CN214100635U - Tunnel cable construction installation device - Google Patents
Tunnel cable construction installation device Download PDFInfo
- Publication number
- CN214100635U CN214100635U CN202022411085.6U CN202022411085U CN214100635U CN 214100635 U CN214100635 U CN 214100635U CN 202022411085 U CN202022411085 U CN 202022411085U CN 214100635 U CN214100635 U CN 214100635U
- Authority
- CN
- China
- Prior art keywords
- groove
- installation
- block
- mounting
- component
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000009434 installation Methods 0.000 title claims abstract description 135
- 238000010276 construction Methods 0.000 title claims abstract description 28
- 230000007246 mechanism Effects 0.000 claims abstract description 25
- 238000002955 isolation Methods 0.000 abstract description 4
- 239000003921 oil Substances 0.000 description 31
- 239000010687 lubricating oil Substances 0.000 description 9
- 238000005461 lubrication Methods 0.000 description 5
- 238000000034 method Methods 0.000 description 4
- 230000009471 action Effects 0.000 description 3
- 238000002347 injection Methods 0.000 description 3
- 239000007924 injection Substances 0.000 description 3
- 230000002633 protecting effect Effects 0.000 description 3
- 239000002699 waste material Substances 0.000 description 3
- 230000008859 change Effects 0.000 description 2
- 239000004020 conductor Substances 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 230000001681 protective effect Effects 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000011248 coating agent Substances 0.000 description 1
- 238000000576 coating method Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009422 external insulation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000000737 periodic effect Effects 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Abstract
The utility model discloses a tunnel cable construction installation device, which comprises an installation mechanism and a protection mechanism, wherein the installation mechanism is arranged at two ends of the protection mechanism, the device adopts a layered isolation design to install cables, when the cables are installed, the device is firstly installed inside a cable construction groove, a through groove is matched with a threaded rod, a second installation groove is matched with a first installation groove, a sliding groove is matched with a sliding block, the cables are firstly clamped through the first installation groove and the second installation groove which are matched with the sliding block, then the installation component is fixed through the nut, the first installation component, the second installation component and the third installation component are mutually separated through the sliding block, the threaded rod and the nut are matched for fixing, the integral stability of the device is ensured, the cables are conveniently isolated and disassembled and assembled, so that when one cable is disassembled and assembled and maintained, the stability of other cable installations is not influenced, and the phenomenon that other cable installations are not flexible is avoided.
Description
Technical Field
The utility model relates to the technical field of cables, specifically be a tunnel cable construction installation device.
Background
Cable: typically a rope-like cable made up of several or groups of conductors (at least two in each group) twisted together, with the conductors of each group being insulated from one another and often twisted around a center, the entire outer surface being coated with a highly insulating coating. The cable has the characteristics of internal electrification and external insulation.
Present tunnel cable construction installation device is not convenient for carry out single layering to the cable and fixes, if the cable damages, when needing to be changed, causes not hard up to other cables easily, and to the great tunnel of some crooked radians, is not convenient for carry out the problem of protecting to the cable.
To solve the above problems. Therefore, the tunnel cable construction installation device is provided.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a tunnel cable construction installation device to having solved among the prior art tunnel cable construction installation device and having been convenient for carry out single layering to the cable and fixed, if the cable appears damaging, when needing to be changed, causing not hard up to other cables easily, and to the great tunnel of a little crooked radian, be not convenient for carry out the problem of protecting to the cable.
In order to achieve the above object, the utility model provides a following technical scheme: a tunnel cable construction installation device comprises an installation mechanism and a protection mechanism, wherein the installation mechanism is arranged at two ends of the protection mechanism and comprises a fixing component, a first installation component, a second installation component, a third installation component and a fixing base, the first installation component, the second installation component and the third installation component are arranged on one side of the fixing component, the second installation component is positioned below the first installation component, the third installation component is positioned below the second installation component, and the fixing base is arranged at one end of the fixing component;
protection machanism includes protection film and links up the piece, links up the piece setting at the both ends of protection film, and links up the both sides that the piece set up at installation mechanism.
Preferably, the fixed subassembly includes fixed block, threaded rod and nut, and one side of fixed block sets up three threaded rods, and the nut matches with the threaded rod.
Preferably, the fixed block comprises a first connection groove and a first installation groove, the first connection groove is formed in the surface of the fixed block and matched with the connection block, and three first installation grooves are formed in one side of the fixed block.
Preferably, the first mounting assembly, the second mounting assembly and the third mounting assembly are consistent in structure, the first mounting assembly comprises a mounting block and a sliding block, and the sliding block is arranged on one side of the upper end of the mounting block.
Preferably, the installation piece includes that the second links up groove, oiling groove and oil drip groove, and the second has been seted up on the surface of installation piece and has been linked up the groove, and oiling groove and oil drip groove have been seted up to the inside of installation piece, and are linked together between oiling groove and the oil drip groove.
Preferably, the second joining grooves are matched with the joining blocks, and the oil filling groove is of an inclined structure.
Preferably, the installation block further comprises a through groove, a sliding groove and a second installation groove, the through groove is formed in the installation block, the sliding groove is formed in the bottom surface of the installation block, and the second installation groove is formed in one side of the installation block.
Preferably, lead to groove and threaded rod phase-match, second mounting groove and first mounting groove phase-match, spout and slider phase-match, and be linked together between spout and the oil drip groove.
Compared with the prior art, the beneficial effects of the utility model are as follows:
1. the utility model provides a tunnel cable construction installation device, which adopts the layered isolation design to install the cable, when the cable is installed, the device is firstly installed in a cable construction groove, the through groove is matched with the threaded rod, the second installation groove is matched with the first installation groove, the sliding groove is matched with the sliding block, the cable is firstly clamped by matching the first installation groove and the second installation groove with the sliding block, and then the installation component is fixed by matching the nut, and the first mounting component, the second mounting component and the third mounting component are separated from each other through the slide block and are fixed by matching with the threaded rod and the screw cap, so that the integral stability of the device is ensured, the cables are convenient to be detached in an isolated manner, so that the stability of the installation of other cables is not influenced while one cable is detached, maintained and prevented from being loosened;
2. the utility model provides a tunnel cable construction installation device, the surface through the fixed block is seted up first linking groove, and first linking groove and linking piece phase-match, cooperatees between the second linking groove and links up piece phase-match, and the protection film that deuterogamies can connect at the bend in tunnel, protects the cable that finishes installing, through linking the embedded connection between groove and linking piece, is convenient for regularly change the protection film, ensures the protective effect to the cable;
3. the utility model provides a tunnel cable construction installation device, when the cable need overhaul and change, set up oiling groove and oil drip groove through the inside of installation piece, and be linked together between oiling groove and the oil drip groove, be linked together between spout and the oil drip groove, cooperate lubricating oil to lubricate the spout, the removal of installation piece of being convenient for improves the dismouting efficiency of cable;
4. the utility model provides a pair of tunnel cable construction installation device is an inclined structure through the oiling groove, and the cooperation drips when the oil groove can carry out even lubrication to the spout, makes lubricating oil obtain abundant utilization, avoids lubricating oil to pile up at the oiling groove, causes the waste for the lubrication efficiency to the spout simultaneously.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is an enlarged schematic perspective view of the utility model at a in fig. 1;
FIG. 3 is a schematic view of the three-dimensional structure of the installation mechanism of the present invention;
fig. 4 is a schematic perspective view of a first mounting assembly of the present invention;
fig. 5 is a schematic sectional structural view of the first mounting assembly of the present invention.
In the figure: 1. an installation mechanism; 11. a fixing assembly; 111. a fixed block; 1111. a first engagement slot; 1112. a first mounting groove; 112. a threaded rod; 113. a nut; 12. a first mounting assembly; 121. a slider; 122. mounting blocks; 1221. a second engagement slot; 1222. an oil injection groove; 1223. an oil dripping groove; 1224. a through groove; 1225. a chute; 1226. a second mounting groove; 13. a second mounting assembly; 14. a third mounting assembly; 15. a fixed base; 2. a protection mechanism; 21. a protective film; 22. a connecting block.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, a tunnel cable construction installation device includes an installation mechanism 1 and a protection mechanism 2, the installation mechanism 1 is disposed at two ends of the protection mechanism 2, the installation mechanism 1 includes a fixing component 11, a first installation component 12, a second installation component 13, a third installation component 14 and a fixing base 15, the first installation component 12, the second installation component 13 and the third installation component 14 are disposed at one side of the fixing component 11, the second installation component 13 is located below the first installation component 12, the third installation component 14 is located below the second installation component 13, the fixing base 15 is disposed at one end of the fixing component 11, the protection mechanism 2 includes a protection film 21 and a linking block 22, the linking block 22 is disposed at two ends of the protection film 21, the linking block 22 is disposed at two sides of the installation mechanism 1, the fixing component 11 includes a fixing block 111, a threaded rod 112 and a nut 113, three threaded rods 112 are arranged on one side of a fixed block 111, a screw cap 113 is matched with the threaded rods 112, the fixed block 111 comprises a first connection groove 1111 and a first installation groove 1112, the surface of the fixed block 111 is provided with the first connection groove 1111, the first connection groove 1111 is matched with a connection block 22, one side of the fixed block 111 is provided with the three first installation grooves 1112, the first installation component 12, the second installation component 13 and the third installation component 14 are consistent in structure, the first installation component 12 comprises a sliding block 121 and an installation block 122, the sliding block 121 is arranged on one side of the upper end of the installation block 122, the installation block 122 further comprises a through groove 1224, a sliding groove 1225 and a second installation groove 1226, the through groove 1224 is arranged inside the installation block 122, the bottom surface of the installation block 122 is provided with the sliding groove 1225, the second installation groove 1226 is arranged on one side of the installation block 122, the through groove 1224 is matched with the threaded rods 112, and the second installation groove 1226 is matched with the first installation groove 1112, the sliding groove 1225 is matched with the sliding block 121, the sliding groove 1225 is communicated with the oil dripping groove 1223, the cable is installed by adopting a layered isolation design, when the cable is installed, the cable installation device is installed inside the cable construction groove firstly, the through groove 1224 is matched with the threaded rod 112, the second installation groove 1226 is matched with the first installation groove 1112, the sliding groove 1225 is matched with the sliding block 121, the cable is clamped by matching the first installation groove 1112 and the second installation groove 1226 with the sliding block 121 firstly, then the installation component is fixed by matching the nut 113, the first installation component 12, the second installation component 13 and the third installation component 14 are separated by matching the sliding block 121, the threaded rod 112 and the nut 113 are matched for fixing, the integral stability of the device is guaranteed, the cable is convenient to be isolated, disassembled and assembled, and maintained, and simultaneously, do not influence the stability of other cable installations, avoid appearing the not hard up phenomenon of other cable installations, first link up groove 1111 has been seted up through the surface of fixed block 111, and first link up groove 1111 and link up piece 22 phase-match, cooperate between the second link up groove 1221 and link up piece 22 phase-match, it can connect at the bight in tunnel to cooperate protection film 21 again, the cable that finishes the installation protects, through linking up the embedded connection between groove and the link up piece 22, be convenient for carry out periodic replacement to protection film 21, the guarantee is to the protecting effect of cable.
Referring to fig. 5, in a tunnel cable construction installation apparatus, an installation block 122 includes a second connection groove 1221, an oil filling groove 1222 and an oil dripping groove 1223, the surface of the installation block 122 is provided with the second connection groove 1221, the installation block 122 is internally provided with the oil filling groove 1222 and the oil dripping groove 1223, the oil filling groove 1222 and the oil dripping groove 1223 are communicated, the second connection groove 1221 is matched with the connection block 22, the oil filling groove 1222 is an inclined structure, when a cable needs to be repaired and replaced, the oil filling groove 1222 and the oil dripping groove 1223 are provided through the installation block 122, the oil filling groove 1222 and the oil dripping groove 1223 are communicated, the sliding groove 1225 is lubricated by matching with lubricating oil, the installation block 122 is convenient to move, the cable disassembly and assembly efficiency is improved, the oil filling groove 1222 is an inclined structure, the oil dripping groove 1223 can uniformly lubricate the sliding groove 1225, make lubricating oil obtain abundant utilization, avoid lubricating oil to pile up at oiling groove 1222, cause the waste, accelerate the lubrication efficiency to spout 1225 simultaneously.
In summary, the following steps: the utility model provides a tunnel cable construction installation device, including installation mechanism 1 and protection machanism 2, installation mechanism 1 sets up the both ends at protection machanism 2, this device adopts the design of layering isolation to install the cable, when installing the cable, install this device at first inside the cable construction groove, logical groove 1224 and threaded rod 112 phase-match, second mounting groove 1226 and first mounting groove 1112 phase-match, spout 1225 and slider 121 phase-match, first cooperate slider 121 to centre gripping the cable through first mounting groove 1112 and second mounting groove 1226, cooperate nut 113 to fix the installation component again, and first installation component 12, second installation component 13 and third installation component 14 separate through slider 121 each other, cooperate threaded rod 112 and nut 113 to fix, when having ensured the whole steadiness of device, be convenient for keep apart the dismouting to the cable, when one cable is dismounted and overhauled, the stability of other cables is not influenced, the phenomenon of looseness of other cables is avoided, a first connection groove 1111 is formed in the surface of the fixing block 111 and matched with the connection block 22, the second connection grooves 1221 are matched with the connection block 22, and a protection film 21 is matched to connect the bent part of the tunnel to protect the mounted cable, the protection film 21 is periodically replaced through embedded connection between the connection grooves and the connection block 22, the protection effect of the cable is guaranteed, when the cable needs to be dismounted and replaced, an oil injection groove 1222 and an oil drip groove 1223 are formed in the mounting block 122 and communicated with the oil injection groove 1222 and the oil drip groove 1223, the sliding groove 1225 and the oil drip groove 1223 are communicated with each other, and the sliding groove 1225 is lubricated by matching with lubricating oil, the removal of installation piece 122 of being convenient for improves the dismouting efficiency of cable, is an inclined column structure through oiling groove 1222, and when cooperation oil drip groove 1223 can carry out even lubrication to spout 1225, make lubricating oil obtain abundant utilization, avoids lubricating oil to pile up at oiling groove 1222, causes the waste for the lubrication efficiency to spout 1225 simultaneously.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (8)
1. The utility model provides a tunnel cable construction installation device, includes installation mechanism (1) and protection machanism (2), installation mechanism (1) sets up the both ends at protection machanism (2), its characterized in that: the mounting mechanism (1) comprises a fixing component (11), a first mounting component (12), a second mounting component (13), a third mounting component (14) and a fixing base (15), wherein the first mounting component (12), the second mounting component (13) and the third mounting component (14) are arranged on one side of the fixing component (11), the second mounting component (13) is positioned below the first mounting component (12), the third mounting component (14) is positioned below the second mounting component (13), and the fixing base (15) is arranged at one end of the fixing component (11);
protection machanism (2) are including protection film (21) and link up piece (22), link up the both ends that piece (22) set up at protection film (21), and link up the both sides that piece (22) set up at installation mechanism (1).
2. The installation device for tunnel cable construction according to claim 1, wherein: the fixing component (11) comprises a fixing block (111), a threaded rod (112) and a screw cap (113), wherein three threaded rods (112) are arranged on one side of the fixing block (111), and the screw cap (113) is matched with the threaded rods (112).
3. The installation device for tunnel cable construction according to claim 2, wherein: the fixed block (111) comprises a first connection groove (1111) and a first installation groove (1112), the surface of the fixed block (111) is provided with the first connection groove (1111), the first connection groove (1111) is matched with the connection block (22), and one side of the fixed block (111) is provided with three first installation grooves (1112).
4. The installation device for tunnel cable construction according to claim 1, wherein: the structure of the first installation component (12), the structure of the second installation component (13) and the structure of the third installation component (14) are consistent, the first installation component (12) comprises a sliding block (121) and an installation block (122), and the sliding block (121) is arranged on one side of the upper end of the installation block (122).
5. The installation device for tunnel cable construction according to claim 4, wherein: the mounting block (122) comprises a second connection groove (1221), an oil filling groove (1222) and an oil dripping groove (1223), the second connection groove (1221) is formed in the surface of the mounting block (122), the oil filling groove (1222) and the oil dripping groove (1223) are formed in the mounting block (122), and the oil filling groove (1222) is communicated with the oil dripping groove (1223).
6. The installation device for tunnel cable construction according to claim 5, wherein: the second connecting grooves (1221) are matched with the connecting blocks (22), and the oil filling grooves (1222) are of an inclined structure.
7. The installation device for tunnel cable construction according to claim 4, wherein: the mounting block (122) further comprises a through groove (1224), a sliding groove (1225) and a second mounting groove (1226), the through groove (1224) is formed in the mounting block (122), the sliding groove (1225) is formed in the bottom surface of the mounting block (122), and the second mounting groove (1226) is formed in one side of the mounting block (122).
8. The installation device for tunnel cable construction according to claim 7, wherein: the through groove (1224) is matched with the threaded rod (112), the second mounting groove (1226) is matched with the first mounting groove (1112), the sliding groove (1225) is matched with the sliding block (121), and the sliding groove (1225) is communicated with the oil dripping groove (1223).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022411085.6U CN214100635U (en) | 2020-10-27 | 2020-10-27 | Tunnel cable construction installation device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022411085.6U CN214100635U (en) | 2020-10-27 | 2020-10-27 | Tunnel cable construction installation device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214100635U true CN214100635U (en) | 2021-08-31 |
Family
ID=77445672
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202022411085.6U Expired - Fee Related CN214100635U (en) | 2020-10-27 | 2020-10-27 | Tunnel cable construction installation device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214100635U (en) |
-
2020
- 2020-10-27 CN CN202022411085.6U patent/CN214100635U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9725921B2 (en) | Kit for mounting one or more appliances on a pole | |
CN214100635U (en) | Tunnel cable construction installation device | |
CN2899221Y (en) | Connecting protecting jacket of non-filled telecommunicating cable/optical cable | |
CN211266264U (en) | Electric wire wiring frame | |
CN204792131U (en) | Waterproof shielding temperature measurement cable of resistant oil with fixed structure | |
CN202424073U (en) | Jumper supporting spacing rod | |
CN109799586B (en) | Wall-mounted optical cable fiber distribution box with wire arrangement structure | |
CN210635402U (en) | Power cable reel | |
CN206401688U (en) | Staged rotary connector | |
CN206020766U (en) | A kind of power transmission line column draws lower securing member with OPGW insulation | |
CN217692338U (en) | Stringing device for electric power construction | |
CN211829219U (en) | JBY type moment formula stride footpath fastener with insulating layer | |
CN220673259U (en) | Cable fixing device for weak current installation | |
CN218732869U (en) | A fixed protection component for leading cable under pole | |
CN204792155U (en) | Resistant oily waterproof shielded cable with fixed structure | |
CN212749330U (en) | Novel distributing box mounting rack | |
CN216101955U (en) | Electronic wire harness fixing support with anti-crossing function | |
CN220475095U (en) | Corrosion-resistant cable | |
CN217115476U (en) | Installation wire casing of high waterproof video net twine combination line | |
RU206797U1 (en) | Distribution block with locking latch | |
CN217879765U (en) | Optical cable fixing wire clamp for electric power design | |
CN214996581U (en) | Safety protection net for building engineering | |
CN211508482U (en) | Electrical equipment wiring bridge | |
CN216357752U (en) | Corrosion-resistant street lamp power cover | |
CN210224889U (en) | Busbar groove for lighting and power supply |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210831 |