CN214272959U - Civil engineering construction support - Google Patents

Civil engineering construction support Download PDF

Info

Publication number
CN214272959U
CN214272959U CN202120031276.1U CN202120031276U CN214272959U CN 214272959 U CN214272959 U CN 214272959U CN 202120031276 U CN202120031276 U CN 202120031276U CN 214272959 U CN214272959 U CN 214272959U
Authority
CN
China
Prior art keywords
frame
groove
draw
connecting rod
civil engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120031276.1U
Other languages
Chinese (zh)
Inventor
王剑非
孙连臻
刘芯语
国栋铭
王得骁
刘威宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202120031276.1U priority Critical patent/CN214272959U/en
Application granted granted Critical
Publication of CN214272959U publication Critical patent/CN214272959U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a civil engineering construction support, including first frame, second frame, the second frame is located one side of first frame, the internal connection of first frame has first support frame, the internal connection of second frame has the second support frame, the front end edge center department of first support frame, second support frame is provided with strengthening mechanism, strengthening mechanism includes head rod, second connecting rod, the one end of head rod is provided with first draw-in groove, and the one end of second connecting rod is provided with the second draw-in groove, the dead lever has been cup jointed with the inside of second draw-in groove to first draw-in groove. A civil engineering construction support, can consolidate first frame, second frame, fixed more firm avoids not hard up emergence that leads to the accident between first frame and the second frame, relatively safe, can dismantle the bracing piece after the use is accomplished, the operation is more convenient.

Description

Civil engineering construction support
Technical Field
The utility model relates to a building technical field, in particular to civil engineering building construction support.
Background
Civil engineering construction is a general term of science and technology for building various land engineering facilities, which refers to applied materials, equipment, technical activities such as surveying, designing, constructing, maintaining and repairing, and also refers to objects of engineering construction, i.e. various engineering facilities which are built on the ground or underground or on land and directly or indirectly serve human life, production, military and scientific research, such as houses, roads, railways, pipelines, tunnels, bridges, canals, dams, harbors, power stations, airports, ocean platforms, water supply and drainage, protection engineering and the like. The civil engineering refers to engineering entities for surveying, planning, designing, constructing, installing and maintaining various technical works and the like of newly-built, reconstructed or expanded buildings, structures, related supporting facilities and the like of various projects except house buildings.
The construction support is a temporary supporting structure, is manufactured according to design requirements, enables a concrete structure and a member to be formed according to specified positions and geometric dimensions, keeps the correct position, bears the self weight of a building and external loads acting on the building, ensures the quality and the construction safety of a concrete project, accelerates the construction progress and reduces the engineering cost; only through bolted connection between the current construction support, it is firm inadequately to fix, easily not hard up between the frame, leads to the occurence of failure, uses very unsafe, and the bracing piece installation of frame is inconvenient with the dismantlement, in order to solve above-mentioned problem, we have proposed a civil engineering construction support.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a main aim at provides a civil engineering construction support can effectively solve the problem in the background art.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a civil engineering construction support, includes first frame, second frame, the second frame is located one side of first frame, the internal connection of first frame has first support frame, the internal connection of second frame has the second support frame, the front end edge center department of first support frame, second support frame is provided with strengthening mechanism, strengthening mechanism includes head rod, second connecting rod, the one end of head rod is provided with first draw-in groove, and the one end of second connecting rod is provided with the second draw-in groove, the dead lever has been cup jointed to the inside of first draw-in groove and second draw-in groove, the screw hole has all been seted up to the inside of first draw-in groove, second draw-in groove, dead lever, the internal connection of screw hole has fixing bolt, the front end slope of dead lever is provided with the bracing piece.
Preferably, the first connecting rod and the second connecting rod are both L-shaped, the rear end of the first connecting rod is welded at the front end of the first support frame, the second connecting rod is welded at the front end of the second support frame, and the tangent planes of the first clamping groove and the second clamping groove are both semicircular.
Preferably, the outer fixed surface of one end of first draw-in groove and head rod is connected, and the outer fixed surface of one end of second draw-in groove and second connecting rod is connected, the diameter of fixed rod and the internal diameter size looks adaptation of the pipe that first draw-in groove, second draw-in groove are constituteed, fixing bolt runs through in the inside of first draw-in groove and second draw-in groove, the dead lever is fixed in the inside of first draw-in groove and second draw-in groove through fixing bolt, the crack between head rod and the second connecting rod is the character cut in bas-relief, be connected as an organic whole between dead lever and the bracing piece.
Preferably, the dead lever perpendicular to first frame, second frame, the contained angle between bracing piece and the dead lever is 135 degrees, the lower extreme welding of bracing piece has the bottom plate.
Preferably, fastening bolts are installed on the inner wall connected between the first frame and the second frame, the number of the fastening bolts is four, the fastening bolts are linearly arranged, the first frame and the second frame are fixedly connected through the fastening bolts and a reinforcing mechanism, and the first frame and the second frame are identical in structure.
Preferably, the first support frame and the second support frame are respectively welded on the inner side surfaces of the first frame and the second frame, and the first frame and the second frame are made of stainless steel materials.
Compared with the prior art, the utility model discloses following beneficial effect has: the civil engineering building construction support can fix a second frame at one side of a first frame through a fastening bolt, further enable a first clamping groove at one end of the first connecting rod to be attached to a second clamping groove at one end of the second connecting rod, insert a fixed rod into a round pipe formed by the first clamping groove and the second clamping groove, enable threaded holes in the first clamping groove, the second clamping groove and the second clamping groove to be aligned, screw the fixed bolt into the threaded holes, enable the fixed rod to be fixed between the first clamping groove and the second clamping groove, enable the first connecting rod to be connected with the second connecting rod, enable the first frame and the second frame to be connected into a whole, reinforce the first frame and the second frame, and enable a supporting rod and a bottom plate to be fixed below the joint of the first frame and the second frame after the fixed rod is connected, and enable the first frame and the bottom plate to be connected with the first frame through the supporting rod and the bottom plate, The second frame plays good supporting role, and is fixed more firm, avoids not hard up emergence that leads to the accident between first frame and the second frame, and is safer, and not hard up fixing bolt can be with first draw-in groove, second draw-in groove, dead lever separation, can dismantle the bracing piece, and the operation is more convenient, and the effect of use is better for traditional mode.
Drawings
FIG. 1 is a schematic view of the whole structure of the civil engineering construction support of the present invention;
fig. 2 is an exploded schematic view of the reinforcing mechanism of the civil engineering construction support of the present invention;
fig. 3 is the utility model relates to a civil engineering construction support's strengthening mechanism's local structure schematic diagram.
In the figure: 1. a first frame; 2. a second frame; 3. a first support frame; 4. a second support frame; 5. fastening a bolt; 6. a reinforcement mechanism; 61. a first connecting rod; 62. a first card slot; 63. a second connecting rod; 64. a second card slot; 65. fixing the bolt; 66. fixing the rod; 67. a threaded hole; 7. a support bar; 8. a base plate.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
As shown in fig. 1-3, a civil engineering construction support comprises a first frame 1 and a second frame 2, the second frame 2 is located at one side of the first frame 1, the first frame 1 is internally connected with a first support frame 3, the second frame 2 is internally connected with a second support frame 4, a reinforcing mechanism 6 is arranged at the center of the front end edge of the first support frame 3 and the second support frame 4, the reinforcing mechanism 6 comprises a first connecting rod 61 and a second connecting rod 63, one end of the first connecting rod 61 is provided with a first clamping groove 62, and one end of the second connecting rod 63 is provided with a second clamping groove 64, the fixing rod 66 is sleeved in the first clamping groove 62 and the second clamping groove 64, threaded holes 67 are formed in the first clamping groove 62, the second clamping groove 64 and the fixing rod 66, the fixing bolt 65 is connected in the threaded hole 67, and the supporting rod 7 is obliquely arranged at the front end of the fixing rod 66.
In this embodiment, the first connecting rod 61 and the second connecting rod 63 are both L-shaped, the rear end of the first connecting rod 61 is welded to the front end of the first support frame 3, the second connecting rod 63 is welded to the front end of the second support frame 4, and the cross sections of the first clamping groove 62 and the second clamping groove 64 are both semicircular.
First draw-in groove 62 and the one end outer fixed surface of first connecting rod 61 are connected, and the one end outer fixed surface of second draw-in groove 64 and second connecting rod 63 is connected, the diameter and the first draw-in groove 62 of dead lever 66, the internal diameter size looks adaptation of the pipe that second draw-in groove 64 is constituteed, fixing bolt 65 runs through in the inside of first draw-in groove 62 and second draw-in groove 64, dead lever 66 passes through fixing bolt 65 and is fixed in the inside of first draw-in groove 62 and second draw-in groove 64, the crack between first connecting rod 61 and the second connecting rod 63 is the character cut in bas-relief, be connected as an organic whole between dead lever 66 and the bracing piece 7.
Specifically, in inserting the dead lever 66 into the round tube that first draw-in groove 62 and second draw-in groove 64 are constituteed, enable the inside screw hole 67 of first draw-in groove 62, second draw-in groove 64 to align, twist fixing bolt 65 into the inside of screw hole 67, can make dead lever 66 fix first draw-in groove 62 make and second draw-in groove 64 between, enable first connecting rod 61 and second connecting rod 63 to be connected, can make first frame 1, second frame 2 connect into a whole.
In this embodiment, the fixing rod 66 is perpendicular to the first frame 1 and the second frame 2, an included angle between the supporting rod 7 and the fixing rod 66 is 135 degrees, and the bottom plate 8 is welded at the lower end of the supporting rod 7.
Specifically, the support rods 7 and the bottom plate 8 can support the first frame 1 and the second frame 2 well.
In this embodiment, the fastening bolts 5 are installed on the inner wall connected between the first frame 1 and the second frame 2, the number of the fastening bolts 5 is four, the fastening bolts 5 are linearly arranged, the first frame 1 and the second frame 2 are fixedly connected through the fastening bolts 5 and the reinforcing mechanism 6, and the first frame 1 and the second frame 2 have the same structure.
The first support frame 3 and the second support frame 4 are respectively welded on the inner side surfaces of the first frame 1 and the second frame 2, and the first frame 1 and the second frame 2 are made of stainless steel materials.
Specifically, the first frame 1 and the second frame 2 can be reinforced by the first support frame 3 and the second support frame 4, so that the first frame 1 and the second frame 2 are prevented from deforming after cement is poured, and the service life is long.
It should be noted that, the utility model relates to a civil engineering construction support, the user passes through fastening bolt 5 with second frame 2 and fixes in one side of first frame 1, and then enable the first draw-in groove 62 of first connecting rod 61 one end and the second draw-in groove 64 of second connecting rod 63 one end to laminate mutually, insert dead lever 66 in the pipe that first draw-in groove 62 and second draw-in groove 64 are constituteed, enable first draw-in groove 62, second draw-in groove 64, the inside screw hole 67 of second draw-in groove 64 aligns, twist fixing bolt 65 into the inside of screw hole 67, can make dead lever 66 fix between first draw-in groove 62 makes and second draw-in groove 64, enable first frame 1, second frame 2 connects into an entirety, can fix bracing piece 7, bottom plate 8 in the below of first frame 1, second frame 2 junction after dead lever 66 connects, through bracing piece 7, bottom plate 8 can be to first frame 1, The second frame 2 plays a good supporting role and is practical.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides a civil engineering construction support, includes first frame (1), second frame (2), its characterized in that: the second frame (2) is positioned on one side of the first frame (1), a first supporting frame (3) is connected inside the first frame (1), a second supporting frame (4) is connected inside the second frame (2), a reinforcing mechanism (6) is arranged at the center of the front end edge of the first supporting frame (3) and the second supporting frame (4), the reinforcing mechanism (6) comprises a first connecting rod (61) and a second connecting rod (63), a first clamping groove (62) is arranged at one end of the first connecting rod (61), a second clamping groove (64) is arranged at one end of the second connecting rod (63), fixing rods (66) are sleeved inside the first clamping groove (62) and the second clamping groove (64), threaded holes (67) are formed inside the first clamping groove (62), the second clamping groove (64) and the fixing rods (66), and fixing bolts (65) are connected inside the threaded holes (67), the front end of the fixed rod (66) is obliquely provided with a supporting rod (7).
2. The civil engineering construction support of claim 1, wherein: the first connecting rod (61) and the second connecting rod (63) are L-shaped, the rear end of the first connecting rod (61) is welded at the front end of the first supporting frame (3), the second connecting rod (63) is welded at the front end of the second supporting frame (4), and the tangent planes of the first clamping groove (62) and the second clamping groove (64) are semicircular.
3. The civil engineering construction support of claim 1, wherein: the utility model discloses a fixing device for fixing a support rod, including first draw-in groove (62), second draw-in groove (64), the inside diameter size looks adaptation of the pipe that diameter and first draw-in groove (62), second draw-in groove (64) of dead lever (66) are constituteed, fixing bolt (65) run through in the inside of first draw-in groove (62) and second draw-in groove (64), dead lever (66) are fixed in the inside of first draw-in groove (62) and second draw-in groove (64) through fixing bolt (65), the crack between first draw-in groove (61) and second connecting rod (63) is character cut in bas-relief, be connected as an organic whole between dead lever (66) and bracing piece (7).
4. The civil engineering construction support of claim 1, wherein: dead lever (66) perpendicular to first frame (1), second frame (2), the contained angle between bracing piece (7) and dead lever (66) is 135 degrees, the lower extreme welding of bracing piece (7) has bottom plate (8).
5. The civil engineering construction support of claim 1, wherein: fastening bolts (5) are installed on the inner wall connected between the first frame (1) and the second frame (2), the number of the fastening bolts (5) is four, the fastening bolts (5) are linearly arranged, the first frame (1) and the second frame (2) are fixedly connected through the fastening bolts (5) and the reinforcing mechanism (6), and the first frame (1) and the second frame (2) are identical in structure.
6. The civil engineering construction support of claim 1, wherein: the first support frame (3) and the second support frame (4) are respectively welded on the inner side surfaces of the first frame (1) and the second frame (2), and the first frame (1) and the second frame (2) are made of stainless steel materials.
CN202120031276.1U 2021-01-07 2021-01-07 Civil engineering construction support Expired - Fee Related CN214272959U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120031276.1U CN214272959U (en) 2021-01-07 2021-01-07 Civil engineering construction support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120031276.1U CN214272959U (en) 2021-01-07 2021-01-07 Civil engineering construction support

Publications (1)

Publication Number Publication Date
CN214272959U true CN214272959U (en) 2021-09-24

Family

ID=77791030

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120031276.1U Expired - Fee Related CN214272959U (en) 2021-01-07 2021-01-07 Civil engineering construction support

Country Status (1)

Country Link
CN (1) CN214272959U (en)

Similar Documents

Publication Publication Date Title
CN201546227U (en) Steel support beam for supporting foundation pit bracing piling wall and basement structure outer wall
CN113279414A (en) Octagonal working pit supporting member and installation and construction method thereof
CN214272959U (en) Civil engineering construction support
CN110258528B (en) Assembled and inserted self-clamping type prefabricated hollow underground continuous wall and construction method thereof
CN117248530A (en) Conjuncted construction device and construction method for existing building additionally provided with elevator foundation pit structure
CN207934185U (en) A kind of detachably prefabricated assembled concrete-filled steel square tubular column and girder steel combined joint
CN204001665U (en) A kind of scaffold assembling wall-connecting piece
CN213682679U (en) Flexible connection's assembled wall body
CN108951657A (en) A kind of pattern foundation pit supporting structure assembled concrete-filled rectangular steel tube diagonal brace
CN213296881U (en) Steel structure upright post for assembly type building
CN204457079U (en) Enclosure upright post
CN212027397U (en) High protection device for civil engineering of security
CN211174153U (en) Supporting structure for underground space construction
CN108330956B (en) Foundation pit fender pile
CN209855819U (en) Component for preventing shield segment of shield tunnel from leaking water
CN113047327A (en) Multi-connected-cylinder rectangular assembled well wall structure and assembling method thereof
CN202114437U (en) Positioning device for foundation bolts
CN217760046U (en) Building templates connects steelframe for civil engineering
CN112049251A (en) Civil engineering is with assembled steel construction concreting building structure exempts from
CN211336045U (en) Rear steel plate installation auxiliary vehicle
CN209780321U (en) Civil engineering construction mounting frame
CN205172029U (en) False hillstone in gardens connects reinforced structure
CN213391530U (en) Building engineering safety control rail
CN214725212U (en) Core concrete component is irritated in prefabrication of PHC tubular pile
CN219586774U (en) Prefabricated retaining wall suitable for crown beam top

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210924