CN213952274U - Hoop type steel pipe support node - Google Patents
Hoop type steel pipe support node Download PDFInfo
- Publication number
- CN213952274U CN213952274U CN202022480748.XU CN202022480748U CN213952274U CN 213952274 U CN213952274 U CN 213952274U CN 202022480748 U CN202022480748 U CN 202022480748U CN 213952274 U CN213952274 U CN 213952274U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- steel
- node
- pipe pile
- hoop
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model relates to a staple bolt formula steel pipe support node is connected with stull and bracing between the adjacent steel pipe stake of steel pipe support, installs the staple bolt with the connected node of stull and bracing on the every steel pipe stake, and the welding has the connecting plate on the staple bolt, and the connecting plate on the both ends of every stull and bracing and the staple bolt on the steel pipe stake passes through bolted connection. The utility model discloses an assembled node can avoid welding repeatedly and cutting to the damage of steel-pipe pile, and when the node position on the steel-pipe pile changes, it can to reciprocate the staple bolt, construction convenience, swift.
Description
Technical Field
The utility model belongs to the building construction field relates to a steel pipe support's that sets up structure in the construction, concretely relates to staple bolt formula steel pipe support node.
Background
The steel pipe support includes the steel-pipe pile of many vertical settings, for guaranteeing that the support is stable, needs set up stull and bracing between adjacent steel pipe pile. The common connection nodes between the cross brace and the diagonal brace and the steel pipe pile are all in a welding structure, or the two ends of the cross brace and the diagonal brace are directly welded with the steel pipe pile, or a connection plate is welded in advance at the node on the steel pipe pile and is welded or connected with the cross brace and the diagonal brace through the connection plate. The positions of the nodes are all not movable, the nodes need to be cut when the support is dismantled, and the nodes need to be welded again when the steel pipe pile is used for erecting the support again or the positions of the nodes change; repeated welding and cutting easily cause damage to the steel pipe pile, and influence the reuse of the steel pipe pile; moreover, the welding type node increases the workload of erecting the support and influences the construction progress.
Disclosure of Invention
The utility model aims at providing staple bolt formula steel pipe support node to the problem that welded formula node exists on the current support, adopting assembled mounting structure, the job site does not involve welding processes, avoids causing the damage to the steel-pipe pile to improve the efficiency of construction.
The technical scheme of the utility model as follows:
the utility model provides a staple bolt formula steel pipe support node, steel pipe support includes the steel-pipe pile of many vertical settings, is connected with stull and bracing, its characterized in that between adjacent steel-pipe pile: the hoop is installed at the connecting node of the cross brace and the diagonal brace on each steel pipe pile, the hoop comprises two semicircular hoop plates, the two hoop plates are fastened on the steel pipe pile through bolts, a connecting plate is welded on one hoop plate, and the two ends of each cross brace and the two ends of each diagonal brace are connected with the connecting plates on the hoops on the two steel pipe piles through bolts.
The utility model has the advantages that:
(1) the anchor ear and the steel pipe pile are connected in an assembling manner, so that the damage to the steel pipe pile caused by repeated welding and cutting can be avoided, and the reuse rate of the steel pipe pile is improved;
(2) the node position can be freely adjusted, and when the node position on the steel pipe pile changes, the anchor ear can be moved up and down, so that the construction is convenient and rapid;
(3) the staple bolt encircles on the steel-pipe pile outer wall, has set up the one deck reinforcing plate in the steel-pipe pile node equivalently, has the reinforcing effect to the atress of steel-pipe pile node.
Drawings
Fig. 1 is a schematic elevation structure of the present invention;
fig. 2 is a schematic cross-sectional view at a node.
Detailed Description
As shown in fig. 1 and 2, the steel pipe support comprises a plurality of vertically arranged steel pipe piles 1, and a cross brace 2 and an inclined brace 3 are connected between adjacent steel pipe piles; the hoop 4 is installed with the connected node department of stull and bracing on every steel-pipe pile 1, the hoop includes two semicircular hooping plates, and two hooping plates pass through bolt 5 fastening on the steel-pipe pile, and the welding has connecting plate 6 on one of them hooping plate, and the both ends of every stull 2 and bracing 3 pass through bolted connection with connecting plate 6 on the hoop on two steel-pipe piles.
The connecting plate is welded on the hoop plate in advance, and a screw hole is preset in the connecting plate. When the support is erected, after the installation of the steel pipe piles is completed, the hoops are basically fixed on the steel pipe piles according to the node positions of the cross braces and the inclined struts, after the angles of the connecting plates are adjusted, the hoop bolts are screwed down to fasten the hoops and the steel pipe piles, and then the two ends of the cross braces and the two ends of the inclined struts are respectively connected with the connecting plates on the hoops on the two steel pipe piles through bolts.
Claims (1)
1. The utility model provides a staple bolt formula steel pipe support node, steel pipe support includes the steel-pipe pile of many vertical settings, is connected with stull and bracing, its characterized in that between adjacent steel-pipe pile: the hoop is installed at the connecting node of the cross brace and the diagonal brace on each steel pipe pile, the hoop comprises two semicircular hoop plates, the two hoop plates are fastened on the steel pipe pile through bolts, a connecting plate is welded on one hoop plate, and the two ends of each cross brace and the two ends of each diagonal brace are connected with the connecting plates on the hoops on the two steel pipe piles through bolts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022480748.XU CN213952274U (en) | 2020-10-31 | 2020-10-31 | Hoop type steel pipe support node |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022480748.XU CN213952274U (en) | 2020-10-31 | 2020-10-31 | Hoop type steel pipe support node |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213952274U true CN213952274U (en) | 2021-08-13 |
Family
ID=77206152
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202022480748.XU Active CN213952274U (en) | 2020-10-31 | 2020-10-31 | Hoop type steel pipe support node |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213952274U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114960476A (en) * | 2022-06-16 | 2022-08-30 | 浙江交工高等级公路养护有限公司 | Steel pipe concrete arch bridge reinforcing structure and construction method thereof |
-
2020
- 2020-10-31 CN CN202022480748.XU patent/CN213952274U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114960476A (en) * | 2022-06-16 | 2022-08-30 | 浙江交工高等级公路养护有限公司 | Steel pipe concrete arch bridge reinforcing structure and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113175091B (en) | Fully assembled prestressed frame cable system combined structure | |
CN213952274U (en) | Hoop type steel pipe support node | |
CN211898386U (en) | Tubular pile perpendicularity adjusting device | |
KR101962788B1 (en) | Temporary bridge construction method using steel girder and composite deck-plate and temporary bridge therewith | |
CN212027084U (en) | Adjustable combined steel formwork with supporting rod | |
CN209816666U (en) | Assembled bracing connection structure between steel-pipe piles | |
JP7058892B1 (en) | Steel structure constructed around the existing columnar body and its construction method | |
CN113944309A (en) | Cold-formed steel support beam framework and construction method thereof | |
CN209816670U (en) | Pedestrian passageway arranged on steel pipe supported in steel sleeve box | |
CN210622440U (en) | Traction wire structure for emergency repair of medium-low voltage distribution network | |
CN112049415A (en) | Construction method of cornice formwork | |
CN111472536A (en) | Template support, steel template and can pin-connected panel unilateral formwork structure | |
CN204551787U (en) | The building structure of a kind of shearing abatement | |
CN219011700U (en) | Concrete beam longitudinal bar construction node at foundation bolt of base | |
CN211229532U (en) | Vertical rod-free wood formwork supporting device and supporting system for shaped beam side | |
CN220133703U (en) | Be applied to assembled fender that encloses on soil matrix | |
CN219260734U (en) | Bridge cylindrical pier capping beam construction platform | |
CN215482993U (en) | Assembled square and rectangular tubular steel supporting beam for foundation pit support | |
CN214364132U (en) | Section steel concrete beam column node | |
CN219826301U (en) | Temporary supporting structure for heavier PC beam | |
CN212002423U (en) | Non-welding type bracing reinforcing apparatus of steel construction factory building beam column | |
CN211776396U (en) | Assembled building rail guard | |
CN217870013U (en) | Assembled steel support connection component | |
CN217761020U (en) | Welding type H-shaped steel surrounding purlin structure of large-diameter circular working well | |
CN214885399U (en) | Adjustable operation construction equipment of steel column |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |