CN213906164U - Movable cable bridge - Google Patents

Movable cable bridge Download PDF

Info

Publication number
CN213906164U
CN213906164U CN202022529062.5U CN202022529062U CN213906164U CN 213906164 U CN213906164 U CN 213906164U CN 202022529062 U CN202022529062 U CN 202022529062U CN 213906164 U CN213906164 U CN 213906164U
Authority
CN
China
Prior art keywords
flat plate
steel pipe
flat
assembly
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022529062.5U
Other languages
Chinese (zh)
Inventor
韦加宝
崔小勃
林育明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Jianfeng Electric Power Design Institute Co ltd
Original Assignee
Guangdong Jianfeng Electric Power Design Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Jianfeng Electric Power Design Institute Co ltd filed Critical Guangdong Jianfeng Electric Power Design Institute Co ltd
Priority to CN202022529062.5U priority Critical patent/CN213906164U/en
Application granted granted Critical
Publication of CN213906164U publication Critical patent/CN213906164U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a movable cable testing bridge, include: the supporting arm component comprises a first flat plate and a second flat plate, the supporting arm component is L-shaped and is formed by the first flat plate and the second flat plate, the bottom plate component is in buckled fit with the second flat plate, a plurality of screw holes are formed in the bottom plate component, the steel pipe component is fixedly arranged at the upper end of the first flat plate and comprises at least one steel pipe, the steel pipe is formed with a through hole for installing a cable, the movable cable bridge is convenient to install, the steel pipe component and the supporting arm component are flexible to configure, and the workload of workers is reduced.

Description

Movable cable bridge
Technical Field
The utility model relates to a cable testing bridge technical field, in particular to movable cable testing bridge.
Background
The cable bridge is divided into a groove type, a tray type, a ladder type, a grid type and other structures. The cable bridge frame is composed of a support, a support arm, an installation accessory and the like. The inner bridge frame of the building can be independently erected and also can be laid on various buildings and pipe rack supports, the characteristics of simple structure, attractive appearance, flexible configuration, convenient maintenance and the like are reflected, all parts need to be galvanized, and the inner bridge frame is arranged on an outdoor bridge frame outside the building.
The existing cable bridge frame requires large workload for installation, the installation mode is complex, and the labor intensity of workers is high.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to solve one of the technical problem that exists among the prior art at least, provide a movable cable testing bridge.
According to the utility model discloses an embodiment of the first aspect provides a movable cable testing bridge, include: the supporting arm assembly comprises a first flat plate and a second flat plate, the supporting arm assembly is L-shaped and comprises the first flat plate and the second flat plate, the bottom plate assembly is in buckled fit with the second flat plate, a plurality of screw holes are formed in the bottom plate assembly, the steel pipe assembly is fixedly arranged at the upper end of the first flat plate and comprises at least one steel pipe, and the steel pipe is provided with a through hole for installing a cable.
Has the advantages that: the movable cable tray comprises: the supporting arm component comprises a first flat plate and a second flat plate, the supporting arm component is L-shaped and is formed by the first flat plate and the second flat plate, the bottom plate component is in buckled fit with the second flat plate, a plurality of screw holes are formed in the bottom plate component, the steel pipe component is fixedly arranged at the upper end of the first flat plate and comprises at least one steel pipe, the steel pipe is formed with a through hole for installing a cable, the movable cable bridge is convenient to install, the steel pipe component and the supporting arm component are flexible to configure, and the workload of workers is reduced.
According to the utility model discloses the embodiment of the first aspect movable cable testing bridge, each the steel pipe all adopts earth connection ground connection setting.
According to the utility model discloses movable cable testing bridge, movable cable testing bridge still include the band steel, the band steel compresses tightly on the steel pipe assembly, the band steel with first flat board passes through bolted connection.
According to the utility model discloses the embodiment of the first aspect movable cable testing bridge, the steel pipe is the galvanized steel pipe, the band steel is the galvanized band steel, the bottom plate subassembly is the zinc-plated bottom plate subassembly.
According to the utility model discloses the first aspect embodiment movable cable testing bridge, the bottom plate subassembly is provided with the recess, the second dull and stereotyped with the recess buckle is fixed.
Drawings
The present invention will be further described with reference to the accompanying drawings and examples;
FIG. 1 is an installation front view of a movable cable tray according to an embodiment of the present invention;
FIG. 2 is a side view of the movable cable tray according to an embodiment of the present invention;
FIG. 3 is a side view of a base plate assembly according to an embodiment of the present invention;
FIG. 4 is a top view of a base plate assembly according to an embodiment of the present invention;
FIG. 5 is a side view of a bracket arm assembly according to an embodiment of the present invention;
fig. 6 is a cross-sectional view of a bracket arm assembly according to an embodiment of the present invention.
Detailed Description
This section will describe in detail the embodiments of the present invention, preferred embodiments of the present invention are shown in the attached drawings, which are used to supplement the description of the text part of the specification with figures, so that one can intuitively and vividly understand each technical feature and the whole technical solution of the present invention, but they cannot be understood as the limitation of the protection scope of the present invention.
In the description of the present invention, it should be understood that the orientation or positional relationship indicated with respect to the orientation description, such as up, down, front, rear, left, right, etc., is based on the orientation or positional relationship shown in the drawings, and is only for convenience of description and simplification of description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
In the description of the present invention, a plurality of means are one or more, a plurality of means are two or more, and the terms greater than, less than, exceeding, etc. are understood as not including the number, and the terms greater than, less than, within, etc. are understood as including the number. If the first and second are described for the purpose of distinguishing technical features, they are not to be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated or implicitly indicating the precedence of the technical features indicated.
In the description of the present invention, unless there is an explicit limitation, the words such as setting, installation, connection, etc. should be understood in a broad sense, and those skilled in the art can reasonably determine the specific meanings of the above words in combination with the specific contents of the technical solution.
Referring to fig. 1 to 6, a movable cable tray includes: the bracket arm assembly 100, bottom plate assembly 200 and steel pipe assembly 300, bracket arm assembly 100 includes first flat board 110 and second flat board 120, first flat board 110 and the dull and stereotyped 120 constitution of second are the bracket arm assembly 100 of L type, bottom plate assembly 200 and second flat board 120 snap-fit, be provided with a plurality of screw holes on the bottom plate assembly 200, steel pipe assembly 300 is fixed to be set up in first flat board 110 upper end, steel pipe assembly 300 includes at least one steel pipe, the steel pipe is formed with the through-hole that is used for installing the cable. The bottom plate assembly 200 is fixed to the deck or the river bank by expansion bolts.
Referring to fig. 1 to 6, a movable cable bridge comprises a bracket arm assembly 100, a base plate assembly 200, a steel pipe assembly 300 and a flat steel 400, wherein the bracket arm assembly 100 comprises a first flat plate 110 and a second flat plate 120, the first flat plate 110 and the second flat plate 120 form the L-shaped bracket arm assembly 100, the base plate assembly 200 is in snap fit with the second flat plate 120, a plurality of screw holes are formed in the base plate assembly 200, the flat steel 400 is pressed on the steel pipe assembly 300, and the flat steel 400 is connected with the first flat plate 110 through bolts. The flat bar 400 is bolted to the first plate 110 to form a frame for fastening the steel pipe assembly 300. So that each steel pipe is fixed with the bracket arm assembly 100 by bolts and flat steel. The cable should be fixed by nylon tie after laying. The corner part of the bridge frame should meet the requirement that the bending radius of the cable is not less than 10 times of the outer diameter of the cable.
It will be appreciated that the steel pipe is a galvanized steel pipe, the flat steel 400 is a galvanized flat steel, and the floor assembly 200 is a galvanized floor assembly.
Specifically, each galvanized steel pipe should be provided with a reliable electrical connection ground. The grounding wire can be grounded by adopting a flat iron.
In some of these embodiments, a mobile cable tray, comprises: the bracket arm assembly 100 comprises a first flat plate 110 and a second flat plate 120, the bracket arm assembly 100 is an L-shaped bracket arm assembly 100 consisting of the first flat plate 110 and the second flat plate 120, the base plate assembly 200 is in snap fit with the second flat plate 120, the base plate assembly 200 is provided with a groove 210, the second flat plate 120 is fixed with the groove 210 in a snap fit mode, and the installation and the disassembly are very convenient.
The embodiments of the present invention have been described in detail with reference to the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made without departing from the spirit of the present invention within the knowledge of those skilled in the art.

Claims (5)

1. A movable cable tray, comprising:
the support arm assembly comprises a first flat plate and a second flat plate, and the first flat plate and the second flat plate form an L-shaped support arm assembly;
the bottom plate component is buckled and matched with the second flat plate, and a plurality of screw holes are formed in the bottom plate component;
the steel pipe assembly is fixedly arranged at the upper end of the first flat plate and comprises at least one steel pipe, and through holes for installing cables are formed in the steel pipes.
2. The mobile cable tray of claim 1, wherein: each steel pipe all adopts earth connection ground setting.
3. The mobile cable tray of claim 1, wherein: the movable cable bridge further comprises flat steel, the flat steel is tightly pressed on the steel pipe assembly, and the flat steel is connected with the first flat plate through bolts.
4. The mobile cable tray of claim 3, wherein: the steel pipe is a galvanized steel pipe, the flat steel is a galvanized flat steel, and the bottom plate assembly is a galvanized bottom plate assembly.
5. The mobile cable tray of claim 1, wherein: the bottom plate assembly is provided with a groove, and the second flat plate is fixed with the groove in a buckling mode.
CN202022529062.5U 2020-11-04 2020-11-04 Movable cable bridge Active CN213906164U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022529062.5U CN213906164U (en) 2020-11-04 2020-11-04 Movable cable bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022529062.5U CN213906164U (en) 2020-11-04 2020-11-04 Movable cable bridge

Publications (1)

Publication Number Publication Date
CN213906164U true CN213906164U (en) 2021-08-06

Family

ID=77117135

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022529062.5U Active CN213906164U (en) 2020-11-04 2020-11-04 Movable cable bridge

Country Status (1)

Country Link
CN (1) CN213906164U (en)

Similar Documents

Publication Publication Date Title
US8511007B2 (en) Solar support structure
CN210529958U (en) Civil engineering is with assembled steel construction concreting building structure exempts from
US6237888B1 (en) Antenna mounting system
CN213906164U (en) Movable cable bridge
KR20120004130U (en) Device for branching off cable tray
CN212799185U (en) Multi-angle adjustable car guide rail bracket
CN210430816U (en) Horizontal tee joint of cable bridge
CN210628982U (en) Fireproof plastic-sprayed cable bridge
CN210517676U (en) Corner branching device for cable bridge
CN201838952U (en) Branch groove connecting piece of cable groove
CN202550163U (en) Socket outlet and switch conveniently installed on wall body
CN214249489U (en) Lamp mounting structure with longitudinal and transverse pressing plates
KR20170120965A (en) Bracket for utility pole
CN201708491U (en) Cabling rack of machine room
CN209402136U (en) Lightning-arrest line bracket
CN209233365U (en) A kind of T shape gantry
CN218815580U (en) Communication system and photovoltaic module
CN213018389U (en) Galvanized bearing pedal for electric power facility
CN211480798U (en) Groove type bridge convenient to insert
CN220152035U (en) Bracket for installing comprehensive pipeline
CN218335077U (en) Lean on wall chute installing support
CN212163211U (en) Integration threading termination and applied device's photovoltaic support
CN221929219U (en) Anti-seismic structure of cable bridge
CN220232641U (en) Sign board mounting seat based on channel steel cross rod
CN209958547U (en) Wind-resistant sound barrier

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant