CN213927410U - Casting construction hanging cage - Google Patents

Casting construction hanging cage Download PDF

Info

Publication number
CN213927410U
CN213927410U CN202022572636.7U CN202022572636U CN213927410U CN 213927410 U CN213927410 U CN 213927410U CN 202022572636 U CN202022572636 U CN 202022572636U CN 213927410 U CN213927410 U CN 213927410U
Authority
CN
China
Prior art keywords
shaped frame
rotation
axis
peg
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022572636.7U
Other languages
Chinese (zh)
Inventor
盛伟欢
顾少华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changshu Road And Bridge Engineering Co Ltd
Original Assignee
Changshu Road And Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changshu Road And Bridge Engineering Co Ltd filed Critical Changshu Road And Bridge Engineering Co Ltd
Priority to CN202022572636.7U priority Critical patent/CN213927410U/en
Application granted granted Critical
Publication of CN213927410U publication Critical patent/CN213927410U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The application relates to a casting construction hanging cage, which relates to the field of hanging cages and comprises a first U-shaped frame, a second U-shaped frame, a bottom frame, a first roller, a second roller, a rotating shaft and a driving assembly; the first U-shaped frame and the second U-shaped frame are arranged at intervals, the bottom frame is arranged between the bottom ends of the first U-shaped frame and the second U-shaped frame, first hanging rods are outwards arranged at two ends of the first U-shaped frame, and the first rollers are horizontally and rotatably assembled on the two first hanging rods respectively; the both ends of second U-shaped frame are provided with the second peg outward, the axis of rotation transversely rotates the assembly in two between the second peg, and is a plurality of the second gyro wheel is coaxial to be fixed in the axis of rotation, drive assembly set up in the axis of rotation with between the second U-shaped frame, just drive assembly orders about the axis of rotation rotates. The application has the effect of simple and convenient movement.

Description

Casting construction hanging cage
Technical Field
The application relates to the field of hanging cages, in particular to a hanging cage for pouring construction.
Background
The construction hanging cage is also called a construction hanging basket and a construction hanging basket, in the building pouring construction process, construction usually involves high-altitude operation, high-altitude measurement, high-altitude welding and other high-altitude operations, and during operation, a platform for operation needs to be provided, and most platforms are called hanging cages.
The application number is CN 201921856761.1's chinese patent discloses a pour construction and hang cage, including first U type support frame, two main tributary vaulting poles, second U type support frame and underframe, weld between the inboard top of two main tributary vaulting poles, the top of two main tributary vaulting poles respectively with the both sides fixed connection of first U type support frame inner arm, the bottom of the inboard bottom of two main tributary vaulting poles and the bottom of second U type support frame inner arm both sides all through the round pin axle respectively with the both ends swing joint of underframe both sides, be equipped with a plurality of connecting rod between two main tributary vaulting poles and the second U type support frame, the inside fixed welding of underframe has the backup pad, the both sides of first U type support frame bottom fixed mounting respectively has two pairs of pulleys, will hang the cage through first U type support frame and establish in suitable position, the staff stands to carry out the construction operation in the backup pad.
With respect to the related art among the above, the inventors consider that the following drawbacks exist: when constructors need to move the hanging cage during construction, workers in the hanging cage need to come out to push the whole hanging cage, or other workers push and move the workers standing in the hanging cage together outside, and the movement is troublesome, so that improvement is needed.
SUMMERY OF THE UTILITY MODEL
In order to improve and remove the trouble problem of hanging the cage, this application provides a casting construction and hangs cage.
The application provides a pair of cast construction hangs cage adopts following technical scheme:
a casting construction hanging cage comprises a first U-shaped frame, a second U-shaped frame, a bottom frame, a first roller, a second roller, a rotating shaft and a driving assembly;
the first U-shaped frame and the second U-shaped frame are arranged at intervals, the bottom frame is arranged between the bottom ends of the first U-shaped frame and the second U-shaped frame, first hanging rods are outwards arranged at two ends of the first U-shaped frame, and the first rollers are horizontally and rotatably assembled on the two first hanging rods respectively;
the both ends of second U-shaped frame are provided with the second peg outward, the axis of rotation transversely rotates the assembly in two between the second peg, and is a plurality of the second gyro wheel is coaxial to be fixed in the axis of rotation, drive assembly set up in the axis of rotation with between the second U-shaped frame, just drive assembly orders about the axis of rotation rotates.
Through adopting above-mentioned technical scheme, the underframe links together first U-shaped frame and second U-shaped frame, just can hang the cage through two first peg and second peg and hang on the construction building, constructor just can stand and be under construction in the underframe, and when needing to remove, the staff stands and just can start drive assembly in the underframe, drive assembly orders about the axis of rotation again and rotates, the axis of rotation just can drive a plurality of second gyro wheels and rotate, thereby make whole cage removal of hanging, it is more convenient to remove, and a plurality of first gyro wheels have reduced the frictional force of hanging between cage and the building, it is more convenient to remove the cage, and is laborsaving.
Preferably, two the lower surface of second peg is provided with the mounting panel vertically down, the axis of rotation is rotated and is assembled in two between the mounting panel, it is a plurality of the second gyro wheel coaxial fixation is in the axis of rotation, the second gyro wheel is located under the second peg, the diameter of second gyro wheel is greater than the length of mounting panel.
Through adopting above-mentioned technical scheme, two mounting panels provide better mounted position for the axis of rotation, and when the second peg was hung on the building, it was second gyro wheel and building contact, when the second gyro wheel rotated, the mounting panel also did not influence the normal removal of hanging the cage, and it is more convenient to remove.
Preferably, the driving assembly comprises a driving chain wheel, a driven chain wheel, a chain, a mounting rod and a driving piece;
the installation pole transversely rotates the assembly in on the second U-shaped frame, drive sprocket coaxial fixed in on the installation pole, driven sprocket coaxial fixed in the axis of rotation, just driven sprocket is located two between the second peg, drive sprocket with driven sprocket is in on the same vertical line, the chain cover is located drive sprocket with between the driven sprocket, the driving piece set up in the installation pole is kept away from the one end of second U-shaped frame, just the driving piece orders about the installation pole rotates.
Through adopting above-mentioned technical scheme, after starting the driving piece, the driving piece orders about the drive sprocket rotation on the installation pole, and drive sprocket rethread chain drives driven sprocket and rotates, and driven sprocket drives a plurality of second gyro wheels of axis of rotation again and rotates, and whole cage of hanging just can remove under the cooperation of first gyro wheel and second gyro wheel, and the driving piece design makes things convenient for constructor to start on second U-shaped frame moreover, and it is more convenient to remove.
Preferably, the driving member comprises a turntable and a rocker;
the turntable is coaxially fixed at the end part of the mounting rod, the rocker is rotatably assembled at one side of the turntable, which is far away from the mounting rod, and the edge of the rocker, which is close to the turntable, is designed.
Through adopting above-mentioned technical scheme, when rotating the carousel through the rocker, the axis of rotation just can be taken by the carousel and rotate together to drive the rotation of second gyro wheel through drive sprocket, chain and driven sprocket, simple structure, convenient operation.
Preferably, an L-shaped rod is fixed on the lower surface of the first hanging rod, the L-shaped rod is parallel to the rotating shaft, the diameters of the L-shaped rod and the rotating shaft are consistent, and the first rollers are assembled on the L-shaped rod in a rotating mode at intervals.
Through adopting above-mentioned technical scheme, L shape pole provides better mounted position for first gyro wheel, makes a plurality of first gyro wheels and second gyro wheel can be in on same water flat line, and it is more convenient, laborsaving to remove to hang the cage, hangs the cage moreover and can remove more steadily.
Preferably, the bottom frame comprises a support rod and a coaming;
many the bracing piece transversely is fixed in side by side first U-shaped frame with between the bottom of second U-shaped frame, the bounding wall is the U-shaped, the lower surface of bounding wall is fixed in on the bracing piece, the outer wall of the relative both sides of bounding wall with first U-shaped frame the second U-shaped frame is fixed.
Through adopting above-mentioned technical scheme, many parallel bracing pieces have the supporting role to the constructor who stands in the underframe, and the back plate is fixed back with bracing piece, first U-shaped frame and second U-shaped frame moreover, has not only strengthened the structural strength of underframe, enables the constructor moreover and stands on smooth bounding wall, and the construction is safer, convenient.
Preferably, a plurality of first connecting rods are fixed between the first U-shaped frame and the second U-shaped frame at intervals.
Through adopting above-mentioned technical scheme, the head rod not only has the effect of additional strengthening intensity to whole cage of hanging, and a plurality of head rods link together first U-shaped frame and second U-shaped frame moreover, and the monolithic connectivity between first U-shaped frame and the second U-shaped frame is better, and the structure is more firm.
Preferably, a plurality of second connecting rods are arranged between the two ends of the first U-shaped frame and between the two ends of the second U-shaped frame at intervals.
Through adopting above-mentioned technical scheme, the second connecting rod has strengthened the structural strength of first U-shaped frame, second U-shaped frame, links together the both ends of first U-shaped frame, second U-shaped frame steadily moreover, and the structure is more stable, firm.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the hanging cage is hung on a building through the first hanging rod and the second hanging rod, after a constructor starts the driving assembly, the driving assembly can drive the plurality of second rollers to rotate, the whole hanging cage can move on the building under the matching of the first rollers and the second rollers, and the movement is convenient;
2. when the rocker is rotated, the driving chain wheel can drive the driven chain wheel to rotate through the chain, the driven chain wheel drives the second roller wheel on the rotating shaft to rotate, the hanging cage can move when the second roller wheel rotates, and the rocker is installed on the first U-shaped frame, so that a constructor standing in the bottom frame can conveniently rotate, and the movement is more convenient;
3. the underframe comprises many spinal branchs vaulting pole and bounding wall, makes the underframe have sufficient structural strength and supports the constructor of standing in the underframe, and the bounding wall is more level and more smooth moreover, and constructor stands safelyr, steady on the bounding wall.
Drawings
FIG. 1 is a schematic view of the assembly of an embodiment of the present application to a building.
Fig. 2 is a schematic structural diagram of an embodiment of the present application.
Description of reference numerals: 1. a first U-shaped frame; 11. a first hanging rod; 111. an L-shaped rod; 2. a second U-shaped frame; 21. a second hanging rod; 211. mounting a plate; 3. a bottom frame; 31. a support bar; 32. enclosing plates; 4. a first roller; 5. a second roller; 6. a rotating shaft; 7. a drive assembly; 71. a drive sprocket; 72. a driven sprocket; 73. a chain; 74. mounting a rod; 75. a drive member; 751. a turntable; 752. a rocker; 8. a first connecting rod; 9. a second connecting rod; 101. a building is provided.
Detailed Description
The present application is described in further detail below with reference to figures 1-2.
The embodiment of the application discloses a casting construction hanging cage. Referring to fig. 1 and 2, the casting construction hanging cage comprises a first U-shaped frame 1, a second U-shaped frame 2, a bottom frame 3, a first roller 4, a second roller 5, a rotating shaft 6 and a driving assembly 7; first U-shaped frame 1 and second U-shaped frame 2 are formed by integrative the buckling of stainless steel pipe, underframe 3 level welded fastening is between the bottom of first U-shaped frame 1 and second U-shaped frame 2, the open end of first U-shaped frame 1 and second U-shaped frame 2 up, first U-shaped frame 1 and the horizontal interval of second U-shaped frame 2 are laid, the equal outside integrative extension in top at first U-shaped frame 1 both ends has first peg 11, two first peg 11 levels are laid, the equal outside integrative extension in top at second U-shaped frame 2 both ends has second peg 21, two second peg 21 levels are laid, should pour construction and hang the cage between two buildings 101 through two first pegs 11 and two second peg 21 levels.
Underframe 3 includes bounding wall 32 and many spinal branchs vaulting pole 31, many spinal branchs vaulting pole 31 transversely are fixed side by side between the bottom of first U-shaped frame 1 and second U-shaped frame 2, bounding wall 32 is the U-shaped form, the lower surface and many spinal branchs vaulting pole 31 welded fastening of bounding wall 32, the outer wall and first U-shaped frame 1 of the relative both sides of bounding wall 32, second U-shaped frame 2 welded fastening, wherein, the segmental arc of two tip of bounding wall 32 respectively with the segmental arc adaptation welded fastening of first U-shaped frame 1 and 2 bottoms of second U-shaped frame.
Equal horizontal welding has many shorter second connecting rods 9 between the both ends of first U-shaped frame 1 and second U-shaped frame 2, many second connecting rods 9 on first U-shaped frame 1 are with two end connection on the first U-shaped frame 1 promptly, many second connecting rods 9 on the second U-shaped frame 2 are with two end connection on the second U-shaped frame 2, horizontal welding has many longer head rods 8 between first U-shaped frame 1 and the second U-shaped frame 2, many first connecting rods couple together the pole that lies in same one side of first U-shaped frame 1 and second U-shaped frame 2 promptly, and many stainless steel's head rod 8, second connecting rod 9 all lays along vertical direction interval.
Equal welded fastening of lower surface of two first peg 11 has L shape pole 111, the longer one end level of L shape pole 111 is laid, equal horizontal rotation is equipped with three first gyro wheel 4 on each L shape pole 111, three first gyro wheel 4 interval is laid, the vertical welding of lower surface of the one end that two second pegs 21 kept away from each other has mounting panel 211, horizontal rotation is equipped with an axis of rotation 6 between two mounting panels 211, equal coaxial three second gyro wheel 5 that is fixed with in the both ends of axis of rotation 6, three second gyro wheel 5 is located second peg 21 under, the diameter of second gyro wheel 5 is greater than the length of mounting panel 211, a plurality of first gyro wheels 4 and second gyro wheel 5 flush each other, first gyro wheel 4 and second gyro wheel 5 are rolling contact each other with the building 101 on both sides, conveniently remove this pouring construction and hang the cage.
Drive assembly 7 sets up between axis of rotation 6 and second U-shaped frame 2, when constructor stands to need to remove this construction of pouring and hang the cage in underframe 3, constructor can start drive assembly 7 and rotate in order to order about axis of rotation 6, just can drive six second gyro wheels 5 and rotate simultaneously when axis of rotation 6 rotates, should pour the construction and hang the cage and just can remove under the cooperation of first gyro wheel 4 and second gyro wheel 5.
Wherein, the driving assembly 7 comprises a driving sprocket 71, a driven sprocket 72, a chain 73, a mounting rod 74 and a driving member 75; the mounting rod 74 is transversely and rotatably assembled on the second U-shaped frame 2, the driving sprocket 71 is coaxially fixed on the mounting rod 74, the driven sprocket 72 is coaxially fixed at the center position of the rotating shaft 6, the driving sprocket 71 and the driven sprocket 72 are positioned on the same vertical line, the chain 73 is sleeved between the driving sprocket 71 and the driven sprocket 72, the driving piece 75 comprises a turntable 751 and a rocker 752, the turntable 751 is coaxially fixed at the end part of the mounting rod 74, the rocker 752 is rotatably assembled on one side of the turntable 751, which is far away from the mounting rod 74, and the rocker 752 is designed near the edge of the turntable 751.
When rotating carousel 751 through rocker 752, installation pole 74 is taken together by carousel 751 and rotates to drive axis of rotation 6 through drive sprocket 71, chain 73 and driven sprocket 72 and rotate, when axis of rotation 6 rotated, six second gyro wheels 5 just can rotate, should pour the construction and hang the cage and just can be driven the removal by first gyro wheel 4 and second gyro wheel 5, and rocker 752 designs in constructor pivoted place, stands and just can oneself order about this construction of pouring and hang the cage and remove in underframe 3, and it is simple, convenient to remove.
The implementation principle of the casting construction hanging cage is as follows: hang this casting through two first peg 11 and second peg 21 and hang the cage on two buildings 101, then constructor stands and constructs in underframe 3, when needing to remove this casting and hanging the cage and hang, the constructor who stands in underframe 3 can rotate rocker 752 on the carousel 751, when carousel 751 drive installation pole 74 rotates, through drive sprocket 71, driven sprocket 72 and chain 73 just can drive axis of rotation 6 and rotate, when axis of rotation 6 rotates, first gyro wheel 4 and second gyro wheel 5 just can drive this casting and hang the cage and move, do not need other personnel to push away in the outside, also do not need constructor to come out the removal from underframe 3, it is relatively simple to remove, and is convenient.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a pour construction and hang cage which characterized in that: comprises a first U-shaped frame (1), a second U-shaped frame (2), a bottom frame (3), a first roller (4), a second roller (5), a rotating shaft (6) and a driving component (7);
the first U-shaped frame (1) and the second U-shaped frame (2) are arranged at intervals, the bottom frame (3) is arranged between the bottom ends of the first U-shaped frame (1) and the second U-shaped frame (2), first hanging rods (11) are outwards arranged at two ends of the first U-shaped frame (1), and the first rollers (4) are horizontally and rotatably assembled on the two first hanging rods (11) respectively;
the both ends of second U-shaped frame (2) are outwards provided with second peg (21), axis of rotation (6) transversely rotate the assembly in two between second peg (21), it is a plurality of second gyro wheel (5) coaxial fastening is in on axis of rotation (6), drive assembly (7) set up in axis of rotation (6) with between second U-shaped frame (2), just drive assembly (7) order about axis of rotation (6) rotate.
2. The cast construction hanging cage according to claim 1, characterized in that: two the lower surface of second peg (21) is provided with mounting panel (211) down vertically, axis of rotation (6) rotate the assembly in two between mounting panel (211), it is a plurality of second gyro wheel (5) coaxial fixation is in on axis of rotation (6), second gyro wheel (5) are located under second peg (21), the diameter of second gyro wheel (5) is greater than the length of mounting panel (211).
3. The cast construction hanging cage according to claim 2, characterized in that: the driving assembly (7) comprises a driving chain wheel (71), a driven chain wheel (72), a chain (73), a mounting rod (74) and a driving piece (75);
installation pole (74) transversely rotate the assembly in on second U-shaped frame (2), drive sprocket (71) coaxial fixed in on installation pole (74), driven sprocket (72) coaxial fixed in on axis of rotation (6), just driven sprocket (72) are located two between second peg (21), drive sprocket (71) with driven sprocket (72) are in same vertical on-line, chain (73) cover is located drive sprocket (71) with between driven sprocket (72), driving piece (75) set up in installation pole (74) is kept away from the one end of second U-shaped frame (2), just driving piece (75) order about installation pole (74) rotates.
4. The cast construction hanging cage according to claim 3, characterized in that: the drive member (75) comprises a turntable (751) and a rocker (752);
the rotary disc (751) is coaxially fixed at the end part of the mounting rod (74), the rocker (752) is rotatably assembled at one side of the rotary disc (751) far away from the mounting rod (74), and the rocker (752) is designed close to the edge of the rotary disc (751).
5. The cast construction hanging cage according to claim 2, characterized in that: the lower surface of first peg (11) is fixed with L shape pole (111), L shape pole (111) with axis of rotation (6) are parallel to each other, just L shape pole (111) with the diameter of axis of rotation (6) is unanimous, and is a plurality of first gyro wheel (4) interval rotation assembly in on the L shape pole (111).
6. The cast construction hanging cage according to claim 1, characterized in that: the bottom frame (3) comprises a support rod (31) and a coaming (32);
many bracing piece (31) transversely be fixed in side by side first U-shaped frame (1) with between the bottom of second U-shaped frame (2), bounding wall (32) are the U-shaped, the lower surface of bounding wall (32) is fixed in on bracing piece (31), the outer wall of the relative both sides of bounding wall (32) with first U-shaped frame (1) second U-shaped frame (2) are fixed.
7. The cast construction hanging cage according to claim 1, characterized in that: a plurality of first connecting rods (8) are fixed between the first U-shaped frame (1) and the second U-shaped frame (2) at intervals.
8. The cast construction hanging cage according to claim 1, characterized in that: a plurality of second connecting rods (9) are arranged between the two ends of the first U-shaped frame (1) and between the two ends of the second U-shaped frame (2) at intervals.
CN202022572636.7U 2020-11-09 2020-11-09 Casting construction hanging cage Active CN213927410U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022572636.7U CN213927410U (en) 2020-11-09 2020-11-09 Casting construction hanging cage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022572636.7U CN213927410U (en) 2020-11-09 2020-11-09 Casting construction hanging cage

Publications (1)

Publication Number Publication Date
CN213927410U true CN213927410U (en) 2021-08-10

Family

ID=77167171

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022572636.7U Active CN213927410U (en) 2020-11-09 2020-11-09 Casting construction hanging cage

Country Status (1)

Country Link
CN (1) CN213927410U (en)

Similar Documents

Publication Publication Date Title
CN108487624A (en) Attachment type raise scaffold
CN213927410U (en) Casting construction hanging cage
CN211954952U (en) Detection apparatus for electric power construction safety belt hanger
CN105942936B (en) The adjustable building Green Machine people of one kind lifting
CN221701640U (en) Rotating device for blackening process of wind power bearing
CN207919351U (en) Hanging basket
CN213326390U (en) Flange painting production line
CN211524026U (en) Casting construction hanging cage
CN210289043U (en) Anti-toppling scaffold
CN209481072U (en) A kind of novel hung steel tube device
CN210105347U (en) High-rise partition plate installation equipment with good stability
CN221524186U (en) Hanging basket hanging device for low-temperature storage tank construction
CN209855272U (en) Window cleaning machine for inclined plane of glass curtain wall
CN205954363U (en) Novel cloth inspection machine
CN218372598U (en) Automatic lower hanging machine for electroplating pull head
CN109834116A (en) The replacement system and replacing options of the top roller of horizontal loop
CN218522190U (en) Movable quick-release operation platform suitable for high-altitude edge-facing operation
CN209941490U (en) Hanging ladder walking on anti-collision guardrail
CN214885699U (en) External overhanging net rack for building construction
CN209507463U (en) Lifting device is used in a kind of installation of fire-fighting water main
CN221454783U (en) Hanging type trolley for welding large tank
CN214576151U (en) Carbon fiber flagpole
CN218621894U (en) Basket walking strutting arrangement is hung to trolley-bus triangle
CN217535140U (en) C type hoist auxiliary stand
CN212921582U (en) Bridge steel construction guardrail stand processingequipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant