Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022437890.6U
Other languages
Chinese (zh)
Inventor
王玉艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202022437890.6U priority Critical patent/CN213837635U/en
Application granted granted Critical
Publication of CN213837635U publication Critical patent/CN213837635U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a high-stability platform for construction of building projects, which comprises an outer lifting plate, wherein a first lifting plate, a second lifting plate and an inner lifting plate are sequentially arranged in the outer lifting plate, the inner sides of the outer lifting plate and the first lifting plate are symmetrically provided with two groups of racks, the outer sides of the second lifting plate and the inner lifting plate are symmetrically provided with two groups of racks, a first lifting gear is arranged in the first lifting plate in a penetrating way, a second lifting gear is arranged in the second lifting plate in a penetrating way, and a bearing plate is arranged on the inner lifting plate; the bottom of first lifter plate is equipped with the bottom plate, wears to be equipped with the lead screw on the bottom plate, and the lead screw bottom is equipped with first adjusting gear, and first adjusting gear has the second adjusting gear down, and the wheel is shaken in the connection regulation of second adjusting gear. The utility model discloses when using, rotate the regulation and shake the wheel, make the bearing plate go up and down, let the staff when using, can adjust the construction height at will, improved staff's work efficiency.

Description

High-stability platform for building engineering construction
Technical Field
The utility model relates to a construction platform technical field is built in the room specifically is a platform is used in engineering construction is built in high room of stability.
Background
Along with the sustainable development of economy, the urbanization level of China is higher at present, when construction sites are constructed or decoration operation is carried out, auxiliary tools need to be built to assist workers in finishing painting of corresponding walls, and the traditional method is to assist the workers in finishing construction by building scaffolds.
However, the height of the traditional scaffold cannot be adjusted, workers can only construct at a specific height during construction, and if the heights are different, the scaffold needs to be replaced, so that the construction progress is influenced.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art, the utility model provides a platform is used in engineering construction is built in room that stability is high to traditional scaffold can not highly adjust it among the solution prior art, and the staff can only be under construction at specific height when the construction, if highly when different, then need change the scaffold, thereby influence the technical problem of construction progress.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes:
a high-stability platform for building engineering construction comprises an outer lifting plate, wherein a first lifting plate, a second lifting plate and an inner lifting plate are sequentially arranged in the outer lifting plate, two groups of racks are symmetrically arranged on the inner sides of the outer lifting plate and the first lifting plate, two groups of racks are symmetrically arranged on the outer sides of the second lifting plate and the inner lifting plate, rectangular through grooves are formed in the first lifting plate and the second lifting plate, pin shafts are arranged in the rectangular through grooves, a first lifting gear is arranged in the first lifting plate in a penetrating manner, a second lifting gear is arranged in the second lifting plate in a penetrating manner, the first lifting gear is meshed with the racks arranged on the inner side of the outer lifting plate and the racks arranged on the outer side of the second lifting plate, the second lifting gear is meshed with the racks arranged on the inner side of the first lifting plate and the racks arranged on the outer side of the inner lifting plate, the inner lifting plate is provided with a bearing plate; the bottom of first lifter plate is provided with the bottom plate, set up threaded hole on the bottom plate, threaded hole wears to be equipped with the lead screw, the bottom of lead screw is provided with first adjusting gear, be provided with second adjusting gear under the first adjusting gear, second adjusting gear is connected with the regulation and shakes the wheel.
As the utility model discloses an optimal technical scheme, two sets of T type spouts have all been seted up to the inboard of outer lifter plate, first lifter plate, second lifter plate, one side of first lifter plate, second lifter plate and lifter plate all is provided with two sets of T type sliders, T type slider slidable card is established in the T type spout.
As the utility model discloses a preferred technical scheme, the second adjusting gear passes through the connecting rod and connects the regulation shakes the wheel, the regulation is shaken and is provided with the handle on the wheel.
As the utility model discloses an optimized technical scheme, be provided with curb plate and guardrail on the bearing plate.
As the utility model discloses a preferred technical scheme, be provided with the bearing frame under the outer lifter plate, be provided with fixed stabilizer blade under the four corners of bearing frame.
As the utility model discloses a preferred technical scheme, the bottom of outer lifter plate is provided with the guard box, first adjusting gear with second adjusting gear all sets up in the guard box, the through-hole has been seted up to one side of guard box, the connecting rod is worn to establish in the through-hole.
As an optimal technical scheme of the utility model, the top of lead screw is provided with the stopper, the both sides of rack are provided with spacing.
The utility model provides a high platform for construction of building engineering of stability possesses following beneficial effect:
the utility model discloses when using, rotate the regulation and shake the wheel, second adjusting gear rotates, first adjusting gear meshes with second adjusting gear mutually, thereby make first adjusting gear, the lead screw that sets up on the first adjusting gear rotates, the lead screw cooperatees with the screw hole that the bottom of first lifter plate set up, thereby make first lifter plate go up and down, it goes up and down to make interior lifter plate, welded fastening is passed through at the top of bearing plate and interior lifter plate, thereby make the bearing plate go up and down, let the staff when using, can adjust the construction height at will, staff's work efficiency has been improved.
Drawings
FIG. 1 is a schematic view of a three-dimensional structure of a high-stability platform for building construction of the present invention;
FIG. 2 is an exploded view of the high stability platform for building construction of the present invention;
fig. 3 is the utility model relates to a high platform elevation view is used in construction of building engineering of stability.
In the figure: 1. an outer lifter plate; 2. a rack; 3. a first lifter plate; 4. a rectangular through groove; 5. a pin shaft; 6. A first lifting gear; 7. a second lifter plate; 8. a second lifting gear; 9. an inner lifter plate; 10. a base plate; 11. a threaded hole; 12. a screw rod; 13. a first adjusting gear; 14. a second adjusting gear; 15. a connecting rod; 16. adjusting the rocking wheel; 17. a T-shaped chute; 18. a T-shaped slider; 19. a bearing plate; 20. a bearing frame; 21. a fixed leg; 22. a protection box; 23. a through hole; 24. a handle; 25. a limiting block; 26. a side plate; 27. a guardrail; 28. and (5) a limiting strip.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1 to 3, the present invention provides a technical solution:
the utility model provides a high platform is used in construction of building engineering of stability, includes outer lifter plate 1, first lifter plate 3, second lifter plate 7 and interior lifter plate 9 have set gradually in the outer lifter plate 1, outer lifter plate 1 with the inboard symmetry of first lifter plate 3 is provided with two sets of racks 2, second lifter plate 7 with the outside symmetry of interior lifter plate 9 is provided with two sets of racks 2, first lifter plate 3 with rectangular through groove 4 has all been seted up on the second lifter plate 7, be provided with round pin axle 5 in the rectangular through groove 4, wear to be equipped with first lifting gear 6 in the first lifter plate 3, wear to be equipped with second lifting gear 8 in the second lifter plate 7, first lifting gear 6 with outer lifter plate 1 inboard sets up rack 2 and second lifter plate 7 outside set up rack 2 meshes mutually, second lifting gear 8 with first lifter plate 3 inboard sets up rack 2 and interior lifter plate 9 outside The arranged racks 2 are meshed, and a bearing plate 19 is arranged on the inner lifting plate 9; the bottom of first lifter plate 3 is provided with bottom plate 10, set up threaded hole 11 on the bottom plate 10, lead screw 12 is worn to be equipped with in the threaded hole 11, the bottom of lead screw 12 is provided with first adjusting gear 13, be provided with second adjusting gear 14 under the first adjusting gear 13, second adjusting gear 14 is connected with the regulation and shakes wheel 16.
When the platform for building engineering construction is used, the rocking wheel 16 is rotated and adjusted, the second adjusting gear 14 is rotated, the first adjusting gear 13 is meshed with the second adjusting gear 14, so that the first adjusting gear 13 is rotated, the screw rod 12 arranged on the first adjusting gear 13 is rotated, the screw rod 12 is matched with the threaded hole 11 arranged at the bottom of the first lifting plate 3, so that the first lifting plate 3 is lifted, the outer lifting plate 1 is fixed, the first lifting gear 6 is meshed with the rack 2 arranged at the inner side of the outer lifting plate 1 and the rack 2 arranged at the outer side of the second lifting plate 7, the first lifting gear 6 is rotated, the first lifting gear 6 drives the second lifting plate 7 to be lifted, the second lifting plate 7 is lifted, the second lifting gear 8 is meshed with the rack 2 arranged at the inner side of the first lifting plate 3 and the rack 2 arranged at the outer side of the inner lifting plate 9, second lifting gear 8 rotates to lifter plate 9 goes up and down in the drive, and welded fastening is passed through with the top of interior lifter plate 9 to bearing plate 19 goes up and down, makes bearing plate 19 go up and down, lets the staff when using, can adjust the construction height at will, has improved staff's work efficiency.
Referring to fig. 1 to 3, two sets of T-shaped sliding grooves 17 are formed in the inner sides of the outer lifting plate 1, the first lifting plate 3 and the second lifting plate 7, two sets of T-shaped sliding blocks 18 are arranged on one sides of the first lifting plate 3, the second lifting plate 7 and the lifting plate 9, the T-shaped sliding blocks 18 are slidably clamped in the T-shaped sliding grooves 17, and the T-shaped sliding grooves 17 and the T-shaped sliding blocks 18 are arranged, so that the platform for building engineering construction can lift more stably when in use.
Referring to fig. 1 to 3, the second adjusting gear 14 is connected to the adjusting rocking wheel 16 through a connecting rod 15, and a handle 24 is disposed on the adjusting rocking wheel 16, so that the handle 24 is more convenient for a worker to adjust the height.
Referring to fig. 1 to 3, the bearing plate 19 is provided with a side plate 26 and a guardrail 27, and the side plate 26 and the guardrail 27 ensure the safety of the worker, so that the worker cannot easily fall off.
Referring to fig. 1 to 3, a bearing frame 20 is disposed under the outer lifting plate 1, fixing support legs 21 are disposed under four corners of the bearing frame 20, and the platform for building engineering construction is more firmly and stably fixed by the aid of the bearing frame 20 and the fixing support legs 21.
Referring to fig. 1 to 3, a protection box 22 is disposed at the bottom of the outer lifting plate 1, the first adjusting gear 13 and the second adjusting gear 14 are both disposed in the protection box 22, a through hole 23 is disposed at one side of the protection box 22, the connecting rod 15 is disposed in the through hole 23 in a penetrating manner, and the protection box 22 prolongs the service life of the first adjusting gear 13 and the second adjusting gear 14.
Referring to fig. 1 to 3, a limiting block 25 is arranged at the top of the screw rod 12, limiting strips 28 are arranged on two sides of the rack 2, and the limiting block 25 and the limiting strips 28 prevent the gear and the screw rod 12 from sliding out when the height of a worker is adjusted, so that the service life of the platform for building engineering construction is prolonged.
To sum up, when the platform for building construction is used, the regulating rocking wheel 16 is rotated, the second regulating gear 14 is rotated, the first regulating gear 13 is meshed with the second regulating gear 14, so that the first regulating gear 13 is rotated, the screw rod 12 arranged on the first regulating gear 13 is rotated, the screw rod 12 is matched with the threaded hole 11 arranged at the bottom of the first lifting plate 3, so that the first lifting plate 3 is lifted, the outer lifting plate 1 is fixed, the first lifting gear 6 is meshed with the rack 2 arranged at the inner side of the outer lifting plate 1 and the rack 2 arranged at the outer side of the second lifting plate 7, the first lifting gear 6 is rotated, the first lifting gear 6 drives the second lifting plate 7 to lift, the second lifting plate 7 is lifted, the second lifting gear 8 is meshed with the rack 2 arranged at the inner side of the first lifting plate 3 and the rack 2 arranged at the outer side of the inner lifting plate 9, second lifting gear 8 rotates to lifter plate 9 goes up and down in the drive, and welded fastening is passed through with the top of interior lifter plate 9 to bearing plate 19 goes up and down, makes bearing plate 19 go up and down, lets the staff when using, can adjust the construction height at will, has improved staff's work efficiency. Two sets of T type spout 17 have all been seted up to outer lifter plate 1, first lifter plate 3, the inboard of second lifter plate 7, one side of lifter plate 9 all is provided with two sets of T type sliders 18 in first lifter plate 3, the second lifter plate 7, T type slider 18 slidable card is established in T type spout 17, the T type spout 17 and the T type slider 18 that set up let this platform for the building engineering construction when using, go up and down more steadily. The bearing plate 19 is provided with a side plate 26 and a guardrail 27, and the safety of workers is guaranteed by the side plate 26 and the guardrail 27, so that the workers cannot fall off easily. Outer being provided with bearing frame 20 under the lifter plate 1, being provided with fixed stabilizer blade 21 under the four corners of bearing frame 20, the bearing frame 20 and the fixed stabilizer blade 21 that set up let this room build engineering construction with the platform fixed more firm, stable.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (7)

1. The utility model provides a high room construction engineering construction of stability is with platform which characterized in that: comprises an outer lifting plate (1), a first lifting plate (3), a second lifting plate (7) and an inner lifting plate (9) are sequentially arranged in the outer lifting plate (1), two groups of racks (2) are symmetrically arranged on the inner sides of the outer lifting plate (1) and the first lifting plate (3), two groups of racks (2) are symmetrically arranged on the outer sides of the second lifting plate (7) and the inner lifting plate (9), rectangular through grooves (4) are respectively formed in the first lifting plate (3) and the second lifting plate (7), pin shafts (5) are arranged in the rectangular through grooves (4), first lifting gears (6) are arranged in the first lifting plate (3) in a penetrating manner, second lifting gears (8) are arranged in the second lifting plate (7) in a penetrating manner, and the first lifting gears (6) are meshed with the racks (2) arranged on the inner side of the outer lifting plate (1) and the racks (2) arranged on the outer side of the second lifting plate (7), the second lifting gear (8) is meshed with the rack (2) arranged on the inner side of the first lifting plate (3) and the rack (2) arranged on the outer side of the inner lifting plate (9), and a bearing plate (19) is arranged on the inner lifting plate (9); the bottom of first lifter plate (3) is provided with bottom plate (10), set up threaded hole (11) on bottom plate (10), lead screw (12) wear to be equipped with in screw hole (11), the bottom of lead screw (12) is provided with first adjusting gear (13), be provided with second adjusting gear (14) under first adjusting gear (13), second adjusting gear (14) are connected with the regulation and shake wheel (16).
2. The high-stability platform for building engineering construction according to claim 1, wherein the platform comprises: two sets of T type spout (17) have all been seted up to the inboard of outer lifter plate (1), first lifter plate (3), second lifter plate (7), one side of first lifter plate (3), second lifter plate (7) and lifter plate (9) all is provided with two sets of T type sliders (18), T type slider (18) slidable card is established in T type spout (17).
3. The high-stability platform for building engineering construction according to claim 1, wherein the platform comprises: the second adjusting gear (14) is connected with the adjusting rocking wheel (16) through a connecting rod (15), and a handle (24) is arranged on the adjusting rocking wheel (16).
4. The high-stability platform for building engineering construction according to claim 1, wherein the platform comprises: the bearing plate (19) is provided with a side plate (26) and a guardrail (27).
5. The high-stability platform for building engineering construction according to claim 1, wherein the platform comprises: a bearing frame (20) is arranged below the outer lifting plate (1), and fixing support legs (21) are arranged below four corners of the bearing frame (20).
6. The high-stability platform for building engineering construction according to claim 3, wherein: the bottom of outer lifter plate (1) is provided with guard box (22), first adjusting gear (13) with second adjusting gear (14) all set up in guard box (22), through-hole (23) have been seted up to one side of guard box (22), connecting rod (15) are worn to establish in through-hole (23).
7. The high-stability platform for building engineering construction according to claim 1, wherein the platform comprises: the top of lead screw (12) is provided with stopper (25), the both sides of rack (2) are provided with spacing (28).
CN202022437890.6U 2020-10-28 2020-10-28 High-stability platform for building engineering construction Expired - Fee Related CN213837635U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022437890.6U CN213837635U (en) 2020-10-28 2020-10-28 High-stability platform for building engineering construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022437890.6U CN213837635U (en) 2020-10-28 2020-10-28 High-stability platform for building engineering construction

Publications (1)

Publication Number Publication Date
CN213837635U true CN213837635U (en) 2021-07-30

Family

ID=77012592

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022437890.6U Expired - Fee Related CN213837635U (en) 2020-10-28 2020-10-28 High-stability platform for building engineering construction

Country Status (1)

Country Link
CN (1) CN213837635U (en)

Similar Documents

Publication Publication Date Title
CN205472511U (en) Stable elevating platform that overhauls
CN209855238U (en) Be used for construction template fixing device
CN206156681U (en) Domestic elevating gear
CN111977529A (en) Hoisting tool for construction machinery equipment
CN213837635U (en) High-stability platform for building engineering construction
CN207903826U (en) A kind of Portable elevator for construction material transport
CN205634821U (en) Removable type work platform desktop
CN209098132U (en) A kind of fixed device of building construction hoist
CN208122251U (en) A kind of lift for building automatically adjusting arbitrary height
CN215907341U (en) Interior decoration construction platform
CN213622976U (en) Span adjustable lifting beam machine
CN210239082U (en) Temporary hydropower integrated bracket for construction site
CN210620135U (en) Movable lifting device
CN210508313U (en) But height-adjusting's stable form engineering construction scaffold
CN210563272U (en) Efficient and convenient ground leveling device
CN209703972U (en) A kind of height-adjustable scaffold
CN2806640Y (en) Automatic plastering machine
CN208310286U (en) A kind of building-supporting frame facilitating adjusting
CN213569216U (en) Bridge frame running mechanism of bridge crane
CN207332457U (en) A kind of construction guardrail of detachable lifting
CN218205569U (en) Construction scaffold
CN218708844U (en) Hoisting device is used in building structure construction
CN214329809U (en) Lifting combined platform convenient to adjust for building engineering
CN214834525U (en) Scaffold for building
CN218201966U (en) Elevating gear for construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210730