CN214245733U CN202022090097.3U CN202022090097U CN214245733U CN 214245733 U CN214245733 U CN 214245733U CN 202022090097 U CN202022090097 U CN 202022090097U CN 214245733 U CN214245733 U CN 214245733U
Authority
CN
China
Prior art keywords
reinforcement cage
steel reinforcement
construction
fixed
steel bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022090097.3U
Other languages
Chinese (zh)
Inventor
巩智利
贾远辉
朱斌泉
丁子君
许路
胡留富
黄启
罗浩
周敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
Bridge and Tunnel Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
Bridge and Tunnel Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd, Bridge and Tunnel Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN202022090097.3U priority Critical patent/CN214245733U/en
Application granted granted Critical
Publication of CN214245733U publication Critical patent/CN214245733U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a steel reinforcement cage installation base, the on-line screen storage device comprises two bases, the fixed steel reinforcement cage that is provided with in two base upper ends, steel reinforcement cage upper end is fixed to be provided with two vertical construction panels and two horizontal construction panels, two the steel reinforcement cage installing port has been seted up to the fixed steel reinforcement cage between vertical construction panel and two horizontal construction panels, the equal activity in steel reinforcement cage installing port four corners department is provided with arc limiting plate, four the fixed steel that is provided with between the arc limiting plate protects a section of thick bamboo, the fixed steel reinforcement cage locating support that is provided with in steel reinforcement cage installing port upper end. The utility model discloses a steel reinforcement cage installation base, constructor can splice the construction to the steel reinforcement cage in stake hole top, for constructor provides better construction environment, improves the efficiency and the quality of construction, prevents that the steel reinforcement cage from rocking because of external factors produces in the work progress, influences the concatenation construction of steel reinforcement cage, can guarantee the levelness of construction panel to improve the stability of work progress.

Description

Reinforcement cage mounting base
Technical Field
The utility model relates to a construction auxiliary assembly technical field especially relates to steel reinforcement cage installation base.
Background
Bridge engineering is widely applied to highway engineering and railway engineering due to the advantages of small occupied area, small settlement, multiple structural forms, wide application range and the like, a pile foundation in the bridge engineering is the most common and widely applied foundation form, pile foundation construction is essential foundation work in building construction, the pile foundation construction is usually carried out by drilling, then cleaning is carried out, a reinforcement cage is placed after the cleaning is qualified, and pile foundation concrete is poured at last.
At present, the steel reinforcement cage is installed in the stake hole of directly transferring by the crane after all installing in advance subaerial, but to highway bridge, its drilling depth is darker, and some can reach hundreds of meters even, directly transfers through the crane and is obviously unlikely, to this kind of stake hole, need carry out a festival concatenation to the steel reinforcement cage at the job site to accomplish the installation of steel reinforcement cage, consequently, need use steel reinforcement cage installation base to install the steel reinforcement cage.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a reinforcement cage mounting base.
In order to achieve the above purpose, the utility model adopts the following technical scheme: steel reinforcement cage installation base, including two bases, the fixed steel reinforcement cage that is provided with in two base upper ends, steel reinforcement cage upper end is fixed to be provided with two vertical construction panels and two horizontal construction panels, two the steel reinforcement cage installing port has been seted up to fixed between vertical construction panel and two horizontal construction panels, steel reinforcement cage installing port four corners department all activity is provided with arc limiting plate, four fixed steel that is provided with between the arc limiting plate protects a section of thick bamboo, the fixed steel reinforcement cage locating support that is provided with in steel reinforcement cage installing port upper end.
As a further description of the above technical solution:
and two reinforcing cushion layers are fixedly arranged at the lower ends of the bases.
As a further description of the above technical solution:
the fixed communicating pipe that is provided with in steel bar support skeleton periphery, the equal fixed connection in the department of buckling in communicating pipe four corners has horizontal observation liquid pipe, four horizontal observation liquid pipe is all fixed and is passed vertical construction panel.
As a further description of the above technical solution:
two the leveling device is all fixedly provided with in vertical construction panel angle department both sides, four the leveling device all can be used for the leveling of construction panel, guarantees the levelness of construction panel.
As a further description of the above technical solution:
and a safety protective guard is fixedly arranged on the periphery of the reinforcing cage mounting port.
As a further description of the above technical solution:
the steel bar support framework is erected around the lower ends of the longitudinal construction panel and the transverse construction panel, and the middle part of the steel bar support framework is reserved with an installation space for downward installation of a steel bar cage.
The utility model discloses following beneficial effect has:
the utility model provides a steel reinforcement cage installation base is through setting up the construction panel on the base to set up the backbone and support, guaranteed the safe fastness of construction panel, construction panel middle part is provided with the steel reinforcement cage installing port, makes constructor can splice the construction to the steel reinforcement cage in stake hole top, provides better construction environment for constructor, improves the efficiency of construction and the quality of construction.
The utility model provides a steel reinforcement cage installation base, the installing port outside is provided with the arc limiting plate, can protect a section of thick bamboo to the steel and carry on spacingly, makes the steel protect the installation of a section of thick bamboo and place more accurately, uses more stably, and the installing port upper end is provided with steel reinforcement cage locating support, prevents that the steel reinforcement cage from rocking because of external factors produces in the work progress, influences steel reinforcement cage's concatenation construction.
The utility model provides a steel reinforcement cage installation base, the four corners department of construction panel all is provided with levelling device, can carry out the level (l) ing to the construction panel, guarantee the levelness of construction panel, thereby improve the stability of work progress, the steel bar support skeleton is provided with communicating pipe and horizontal observation liquid pipe all around, inside is provided with liquid, through transparent horizontal observation liquid pipe, the horizontality of reading the platform that can be clear, thereby supplementary levelling device carries out quick accurate leveling work, it is more convenient to use.
Drawings
Fig. 1 is a front view of a reinforcement cage mounting base according to the present invention;
fig. 2 is the utility model provides a top view of steel reinforcement cage installation base.
Illustration of the drawings:
1. a base; 2. supporting the framework by steel bars; 3. a longitudinal construction panel; 4. a transverse construction panel; 5. a communicating pipe; 6. a horizontal observation liquid pipe; 7. a leveling device; 8. a safety guard rail; 9. an arc limiting plate; 10. A reinforcement cage mounting port; 11. a reinforcement cage positioning bracket; 12. a steel casing; 13. and reinforcing the cushion layer.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention; the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance, and furthermore, unless otherwise explicitly stated or limited, the terms "mounted," "connected," and "connected" are to be construed broadly and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1-2, the present invention provides an embodiment: steel reinforcement cage installation base, including two bases 1, the fixed steel reinforcement cage 2 that is provided with in 1 upper end of two bases, 2 upper ends of steel reinforcement cage are fixed and are provided with two vertical construction panels 3 and two horizontal construction panels 4, the steel reinforcement cage installing port 10 has been seted up to two vertical construction panels 3 and two horizontal construction panels between 4, the equal activity in 10 four corners departments of steel reinforcement cage installing port is provided with arc limiting plate 9, the fixed steel that is provided with between four arc limiting plate 9 protects a section of thick bamboo 12, the fixed steel reinforcement cage locating support 11 that is provided with in 10 upper ends of steel reinforcement cage installing port.
1 lower extreme of two bases is all fixed and is provided with reinforcing cushion layer 13, 2 fixed communicating pipes 5 that are provided with in periphery of steel reinforcement support skeleton, 5 equal fixed connection in four corners department of buckling of communicating pipe has horizontal observation liquid pipe 6, four horizontal observation liquid pipe 6 are all fixed and are passed vertical construction panel 3, two vertical construction panel 3 are at the equal fixed levelling device 7 that is provided with in both sides angle department, four levelling device 7 all can be used for the level (l) control of construction panel, guarantee the levelness of construction panel, the fixed safety protective guard 8 that is provided with in 10 peripheries of steel reinforcement cage installing port, steel reinforcement support skeleton 2 sets up around vertical construction panel 3 and horizontal construction panel 4 lower extremes, the installation space is left at the middle part and is used for transferring the installation of steel reinforcement cage.
The working principle is as follows: when the reinforcement cage mounting base is used, a steel protection cylinder 12 is placed inside a reinforcement cage mounting opening 10, then an arc limiting plate 9 is adjusted to enable the steel protection cylinder 12 to be accurately and vertically fixed, then a reinforcement cage is hoisted inside the steel protection cylinder 12 by a hoisting device and is placed downwards, the reinforcement cage is positioned by a reinforcement cage positioning support 11, the reinforcement cage is prevented from shaking due to external factors in the construction process to influence the splicing construction of the reinforcement cage, when the reinforcement cage is quickly placed at the bottom of the reinforcement cage, the reinforcement cage is temporarily hung on the steel protection cylinder 12 to carry out butt joint of the reinforcement cage, constructors can stand on a construction panel to carry out splicing construction on the reinforcement cage, a safety protective guard 8 can protect the safety of the constructors, a better construction environment is provided for the constructors, the construction efficiency and the construction quality are improved, a leveling device 7 can carry out horizontal adjustment on the construction panel, guarantee the levelness of construction panel to improve the stability of work progress, through communicating pipe 5 and horizontal observation liquid pipe 6 can be clear read the horizontality of construction panel, thereby supplementary levelling device 7 carries out quick accurate leveling work, and it is more convenient to use.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and variations can be made in the embodiments or in part of the technical features of the embodiments without departing from the spirit and the scope of the invention.

Claims (6)

1. Steel reinforcement cage installation base, including two bases (1), its characterized in that: two base (1) upper ends are fixed and are provided with steel bar support skeleton (2), steel bar support skeleton (2) upper end is fixed and is provided with two vertical construction panels (3) and two horizontal construction panels (4), two steel bar cage installing port (10) have been seted up to vertical construction panel (3) and two between the horizontal construction panel (4), steel bar cage installing port (10) four corners department is all movable and is provided with arc limiting plate (9), four fixed steel casing (12) that is provided with between arc limiting plate (9), steel bar cage installing port (10) upper end is fixed and is provided with steel bar cage locating support (11).
2. The reinforcement cage mounting base of claim 1, wherein: and the lower ends of the two bases (1) are fixedly provided with reinforcing cushion layers (13).
3. The reinforcement cage mounting base of claim 1, wherein: fixed communicating pipe (5) that is provided with in steel bar support skeleton (2) periphery, the equal fixed connection in department of buckling in communicating pipe (5) four corners has horizontal observation liquid pipe (6), four horizontal observation liquid pipe (6) are all fixed and are passed vertical construction panel (3).
4. The reinforcement cage mounting base of claim 1, wherein: two vertical construction panel (3) all fixedly are provided with levelling device (7) in both sides angle department, four levelling device (7) all can be used for the level (l) ing of construction panel, guarantee the levelness of construction panel.
5. The reinforcement cage mounting base of claim 1, wherein: and a safety protective guard (8) is fixedly arranged on the periphery of the reinforcing cage mounting port (10).
6. The reinforcement cage mounting base of claim 1, wherein: the steel bar supporting framework (2) is erected around the lower ends of the longitudinal construction panel (3) and the transverse construction panel (4), and the middle part of the steel bar supporting framework is reserved with an installation space for downward installation of a steel bar cage.
CN202022090097.3U 2020-09-22 2020-09-22 Reinforcement cage mounting base Active CN214245733U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022090097.3U CN214245733U (en) 2020-09-22 2020-09-22 Reinforcement cage mounting base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022090097.3U CN214245733U (en) 2020-09-22 2020-09-22 Reinforcement cage mounting base

Publications (1)

Publication Number Publication Date
CN214245733U true CN214245733U (en) 2021-09-21

Family

ID=77715263

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022090097.3U Active CN214245733U (en) 2020-09-22 2020-09-22 Reinforcement cage mounting base

Country Status (1)

Country Link
CN (1) CN214245733U (en)

Similar Documents

Publication Publication Date Title
CN106087746A (en) A kind of cast-in-situ box girder falsework construction method and bridge
CN216283541U (en) Quick and accurate measuring device for verticality in mounting of assembled building column
CN111472353A (en) Reverse construction method steel pipe upright pile construction casing device and construction method thereof
CN209369328U (en) A kind of removable die carrier structure of lateral wall mould
CN214245733U (en) Reinforcement cage mounting base
CN106759943A (en) A kind of pre-assembled Anchor Bolts in Steel Column Bases structure
CN105297731A (en) Reverse construction method steel stand column positioning device and positioning method
JPH08120673A (en) Accurate erection method and equipment for steel frame column under ground surface of reverse construction method
CN112523258B (en) Portable single-side formwork supporting system and construction method thereof
CN113585079B (en) Method for quickly installing steel structure stand column
CN216081351U (en) Verticality measuring device suitable for hydraulic creeping formwork
CN212477455U (en) Pre-buried positioner of bridge suspension cable anchor cylinder
CN205134323U (en) Reverse construction method steel stand positioner
CN214460479U (en) Lattice column assembled formwork support bracket
CN211257760U (en) Triangular supporting device for overhanging scaffold
CN113684826A (en) Reverse construction method steel pipe upright pile construction casing device and construction method thereof
CN209741676U (en) Main arch rib auxiliary structure for accurately hoisting large-span steel tube arch bridge
CN112726416A (en) Support structure meeting field construction security and construction method
CN220747318U (en) Steel plate shear wall
CN210507446U (en) One-pile one-column verticality adjusting frame for building construction topdown construction method
CN214996204U (en) A bracing device for accurate location of prefabricated wall body of assembled
CN213265641U (en) A operation device for installation of tunnel top fan
CN220335907U (en) Multifunctional platform for bored concrete pile hole construction
CN219653524U (en) Temporary support is assembled to steel case roof beam cable-stayed bridge single-column internal inclination steel tower bridge position
CN220723393U (en) Tower crane base anchor device for concrete bridge deck

Legal Events