CN214245816U CN202120151932.1U CN202120151932U CN214245816U CN 214245816 U CN214245816 U CN 214245816U CN 202120151932 U CN202120151932 U CN 202120151932U CN 214245816 U CN214245816 U CN 214245816U
Authority
CN
China
Prior art keywords
cutting
retaining wall
concrete pile
bored concrete
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120151932.1U
Other languages
Chinese (zh)
Inventor
阮小峰
董理践
郭建新
范崇满
齐凯
张翔
沈阳
高飞
王俊杰
郭林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Zhongyuan Geotechnical Engineering Co ltd
Original Assignee
Henan Zhongyuan Geotechnical Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Zhongyuan Geotechnical Engineering Co ltd filed Critical Henan Zhongyuan Geotechnical Engineering Co ltd
Priority to CN202120151932.1U priority Critical patent/CN214245816U/en
Application granted granted Critical
Publication of CN214245816U publication Critical patent/CN214245816U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a bar planting barricade structure of cutting bored concrete pile, including cutting, cutting slope, drilling bored concrete pile body, retaining wall and protection rose box, the cutting slope is located the left side of cutting, the drilling bored concrete pile body inlays the inside of establishing at the cutting slope, the fixed surface of drilling bored concrete pile body is connected with links up the reinforcing bar, the right side wall overlap joint of retaining wall and cutting slope, the one end that the drilling bored concrete pile body was kept away from to the linking reinforcing bar runs through the right side wall and the fixedly connected with latch segment of retaining wall. This cutting bored concrete pile's bar planting barricade structure through setting up bored concrete pile body, retaining wall, linking reinforcing bar and latch segment, can reach the purpose of protecting the cutting side slope, avoids the cutting side slope to appear collapsing, through setting up trapezoidal protection ditch, can slow down the water and the earth that the cutting side slope surface flows, avoids appearing soil erosion and water loss phenomenon, has reached the purpose of protecting cutting side slope and cutting.

Description

Bar planting retaining wall structure of cutting cast-in-situ bored pile
Technical Field
The utility model relates to a geotechnical engineering technical field specifically is a muscle barricade structure is planted to cutting drilling bored concrete pile.
Background
Cutting refers to the form of a roadbed excavated from the original ground. The elevation is controlled by easing the longitudinal slope of the road or passing through the ridge through the mountain line.
Cutting side slope is in the crust top layer, and the excavation exposes the back, receives the effect of various conditions and natural factor, takes place to warp easily and destroys, in order to protect the cutting, we need a bar planting barricade structure of cutting drilling bored concrete pile.
Disclosure of Invention
An object of the utility model is to provide a cutting drilling bored concrete pile plants muscle barricade structure to solve the problem that provides among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a cutting bored concrete pile's bar planting barricade structure, includes cutting, cutting slope, drilling bored concrete pile body, retaining wall and protection rose box, the cutting slope is located the left side of cutting, drilling bored concrete pile body inlays the inside of establishing at the cutting slope, the fixed surface of drilling bored concrete pile body is connected with links up the reinforcing bar, the right side wall overlap joint of retaining wall and cutting slope, the one end that links up the reinforcing bar and keep away from the drilling bored concrete pile body runs through the right side wall and the fixedly connected with latch segment of retaining wall, the right side wall fixedly connected with construction bolt of retaining wall, the right side wall of retaining wall passes through construction bolt and protection rose box fixed connection, the water inlet has been seted up on the top of protection rose box, a plurality of filtration pore has been seted up to the bottom equidistance of protection rose box.
Preferably, the upper surface of the cutting slope is longitudinally provided with two trapezoidal protective ditches.
Preferably, the number of linking reinforcing bar is a plurality of, and the reinforcing bar equidistance that a plurality of linked sets up the right flank at drilling bored concrete pile body.
Preferably, the number of bored concrete pile body is a plurality of, a plurality of bored concrete pile body equidistance sets up the inner wall at cutting side slope.
Preferably, the upper surface of the retaining wall is provided with a water outlet, and the water outlet corresponds to the water inlet of the protective filter box.
Preferably, the inside of protection rose box is provided with first filter layer and second filter layer respectively, first filter layer is located the top of second filter layer, the material of first filter layer is river sand, the material of second filter layer is the grit.
Advantageous effects
The utility model provides a cutting drilling bored concrete pile's bar-planting barricade structure possesses following beneficial effect:
1. this cutting bored concrete pile's bar planting barricade structure through setting up bored concrete pile body, retaining wall, linking reinforcing bar and latch segment, can reach the purpose of protecting the cutting side slope, avoids the cutting side slope to appear collapsing, through setting up trapezoidal protection ditch, can slow down the water and the earth that the cutting side slope surface flows, avoids appearing soil erosion and water loss phenomenon, has reached the purpose of protecting cutting side slope and cutting.
2. This cutting drilling bored concrete pile's bar planting barricade structure through setting up the outlet, can utilize retaining wall and outlet to gather together the rainwater, through setting up protection rose box, first filter layer and second filter layer, can filter the rainwater that gathers under the stream on the cutting side slope, avoids appearing the phenomenon of soil erosion and water loss, and has reached the purpose of protecting the cutting.
Drawings
FIG. 1 is a schematic view of a front cross-sectional structure of the present invention;
FIG. 2 is an enlarged schematic view of the structure at A in FIG. 1;
FIG. 3 is a schematic top view of the connection between the retaining wall and the protective filter box.
In the figure: 1 cutting, 2 cutting slopes, 3 bored concrete pile bodies, 4 retaining walls, 5 protection rose boxes, 6 linking reinforcing bars, 7 latch blocks, 8 construction bolts, 9 trapezoidal protection ditches, 10 water outlet, 11 first filter layers, 12 second filter layers.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: the utility model provides a cutting bored concrete pile's bar planting barricade structure, including cutting 1, cutting slope 2, bored concrete pile body 3, retaining wall 4 and protection rose box 5, cutting slope 2 is located cutting 1's left side, trapezoidal protection ditch 9 has vertically been seted up to cutting slope 2's upper surface, the quantity of trapezoidal protection ditch 9 is two, through setting up trapezoidal protection ditch 9, can slow down the water and the earth of 2 surface flows of cutting slope, avoid appearing soil erosion and water loss phenomenon, reached the mesh of protecting cutting slope 2 and cutting 1.
The quantity of bored concrete pile body 3 is a plurality of, 3 equidistance settings of a plurality of bored concrete pile body are at the inner wall of cutting side slope 2, bored concrete pile body 3 inlays the inside of establishing at cutting side slope 2, the fixed surface of bored concrete pile body 3 is connected with linking reinforcing bar 6, the quantity of linking reinforcing bar 6 is a plurality of, 6 equidistance settings of a plurality of linked reinforcing bar are at the right flank of bored concrete pile body 3, retaining wall 4 and the right side wall overlap joint of cutting side slope 2, linking reinforcing bar 6 and keeping away from the one end of bored concrete pile body 3 and running through the right side wall of retaining wall 4 and fixedly connected with latch segment 7, through setting up bored concrete pile body 3, retaining wall 4, link up reinforcing bar 6 and latch segment 7, can reach the mesh of protecting cutting side slope 2, avoid cutting side slope 2 to appear collapsing.
The right side wall of the retaining wall 4 is fixedly connected with a mounting bolt 8, the right side wall of the retaining wall 4 is fixedly connected with a protective filter box 5 through the mounting bolt 8, the top end of the protective filter box 5 is provided with a water inlet, the bottom end of the protective filter box 5 is equidistantly provided with a plurality of filter holes, the upper surface of the retaining wall 4 is provided with a water outlet 10, rainwater can be gathered by utilizing the retaining wall 4 and the water outlet 10 through arranging the water outlet 10, the water outlet 10 corresponds to the position of the water inlet of the protective filter box 5, a first filter layer 11 and a second filter layer 12 are respectively arranged inside the protective filter box 5, the first filter layer 11 is positioned at the top of the second filter layer 12, the first filter layer 11 is made of river sand, the second filter layer 12 is made of sand, and rainwater gathered and flowing down on the cutting slope 2 can be filtered through arranging the protective filter box 5, the first filter layer 11 and the second filter layer 12, the phenomenon of water and soil loss is avoided, and the purpose of protecting the cutting 1 is achieved.
The working principle is as follows: when using this cutting drilling bored concrete pile's bar planting barricade structure, through setting up drilling bored concrete pile body 3, retaining wall 4, join up reinforcing bar 6 and latch segment 7, can reach the purpose of protecting cutting side slope 2, avoid cutting side slope 2 to appear collapsing, through setting up trapezoidal protection ditch 9, can block the water and the earth of cutting side slope 2 surface flow, avoid appearing soil erosion phenomenon, reached the purpose of protecting cutting side slope 2 and cutting 1, through setting up sluicing mouth 10, can utilize retaining wall 4 and sluicing mouth 10 to gather together the rainwater, through setting up protection rose box 5, first filter layer 11 and second filter layer 12, can filter the rainwater that gathers together down on cutting side slope 2, the phenomenon of soil erosion is avoided appearing, and the purpose of protecting cutting 1 has been reached.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a cutting bored concrete pile's bar planting barricade structure, includes cutting (1), cutting slope (2), bored concrete pile body (3), retaining wall (4) and protection rose box (5), its characterized in that: cutting side slope (2) are located the left side of cutting (1), drilling bored concrete pile body (3) inlay the inside of establishing in cutting side slope (2), the fixed surface of drilling bored concrete pile body (3) is connected with linking up reinforcing bar (6), retaining wall (4) and the right side wall overlap joint of cutting side slope (2), the one end that drilling bored concrete pile body (3) were kept away from in linking up reinforcing bar (6) runs through the right side wall and the fixedly connected with latch segment (7) of retaining wall (4), the right side wall fixedly connected with construction bolt (8) of retaining wall (4), the right side wall of retaining wall (4) passes through construction bolt (8) and protection rose box (5) fixed connection, the water inlet has been seted up on the top of protection rose box (5), a plurality of filtration pore has been seted up to the bottom of protection rose box (5) equidistance.
2. The tendon-embedded retaining wall structure of the cut cast-in-situ bored pile according to claim 1, characterized in that: trapezoidal protection ditch (9) have vertically been seted up to the upper surface of cutting slope (2), the quantity of trapezoidal protection ditch (9) is two.
3. The tendon-embedded retaining wall structure of the cut cast-in-situ bored pile according to claim 1, characterized in that: the quantity of linking reinforcing bar (6) is a plurality of, and a plurality of equidistance setting that links up reinforcing bar (6) is in the right flank of drilling bored concrete pile body (3).
4. The tendon-embedded retaining wall structure of the cut cast-in-situ bored pile according to claim 1, characterized in that: the quantity of drilling bored concrete pile body (3) is a plurality of, a plurality of drilling bored concrete pile body (3) equidistance sets up the inner wall at cutting slope (2).
5. The tendon-embedded retaining wall structure of the cut cast-in-situ bored pile according to claim 1, characterized in that: and a water outlet (10) is formed in the upper surface of the retaining wall (4), and the water outlet (10) corresponds to the position of a water inlet of the protective filter box (5).
6. The tendon-embedded retaining wall structure of the cut cast-in-situ bored pile according to claim 1, characterized in that: the inside of protection rose box (5) is provided with first filter layer (11) and second filter layer (12) respectively, first filter layer (11) are located the top of second filter layer (12), the material of first filter layer (11) is river sand, the material of second filter layer (12) is the grit.
CN202120151932.1U 2021-01-20 2021-01-20 Bar planting retaining wall structure of cutting cast-in-situ bored pile Expired - Fee Related CN214245816U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120151932.1U CN214245816U (en) 2021-01-20 2021-01-20 Bar planting retaining wall structure of cutting cast-in-situ bored pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120151932.1U CN214245816U (en) 2021-01-20 2021-01-20 Bar planting retaining wall structure of cutting cast-in-situ bored pile

Publications (1)

Publication Number Publication Date
CN214245816U true CN214245816U (en) 2021-09-21

Family

ID=77751075

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120151932.1U Expired - Fee Related CN214245816U (en) 2021-01-20 2021-01-20 Bar planting retaining wall structure of cutting cast-in-situ bored pile

Country Status (1)

Country Link
CN (1) CN214245816U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114396071A (en) * 2022-01-14 2022-04-26 中铁二院工程集团有限责任公司 Soil retaining assembly and connecting and bar planting anchoring method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114396071A (en) * 2022-01-14 2022-04-26 中铁二院工程集团有限责任公司 Soil retaining assembly and connecting and bar planting anchoring method thereof
CN114396071B (en) * 2022-01-14 2023-05-16 中铁二院工程集团有限责任公司 Soil retaining assembly and connecting and bar planting anchoring method thereof

Similar Documents

Publication Publication Date Title
CN100577918C (en) Watershed weir series treating soil erosion and constructing method thereof
CN103643612B (en) Shallow grass ditch and the manufacture method of shallow grass ditch
CN210712879U (en) Slope ecological restoration structure of damaged mountain
CN105862665B (en) The method in comprehensive treatment of small watersheds-reconstruction good farmland
CN209429048U (en) One kind being suitable for Mountainous Area in North China karez formula underground and catchments water delivery water storage gallery
CN108612047B (en) Ecological repairing structure of river and lake bank slope
CN214245816U (en) Bar planting retaining wall structure of cutting cast-in-situ bored pile
CN111379238B (en) Trench head protection structure for developing erosion gully and construction method thereof
CN105064291A (en) Step sand-blocking dam ecosystem for reservoir desilting and sand prevention
CN206428602U (en) Prevent mud from blocking the roadbed both sides shallow seated groundwater connectivity structure with soil erosion
CN112144488A (en) Multi-curved arch water-permeable stepped energy dissipation secondary dam capable of preventing river channel undercut from being damaged
CN109778798A (en) Multi-stage porous pipe weir shunts and warps method
CN113073706B (en) Submerged flow intercepting water intake structure and construction method
CN210507515U (en) Greening gravity type retaining wall
CN213358503U (en) Natural bank slope protective structure based on sponge city idea
CN114215010A (en) Dam slope protection structure and construction method thereof
CN212983755U (en) Water and soil conservation system suitable for river crossing of directional drilling of oil and gas conveying pipeline
CN211816750U (en) Sponge city rainwater recycling system
CN112252343A (en) Side slope packway with drainage and landscape greening irrigation functions and construction method thereof
CN110306498A (en) The work earth dam that can be prevented erosion
CN205530633U (en) Excavation section of growing up cutting drainage device
CN212294524U (en) Trench head protection structure for developing erosion gully
CN212641508U (en) City river course stereoplasm bank slope ecological transformation integrated configuration
CN217078642U (en) Flood diversion open channel dike structure
CN217053239U (en) Ecological slope protection structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee