CN213867788U - Building concrete pipe pile - Google Patents

Building concrete pipe pile Download PDF

Info

Publication number
CN213867788U
CN213867788U CN202021534671.3U CN202021534671U CN213867788U CN 213867788 U CN213867788 U CN 213867788U CN 202021534671 U CN202021534671 U CN 202021534671U CN 213867788 U CN213867788 U CN 213867788U
Authority
CN
China
Prior art keywords
baffle
plate
wall
tubular pile
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021534671.3U
Other languages
Chinese (zh)
Inventor
李张锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Hujia Housing Industry Co ltd
Original Assignee
Zhejiang Hujia Housing Industry Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Hujia Housing Industry Co ltd filed Critical Zhejiang Hujia Housing Industry Co ltd
Priority to CN202021534671.3U priority Critical patent/CN213867788U/en
Application granted granted Critical
Publication of CN213867788U publication Critical patent/CN213867788U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a building concrete pipe pile, including first tubular pile and second tubular pile, the right side of first tubular pile is equipped with the second tubular pile, fixing device is installed to the outer wall on first tubular pile right side. This building concrete pipe pile, through the sleeve, mutually support between baffle and the circular block isotructure, can install two tubular piles in the sleeve fast, thereby the time has been practiced thrift, through first bolt, mutually support between baffle and the circular block isotructure, can fix first end board and second end board through first bolt, play limiting displacement to the circular block through the baffle simultaneously, through the arc, the L shaped plate, torque spring, mutually support between second bolt and the circular block isotructure, can make the L shaped plate support the baffle tightly through torque spring's elasticity performance and third recess, it is fixed with diaphragm and baffle simultaneously through the second bolt, thereby the result of use of this device has been improved.

Description

Building concrete pipe pile
Technical Field
The utility model relates to a building technical field specifically is a building concrete pipe pile.
Background
The concrete pile is made of concrete (including common reinforced concrete and prestressed concrete), has the advantages of saving wood and steel, durability, low cost and the like, is widely used in the foundation engineering of hydraulic buildings, industrial buildings, civil buildings and bridges, is also commonly used for the skid resistance or water resistance of side slope and foundation pit support, and is usually used in a plurality of sections, so that two tubular piles need to be connected, for example, a concrete precast tubular pile with the patent number of CN 207685821U comprises a tubular pile body, one end of the tubular pile body is provided with a splicing part, the other end of the tubular pile body is provided with a socket part matched with the splicing part, the socket part is provided with a plurality of connecting holes, the splicing part is provided with connecting pieces matched with the connecting holes respectively, although two tubular piles can be connected in the prior art, but too troublesome during the installation, can't accomplish quick installation, two tubular piles's stability is not good among the prior art simultaneously.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building concrete tubular pile to although the prior art that proposes in solving above-mentioned background art can be connected two tubular piles, but too troublesome during the installation, can't accomplish the problem of quick installation.
In order to achieve the above object, the utility model provides a following technical scheme: a building concrete pipe pile comprises a first pipe pile and a second pipe pile, wherein the second pipe pile is arranged on the right side of the first pipe pile, and a fixing device is arranged on the outer wall of the right side of the first pipe pile;
the fixing device comprises a first end plate, a second end plate, a sleeve, a first groove, a first bolt and a through hole;
the left side of first end board links to each other with first tubular pile is fixed, the right side of first end board is equipped with second end board, the right side of second end board links to each other with the second tubular pile is fixed, the sleeve is installed with the outer wall of second end board to first end board, telescopic inside processing has a plurality of first recesses, first recess department inner wall respectively with the outer wall clearance fit of first end board with second end board, the sleeve links to each other with first end board and second end board screw thread respectively through a plurality of first bolts, a plurality of through-holes have been seted up to telescopic upper and lower both sides outer wall.
Preferably, the first end plate and the second end plate are identical in size, so that the stability of the first tubular pile and the second tubular pile can be improved.
Preferably, a limiting device is arranged inside the first groove;
the limiting device comprises an arc-shaped plate, a second groove, a vertical plate, a circular block, a baffle plate and a third groove;
control a plurality of arcs link to each other with the outer wall of first tubular pile and second tubular pile is fixed respectively, the outside processing of arc has a plurality of second recesses, the rigid coupling has the riser in the middle of the outside of arc, the outside rigid coupling of riser has circular block, the baffle is all installed to the left and right sides of circular block, the outside outer wall processing of baffle has the third recess, the outer wall of baffle respectively with second groove department inner wall and through-hole department inner wall clearance fit, can play limiting displacement to circular block through the baffle.
Preferably, control the baffle uses the mid point of circular block to be the symmetric distribution as the center, can prevent like this that circular block from driving first tubular pile and second tubular pile and remove.
Preferably, the left baffle and the right baffle are arranged in parallel, so that the limiting effect of the baffles on the round block can be improved.
Preferably, an elastic device is installed at the outer side of the third groove;
the elastic device comprises an L-shaped plate, a transverse plate, a second bolt and a torsion spring;
from top to bottom the outer wall of a plurality of L shaped plates and the inner wall clearance fit of third recess, the outside of L shaped plate is rotated through the pivot and is connected with the diaphragm, the diaphragm passes through the second bolt and links to each other with the baffle screw thread, a plurality of torque spring are installed to the inboard of diaphragm, torque spring's both sides are fixed with L shaped plate and diaphragm respectively and link to each other, and elasticity performance through torque spring can make the L shaped plate support the baffle tightly.
Preferably, the transverse plate and the baffle plates are vertically arranged, so that two adjacent baffle plates can be on the same horizontal line.
Preferably, the width dimension of the L-shaped plate is smaller than that of the cross plate, so that the L-shaped plate can be rotated more easily.
Compared with the prior art, the beneficial effects of the utility model are that: this building concrete tubular pile through mutually supporting between structures such as sleeve, first tubular pile, second tubular pile, baffle and circular piece, can install two tubular piles in the sleeve fast to the time has been practiced thrift.
Through mutually supporting between first end board, second end board, first bolt, baffle and circular piece isotructure, can fix first end board and second end board through first bolt, play limiting displacement, further improvement fixed effect to circular piece through the baffle simultaneously.
Through mutually supporting between structures such as arc, L shaped plate, torsion spring, second bolt and diaphragm, can make the L shaped plate support the baffle tightly through torsion spring's elasticity performance and third recess, it is fixed with diaphragm and baffle through the second bolt simultaneously to the result of use of this device has been improved.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the first bolt, the first end plate and the sleeve of FIG. 1;
FIG. 3 is a schematic view of the structure of FIG. 1 at the arc, circle and riser;
fig. 4 is a schematic structural view of the torsion spring, the cross plate and the baffle plate in fig. 1.
In the figure: 1. first tubular pile, 2, second tubular pile, 3, fixing device, 301, first end board, 302, second end board, 303, sleeve, 304, first recess, 305, first bolt, 306, through-hole, 4, stop device, 401, arc, 402, second recess, 403, riser, 404, circular piece, 405, baffle, 406, third recess, 5, elastic device, 501, L shaped plate, 502, diaphragm, 503, second bolt, 504, torsion spring.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a building concrete pipe pile comprises a first pipe pile 1 and a second pipe pile 2, the right side of the first pipe pile 1 is provided with the second pipe pile 2, the outer wall of the right side of the first pipe pile 1 is provided with a fixing device 3, the fixing device 3 comprises a first end plate 301, a second end plate 302, a sleeve 303, a first groove 304, a first bolt 305 and a through hole 306, the left side of the first end plate 301 is fixedly connected with the first pipe pile 1, the right side of the first end plate 301 is provided with the second end plate 302, the right side of the second end plate 302 is fixedly connected with the second pipe pile 2, the first end plate 301 and the second end plate 302 are both round iron cakes cast by steel, the outer walls of the first end plate 301 and the second end plate 302 are provided with the sleeve 303, the interior of the sleeve 303 is processed with 2 first grooves 304, the inner wall of the first groove 304 is respectively in clearance fit with the outer walls of the first end plate 301 and the second end plate 302, the first end plate 301 and the second end plate 302 can move at the first groove 304, the sleeve 303 is respectively in threaded connection with the first end plate 301 and the second end plate 302 through 4 first bolts 305, the sleeve 303 is fixed with the first end plate 301 and the second end plate 302 through the first bolts 305, 4 through holes 306 are formed in the outer walls of the upper side and the lower side of the sleeve 303, and the first end plate 301 and the second end plate 302 are completely the same in size.
The limiting device 4 is arranged in the first groove 304, the limiting device 4 comprises an arc-shaped plate 401, a second groove 402 and a vertical plate 403, circular block 404, baffle 405 and third recess 406, it is fixed continuous with the outer wall of first tubular pile 1 and second tubular pile 2 respectively to control 2 arc 401, arc 401's outside processing has 2 second recesses 402, the rigid coupling has riser 403 in the middle of the outside of arc 401, riser 403's outside rigid coupling has circular block 404, baffle 405 is all installed to the left and right sides of circular block 404, baffle 405's outside outer wall processing has third recess 406, baffle 405's outer wall respectively with second recess 402 department inner wall and through-hole 306 department inner wall clearance fit, baffle 405 can remove in second recess 402 department and through-hole 306 department, it is the symmetric distribution to control two adjacent baffles 405 use the mid point of circular block 404 as the center, control baffle 405 for parallel arrangement.
The outer side of the third groove 406 is provided with an elastic device 5, the elastic device 5 comprises an L-shaped plate 501, a transverse plate 502, a second bolt 503 and a torsion spring 504, the outer walls of the upper and lower 4L-shaped plates 501 are in clearance fit with the inner wall of the third groove 406, the L-shaped plate 501 can move at the third groove 406, the outer side of the L-shaped plate 501 is rotatably connected with the transverse plate 502 through a rotating shaft, the L-shaped plate 501 can rotate at the transverse plate 502 through the rotating shaft, the transverse plate 502 is in threaded connection with the baffle 405 through the second bolt 503, the transverse plate 502 can be fixed with the baffle 405 through the second bolt 503, the inner side of the transverse plate 502 is provided with 2 torsion springs 504, and two sides of each torsion spring 504 are respectively fixedly connected with the L-shaped plate 501 and the transverse plate 502, when the L-shaped plate 501 rotates away from the stop plate 405, the torsion spring 504 is in a stretched state, the horizontal plate 502 is perpendicular to the stop plate 405, and the width of the L-shaped plate 501 is smaller than that of the horizontal plate 502.
When an operator needs to use the building concrete pipe pile, firstly, the operator drives the first end plate 301 and the second end plate 302 to enter the first groove 304 of the sleeve 303 respectively by the first pipe pile 1 and the second pipe pile 2, fixes the sleeve 303 with the first end plate 301 and the second end plate 302 by the first bolt 305, enters the baffle 405 into the second groove 402 of the arc plate 401 through the through hole 306 of the sleeve 303, enables the adjacent two baffles 405 to limit the circular block 404, rotates the L-shaped plate 501, elastically deforms the torsion spring 504 through the L-shaped plate 501, installs the transverse plate 502 on the outer wall of the baffle 405, loosens the L-shaped plate 501, enables the L-shaped plate 501 to enter the third groove 406 of the baffle 405, enables the L-shaped plate 501 to clamp the baffle 405 through the elastic property of the torsion spring 504 and the third groove 406, and fixes the transverse plate 502 and the baffle 405 by the second bolt 503, thus, the purpose of improving the connection stability of the first tubular pile 1 and the second tubular pile 2 is achieved.
In the description of the present invention, it is to be understood that the terms "coaxial", "bottom", "one end", "top", "middle", "other end", "upper", "one side", "top", "inner", "front", "center", "both ends", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
In the present invention, unless otherwise expressly stated or limited, the terms "mounted," "disposed," "connected," "fixed," "screwed" and the like are to be construed broadly, e.g., as meaning fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; they may be directly connected or indirectly connected through an intermediate medium, and may be connected through the inside of two elements or in an interaction relationship between two elements, unless otherwise specifically defined, and the specific meaning of the above terms in the present invention will be understood by those skilled in the art according to specific situations.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. The utility model provides a building concrete pipe pile, includes first tubular pile (1) and second tubular pile (2), the right side of first tubular pile (1) is equipped with second tubular pile (2), its characterized in that: a fixing device (3) is arranged on the outer wall of the right side of the first tubular pile (1);
the fixing device (3) comprises a first end plate (301), a second end plate (302), a sleeve (303), a first groove (304), a first bolt (305) and a through hole (306);
the left side of first end board (301) is fixed continuous with first tubular pile (1), the right side of first end board (301) is equipped with second end board (302), the right side of second end board (302) is fixed continuous with second tubular pile (2), sleeve (303) are installed to the outer wall of first end board (301) and second end board (302), the inside processing of sleeve (303) has a plurality of first recess (304), first recess (304) locate the inner wall respectively with the outer wall clearance fit of first end board (301) and second end board (302), sleeve (303) link to each other with first end board (301) and second end board (302) screw thread respectively through a plurality of first bolts (305), a plurality of through-holes (306) have been seted up to the upper and lower both sides outer wall of sleeve (303).
2. The building concrete pipe pile of claim 1, wherein: the first end head plate (301) and the second end head plate (302) are identical in size.
3. The building concrete pipe pile of claim 1, wherein: a limiting device (4) is arranged in the first groove (304);
the limiting device (4) comprises an arc-shaped plate (401), a second groove (402), a vertical plate (403), a circular block (404), a baffle (405) and a third groove (406);
control a plurality of arcs (401) link to each other with the outer wall of first tubular pile (1) and second tubular pile (2) is fixed respectively, the outside processing of arc (401) has a plurality of second recesses (402), the rigid coupling has riser (403) in the middle of the outside of arc (401), the outside rigid coupling of riser (403) has circular block (404), baffle (405) are all installed to the left and right sides of circular block (404), the outside outer wall processing of baffle (405) has third recess (406), the outer wall of baffle (405) locates inner wall clearance fit with second recess (402) respectively and through-hole (306).
4. The building concrete pipe pile of claim 3, wherein: the left baffle plate and the right baffle plate (405) are symmetrically distributed by taking the middle point of the circular block (404) as the center.
5. The building concrete pipe pile of claim 3, wherein: the left baffle plate and the right baffle plate (405) are arranged in parallel.
6. The building concrete pipe pile of claim 3, wherein: an elastic device (5) is arranged on the outer side of the third groove (406);
the elastic device (5) comprises an L-shaped plate (501), a transverse plate (502), a second bolt (503) and a torsion spring (504);
from top to bottom the outer wall of a plurality of L shaped plate (501) and third recess (406) department inner wall clearance fit, the outside of L shaped plate (501) is rotated through the pivot and is connected with diaphragm (502), diaphragm (502) link to each other with baffle (405) screw thread through second bolt (503), a plurality of torsion spring (504) are installed to the inboard of diaphragm (502), the both sides of torsion spring (504) are fixed continuous with L shaped plate (501) and diaphragm (502) respectively.
7. The building concrete pipe pile of claim 6, wherein: the transverse plate (502) and the baffle (405) are vertically arranged.
8. The building concrete pipe pile of claim 6, wherein: the width dimension of the L-shaped plate (501) is smaller than that of the transverse plate (502).
CN202021534671.3U 2020-07-29 2020-07-29 Building concrete pipe pile Expired - Fee Related CN213867788U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021534671.3U CN213867788U (en) 2020-07-29 2020-07-29 Building concrete pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021534671.3U CN213867788U (en) 2020-07-29 2020-07-29 Building concrete pipe pile

Publications (1)

Publication Number Publication Date
CN213867788U true CN213867788U (en) 2021-08-03

Family

ID=77033879

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021534671.3U Expired - Fee Related CN213867788U (en) 2020-07-29 2020-07-29 Building concrete pipe pile

Country Status (1)

Country Link
CN (1) CN213867788U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114657976A (en) * 2022-04-19 2022-06-24 北京首钢建设集团有限公司 Prestressed steel pipe concrete pile and construction process thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114657976A (en) * 2022-04-19 2022-06-24 北京首钢建设集团有限公司 Prestressed steel pipe concrete pile and construction process thereof
CN114657976B (en) * 2022-04-19 2024-01-05 北京首钢建设集团有限公司 Prestressed concrete-filled steel tube pile and construction process thereof

Similar Documents

Publication Publication Date Title
CN108978866B (en) Beam-column connection node
CN213867788U (en) Building concrete pipe pile
CN109537600B (en) Assembled all-steel crown beam for foundation pit enclosure wall
CN218440059U (en) Novel chain staple bolt
CN212865961U (en) Detachable building foundation pit supporting beam
CN210764031U (en) Steel structure supporting beam
CN211773699U (en) Steel support four-way joint
CN221072653U (en) Foundation pit steel pipe pile structure
CN210597277U (en) Spliced concrete pile
CN218067496U (en) Pseudo-static test loading device of assembled tubular pier
CN214006025U (en) Beam structure for assembly type building
KR200381406Y1 (en) The support of a mold
CN212956953U (en) Shaped column for building steel structure
CN216866181U (en) Rigidity-adjustable column-column joint connection structure for layered assembly type steel structure
CN210946843U (en) Arch ring support piece for grouted arch slope protection
CN109024616B (en) Joint for connecting steel pipe support and section steel
CN220888964U (en) Corrosion-resistant and wear-resistant steel structural member
CN215907077U (en) Connecting structure capable of replacing coupling beam damper
CN220301355U (en) Side slope reinforcing and fixing device for constructional engineering
CN219637911U (en) Prefabricated tubular pile supporting and connecting device
CN213267975U (en) Foundation pile for road and bridge construction
CN215165743U (en) Hydraulic engineering cofferdam reinforced structure
CN217517593U (en) Road repairing foundation pit reinforcing structure
CN220301844U (en) Reinforcement tool for masonry corner constructional column
CN210658457U (en) Assembled three-way cable work well

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210803