CN213710451U - Civil engineering construction is with room construction job site unwrapping wire equipment - Google Patents

Civil engineering construction is with room construction job site unwrapping wire equipment Download PDF

Info

Publication number
CN213710451U
CN213710451U CN202021895296.5U CN202021895296U CN213710451U CN 213710451 U CN213710451 U CN 213710451U CN 202021895296 U CN202021895296 U CN 202021895296U CN 213710451 U CN213710451 U CN 213710451U
Authority
CN
China
Prior art keywords
fixed mounting
bearing
stand
type frame
bottom plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021895296.5U
Other languages
Chinese (zh)
Inventor
郑浩
陈浩
魏伟
刘娟
刘复超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021895296.5U priority Critical patent/CN213710451U/en
Application granted granted Critical
Publication of CN213710451U publication Critical patent/CN213710451U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The utility model discloses a civil engineering construction is built job site unwrapping wire equipment with room, comprising a base plate, U type frame and driving motor, the top fixed mounting of bottom plate has first stand, and spacing spout has been seted up to one side of first stand, and the top fixed mounting of bottom plate has the second stand, and the rectangular channel has been seted up to one side of second stand, and the inside fixed mounting of second stand has first bearing, and the inside fixed mounting of first bearing has the threaded rod, and the top fixed mounting of U type frame has L type baffle, and one side fixed mounting of U type frame has spacing slider, and the opposite side fixed mounting of U type frame has the connecting block. Can make the screw hole piece reciprocate through rotating the threaded rod to drive U type frame and reciprocate, thereby adjustment pay-off's height makes pay-off be applicable to the unwrapping wire of co-altitude not, when carrying out the unwrapping wire to higher position, need not bed up the height that the pay off rack just can reach needs, not only improves the precision of unwrapping wire, has improved unwrapping wire efficiency moreover.

Description

Civil engineering construction is with room construction job site unwrapping wire equipment
Technical Field
The utility model belongs to the technical field of civil engineering, concretely relates to civil engineering construction is with room construction job site unwrapping wire equipment.
Background
The building construction paying-off is one of basic skills of construction managers, construction positioning paying-off is started at the beginning of construction of each building engineering, the success or failure of the whole engineering is related, the phenomenon that a house is misplaced due to paying-off errors and cannot meet the requirements of functional facilities is frequently seen, the construction paying-off is a ring which is crucial to guarantee the engineering quality, house construction paying-off is convenient for workers to live and can be constructed according to design drawings strictly, generally all building axes can be called as large lines, and corresponding small lines are side lines and dimension lines of structural members, so the appearance of the building is directly influenced by paying-off specifications.
At present, most workers pay off by holding a measuring line by two hands, so that manpower is wasted, the paying off accuracy is low, the paying off is important for a high position, a general paying-off rack needs to be lifted to reach a required height, the paying-off efficiency is reduced, and when the paying-off rack is taken up, dust on the ground of the measuring line is accumulated in a wire box to enable the measuring line to be wound in a disordered manner, the wire outlet speed is influenced, and the paying-off rack is very inconvenient to use.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a civil engineering construction is built job site unwrapping wire equipment with room to it builds job site unwrapping wire mode in the use to provide a current room in solving above-mentioned background art, because the method that present most workman's unwrapping wire was taken all is the handheld measuring wire unwrapping wire of two people, thereby leads to the problem of the inefficiency of the precision ratio lower and unwrapping wire.
In order to achieve the above object, the utility model provides a following technical scheme: a building construction site paying-off device for civil engineering construction comprises a bottom plate, a U-shaped frame and a driving motor, wherein a first upright post is fixedly mounted at the top of the bottom plate, a limiting sliding groove is formed in one side of the first upright post, a second upright post is fixedly mounted at the top of the bottom plate, a rectangular groove is formed in one side of the second upright post, a first bearing is fixedly mounted in the second upright post, a threaded rod is fixedly mounted in the first bearing, an L-shaped partition plate is fixedly mounted at the top of the U-shaped frame, a limiting sliding block is fixedly mounted at one side of the U-shaped frame, a connecting block is fixedly mounted at the other side of the U-shaped frame, a threaded hole block is fixedly mounted at the other end of the connecting block, a mounting plate is fixedly mounted at the front of the U-shaped frame, two supporting plates are fixedly mounted at the top of the mounting, the utility model discloses a mud scraper, including mounting panel, fixed plate, driving motor's drive end fixed mounting has the rope roller, the outside winding of rope roller has the measuring line, the outside fixed mounting of rope roller has the anticreep board.
Preferably, the front and the back of the bottom plate are fixedly provided with two mounting rods, the outer side of one end, far away from the bottom plate, of each mounting rod is fixedly provided with a second bearing, and the outer side of each second bearing is fixedly provided with a wheel.
Preferably, the inside fixed mounting of L type baffle one side lateral wall has the third bearing, the inside fixed mounting of one side of U type frame erection joint piece has the fourth bearing, the one end fixed mounting of rope roller is in the inside of third bearing, the other end fixed mounting of rope roller is in the inside of fourth bearing.
Preferably, the threaded hole that matches with the threaded rod is seted up to the inside of screw hole piece, and the screw hole piece passes through the screw hole and articulates in the outside of threaded rod, the top fixed mounting of threaded rod has the hand-operated handle.
Preferably, the specification and size of the limiting sliding block are matched with the specification and size of the limiting sliding groove, the limiting sliding block is slidably mounted in the limiting sliding groove, and the connecting block is movably mounted in the rectangular groove.
Preferably, the top of the bottom plate is fixedly provided with a storage battery.
Compared with the prior art, the beneficial effects of the utility model are that:
1. can make the screw hole piece reciprocate through rotating the threaded rod to drive U type frame and reciprocate, thereby adjustment pay-off's height makes pay-off be applicable to the unwrapping wire of co-altitude not, when carrying out the unwrapping wire to higher position, need not bed up the height that the pay off rack just can reach needs, not only improves the precision of unwrapping wire, has improved unwrapping wire efficiency moreover.
2. The mud pipe and the brush roll are scraped through the setting to clean up the measuring line of retrieving, scrape the mud pipe and can scrape away the bold earth that the measuring line outside is infected with, the brush roll can be cleared up the remaining fritter earth of measuring line outside, effectively brushes away the ash layer on the measuring line, avoids the measuring line to take place in the chaotic condition of rope roller outside winding, guarantees that the measuring line can not knot outside the rope roller, improves the efficiency of being qualified for the next round of competitions, and it is very convenient to use.
Drawings
Fig. 1 is a schematic view of the front-view three-dimensional appearance structure of the present invention;
fig. 2 is a schematic view of the top-view three-dimensional appearance structure of the present invention;
fig. 3 is a schematic view of the front view of the partial sectional structure of the present invention.
In the figure: 1. a base plate; 2. a U-shaped frame; 3. a first upright post; 4. a storage battery; 5. a limiting slide block; 6. a wheel; 7. a support plate; 8. a brush roll; 9. a rectangular groove; 10. a second upright post; 11. a handle; 12. an L-shaped partition plate; 13. a drive motor; 14. measuring a line; 15. a rope roller; 16. an anti-drop plate; 17. mounting a plate; 18. a fixing plate; 19. a mud scraping pipe; 20. a second bearing; 21. mounting a rod; 22. a limiting chute; 23. a fourth bearing; 24. a threaded rod; 25. connecting blocks; 26. a threaded hole block; 27. a first bearing; 28. and a third bearing.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: the building construction site pay-off equipment for civil engineering construction comprises a bottom plate 1, a U-shaped frame 2 and a driving motor 13, wherein a first upright post 3 is fixedly mounted at the top of the bottom plate 1, a limiting sliding groove 22 is formed in one side of the first upright post 3, a second upright post 10 is fixedly mounted at the top of the bottom plate 1, a rectangular groove 9 is formed in one side of the second upright post 10, a first bearing 27 is fixedly mounted inside the second upright post 10, a threaded rod 24 is fixedly mounted inside the first bearing 27, an L-shaped partition plate 12 is fixedly mounted at the top of the U-shaped frame 2, a limiting sliding block 5 is fixedly mounted at one side of the U-shaped frame 2, a connecting block 25 is fixedly mounted at the other side of the U-shaped frame 2, a threaded hole block 26 is fixedly mounted at the other end of the connecting block 25, a mounting plate 17 is fixedly mounted at the front of the U-shaped frame 2, two supporting plates 7 are, two brush rolls 8 are installed to the opposite face of backup pad 7, the top fixed mounting of mounting panel 17 has fixed plate 18, the inside fixed mounting of fixed plate 18 has mud scraping pipe 19, driving motor 13's drive end fixed mounting has rope roller 15, the outside winding of rope roller 15 has measuring line 14, the outside fixed mounting of rope roller 15 has anticreep board 16.
In the embodiment, the wheel 6 is rotated by pushing the bottom plate 1, the pushing is stopped when the wheel reaches a required position, the threaded rod 24 is rotated by the hand rotating handle 11, the threaded rod 24 rotates to enable the threaded hole block 26 on the outer side to move up and down, the U-shaped frame 2 is driven by the connecting block 25 to move up and down, so that the height of the pay-off device is adjusted according to the actual required height, then the driving motor 13 is started, the driving end of the driving motor 13 drives the rope roller 15 to rotate, so that the measuring line 14 is released, after the required line is released, the driving motor 13 is stopped to rotate, the pay-off operation is completed, after the measurement is completed, the driving motor 13 is started to rotate reversely, the driving end drives the rope roller 15 to rotate, the measuring line 14 is recovered, in the recovery process, the mud scraping pipe 19 can scrape large mud contaminated on the outer side of the measuring line 14, the brush roller 8 can clean residual small, effectively brush away the ash layer on the measuring wire 14, avoid measuring wire 14 to take place in the chaotic condition of rope roller 15 outside winding, guarantee that measuring wire 14 can not knot at rope roller 15, improve the efficiency of being qualified for the next round of competitions, it is very convenient to use.
Specifically, two mounting rods 21 are fixedly mounted on the front side and the back side of the bottom plate 1, a second bearing 20 is fixedly mounted on the outer side of one end, far away from the bottom plate 1, of each mounting rod 21, and a wheel 6 is fixedly mounted on the outer side of each second bearing 20.
In this embodiment, the wheel 6 can rotate through the second bearing 20, thereby facilitating the overall movement of the device.
Specifically, the inside fixed mounting of L type baffle 12 one side lateral wall has third bearing 28, the inside fixed mounting of one side of U type frame 2 erection joint piece 25 has fourth bearing 23, the one end fixed mounting of rope roller 15 is in the inside of third bearing 28, the other end fixed mounting of rope roller 15 is in the inside of fourth bearing 23.
In this embodiment, the third bearing 28 and the fourth bearing 23 function to protect the rope roller 15.
Specifically, a threaded hole matched with the threaded rod 24 is formed in the threaded hole block 26, the threaded hole block 26 is hinged to the outer side of the threaded rod 24 through the threaded hole, and the top of the threaded rod 24 is fixedly provided with a hand-operated handle 11.
In this embodiment, when the threaded rod 24 is rotated by the handle 11, the threaded rod 24 is rotated to move the outer threaded hole block 26 up and down.
Specifically, the specification and size of the limiting slide block 5 are matched with the specification and size of the limiting slide groove 22, the limiting slide block 5 is slidably mounted in the limiting slide groove 22, and the connecting block 25 is movably mounted in the rectangular groove 9.
In this embodiment, the limit slide block 5 can slide inside the limit slide groove 22, and the connection block 25 can slide inside the rectangular groove 9.
Specifically, a storage battery 4 is fixedly mounted at the top of the bottom plate 1.
In the present embodiment, the battery 4 supplies power to the drive motor 13.
The utility model discloses a theory of operation and use flow: the wheel 6 is rotated by pushing the bottom plate 1, the wheel reaches a required position and stops pushing, then the threaded rod 24 is rotated by the hand rotating handle 11, the threaded rod 24 rotates to enable the threaded hole block 26 on the outer side to move up and down, the U-shaped frame 2 is driven by the connecting block 25 to move up and down, so that the height of the pay-off device is adjusted according to the actual required height, then the driving motor 13 is started, the driving end of the driving motor 13 drives the rope roller 15 to rotate, so that the measuring line 14 is released, after the required line is released, the driving motor 13 is stopped to rotate, the pay-off operation is completed, after the measurement is completed, the driving motor 13 is started to rotate reversely, the driving end drives the rope roller 15 to rotate, the measuring line 14 is recovered, in the recovery process, the mud scraping pipe 19 can scrape large soil stained on the outer side of the measuring line 14, the brush roll 8 can clean small soil remained on the outer side of the measuring line 14, avoid measuring line 14 to take place in the chaotic condition of rope roller 15 outside winding, guarantee that measuring line 14 can not knot at rope roller 15, improve the efficiency of being qualified for the next round of competitions, it is very convenient to use.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a civil engineering construction is with room construction job site unwrapping wire equipment, includes bottom plate (1), U type frame (2) and driving motor (13), its characterized in that: the top fixed mounting of bottom plate (1) has first stand (3), spacing spout (22) have been seted up to one side of first stand (3), the top fixed mounting of bottom plate (1) has second stand (10), rectangular channel (9) have been seted up to one side of second stand (10), the inside fixed mounting of second stand (10) has first bearing (27), the inside fixed mounting of first bearing (27) has threaded rod (24), the top fixed mounting of U type frame (2) has L type baffle (12), one side fixed mounting of U type frame (2) has spacing slider (5), the opposite side fixed mounting of U type frame (2) has connecting block (25), the other end fixed mounting of connecting block (25) has threaded hole block (26), the front fixed mounting of U type frame (2) has mounting panel (17), the top fixed mounting of mounting panel (17) has two backup pads (7), two brush roller (8) are installed to the opposite face of backup pad (7), the top fixed mounting of mounting panel (17) has fixed plate (18), the inside fixed mounting of fixed plate (18) has mud scraping pipe (19), the drive end fixed mounting of driving motor (13) has rope roller (15), the outside winding of rope roller (15) has measuring line (14), the outside fixed mounting of rope roller (15) has anticreep board (16).
2. The building construction site line laying device for civil engineering construction according to claim 1, characterized in that: the front and the back of the bottom plate (1) are fixedly provided with two mounting rods (21), the outer side of one end of the bottom plate (1) far away from the mounting rods (21) is fixedly provided with a second bearing (20), and the outer side of the second bearing (20) is fixedly provided with a wheel (6).
3. The building construction site line laying device for civil engineering construction according to claim 1, characterized in that: the inside fixed mounting of L type baffle (12) one side lateral wall has third bearing (28), the inside fixed mounting of one side of U type frame (2) erection joint piece (25) has fourth bearing (23), the one end fixed mounting of rope roller (15) is in the inside of third bearing (28), the other end fixed mounting of rope roller (15) is in the inside of fourth bearing (23).
4. The building construction site line laying device for civil engineering construction according to claim 1, characterized in that: the threaded hole block (26) is internally provided with a threaded hole matched with the threaded rod (24), the threaded hole block (26) is hinged to the outer side of the threaded rod (24) through the threaded hole, and the top of the threaded rod (24) is fixedly provided with a hand rotating handle (11).
5. The building construction site line laying device for civil engineering construction according to claim 1, characterized in that: the specification and size of the limiting sliding block (5) are matched with the specification and size of the limiting sliding groove (22), the limiting sliding block (5) is slidably mounted in the limiting sliding groove (22), and the connecting block (25) is movably mounted in the rectangular groove (9).
6. The building construction site line laying device for civil engineering construction according to claim 1, characterized in that: and a storage battery (4) is fixedly mounted at the top of the bottom plate (1).
CN202021895296.5U 2020-09-02 2020-09-02 Civil engineering construction is with room construction job site unwrapping wire equipment Expired - Fee Related CN213710451U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021895296.5U CN213710451U (en) 2020-09-02 2020-09-02 Civil engineering construction is with room construction job site unwrapping wire equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021895296.5U CN213710451U (en) 2020-09-02 2020-09-02 Civil engineering construction is with room construction job site unwrapping wire equipment

Publications (1)

Publication Number Publication Date
CN213710451U true CN213710451U (en) 2021-07-16

Family

ID=76792562

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021895296.5U Expired - Fee Related CN213710451U (en) 2020-09-02 2020-09-02 Civil engineering construction is with room construction job site unwrapping wire equipment

Country Status (1)

Country Link
CN (1) CN213710451U (en)

Similar Documents

Publication Publication Date Title
CN112177282A (en) Whitewash device is used in building engineering construction
CN213710451U (en) Civil engineering construction is with room construction job site unwrapping wire equipment
CN111002455B (en) Assembly type building element production system
CN211659571U (en) Environmental protection dust collecting equipment of building engineering construction
CN214600036U (en) Intelligent brushing equipment for constructional engineering
CN217810392U (en) Town road length measuring device
CN216432734U (en) Winding device for measuring tape distance measuring instrument
CN212801124U (en) Width measuring device is used in town road construction
CN214007117U (en) Oil field water injection well is with scale removal device that has protective structure
CN213761459U (en) Civil engineering is with agitating unit convenient to wash
CN214217793U (en) Pay-off rack for construction site of building construction
CN212586007U (en) Sampling device for soil remediation
CN112031348A (en) Be used for building wall high efficiency to whitewash device
CN218403176U (en) Water-carrying detection equipment for drainage pipe network
CN214441094U (en) Management platform for construction engineering based on network technology
CN213167567U (en) Architectural decoration decorates with floating device of decorative paper
CN216075490U (en) Box culvert is with visual high pressure desilting device
CN216206367U (en) Measuring device for building management
CN220538418U (en) Road bridge tunnel building construction safety device
CN211992950U (en) Wall marking device for architectural decoration
CN219380249U (en) Rust removal device for bridge construction steel bars
CN217448794U (en) Water conservancy fire extinguishing system equipment
CN216770613U (en) Engineering survey pay-off
CN218239031U (en) A unmanned on duty weighing device for building site
CN219315464U (en) Gap filling equipment with push-flat structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210716