CN214091043U - Device is pour in housing construction main part construction - Google Patents
Device is pour in housing construction main part construction Download PDFInfo
- Publication number
- CN214091043U CN214091043U CN202022641096.3U CN202022641096U CN214091043U CN 214091043 U CN214091043 U CN 214091043U CN 202022641096 U CN202022641096 U CN 202022641096U CN 214091043 U CN214091043 U CN 214091043U
- Authority
- CN
- China
- Prior art keywords
- box
- concrete
- bottom plate
- delivery pump
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 40
- 230000001815 facial effect Effects 0.000 claims abstract description 10
- 238000009435 building construction Methods 0.000 claims description 4
- 238000007599 discharging Methods 0.000 abstract description 8
- 230000000694 effects Effects 0.000 description 4
- 238000000034 method Methods 0.000 description 3
- 238000005096 rolling process Methods 0.000 description 2
- 239000002969 artificial stone Substances 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
- 239000003643 water by type Substances 0.000 description 1
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a device is pour in building main part construction, including the bottom plate, the bottom plate facial make-up is equipped with the box, and the perforation has been seted up to one side of box, and the perforation endotheca is equipped with the inlet pipe, and the inlet pipe cover is put on the input of delivery pump, and the delivery pump is installed on the bottom plate, and the output tube has been put to the cover on the output of delivery pump, and the box facial make-up is equipped with the roof, and the bobbing machine has been installed to the roof bottom, and the output facial make-up of bobbing machine is equipped with the vibrations stick, has seted up the through-hole on the box. The operation bobbing machine makes the bobbing machine drive the vibrations stick and vibrates the concrete in to the box for the consistency of concrete is just, has avoided constructor manual to vibrate the concrete, and rethread operation delivery pump can make the inlet pipe in the perforation inhale the concrete from the box, discharges through the discharging pipe, makes things convenient for the handheld discharging pipe of constructor to pour the house main part, has avoided constructor to work repeatedly, can improve the efficiency of pouring the operation.
Description
Technical Field
The utility model belongs to the technical field of the housing construction, concretely relates to device is pour in housing construction main part construction.
Background
The building construction refers to production activities in the engineering construction implementation stage, is the construction process of various buildings, and also can be said to be the process of changing various lines on design drawings into real objects at specified places, and comprises the steps of foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like, wherein the construction site is called a construction site or a construction site, also called a construction site, concrete pouring operation is needed during the construction of a building main body, concrete is artificial stone which is formed by uniformly mixing, pouring and vibrating dense mixing a cementing material, water, a coarse aggregate and a fine aggregate according to a certain proportion, and curing and hardening under a certain temperature and moderate conditions, and the concrete pouring refers to the process of pouring concrete into a mold until plasticizing, so a pouring device is needed.
Present housing construction main part construction pouring device is many through constituteing such as concrete placement car, conveyer pipe, can promote the concrete to the height through the concrete placement car, again through fixed connection conveyer pipe on the output port of concrete placement car, waters the house main part through removing the conveyer pipe and manual vibrate the concrete of rethread manual, can pour the operation, and the weak point of existence has: when the constructor pours the concrete, need pour earlier, then use manual use vibrting spear to vibrate again, lead to the speed of pouring to be slower, need constructor to go on repeatedly moreover to the efficiency of work is influenced.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a device is pour in housing construction main part construction to solve current housing construction main part construction and pour the problem that the device pour inefficiency.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a device is pour in housing construction main part construction, includes the bottom plate, the bottom plate facial make-up is equipped with the box, the perforation has been seted up to one side of box, the inlet pipe is equipped with to the perforation endotheca, the inlet pipe cover is put on the input of delivery pump, the delivery pump is installed on the bottom plate, the output tube has been put to the cover on the output of delivery pump, the box facial make-up is equipped with the roof, the bobbing machine has been installed to the roof bottom, the output facial make-up of bobbing machine is equipped with the vibrting spear, the through-hole has been seted up on the box, it has the vibrting spear to run through in the through-hole.
Preferably, the box body is symmetrically provided with automatic telescopic rods, and the telescopic ends of the automatic telescopic rods are provided with top plates.
Preferably, a feed inlet is formed in the upper portion of one side of the box body, a fixing hole is formed in the orifice of the feed inlet, a conveying pipe is sleeved on the feed inlet, a flange plate is arranged on the conveying pipe in an assembled mode, a connecting hole is formed in the flange plate, and bolts penetrate through the connecting hole and the fixing hole.
Preferably, the bottom of the bottom plate is provided with a roller seat, one side of the bottom plate is provided with a vertical plate, the upper part of one side of the vertical plate is provided with a connecting block, and a push rod is arranged between the connecting blocks.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model provides a device is pour in housing construction main part construction, compare with prior art, when carrying out concrete placement to the housing construction main part, the bobbing machine of operation, make the bobbing machine drive the vibrations stick and vibrate the concrete in the box, vibrations through the vibrations of vibrations stick, make the consistency of concrete just, avoided constructor manual to vibrate the concrete, rethread operation delivery pump, can make the downthehole inlet pipe of wearing suck the concrete from the box, through discharging pipe discharge concrete, make things convenient for the handheld discharging pipe of constructor to pour the housing main part, avoided constructor to operate repeatedly, can improve the efficiency of pouring the operation.
The utility model provides a device is pour in housing construction main part construction, constructor alternates the bolt in the fixed orifices of connecting hole and box on the ring flange, through the screw-thread fit of bolt and fixed orifices, can be with conveyer pipe fixed connection in the feed inlet department of box, conveniently carry in the concrete entering box, again through the rolling effect of gyro wheel in the bottom plate gyro wheel seat, constructor can hold the push rod with the hand and push away for the gyro wheel in the gyro wheel seat under the bottom plate can be driven to the riser rolls, conveniently removes the operation.
Drawings
Fig. 1 is a schematic front view of the present invention;
fig. 2 is a right-side schematic view of the present invention;
fig. 3 is a schematic view of the structure of the present invention.
In the figure: the device comprises a base plate 1, a box body 2, a perforation 3, a feeding pipe 4, a delivery pump 5, a discharge pipe 6, a top plate 7, a vibrator 8, a vibration rod 9, a through hole 10, an automatic telescopic rod 11, a feeding hole 12, a fixing hole 13, a delivery pipe 14, a flange 15, a connecting hole 16, a bolt 17, a roller seat 18, a vertical plate 19, a connecting block 20 and a push rod 21.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.
Referring to fig. 1, 2 and 3, a building main body construction pouring device comprises a bottom plate 1 which is a square plate, and a box body 2 welded and connected with the upper surface of the bottom plate 1, wherein the box body 2 is a square box, a through hole 3 is formed in the right side of the box body 2, the through hole 3 is a circular hole and is located in the middle position, a feed pipe 4 is sleeved in the through hole 3, the left port of the feed pipe 4 is located below the inner part of the box body 2, the right port of the feed pipe 4 is sleeved in the input end of a delivery pump 5 and is in interference fit, the delivery pump 5 is welded and connected with the upper surface of the bottom plate 1 and is located on the right side of the box body 2, the delivery pump 5 is a concrete delivery pump with the model of BC-15, a discharge pipe 6 is sleeved on the output end of the delivery pump 5 and is in interference fit, the discharge pipe 6 is a soft pipe, the left side and the right side of the top of the upper end of the box body 2 are symmetrically welded and connected with the bottom of an automatic telescopic rod 11, the model of the automatic telescopic rod 11 is XDHA12-50, the number is 2, the telescopic end of the automatic telescopic rod 11 is welded and connected with a top plate 7, the top plate 7 is a square plate, the position of the top plate 7 can be controlled by starting the automatic telescopic rod 11, the vibration effect of different depths of concrete in the box body 2 is convenient, the bottom of the top plate 7 is welded and connected with a vibrator 8 which is positioned at the middle position, the model of the vibrator 8 is VBE-13, the output end of the vibrator 8 is welded and connected with a vibrating rod 9, the vibrating rod 9 is a cylindrical rod, the top of the upper end of the box body 2 is provided with a through hole 10, the through hole 10 is a circular hole which is positioned at the middle position, the vibrating rod 9 penetrates through the through hole 10, the vibrating rod 9 is driven by the vibrator 8 to vibrate, the consistency of the concrete in the box body 2 is convenient to adjust, when the building main body is poured, the vibrator 8 is operated, make 8 the vibrator drive the concrete of vibrations stick 9 in to box 2 vibrate, vibrations effect through vibration stick 8, make the consistency of concrete change, avoided constructor manual to vibrate the concrete, rethread operation delivery pump 5, can make inlet pipe 4 in the perforation 3 inhale the concrete from box 2, through 6 discharge concrete of discharging pipe, make things convenient for constructor to hand discharging pipe 6 and pour the house main part, avoided constructor to operate repeatedly, can improve the efficiency of pouring the operation.
Referring to fig. 1, 2 and 3, a feed inlet 12 is formed in the upper portion of the left side of the box body 1, the feed inlet 12 is a circular hole and is located in the middle, fixing holes 13 are formed around the left end of the feed inlet 12, the fixing holes 13 are threaded holes, the number of the fixing holes is 2, a conveying pipe 14 is sleeved at the end of the feed inlet 12, a flange plate 15 is welded to the conveying pipe 14, and the flange plate 15 is a circular ring plate. The flange plate 15 is provided with a connecting hole 16, the connecting hole 16 is a circular hole and 2, a bolt 17 is inserted into the connecting hole 16 and the fixing hole 13, the bolt 17 is inserted into the connecting hole 16 on the flange plate 15 and the fixing hole 13 of the box body 2, the conveying pipe 14 can be fixedly connected to the feed inlet 12 of the box body 2 through the threaded fit of the bolt 17 and the fixing hole 13, so that concrete can be conveniently conveyed into the box body 2, the periphery of the bottom plate 1 is welded with a roller seat 18, the type is DS94, the number is 4, the left side of the upper end of the bottom plate 1 is welded with a vertical plate 19 which is a square plate, the upper part of the left side of the vertical plate 19 is welded with a connecting block 20, the connecting block 20 is a square block and 2, a push rod 21 is welded between the connecting blocks 20, the push rod 21 is a cylindrical rod and is located at the middle position, through the rolling action of rollers in the roller seat 18 at the bottom of the bottom plate 1, constructors can hold the push rod 21 by hands to push forwards, so that the vertical plate 20 can drive the rollers in the roller seats 18 below the bottom plate 1 to roll, the moving operation is convenient, and the concrete pouring operation efficiency is improved.
When the concrete pouring machine is used, the bolts 17 are inserted into the connecting holes 16 on the flange plate 15 and the fixing holes 13 of the box body 2, the conveying pipes 14 can be fixedly connected to the feed inlet 12 of the box body 2 through the threaded matching of the bolts 17 and the fixing holes 13, the concrete is conveyed into the box body 2, when the main body of a house building is subjected to concrete pouring, the vibrating machine 8 is operated, the vibrating machine 8 drives the vibrating rods 9 to vibrate the concrete in the box body 2, the thickness of the concrete is changed through the vibrating action of the vibrating rods 8, the concrete is prevented from being manually vibrated by constructors, the feeding pipes 4 in the through holes 3 can suck the concrete from the box body 2 through the conveying pipes 5, the concrete is discharged through the discharging pipes 6, the constructors can conveniently hold the discharging pipes 6 to pour the main body of the house, the repeated operation of the constructors is avoided, and the pouring efficiency can be improved, the problem of current housing construction main part construction pour the device and pour inefficiency is solved.
Claims (4)
1. The utility model provides a device is pour in housing construction main part construction, includes bottom plate (1), its characterized in that: bottom plate (1) facial make-up is equipped with box (2), perforation (3) have been seted up to one side of box (2), perforation (3) endotheca is equipped with inlet pipe (4), inlet pipe (4) cover is put on the input of delivery pump (5), install on bottom plate (1) delivery pump (5), output tube (6) have been put to the cover on the output of delivery pump (5), box (2) facial make-up is equipped with roof (7), bobbing machine (8) have been installed to roof (7) bottom, the output facial make-up of bobbing machine (8) is equipped with vibrting spear (9), through-hole (10) have been seted up on box (2), it has vibrting spear (9) to run through in through-hole (10).
2. The building construction main body construction pouring device according to claim 1, characterized in that: automatic telescopic rods (11) are symmetrically arranged on the box body (2), and a top plate (7) is arranged at the telescopic end of each automatic telescopic rod (11).
3. The building construction main body construction pouring device according to claim 2, characterized in that: feed inlet (12) have been seted up on one side upper portion of box (2), fixed orifices (13) have been seted up in the drill way department of feed inlet (12), the cover is equipped with conveyer pipe (14) on feed inlet (12), conveyer pipe (14) facial make-up is equipped with ring flange (15), connecting hole (16) have been seted up on ring flange (15), bolt (17) have been alternate in connecting hole (16) and fixed orifices (13).
4. The building construction main body construction pouring device according to claim 1, characterized in that: the bottom of the bottom plate (1) is provided with a roller seat (18), one side of the bottom plate (1) is provided with a vertical plate (19), the upper part of one side of the vertical plate (19) is provided with connecting blocks (20), and push rods (21) are arranged among the connecting blocks (20).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022641096.3U CN214091043U (en) | 2020-11-16 | 2020-11-16 | Device is pour in housing construction main part construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022641096.3U CN214091043U (en) | 2020-11-16 | 2020-11-16 | Device is pour in housing construction main part construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214091043U true CN214091043U (en) | 2021-08-31 |
Family
ID=77450219
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202022641096.3U Expired - Fee Related CN214091043U (en) | 2020-11-16 | 2020-11-16 | Device is pour in housing construction main part construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214091043U (en) |
-
2020
- 2020-11-16 CN CN202022641096.3U patent/CN214091043U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110173119A (en) | A kind of pumping of concrete construction is vibrated integrated equipment | |
CN104131564A (en) | Manufacturing process of vibration and powder-spraying gravel pile and vibrating equipment of process | |
CN210633868U (en) | Mortar mixer with high-pressure washing unit | |
CN214091043U (en) | Device is pour in housing construction main part construction | |
CN104099932A (en) | Breaking device and breaking method of pile head of underwater concrete pile | |
CN110126059A (en) | A kind of preparation process of precast concrete | |
CN211616117U (en) | Concrete mixing device is used in traffic engineering construction | |
CN205576924U (en) | Water conservancy construction feeding device | |
CN112412013A (en) | Construction method for plugging reserved hole of structural outer wall | |
CN202510133U (en) | Uniform dropping type blanking device | |
CN113235379A (en) | Concrete road surface construction patching device | |
CN211415673U (en) | Multifunctional pouring equipment | |
CN210552101U (en) | Concrete mixing device for building engineering | |
CN208131132U (en) | A kind of method for recycling waste concrete | |
CN112267469A (en) | Cement pouring equipment for building engineering | |
EP1520936A3 (en) | Boring method and apparatus | |
CN207667806U (en) | A kind of concrete gravel separator | |
CN206870129U (en) | A kind of grout recycling utilizes system | |
CN220058898U (en) | Spiral ball vibrator for sloping roof | |
CN218138926U (en) | Cement pipe is prefabricated with mixing material device | |
CN221183690U (en) | Screening device for concrete mixing | |
CN201687217U (en) | Vacuum suction filter | |
CN103737711B (en) | The die sinking distribution device of prestressed centrifugally stake | |
CN101037003B (en) | Method and device for forecasting concrete anti-leaking U-shaped groove by using permeability formwork gasket | |
CN108409264A (en) | A kind of preparation method of L-type precast terrazzo Decorative hanging board |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210831 |