CN214117687U - Base station tower equipment integration cabin maintenance platform - Google Patents

Base station tower equipment integration cabin maintenance platform Download PDF

Info

Publication number
CN214117687U
CN214117687U CN202022871670.4U CN202022871670U CN214117687U CN 214117687 U CN214117687 U CN 214117687U CN 202022871670 U CN202022871670 U CN 202022871670U CN 214117687 U CN214117687 U CN 214117687U
Authority
CN
China
Prior art keywords
maintenance platform
tower body
mounting panel
fixedly connected
base station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022871670.4U
Other languages
Chinese (zh)
Inventor
陈龙祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Yishengfeng Communication Engineering Co ltd
Original Assignee
Guizhou Xianghuan Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Xianghuan Technology Co ltd filed Critical Guizhou Xianghuan Technology Co ltd
Priority to CN202022871670.4U priority Critical patent/CN214117687U/en
Application granted granted Critical
Publication of CN214117687U publication Critical patent/CN214117687U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The utility model discloses a platform is maintained in integrated cabin of base station tower equipment, comprising a tower body, be equipped with the slot in the tower body, sliding connection has the anticreep piece in the slot, be equipped with on the lateral wall of tower body with the communicating opening of slot, the tower body is close to open-ended one side and is equipped with the mounting panel, one side fixedly connected with supporting shoe that the mounting panel is close to the tower body, the one end of supporting shoe run through the opening and with anticreep piece fixed connection, one side fixedly connected with maintenance platform of tower body is kept away from to the mounting panel, maintenance platform's lower extreme is equipped with the bolt, the one end of bolt runs through the mounting panel and extends to in the tower body, be threaded connection between bolt and mounting panel, the tower body. The utility model discloses a stop gear's setting plays the effect that supports the anticreep to the maintenance platform in advance, reduces workman's physical expenditure, improves the security when changing.

Description

Base station tower equipment integration cabin maintenance platform
Technical Field
The utility model relates to a basic station technical field especially relates to a platform is maintained in integrated cabin of basic station tower equipment.
Background
With the advance of industrialization, at present, high-rise steel structures are more and more, and for example, a large number of steel pipe towers are built in the aspects of communication, electric power, petroleum and the like. For a base station, integrated cabins for placing equipment may be integrated on a tower body of the base station, and the integrated cabins are generally high in suspension height, so that a maintenance operation platform is necessarily required to be installed on the tower body for installation, maintenance or overhaul of the equipment by a maintainer.
The existing maintenance platform is generally fixed with the tower body through bolts, when the maintenance platform is damaged or the service life is due and needs to be replaced, a worker needs to support the maintenance platform by hands to prevent the maintenance platform from falling after the bolts are unscrewed, and a large amount of physical power of the worker can be consumed due to the fact that the maintenance platform is heavy, and certain potential safety hazards exist.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the workman and need supporting the maintenance platform with the hand, prevent that the bolt from unscrewing back maintenance platform and falling, because the maintenance platform is heavier, can consume a large amount of physical power of workman, have certain potential safety hazard, and the integrated cabin maintenance platform of a basic station tower equipment that provides.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a base station tower equipment integration cabin maintenance platform, includes the tower body, be equipped with the slot in the tower body, sliding connection has the anticreep piece in the slot, be equipped with on the lateral wall of tower body with the communicating opening of slot, the tower body is close to open-ended one side and is equipped with the mounting panel, one side fixedly connected with supporting shoe that the mounting panel is close to the tower body, the one end of supporting shoe run through the opening and with anticreep piece fixed connection, one side fixedly connected with maintenance platform of tower body is kept away from to the mounting panel, maintenance platform's lower extreme is equipped with the bolt, the one end of bolt runs through the mounting panel and extends to in the tower body, be threaded connection between bolt and mounting panel, the tower body.
Preferably, the lower end of the maintenance platform is fixedly connected with a first supporting rod, and the lower end of the first supporting rod is fixedly connected with the side wall of the mounting plate.
Preferably, the number of the first support rods is plural.
Preferably, the lateral wall of the first supporting rod is fixedly connected with a second supporting rod, and the upper end of the second supporting rod is fixedly connected with the lower end of the maintenance platform.
Preferably, the upper end of the maintenance platform is fixedly connected with a first rubber pad.
Preferably, a second rubber pad is fixedly connected to the side wall of the inner bottom end of the opening.
Has the advantages that:
1. when the anti-drop device is used, firstly, the bolt is screwed off, then the maintenance platform is pushed upwards, the maintenance platform drives the anti-drop block to move upwards through the supporting block, when the anti-drop block moves to the opening, the maintenance platform is pulled to drive the anti-drop block to be separated from the opening through the supporting block, then a brand new maintenance platform is replaced, the anti-drop block is pushed into the slot after being aligned with the opening, then the maintenance platform is pushed downwards, the supporting block is enabled to be abutted against the side wall of the inner bottom end of the opening, the maintenance platform is prevented from dropping through the anti-drop block, and at the moment, the bolt is screwed on again, through the arrangement of the limiting mechanism, the anti-drop device plays a role in supporting the anti-drop effect on the maintenance platform in advance, reduces the physical expenditure of workers and improves the safety during replacement;
2. through the setting of first bracing piece, can play the supporting role to maintenance platform, through the setting of a plurality of first bracing pieces, can improve the supporting effect, through the setting of second bracing piece, can strengthen the supporting effect, through the setting of first rubber pad, can play anti-skidding effect, through the setting of second rubber pad, wearing and tearing between reducible supporting shoe and the opening bottom end lateral wall.
Drawings
Fig. 1 is a schematic structural diagram of a maintenance platform of an integrated cabin of base station tower equipment according to the present invention;
fig. 2 is the utility model provides a base station tower equipment integration cabin maintenance platform's a department structure sketch map.
In the figure: the anti-falling tower comprises a tower body 1, an anti-falling block 2, an installation plate 3, a first support rod 4, a bolt 5, a second support rod 6, a maintenance platform 7, a first rubber pad 8, a support block 9 and a second rubber pad 10.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-2, a maintenance platform of an integrated cabin of base station tower equipment comprises a tower body 1, wherein a slot is arranged in the tower body 1, an anti-falling block 2 is connected in the slot in a sliding manner and used for preventing the maintenance platform 7 from falling off, an opening communicated with the slot is arranged on the outer side wall of the tower body 1, and a second rubber pad 10 is fixedly connected on the side wall of the inner bottom end of the opening and used for reducing the abrasion between a supporting block 9 and the side wall of the inner bottom end of the opening;
in the embodiment, one side of the tower body 1 close to the opening is provided with a mounting plate 3 for mounting a maintenance platform 7, one side of the mounting plate 3 close to the tower body 1 is fixedly connected with a supporting block 9 for supporting the mounting plate 3, and one end of the supporting block 9 penetrates through the opening and is fixedly connected with the anti-falling block 2;
in the embodiment, a maintenance platform 7 is fixedly connected to one side of the mounting plate 3, which is far away from the tower body 1, a first rubber pad 8 is fixedly connected to the upper end of the maintenance platform 7 and used for playing a role in skid resistance, a bolt 5 is arranged at the lower end of the maintenance platform 7 and used for fixing the maintenance platform 7 on the tower body 1, one end of the bolt 5 penetrates through the mounting plate 3 and extends into the tower body 1, and the bolt 5 is in threaded connection with the mounting plate 3 and the tower body 1;
in this embodiment, the lower end of the maintenance platform 7 is fixedly connected with a first support rod 4 for supporting the maintenance platform 7 and improving the stability of the maintenance platform 7, the lower end of the first support rod 4 is fixedly connected with the side wall of the mounting plate 3, the number of the first support rods 4 is multiple for improving the support effect, the side wall of the first support rod 4 is fixedly connected with a second support rod 6 for enhancing the support effect, and the upper end of the second support rod 6 is fixedly connected with the lower end of the maintenance platform 7;
in this embodiment, at first screw down bolt 5, then upwards promote maintenance platform 7, maintenance platform 7 drives anticreep piece 2 rebound through supporting shoe 9, when anticreep piece 2 removes to the opening part, pulling maintenance platform 7 drives anticreep piece 2 through supporting shoe 9 and breaks away from in the opening, then replace brand-new maintenance platform 7, aim at anticreep piece 2 and push into in the slot after the opening, then promote maintenance platform 7 downwards, make supporting shoe 9 and opening inside bottom lateral wall offset, prevent through anticreep piece 2 that maintenance platform 7 from droing, at this moment, it can to twist bolt 5 again, the utility model discloses a stop gear's setting plays the effect of support anticreep to maintenance platform in advance, reduces workman's physical expenditure, improves the security when changing.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides a base station tower equipment integration cabin maintenance platform, includes tower body (1), its characterized in that: be equipped with the slot in tower body (1), sliding connection has anticreep piece (2) in the slot, be equipped with on the lateral wall of tower body (1) with the communicating opening of slot, tower body (1) is close to open-ended one side and is equipped with mounting panel (3), one side fixedly connected with supporting shoe (9) that mounting panel (3) are close to tower body (1), the one end of supporting shoe (9) run through the opening and with anticreep piece (2) fixed connection, one side fixedly connected with maintenance platform (7) of tower body (1) are kept away from in mounting panel (3), the lower extreme of maintenance platform (7) is equipped with bolt (5), the one end of bolt (5) runs through in mounting panel (3) and extends to tower body (1), be threaded connection between bolt (5) and mounting panel (3), tower body (1).
2. The base station tower equipment integration cabin maintenance platform of claim 1, wherein: the lower extreme fixedly connected with first bracing piece (4) of maintenance platform (7), the lower extreme of first bracing piece (4) and the lateral wall fixed connection of mounting panel (3).
3. The base station tower equipment integration cabin maintenance platform of claim 2, wherein: the number of the first supporting rods (4) is multiple.
4. The base station tower equipment integration cabin maintenance platform of claim 2, wherein: fixedly connected with second bracing piece (6) on the lateral wall of first bracing piece (4), the upper end of second bracing piece (6) and the lower extreme fixed connection of maintenance platform (7).
5. The base station tower equipment integration cabin maintenance platform of claim 1, wherein: the upper end of the maintenance platform (7) is fixedly connected with a first rubber pad (8).
6. The base station tower equipment integration cabin maintenance platform of claim 1, wherein: and a second rubber pad (10) is fixedly connected to the side wall of the inner bottom end of the opening.
CN202022871670.4U 2020-12-02 2020-12-02 Base station tower equipment integration cabin maintenance platform Active CN214117687U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022871670.4U CN214117687U (en) 2020-12-02 2020-12-02 Base station tower equipment integration cabin maintenance platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022871670.4U CN214117687U (en) 2020-12-02 2020-12-02 Base station tower equipment integration cabin maintenance platform

Publications (1)

Publication Number Publication Date
CN214117687U true CN214117687U (en) 2021-09-03

Family

ID=77508426

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022871670.4U Active CN214117687U (en) 2020-12-02 2020-12-02 Base station tower equipment integration cabin maintenance platform

Country Status (1)

Country Link
CN (1) CN214117687U (en)

Similar Documents

Publication Publication Date Title
CN201598821U (en) Steel wire suspending system of high altitude operating nacelle
CN111371039A (en) Cable erecting device for building electromechanical installation
CN214117687U (en) Base station tower equipment integration cabin maintenance platform
CN204163342U (en) A kind of pipe-hanging hook for tread air channel, station of constructing
CN101402436B (en) Method and apparatus for disassembling cargo boom of climbing tower crane
CN209212031U (en) A kind of novel steel pipe pole equipped with telescoping mechanism
CN217148204U (en) Construction elevator lubricating arrangement
CN203494080U (en) Safety rope suspension device for transformer
CN202429949U (en) Jack
CN201801267U (en) Simple passenger carrying device for large-sized hoisting facility
CN204265210U (en) A kind of telescopic slipping tail sling system
CN204167786U (en) A kind of accessory cart of built on stilts bus lifting
CN209203131U (en) It can be used for the locking disconnected structure of wirerope of hoisting system
CN208401377U (en) A kind of inspection platform for power station high voltage switchyard
CN205777888U (en) A kind of transformer station sucked type fence bracing frame
CN204651744U (en) On load tap changer core bucket extracting tool
CN215402431U (en) Elevator anti-slip device under maintenance state
CN220748909U (en) Anti-collision buffer device for lifting machine
CN214834647U (en) Horizontal protection device for scaffold on elevator shaft operating floor
CN221150772U (en) Cable laying tool for mine
CN205303104U (en) Transformer line outgoing cabinet
CN205187789U (en) Building hanging flower basket lifting machine structure
CN212462478U (en) Safety prefabricated substation
CN215148618U (en) Wind power generation yaw brake dismounting device
CN221255781U (en) Energy dissipation shock-absorbing building bearing structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230815

Address after: No. 1000, North Section of Binjiang Road, Liucheng, Wenjiang District, Chengdu, Sichuan Province, 611130

Patentee after: Li Guishu

Address before: 563000 No. 6-2, unit 2, building 16, lanshuiwan, west of No. 1 road, Zunyi Avenue, guihuaqiao street, Bozhou District, Zunyi City, Guizhou Province

Patentee before: Guizhou Xianghuan Technology Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231010

Address after: No. 9, 19th Floor, Building 8, No. 88 Shengbang Street, Chengdu High tech Zone, China (Sichuan) Pilot Free Trade Zone, Wuhou District, Chengdu City, Sichuan Province, 610000

Patentee after: Chengdu yishengfeng Communication Engineering Co.,Ltd.

Address before: No. 1000, North Section of Binjiang Road, Liucheng, Wenjiang District, Chengdu, Sichuan Province, 611130

Patentee before: Li Guishu