CN213692961U - Laying frame for circuit distribution network reconstruction - Google Patents

Laying frame for circuit distribution network reconstruction Download PDF

Info

Publication number
CN213692961U
CN213692961U CN202022600698.4U CN202022600698U CN213692961U CN 213692961 U CN213692961 U CN 213692961U CN 202022600698 U CN202022600698 U CN 202022600698U CN 213692961 U CN213692961 U CN 213692961U
Authority
CN
China
Prior art keywords
fixedly connected
top side
cable
distribution network
circuit distribution
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022600698.4U
Other languages
Chinese (zh)
Inventor
斯应昌
李连强
金波
秦裕强
蔡占峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Shengneng Electric Power Technology Co ltd
Original Assignee
Hangzhou Shengneng Electric Power Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Shengneng Electric Power Technology Co ltd filed Critical Hangzhou Shengneng Electric Power Technology Co ltd
Priority to CN202022600698.4U priority Critical patent/CN213692961U/en
Application granted granted Critical
Publication of CN213692961U publication Critical patent/CN213692961U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model discloses a net transformation is joined in marriage with laying frame to circuit relates to the net field is joined in marriage to the circuit, including the base, the ring channel has been seted up to the top side of base, the top side fixed mounting of base has the motor, the seat is accepted to the output fixedly connected with of motor, accept four bracing pieces of the bottom side fixedly connected with of seat, four the runner is all installed, four to the bottom of bracing piece all rotates the runner all with slidable mounting in the ring channel, accept the top side fixedly connected with dead lever of seat. The utility model discloses it is rational in infrastructure, establish the cable reel cover on the dead lever, the top of dead lever is pegged graft to the auxiliary plate, screws up afterwards to support the bolt and fix, and circular briquetting compresses tightly the cable reel is automatic, and the head end of cable is passed and is walked the line ring and move the connecting block and make the slider in the spout displacement, carries out position control and can prevent simultaneously that the cable from rocking when laying and causing the cable surface wearing and tearing, and avoids the more chaotic condition of laying of cable kind.

Description

Laying frame for circuit distribution network reconstruction
Technical Field
The utility model relates to a circuit distribution network field, in particular to circuit distribution network reforms transform with laying frame.
Background
The power distribution network is a power network which receives electric energy from a transmission network or a regional power plant, distributes the electric energy on site through a power distribution facility or distributes the electric energy to various users step by step according to voltage, circuit reconstruction relates to a lot of questions, if a person who is not a professional can know that things are not many, but people also need to know basic knowledge, and therefore the person can not enter a wrong area in the construction process.
Many large-scale buildings such as hospital need lay the underground line when the construction, especially the circuit of some weak current, generally need use the circuit to lay the frame and lay when laying, traditional mode of laying generally is manual operation, the change installation that can not be quick after the cable book is used up simultaneously, and can not separately place various wire and cable, make various wire and cable intertwine together easily, make wire and cable suffer from the damage, constructor's working strength has both been increased, work efficiency has been reduced, in addition, generally can only lay a cable on the same cable frame, limitation has during the use, application scope is less, for this reason, we have provided a circuit and have joined in marriage net transformation with laying the frame.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a circuit distribution network reforms transform with laying frame to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a circuit distribution network reforms transform with laying frame, includes the base, the ring channel has been seted up on the top side of base, the top side fixed mounting of base has the motor, the output fixedly connected with of motor accepts the seat, accept four bracing pieces of bottom side fixedly connected with of seat, four the runner is all rotated to the bottom of bracing piece, four the runner all with slidable mounting in the ring channel, the top side fixedly connected with dead lever of accepting the seat, the top joint of dead lever has the connecting piece, the auxiliary disc has been cup jointed in the activity on the connecting piece.
Preferably, the bottom side of the auxiliary disc is fixedly connected with three fixed pressing rods, notches are formed in the bottom sides of the three fixed pressing rods, circular pressing blocks are slidably mounted in the notches, springs are fixedly connected to the top sides of the circular pressing blocks, and the top ends of the springs are fixedly connected with the inner walls of the top sides of the notches.
Preferably, a plurality of jacks are uniformly distributed on the top sides of the fixing rod and the connecting piece.
Preferably, the connecting piece is fixedly provided with two slide rails on the peripheral side, the auxiliary disc is provided with two slide grooves on the inner wall on the peripheral side, the two slide rails are respectively slidably arranged on the two slide grooves, and the connecting piece is fixedly connected with a plurality of inserted rods on the bottom side.
Preferably, a plurality of the insertion holes are respectively matched with a plurality of the insertion rods.
Preferably, the fixed rod and the circumferential side of the connecting piece are both provided with abutting bolts in a threaded manner.
Preferably, the top side of base has been seted up the bar spout, slidable mounting has a plurality of sliders in the bar spout, and is a plurality of the equal fixedly connected with connecting block in top side of slider, it is a plurality of the equal fixedly mounted in top side of connecting block has the wire loop.
The utility model discloses a technological effect and advantage:
1. the utility model has reasonable structure, the cable winding shaft sleeve is sleeved on the fixed rod, the auxiliary disc is inserted above the fixed rod, then the tightening bolt is tightened to fix, the circular pressing block automatically compresses the cable coil, the head end of the cable passes through the wiring ring movable connecting block to enable the sliding block to displace in the sliding groove, the position adjustment is carried out, meanwhile, the cable can be prevented from shaking to cause the surface abrasion of the cable when being laid, and the condition that the cable is more in types and is disordered when being laid is avoided;
2. the utility model discloses in, the motor drives accepts the seat and makes the cable unreel, accepts the seat and drives the bracing piece and make the runner shift in the ring channel, can reduce the resistance of bracing piece when rotating and play relative supporting role, makes the unwrapping wire lay work can be more stable, decides the number of erection joint spare and auxiliary disc according to the radical of the cable that will lay to can lay many cables, can reach save time and manpower, enlarge the effect of laying a application scope, easy operation.
Drawings
FIG. 1 is a schematic perspective view of the present invention;
FIG. 2 is a schematic front view of the present invention;
FIG. 3 is an enlarged schematic view of the connecting member of the present invention;
fig. 4 is a schematic view of the internal structure of the fixing compression bar of the present invention.
In the figure: 1. a base; 2. a motor; 3. a bearing seat; 4. fixing the rod; 5. a connecting member; 6. an auxiliary disc; 7. fixing the compression bar; 8. a circular pressing block; 9. a spring; 10. a support bar; 11. a rotating wheel; 12. an annular groove; 13. a slider; 14. connecting blocks; 15. a wiring ring; 16. a jack; 17. inserting a rod; 18. the bolt is pressed tightly.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The utility model provides a as shown in fig. 1-4 a circuit distribution net is reformed transform with laying frame, including base 1, ring channel 12 has been seted up to base 1's top side, base 1's top side fixed mounting has motor 2, motor 2's output fixedly connected with accepts seat 3, accept four bracing pieces of bottom side fixedly connected with 10 of seat 3, the bottom of four bracing pieces 10 is all rotated and is installed runner 11, four runner 11 all with slidable mounting in ring channel 12, accept seat 3's top side fixedly connected with dead lever 4, the top joint of dead lever 4 has connecting piece 5, auxiliary plate 6 has been cup jointed in the activity on connecting piece 5, setting through bracing piece 10 can play certain supporting role to accepting seat 3.
Further, in above-mentioned scheme, three fixed depression bar 7 of bottom side fixedly connected with of auxiliary disc 6, the notch has all been seted up to the bottom side of three fixed depression bar 7, and equal slidable mounting has circular briquetting 8 in the three notch, and the equal fixedly connected with spring 9 in top side of three circular briquetting 8, the top of three spring 9 respectively with the top side inner wall fixed connection of three notch, through the setting of spring 9 with circular briquetting 8, can compress tightly the cable dish.
Furthermore, in the above scheme, a plurality of jacks 16 are uniformly distributed on the top sides of the fixing rod 4 and the connecting piece 5, and the connecting piece 5 can be conveniently mounted through the jacks 16.
Further, in the above scheme, two slide rails are fixedly mounted on the peripheral side of the connecting member 5, two slide grooves are formed in the peripheral side inner wall of the auxiliary disc 6, the two slide rails are respectively slidably mounted in the two slide grooves, a plurality of insertion rods 17 are fixedly connected to the bottom side of the connecting member 5, and the auxiliary disc 6 can be mounted through the slide rails.
Further, in the above solution, the plurality of insertion holes 16 are respectively adapted to the plurality of insertion rods 17, and the plurality of connection members 5 can be installed by the cooperation of the insertion holes 16 and the insertion rods 17.
Further, in the above scheme, the fastening bolts 18 are threadedly mounted on the peripheral sides of the fixing rod 4 and the connecting member 5, and the connecting member 5 can be reinforced by the fastening bolts 18.
Further, in above-mentioned scheme, the bar spout has been seted up on the top side of base 1, and slidable mounting has a plurality of sliders 13 in the bar spout, and the equal fixedly connected with connecting block 14 in top side of a plurality of sliders 13, the equal fixedly mounted in top side of a plurality of connecting blocks 14 has wire loop 15 of walking, through the setting of slider 13, is many in order to drive the position removal of wire loop 15 of walking.
This practical theory of operation:
the model of the motor 2 is: 5IK120RGN, the staff firstly sleeves the cable roll or the spool rolled with the cable on the fixed rod 4, the auxiliary disc 6 is inserted above the fixed rod 4, the connecting piece 5 is inserted at the same time, and then the abutting bolt 18 abuts against the circumferential surfaces of the fixed rod 4 and the inserted rod 17, so that the auxiliary disc 6 can be fixed more firmly, under the action of the spring 9, the circular pressing block 8 can be driven to automatically press one side of the cable roll, at the moment, the cable roll or the spool can abut against the upper surface of the bearing seat 3, the head end of the cable firstly passes downwards through the wiring ring 15, the wiring ring 15 drives the connecting block 14, the connecting block 14 drives the sliding block 13 to generate displacement in the sliding chute, and then the position of the wiring ring 15 can be adjusted according to the laying position of the cable, so that the cable can be prevented from shaking to cause the surface abrasion of the cable when being laid, and the situation that the type of the, subsequently, start motor 2, motor 2's output drives accepts seat 3 and rotates, and then drive the process that the cable unreeled, the in-process that the cable unreeled, accept seat 3 and drive bracing piece 10 and produce the displacement, bracing piece 10 drives runner 11 and produces the displacement in ring channel 12, just so reached the effect that makes things convenient for the cable drum to lay, reduce the resistance of bracing piece 10 when rotating simultaneously and play relative supporting role, make the unwrapping wire lay work can be more stable, when needs lay two kinds or more than two kinds of cables simultaneously, the staff can decide the number of erection joint spare 5 and auxiliary disc 6 according to the radical of the cable that will lay, thereby can lay many cables, can reach save time and manpower, expand the effect of laying frame application scope, and is simple in operation.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and variations can be made in the embodiments or in part of the technical features of the embodiments without departing from the spirit and the scope of the invention.

Claims (7)

1. The utility model provides a circuit distribution network reforms transform with laying frame, includes base (1), its characterized in that: annular groove (12) have been seted up to the top side of base (1), the top side fixed mounting of base (1) has motor (2), the output fixedly connected with of motor (2) accepts seat (3), the bottom side fixedly connected with four bracing pieces (10) of accepting seat (3), four the bottom of bracing piece (10) is all rotated and is installed runner (11), four runner (11) all with slidable mounting in annular groove (12), the top side fixedly connected with dead lever (4) of accepting seat (3), the top joint of dead lever (4) has connecting piece (5), supplementary dish (6) have been cup jointed in the activity on connecting piece (5).
2. The laying frame for circuit distribution network reconstruction according to claim 1, characterized in that: the bottom side of auxiliary plate (6) fixedly connected with three fixed depression bar (7), it is three the notch has all been seted up to the bottom side of fixed depression bar (7), it is three equal slidable mounting has circular briquetting (8) in the notch, it is three equal fixedly connected with spring (9) in the top side of circular briquetting (8), it is three the top of spring (9) respectively with three the top side inner wall fixed connection of notch.
3. The laying frame for circuit distribution network reconstruction according to claim 1, characterized in that: and a plurality of jacks (16) are uniformly distributed on the top sides of the fixing rod (4) and the connecting piece (5).
4. The laying frame for circuit distribution network reconstruction according to claim 1, characterized in that: the side fixed mounting of week of connecting piece (5) has two slide rails, seted up two spouts on the side inner wall of week of auxiliary plate (6), two the slide rail is sliding mounting respectively two the spout, a plurality of inserted bars (17) of bottom side fixedly connected with of connecting piece (5).
5. The laying frame for circuit distribution network reconstruction according to claim 3, characterized in that: the plurality of the jacks (16) are respectively matched with the plurality of inserting rods (17).
6. The laying frame for circuit distribution network reconstruction according to claim 1, characterized in that: and abutting bolts (18) are arranged on the circumferential sides of the fixing rod (4) and the connecting piece (5) in a threaded manner.
7. The laying frame for circuit distribution network reconstruction according to claim 1, characterized in that: the bar spout has been seted up to the top side of base (1), slidable mounting has a plurality of sliders (13) in the bar spout, and is a plurality of the equal fixedly connected with connecting block (14) in top side of slider (13), it is a plurality of the equal fixed mounting in top side of connecting block (14) walks wire loop (15).
CN202022600698.4U 2020-11-11 2020-11-11 Laying frame for circuit distribution network reconstruction Active CN213692961U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022600698.4U CN213692961U (en) 2020-11-11 2020-11-11 Laying frame for circuit distribution network reconstruction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022600698.4U CN213692961U (en) 2020-11-11 2020-11-11 Laying frame for circuit distribution network reconstruction

Publications (1)

Publication Number Publication Date
CN213692961U true CN213692961U (en) 2021-07-13

Family

ID=76732612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022600698.4U Active CN213692961U (en) 2020-11-11 2020-11-11 Laying frame for circuit distribution network reconstruction

Country Status (1)

Country Link
CN (1) CN213692961U (en)

Similar Documents

Publication Publication Date Title
CN209516470U (en) A kind of power ampere loads line apparatus
CN213692961U (en) Laying frame for circuit distribution network reconstruction
CN110667909A (en) Binding apparatus for reinforcing bar convenient to remove
CN211707973U (en) Power line bracing coil clamping mechanism
CN207010097U (en) A kind of wire installation of electric wire laying
CN215580179U (en) Light current engineering spool connecting device
CN213802329U (en) Cable coiling device for 110kV and below transformer substation
CN217051014U (en) Photovoltaic cable exhibition frame
CN213278874U (en) Movable box-type substation
CN211733418U (en) Wire take-up is used in electric wire engineering construction
CN209805353U (en) Fixing and supporting device for bus duct
CN209545086U (en) It is a kind of convenient for fixed cable processing tensioning apparatus
CN217847686U (en) Winding machine with tightening function for discharge coil
CN215071337U (en) Cable splicing limiting frame for power maintenance
CN208445212U (en) A kind of multi-functional electric wire laying apparatus of power domain
CN211172147U (en) Electric power construction wire pole foundation ditch trimming device
CN213243387U (en) Electric power construction is with reason line frame
CN110394408A (en) A kind of high-voltage connection cutting line platform
CN114635594B (en) Electric pole correcting device for electric power engineering
CN215326172U (en) Engineering supervision pay-off equipment placer
CN115405125A (en) Electric pole crack reinforcing device and using method
CN214379223U (en) High-voltage line connector binding apparatus of being convenient for
CN209999445U (en) prestressed bar tensioning device for prestressed concrete structure production
CN214100610U (en) Electric power overhead line conductor installation device
CN214543491U (en) Telescopic cable fixing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant