CN214023352U - Large casting pouring system - Google Patents

Large casting pouring system Download PDF

Info

Publication number
CN214023352U
CN214023352U CN202023234889.XU CN202023234889U CN214023352U CN 214023352 U CN214023352 U CN 214023352U CN 202023234889 U CN202023234889 U CN 202023234889U CN 214023352 U CN214023352 U CN 214023352U
Authority
CN
China
Prior art keywords
pouring
sand box
box
basin
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023234889.XU
Other languages
Chinese (zh)
Inventor
邓小明
王常银
涂建平
毛飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Jiali Wind Power Technology Co ltd
Original Assignee
Zhejiang Jiali Wind Power Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Jiali Wind Power Technology Co ltd filed Critical Zhejiang Jiali Wind Power Technology Co ltd
Priority to CN202023234889.XU priority Critical patent/CN214023352U/en
Application granted granted Critical
Publication of CN214023352U publication Critical patent/CN214023352U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Molds, Cores, And Manufacturing Methods Thereof (AREA)

Abstract

The utility model discloses a large casting gating system belongs to the casting technique, if the workshop direction of height space is not enough during the production of large casting, can't produce the pouring, the utility model discloses install the sand box of passing a bridge in the side of main sand box and the top surface of passing a bridge the sand box is not higher than the top surface of main sand box to with the high reduction of runner basin, leave sufficient space in the top of runner basin, make the pouring opening of ladle can be higher than the runner basin and pour into a mould. Moreover, a gap bridge sand box and a pouring basin are arranged on two opposite sides of the main sand box; two traveling cranes are used for respectively hoisting a ladle and simultaneously pouring the pouring basins on the two sides, so that the ladle with a short height and a small capacity can be used for pouring large castings, the pouring opening of the ladle is higher than the pouring basin, the product quality is ensured, and the pouring efficiency is improved.

Description

Large casting pouring system
Technical Field
The utility model belongs to the casting technique, concretely relates to large-scale foundry goods gating system is applicable to large-scale foundry goods height very high, the manufacturing under the high space restricted condition in workshop during the pouring.
Background
In a general foundry, for pouring large castings (such as castings of more than 40 tons), it is important to ensure that an effective space exists in the height direction of a workshop, and if the space in the height direction of the workshop is insufficient, pouring cannot be performed.
The pouring basin of the existing pouring system is directly placed on the cover box, or the gap bridge sand box is installed on the cover box, and then the pouring basin is placed on the gap bridge sand box, so that the whole height of the pouring system is too large, and the pouring opening of the ladle is lower than the pouring basin on the premise that the effective space in the height direction of a workshop is set, and pouring cannot be carried out.
SUMMERY OF THE UTILITY MODEL
The utility model discloses the technical problem that solve and the technical task that provides are that workshop direction of height space is not enough when overcoming the large-scale foundry goods of production, can't produce the defect of pouring, provide a large-scale foundry goods gating system.
In order to achieve the above object, the utility model discloses a large casting gating system, be in including main sand box, packing molding sand in the main sand box, gap bridge sand box, install runner basin on the gap bridge sand box, form die cavity, characterized by in the molding sand: the gap bridge sand box is arranged on the side surface of the main sand box, and the top surface of the gap bridge sand box is not higher than that of the main sand box.
As a preferable technical means: the main sand box comprises a bottom box, at least one sand box ring and a cover box which are sequentially stacked together from bottom to top, the gap bridge sand box is arranged on the side surface of the cover box, and the top surface of the gap bridge sand box is not higher than that of the cover box.
As a preferable technical means: the two opposite sides of the main sand box are provided with the gap bridge sand box and the pouring basin.
As a preferable technical means: and a sprue, an ingate and a cross gate are arranged in the molding sand in the main sand box.
The utility model discloses install the sand box of passing a bridge in the side of main sand box and the top surface of sand box of passing a bridge not be higher than the top surface of main sand box to with the high reduction of runner basin, leave sufficient space in the top of runner basin, make the pouring opening of ladle can be higher than the runner basin and pour into a mould.
Moreover, a gap bridge sand box and a pouring basin are arranged on two opposite sides of the main sand box; the two traveling cranes can respectively hoist a ladle to simultaneously pour the pouring basins on the two sides, so that the pouring efficiency is improved, the ladle with a short height and a small capacity can be used for pouring large castings, the pouring opening of the ladle is higher than the pouring basin, and the product quality is ensured.
Drawings
FIG. 1 is a schematic view of a large casting gating system of the present invention;
the reference numbers in the figures illustrate: 01 main sand box, 1 ladle, 2 pouring basin, 3 sprue, 4-bridge-crossing sand box, 5-cavity, 6-cover box, 7-sand box ring, 8-bottom box, 9-ingate, 10-cross gate, 11-crane hook and 12-molding sand.
Detailed Description
The present invention will be further explained with reference to the drawings attached to the specification.
The large casting pouring system shown in fig. 1 comprises a main sand box 01, molding sand 12 filled in the main sand box, a gap bridge sand box 4 and a pouring basin 2 installed on the gap bridge sand box, wherein the main sand box 01 comprises a bottom box 8, a plurality of sand box rings 7 and a cover box 6 which are sequentially stacked together from bottom to top, a cavity 5 is formed in the molding sand, the gap bridge sand box 4 is installed on the side surface of the cover box 6, and the top surface of the gap bridge sand box 4 is not higher than the top surface of the cover box 6. A sprue 3, an ingate 9 and a cross runner 10 which are communicated with the sprue basin 2 and the cavity 5 are arranged in the molding sand of the main sand box 01. As shown in the figure, the height of the top surface of the cover box 6 is H, the height of the pouring opening of the ladle 1 is H, and the height of the upper edge of the pouring basin 2 is H1, so that H1= H is limited, thereby achieving the purpose of lowering H1 to enable H1 to be less than H, and thus, a sufficient space is left above the pouring basin 2 to enable the pouring opening of the ladle to be higher than the pouring basin for pouring.
The pouring height can be reduced by the aid of the large casting pouring system. Moreover, in order to improve the pouring efficiency, the bridge sand box 4 and the pouring basin 2 are arranged on two opposite sides of the cover box 6 of the main sand box 01. Two traveling cranes are used for respectively hoisting a ladle 1 and simultaneously pouring the pouring basins 2 on the two sides, the ladle with a short height and a small capacity can be used for pouring large castings, the pouring opening of the ladle is higher than the pouring basin, and the product quality is ensured.

Claims (4)

1. Large casting gating system, including the main flask (01), pack in molding sand (12) of main flask, gap bridge sand box (4), install runner basin (2) on the gap bridge sand box, form die cavity (5) in the molding sand, characterized by: the gap bridge sand box (4) is arranged on the side surface of the main sand box (01) and the top surface of the gap bridge sand box (4) is not higher than the top surface of the main sand box (01).
2. The large casting gating system of claim 1, wherein: the main sand box (01) comprises a bottom box (8), at least one sand box ring (7) and a cover box (6) which are sequentially stacked together from bottom to top, the gap bridge sand box (4) is arranged on the side face of the cover box (6), and the top face of the gap bridge sand box (4) is not higher than the top face of the cover box (6).
3. The large casting gating system of claim 1, wherein: the two opposite sides of the main sand box (01) are provided with the gap bridge sand box (4) and the pouring basin (2).
4. The large casting gating system of claim 1, wherein: and a sprue (3), an ingate (9) and a cross gate (10) are arranged in the molding sand in the main sand box.
CN202023234889.XU 2020-12-29 2020-12-29 Large casting pouring system Active CN214023352U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023234889.XU CN214023352U (en) 2020-12-29 2020-12-29 Large casting pouring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023234889.XU CN214023352U (en) 2020-12-29 2020-12-29 Large casting pouring system

Publications (1)

Publication Number Publication Date
CN214023352U true CN214023352U (en) 2021-08-24

Family

ID=77343155

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023234889.XU Active CN214023352U (en) 2020-12-29 2020-12-29 Large casting pouring system

Country Status (1)

Country Link
CN (1) CN214023352U (en)

Similar Documents

Publication Publication Date Title
CN201300190Y (en) Sand mold device for cluster casting of hammer heads
CN205217919U (en) Core assembly molding sand mould structure of transmission housing foundry goods
CN206425523U (en) A kind of casting die being easily stripped
CN111451455B (en) Box stacking casting method for nodular cast iron wind power brake disc
CN105414487A (en) Large loam core fixing method
CN202877483U (en) Medium-small type and large-batch steel casting production and casting mould
CN202639227U (en) Automobile brake caliper casing pouring system on vertical parting molding line
CN214023352U (en) Large casting pouring system
CN206382506U (en) A kind of improved medicine equipment mould
CN112658215B (en) Large casting pouring system and method for reducing pouring height
CN210172498U (en) Casting structure for improving process yield of engine crankcase
CN204975276U (en) Device of running away is prevented to low pressure casting
CN203992259U (en) The running channel of thin-wall ductile iron piston
CN201432079Y (en) Horizontal parting sand mold molding device with stacked boxes
CN212042549U (en) Core assembly feeding side pouring system for multiple base parts
CN203437595U (en) Gating system
CN202037308U (en) Automatic slip flask molding production device for castings
CN202639254U (en) Pouring and inoculation device of heavy casting
CN203426384U (en) Traction sheave casting sand mold structure
CN210547854U (en) Lost foam casting gate valve
CN102962408A (en) Sand-saving type sand box for manufacturing high-strength sand mould
CN204504147U (en) " point type " apparatus for pouring of nodular iron casting
CN103600035A (en) Manufacturing technology of walking machinery bracket casting
CN206382507U (en) A kind of mould of improved high-precision gearing casing
CN202517006U (en) Flange casting system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant