- CN213909969U CN213909969U CN202022840379.0U CN202022840379U CN213909969U CN 213909969 U CN213909969 U CN 213909969U CN 202022840379 U CN202022840379 U CN 202022840379U CN 213909969 U CN213909969 U CN 213909969U
- Authority
- CN
- China
- Prior art keywords
- drain pipe
- integrated
- structure suitable
- chassis
- opening
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000010865 sewage Substances 0.000 claims abstract description 21
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 10
- 238000004806 packaging method and process Methods 0.000 claims description 4
- 238000009434 installation Methods 0.000 abstract description 9
- 230000000694 effects Effects 0.000 abstract description 4
Images
Landscapes
- Sink And Installation For Waste Water (AREA)
Abstract
The utility model relates to a drain pipe lays structure suitable for integrated bathroom, including integrated bathroom, integrated bathroom's chassis is pre-buried to have by the head end toward the drain pipe of tail end slope gradually, and the drain pipe is opened has the first opening that is used for connecting the outlet of wash-basin/bathtub and is used for connecting the sewage export of sewage riser, the height of sewage export all is less than first open-ended height. The pre-buried drain pipe that has of chassis has reduced the occupation of ground walk pipe to the space, strengthens the travelling comfort of integrated bathroom, has avoided establishing the possibility that the caisson secondary leaked moreover, only need during the installation connect at first opening and sewage outlet can, the installation is simple, and it is convenient to overhaul, and the drain pipe is by the head end toward the tail end slope gradually moreover, and the drainage of drain pipe is more smooth in the same direction as, improves drainage effect.
Description
Technical Field
The utility model relates to a drain pipe lays structure suitable for integrated bathroom.
Background
In the existing integrated bathroom project, in order to prevent water, a chassis in a dry and wet area is poured into a whole, and due to the spatial arrangement relationship of a wash basin, a shower room and a closestool, in order to not influence the ground use function of the local bathroom, a certain drainage pipeline channel is often required to be reserved between a wall plate and a structural wall so as to lead the drainage of the wash basin or a bathtub to pass through a sewage vertical pipe connected to a pipe well on the chassis, thus greatly influencing the use space of the bathroom, and influencing the scheme design of the whole floor if the space of the bathroom is enlarged.
If arrange the drain pipe between the chassis and the floor, on the one hand be difficult to overhaul, on the other hand will increase waterproof again, both increase the cost, influence the floor height again.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a reduce space and occupy, avoid caisson secondary to leak water one kind be applicable to integrated bathroom's drain pipe and lay the structure.
The purpose of the utility model is realized like this:
the utility model provides a drain pipe lays structure suitable for integrated bathroom, includes integrated bathroom, integrated bathroom's chassis pre-buried has by the head end toward the drain pipe of tail end slope gradually, and the drain pipe is opened has the first opening that is used for connecting the outlet of wash-basin/bathtub and is used for connecting the sewage export of sewage riser, the height of sewage export all is less than first open-ended height. The pre-buried drain pipe that has of chassis has reduced the occupation of ground walk pipe to the space, strengthens the travelling comfort of integrated bathroom, has avoided establishing the possibility that the caisson secondary leaked moreover, only need during the installation connect at first opening and sewage outlet can, the installation is simple, and it is convenient to overhaul, and the drain pipe is by the head end toward the tail end slope gradually moreover, and the drainage of drain pipe is more smooth in the same direction as, improves drainage effect.
The purpose of the utility model can also adopt the following technical measures to solve:
more specifically, the head end of the drain pipe is provided with a 90-degree elbow which is convenient for connecting the drain pipe to form the first opening, and the elbow is flush with the surface of the chassis.
More specifically, the tail end of the drain pipe penetrates through the chassis and is exposed outside for 5cm to form the sewage outlet.
As a more specific scheme, the drain pipe is embedded in the chassis in an integrated packaging mode. The drain pipe of the wash basin or the bathtub far away from the pipe well and the base plate of the integrated bathroom are embedded in an integrated packaging mode, and the connecting pipe is connected to the inlet and the outlet in a follow-up mode, so that the possibility of secondary water leakage of the caisson is avoided, the occupation of the ground pipe to the space is reduced, and the overhaul is convenient.
More specifically, the drain pipe and the chassis are integrally cast.
More specifically, the base plate is provided with a first drainage hole, and the first drainage hole is communicated with the first opening. The chassis is preset with a first drainage hole, and a drainage pipe of the hand basin/bathtub/floor drain can be connected with a corresponding first opening by being inserted into the first drainage hole, so that the installation is easy.
More specifically, the drain pipe is provided with a second opening for connecting the floor drain, and the second opening is higher than the sewage outlet.
The utility model has the advantages as follows:
the utility model discloses, the chassis is pre-buried to have the drain pipe, has reduced the ground and has walked the pipe and to occuping of space, strengthens the travelling comfort of integrated bathroom, has avoided establishing the possibility that the caisson secondary leaked moreover, only need during the installation connect at first opening and sewage outlet can, the installation is simple, and it is convenient to overhaul, and the drain pipe is inclined gradually toward the tail end by the head end in addition, and the drainage of drain pipe is more smooth in the same direction as, improves drainage effect.
The utility model discloses, the drain pipe of the wash-basin or the bathtub that will keep away from the tube well adopts the mode of integrative package pre-buried with the chassis of integrated bathroom, follow-up only need in the access & exit termination good connecting pipe can, avoided establishing the possibility that the caisson secondary leaked, reduced the occupation of ground walk pipe to the space, and it is convenient to overhaul.
Drawings
Fig. 1 is a schematic view of a water drainage pipe laying structure suitable for an integrated bathroom.
Fig. 2 is a schematic plan view of a drainage pipe laying structure suitable for an integrated bathroom.
Fig. 3 is a sectional view a-a of fig. 2.
Fig. 4 is a sectional view B-B of fig. 2.
Detailed Description
The invention will be further described with reference to the following drawings and examples:
an embodiment, as shown in fig. 1 to 4, is a drain pipe laying structure suitable for an integrated bathroom, including the integrated bathroom, a drain pipe 2 that gradually inclines from a head end to a tail end is pre-buried in a chassis 1 of the integrated bathroom, a 90-degree elbow (not shown in the figure) that is convenient for connecting the drain pipe 2 is installed at the head end of the drain pipe 2 to form a first opening 3 for connecting a drain outlet of a washbasin/bathtub, the elbow is flush with the surface of the chassis 1, the tail end of the drain pipe 2 passes through the chassis 1 and is exposed by 5cm outwards to form a sewage outlet 4 for connecting a sewage stand pipe, and the height of the sewage outlet 4 is lower than the height of the first opening 3.
The drainage pipe 2 and the chassis 1 are integrally poured, and are embedded in the chassis 1 in an integrated packaging mode, the chassis 1 is provided with a first drainage hole, and the first drainage hole is communicated with the first opening 3.
The utility model discloses, chassis 1 pre-buried has drain pipe 2, has reduced the ground and has walked the pipe and to occuping of space, strengthens the travelling comfort of integrated bathroom, has avoided establishing the possibility that the caisson secondary leaked moreover, only need during the installation connect at first opening 3 and outlet for sewage 4 can, the installation is simple, and it is convenient to overhaul, and drain pipe 2 is by the head end toward the tail end slope gradually moreover, and drain pipe 2's drainage is more smooth in the same direction as, improves drainage effect.
Claims (7)
1. The utility model provides a drain pipe lays structure suitable for integrated bathroom, includes integrated bathroom, its characterized in that: the integrated bathroom is characterized in that a drain pipe which gradually inclines from the head end to the tail end is embedded in the base plate of the integrated bathroom, the drain pipe is provided with a first opening used for being connected with a drain outlet of a hand basin/bathtub and a sewage outlet used for being connected with a sewage vertical pipe, and the height of the sewage outlet is lower than that of the first opening.
2. The water drainage pipe laying structure suitable for integrated bathrooms according to claim 1, wherein: the head end of the drain pipe is provided with a 90-degree elbow which is convenient for connecting the drain pipe to form the first opening, and the elbow is flush with the surface of the chassis.
3. The water drainage pipe laying structure suitable for integrated bathrooms according to claim 1, wherein: the tail end of the drain pipe penetrates through the base plate and is exposed outside for 5cm to form the sewage outlet.
4. The water drainage pipe laying structure suitable for integrated bathrooms according to claim 1, wherein: the drain pipe is embedded in the chassis in an integrated packaging mode.
5. The water drainage pipe laying structure suitable for integrated bathrooms according to claim 1, wherein: and the drain pipe and the chassis are integrally cast.
6. The water drainage pipe laying structure suitable for integrated bathrooms according to claim 1, wherein: the chassis is provided with a first drainage hole which is communicated with the first opening.
7. The water drainage pipe laying structure suitable for integrated bathrooms according to claim 1, wherein: the drain pipe is provided with a second opening used for being connected with a floor drain, and the second opening is higher than the sewage outlet.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022840379.0U CN213909969U (en) | 2020-11-30 | 2020-11-30 | Drain pipe laying structure suitable for integrated bathroom |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022840379.0U CN213909969U (en) | 2020-11-30 | 2020-11-30 | Drain pipe laying structure suitable for integrated bathroom |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213909969U true CN213909969U (en) | 2021-08-10 |
Family
ID=77146405
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202022840379.0U Expired - Fee Related CN213909969U (en) | 2020-11-30 | 2020-11-30 | Drain pipe laying structure suitable for integrated bathroom |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213909969U (en) |
-
2020
- 2020-11-30 CN CN202022840379.0U patent/CN213909969U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109162338A (en) | A kind of assembled architecture embedding pipe fittings | |
CN213909969U (en) | Drain pipe laying structure suitable for integrated bathroom | |
CN2647954Y (en) | Water sealing box for water draining vertical pipe | |
KR20100093246A (en) | Construction method for on-floor drainage piping system of bathroom in multistory building | |
CN111173084A (en) | Accumulated water remover | |
CN217783008U (en) | Drain pipe laying structure of integrated bathroom | |
CN216380401U (en) | Integrated bathroom waterproof construction | |
CN214497714U (en) | Bathroom drainage system | |
CN211006895U (en) | Pre-buried formula cast iron is with layer drainage connecting device | |
CN217460789U (en) | Novel drainage structure for preventing drainage of toilet from returning odor | |
CN210684920U (en) | Integrated sanitary convenient pool | |
KR101229734B1 (en) | Drain trap for on-floor drainage piping system | |
CN203514464U (en) | Squatting pan | |
CN212053032U (en) | Drainage system capable of preventing water accumulation | |
CN103161204B (en) | Same floor drainage receiver | |
KR101342860B1 (en) | Drainpipe system | |
CN206545242U (en) | Water-bound component under a kind of integrated toilet bottom plate made by hand | |
CN218508571U (en) | Same-floor drainage system for toilet | |
CN220747184U (en) | Shower room drainage structure | |
CN215105788U (en) | Short-runner water replenishing type trap | |
CN214061834U (en) | Bathroom chassis drain pipe structure of plugging into | |
RU10406U1 (en) | SYSTEM OF THE SANITARY TECHNICAL DEVICE OF THE BUILDING | |
CN203188311U (en) | Same-floor drainage access point | |
CN211172222U (en) | Same-floor drainage backfill layer accumulated water drainage device | |
CN218264222U (en) | Subway station public area reaches from wall ditch primary and secondary floor drain arrangement structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210810 |
|
CF01 | Termination of patent right due to non-payment of annual fee |