.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a template is pour in civil engineering construction to the current template of pouring that proposes in solving above-mentioned background art forms through binder high temperature bonding, but when dismantling the template of pouring, can appear the phenomenon of the surface destruction of pouring the template, thereby causes the whole template of pouring can not be at the use problem.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a template is pour in civil engineering construction, includes shielding plate A and shielding plate B, shielding plate B is installed under shielding plate A, be provided with the backup pad device between shielding plate A and the shielding plate B, the backup pad device includes intermediate layer board A, supporting splint, intermediate layer board B, bolt, shielding splint and holding back, intermediate layer board A's lower extreme is provided with the holding splint, the lower extreme of holding splint is provided with intermediate layer board B, the inside of holding splint is provided with holding back plate, carry out fixed connection through the bolt between holding back plate, intermediate layer board A and the intermediate layer board B, connect through shielding splint between shielding plate A and the shielding plate B.
Preferably, baffle-plate A, baffle-plate B, sandwich panel A and sandwich panel B are made by timber matter, baffle-plate A and baffle-plate B's shape, size are all the same, sandwich panel A and sandwich panel B's shape, size are all the same, baffle-plate A and baffle-plate B's plane dimension is greater than sandwich panel A and sandwich panel B's plane dimension.
Preferably, the support splint, shelter from splint and holding back plate are made by the aluminum alloy material, the whole outward appearance of support splint is the square form, the plane size of support splint is the same with sandwich panel A's plane size.
Preferably, it is provided with two altogether to shelter from splint, two it carries out fixed connection, two to shelter from splint and support plate through the screw the whole outward appearance that shelters from splint is the U word shape.
Preferably, the shielding plate a and the shielding plate B are provided with grooves at the outer portions thereof, and the two shielding clamping plates can move in the front-back direction at the outer portions of the shielding plate a and the shielding plate B.
Preferably, the outer wall of the supporting baffle plate is completely attached to the inner wall of the supporting clamping plate, the whole appearance of the supporting baffle plate is in a cross shape, and the supporting baffle plate and the supporting clamping plate are fixedly connected through welding.
Compared with the prior art, the utility model provides a template is pour in civil engineering construction possesses following beneficial effect:
the utility model discloses the backup pad device of template is pour in civil engineering construction that has now been changed, the backup pad device includes sandwich panel A, supporting splint, sandwich panel B, the bolt, shelter from splint and supporting baffle, construction worker runs into when pouring the template surface and appear damaged, construction worker uses the spanner to demolish two fixed screws that shelter from splint and supporting splint, then remove two recess departments that shelter from splint from shielding plate A and shielding plate B, then change the back with the shielding plate A or the shielding plate B that damage, shelter from splint with both sides again and connect shielding plate A and shielding plate B, then use the screw to shelter from splint and supporting splint with two and fix the back, thereby the change of the shielding plate of pouring the template has been accomplished, thereby avoid pouring the holistic waste of template.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description, do not constitute a limitation of the invention, in which:
fig. 1 is a schematic view of the whole structure of a civil engineering construction pouring template provided by the utility model;
FIG. 2 is a schematic view of a sectional structure of a civil engineering construction pouring template provided by the utility model;
fig. 3 is a schematic view of a top-view cross-sectional structure of a civil engineering construction pouring template provided by the utility model;
fig. 4 is a schematic view of a three-dimensional structure of a civil engineering construction pouring template provided by the utility model;
in the figure: 1. a shielding plate A; 2. a support plate arrangement; 3. a shielding plate B; 4. a sandwich panel A; 5. supporting the clamping plate; 6. a sandwich panel B; 7. a bolt; 8. a shielding splint; 9. and supporting the baffle.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a civil engineering construction pouring template comprises a shielding plate A1 and a shielding plate B3, wherein a shielding plate B3 is installed right below a shielding plate A1, grooves are formed in the outer portions of the shielding plate A1 and the shielding plate B3, two shielding clamp plates 8 can move in the front-back direction of the outer portions of a shielding plate A1 and a shielding plate B3, the two shielding clamp plates 8 are connected through moving in the grooves in the outer portions of the shielding plate A1 and the shielding plate B3, so that the shielding plate A1 and the shielding plate B3 are prevented from being separated, a supporting plate device 2 is arranged between the shielding plate A1 and the shielding plate B3, the supporting plate device 2 comprises a sandwich plate A4, a supporting clamp plate 5, a sandwich plate B6, a bolt 7, a shielding clamp plate 8 and a supporting baffle plate 9, a supporting clamp plate 5 is arranged at the lower end of the sandwich plate A4, the shielding plates A1, the shielding plates B3, the shielding plates A4 and the B6 are all made of wood, the shielding plate A1 and the shielding plate B3 are the same in shape and size, the shape and the size of the sandwich plate A4 and the sandwich plate B6 are the same, the plane size of the baffle plate A1 and the baffle plate B3 is larger than the plane size of the sandwich plate A4 and the sandwich plate B6, the lower end of the supporting splint 5 is provided with the sandwich plate B6, the supporting splint 5 is internally provided with a supporting baffle plate 9, the outer wall of the supporting baffle plate 9 is completely attached to the inner wall of the supporting splint 5, the whole appearance of the supporting baffle plate 9 is in a cross shape, the supporting baffle plate 9 and the supporting splint 5 are fixedly connected by welding, the supporting baffle plate 9 and the supporting splint 5 are welded to be firmer and less prone to damage, the supporting baffle plate 9 is in a cross shape, the supporting baffle plate can better play a supporting role, the inner cavity of a pouring formwork can not be poured, collapse is avoided, the supporting splint 5, the shielding splint 8 and the supporting baffle plate 9 are made of materials, the whole appearance of the supporting splint 5 is in a square shape, the plane size of the supporting splint 5 is the same as that of the sandwich plate A4, the supporting splint 5, the shielding splint 8 and the supporting baffle 9 made of aluminum alloy are stronger and firmer in bearing force, meanwhile, the whole weight is not very heavy, the supporting baffle 9, the sandwich plate A4 and the sandwich plate B6 are fixedly connected through bolts 7, the shielding splint A1 and the shielding splint B3 are connected through the shielding splint 8, the shielding splint 8 is provided with two shielding splints 8, the two shielding splints 8 and the supporting splint 5 are fixedly connected through screws, the whole appearance of the two shielding splint 8 is U-shaped, the two shielding splints 8 can completely complement the sizes between the shielding splint A1 and the shielding splint B3 and the supporting splint 5, between the sandwich plate A4 and the sandwich plate B6, so that the fall of the shielding plate A1, the sandwich plate A4, the supporting splint 5, the sandwich plate B6 and the shielding plate B3 is avoided, thereby avoiding hanging on the clothing or body of the construction worker.
The utility model discloses a theory of operation and use flow: the utility model discloses after having installed, earlier weld back through the welding machine with supporting baffle 9 and supporting splint 5, place sandwich panel B6 at supporting splint 5's lower extreme again, then use bolt 7 to run through the screw hole on sandwich panel B6 and the supporting splint 9, place sandwich panel A4 at supporting splint 5's upper end again, make the screw hole on the sandwich panel A4 pass bolt 7, then use the spanner to carry out the swivelling joint with bolt 7, will place shielding plate A1 and shielding plate B3 respectively in the both sides of sandwich panel A4 and sandwich panel B6 on next step, again with two shielding splint 8 connect through the outside recess of shielding plate A1 and shielding plate B3, shelter from splint 8 and supporting splint 5 through the screw at last and carry out fixed connection with two, later normal use pour the template can.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (6)
1. The utility model provides a template is pour in civil engineering construction, includes shielding plate A (1) and shielding plate B (3), its characterized in that: a baffle plate B (3) is arranged right below the baffle plate A (1), a supporting plate device (2) is arranged between the baffle plate A (1) and the baffle plate B (3), the supporting plate device (2) comprises a sandwich plate A (4), a supporting clamping plate (5), a sandwich plate B (6), a bolt (7), a shielding clamping plate (8) and a supporting baffle plate (9), a supporting splint (5) is arranged at the lower end of the interlayer plate A (4), an interlayer plate B (6) is arranged at the lower end of the supporting splint (5), a supporting baffle plate (9) is arranged inside the supporting splint (5), the supporting baffle plate (9), the sandwich plate A (4) and the sandwich plate B (6) are fixedly connected through a bolt (7), the shielding plate A (1) and the shielding plate B (3) are connected through a shielding clamping plate (8).
2. The civil engineering construction pouring template according to claim 1, characterized in that: baffle-plate A (1), baffle-plate B (3), sandwich panel A (4) and sandwich panel B (6) are made by timber matter, the shape, the size of baffle-plate A (1) and baffle-plate B (3) are all the same, the shape, the size of sandwich panel A (4) and sandwich panel B (6) are all the same, the plane size of baffle-plate A (1) and baffle-plate B (3) is greater than the plane size of sandwich panel A (4) and sandwich panel B (6).
3. The civil engineering construction pouring template according to claim 1, characterized in that: support splint (5), shelter from splint (8) and supporting baffle (9) and make by the aluminum alloy material, the whole outward appearance of support splint (5) is the square form, the plane size of support splint (5) is the same with the plane size of sandwich panel A (4).
4. The civil engineering construction pouring template according to claim 1, characterized in that: shelter from splint (8) and be provided with two altogether shelter from splint (8) and support splint (5) and carry out fixed connection, two through the screw the whole outward appearance that shelters from splint (8) is the U word shape.
5. The civil engineering construction pouring template according to claim 1, characterized in that: the outside of shielding plate A (1) and shielding plate B (3) is provided with a groove, and two shielding clamping plates (8) can move in the front-back direction outside shielding plate A (1) and shielding plate B (3).
6. The civil engineering construction pouring template according to claim 1, characterized in that: the outer wall of the supporting baffle plate (9) is completely attached to the inner wall of the supporting clamping plate (5), the whole appearance of the supporting baffle plate (9) is in a cross shape, and the supporting baffle plate (9) and the supporting clamping plate (5) are fixedly connected through welding.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120160071.3U CN214302842U (en) | 2021-01-21 | 2021-01-21 | Civil engineering construction pouring template |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120160071.3U CN214302842U (en) | 2021-01-21 | 2021-01-21 | Civil engineering construction pouring template |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214302842U true CN214302842U (en) | 2021-09-28 |
Family
ID=77828496
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202120160071.3U Expired - Fee Related CN214302842U (en) | 2021-01-21 | 2021-01-21 | Civil engineering construction pouring template |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214302842U (en) |
-
2021
- 2021-01-21 CN CN202120160071.3U patent/CN214302842U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106926359A (en) | A kind of vertical manufacture method of slag concrete sandwich insulation exterior wall plate | |
CN202627491U (en) | Forming template for deformation joint position shear wall of high-rise building | |
CN214302842U (en) | Civil engineering construction pouring template | |
CN204282803U (en) | To encorbelment formwork structure for mounting platform | |
CN206000163U (en) | Aluminum alloy building template splicing component | |
CN201671227U (en) | SRC column with diagonally arranged cross steels with flanges | |
CN207761280U (en) | A kind of building aluminum alloy mould plate composite structure | |
CN206279764U (en) | A kind of beam-column joint combination template | |
CN201339320Y (en) | High-altitude overhanging hanging reinforced concrete hanging bracket | |
CN213742326U (en) | Building engineering construction template fastener | |
CN213952915U (en) | A operating platform that encorbelments of formula that can have enough to meet need for in well | |
CN212866844U (en) | Main part construction quick assembly disassembly template is built in room | |
CN201560582U (en) | Supporting piece used for wall, column and girder in construction engineering | |
CN210122816U (en) | Be used for assembled coincide floor bottom plate board seam template reinforcing apparatus | |
CN202787960U (en) | Steel girder grid floor formwork system | |
CN103216087B (en) | A kind of two-way self-bearing type construction formwork system | |
CN219298791U (en) | Multifunctional aluminum die inclined support | |
CN107663898B (en) | A kind of connection load-carrying members of I-beam | |
CN214117504U (en) | Portable steel concrete composite beam construction formwork support device | |
CN205935695U (en) | Cloth mechanic possesses formula platform | |
CN215829473U (en) | Piping lane axillary angle steel template | |
CN212050281U (en) | High stability cantilever crane for building | |
CN205000634U (en) | Floor supports first both sides connecting elements | |
CN212295553U (en) | Auxiliary supporting scaffold for hydroelectric installation | |
CN215672246U (en) | Tunnel lining preformed hole template adds fixed bit architecture |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210928 |
|
CF01 | Termination of patent right due to non-payment of annual fee |