- sealing
- seal groove
- block
- template
- formwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 20
- 238000009415 formwork Methods 0.000 claims abstract description 33
- 238000007789 sealing Methods 0.000 claims description 37
- 238000005728 strengthening Methods 0.000 abstract description 7
- 230000000694 effects Effects 0.000 abstract description 5
- 230000037431 insertion Effects 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses a building engineering construction formwork device, which comprises a formwork, first seal groove has all been seted up on the lateral wall about the template, the second seal groove has all been seted up on the top of template and the bottom, two equal sliding connection has first sealed piece on the first seal groove, the third seal groove has all been seted up on the top of first sealed piece and the bottom, third seal groove and second seal groove intercommunication setting, sliding connection has the sealed piece of same piece second in second seal groove and the third seal groove, fixed mounting has the stopper on the first sealed piece. The utility model discloses a cooperation between template, first seal groove, first sealed piece, first fixed block, first mounting hole and the first tensioning mechanism is used, has realized through setting up first seal groove and first sealed piece, has realized strengthening the purpose of the leakproofness between two templates about, realizes the zonulae occludens of two templates of effect simultaneously.
Description
Technical Field
The utility model belongs to the technical field of the building, especially, relate to a building engineering construction template device.
Background
The building engineering refers to an engineering entity formed by the construction of various house buildings and auxiliary facilities thereof and the installation activities of lines, pipelines and equipment matched with the house buildings, templates are frequently used in the building engineering, the templates form a wall by splicing, and the purpose of fixing the templates is realized by external steel pipes.
When the existing building engineering construction formwork device is used, the formworks are spliced together, and the existing formwork does not have the function of strengthening the connection between the formworks, so that the sealing performance between the formworks is low, and the building engineering construction formwork device is provided.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the shortcoming that does not have the function of strengthening the connection between the template that exists among the prior art, and the building engineering construction template device who proposes.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a building engineering construction formwork device, includes the template, first seal groove has all been seted up on the lateral wall about the template, the second seal groove has all been seted up on the top of template and the bottom, two equal sliding connection has first sealed piece on the first seal groove, the third seal groove has all been seted up on the top of first sealed piece and the bottom, third seal groove and second seal groove intercommunication set up, sliding connection has the same sealed piece of second in second seal groove and the third seal groove, fixed mounting has the stopper on the first sealed piece, controls two fixed mounting has same first straining device between the template, straining device slides and runs through the stopper setting, two from top to bottom fixed mounting has same second straining device between the template.
Preferably, a through hole is formed in the limiting block, and the first tensioning mechanism penetrates through the through hole.
Preferably, the first tensioning mechanism comprises a first fixed block fixedly mounted on the template, a first mounting hole is formed in the first fixed block, a left mounting hole and a right mounting hole are formed in the first mounting hole, a first pair of pull screws are slidably arranged in the first mounting hole, the first pair of pull screws penetrate through the through hole, and two first tensioning nuts are in threaded connection with the first pair of pull screws.
Preferably, the second tensioning mechanism comprises a second fixed block fixedly mounted on the template, a second mounting hole is formed in the second fixed block, the upper and lower second mounting holes are internally provided with a same second counter-pulling screw rod in a sliding manner, and a second tensioning nut is connected to the second counter-pulling screw rod in a threaded manner.
Preferably, equal fixed mounting has first inserted block on the both ends lateral wall about first sealed block, first inserted block slides and locates in the first seal groove, first inserted block and first seal groove all are the setting of dovetail.
Preferably, the top and the bottom of the second sealing block are both fixedly provided with a second insert block, and the second insert block is slidably arranged in the second sealing groove.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses a cooperation between template, first seal groove, first sealed piece, first fixed block, first mounting hole and the first tensioning mechanism is used, has realized through setting up first seal groove and first sealed piece, has realized strengthening the purpose of the leakproofness between two templates about, realizes the zonulae occludens of two templates of effect simultaneously.
2. The utility model discloses a cooperation between template, second seal groove, third seal groove, the sealed piece of second, second fixed block, second mounting hole and the taut mechanism of second is used, has realized through setting up the sealed piece of second seal groove and second, has realized strengthening the purpose of the leakproofness between two blocks of templates from top to bottom, realizes strengthening the connection between two blocks of templates from top to bottom simultaneously.
Drawings
Fig. 1 is a schematic front perspective structural view of a construction formwork apparatus for building engineering provided by the present invention;
fig. 2 is a schematic view of a back perspective structure of a construction formwork device for construction engineering provided by the present invention;
fig. 3 is a schematic view of a overlooking partial perspective structure of the construction form device for building engineering provided by the utility model.
In the figure: the sealing structure comprises a template 1, a first sealing groove 2, a second sealing groove 3, a first sealing block 4, a third sealing groove 5, a second sealing block 6, a limiting block 7, a through hole 8, a first fixing block 9, a first mounting hole 10, a first pair of pull screws 11, a first tensioning nut 12, a second fixing block 13, a second mounting hole 14, a second pair of pull screws 15, a second tensioning nut 16, a first insertion block 17 and a second insertion block 18.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-3, a building engineering construction formwork device, including template 1, first seal groove 2 has all been seted up on the lateral wall about template 1, second seal groove 3 has all been seted up on the top of template 1 and the bottom, equal sliding connection has first seal block 4 on two first seal grooves 2, wherein, equal fixed mounting has first inserted block 17 on the both ends lateral wall about first seal block 4, first inserted block 17 slides and locates in first seal groove 2, first inserted block 17 all is the dovetail setting with first seal groove 2, it is concrete, first inserted block 17 and first seal groove 2 are the dovetail setting, can realize the preliminary spacing mesh between first seal block 4 and the first seal groove 2, can strengthen the leakproofness simultaneously.
A limiting block 7 is fixedly mounted on the first sealing block 4, a same first tensioning mechanism is fixedly mounted between the left template 1 and the right template 1, the tensioning mechanism slides to penetrate through the limiting block 7, and a same second tensioning mechanism is fixedly mounted between the upper template 1 and the lower template 1.
Wherein, the through hole 8 has been seted up on the stopper 7, and first tensioning mechanism passes through the setting of through hole 8, and is further, and first tensioning mechanism includes fixed mounting first fixed block 9 on template 1, has seted up first mounting hole 10 on the first fixed block 9, slides in two first mounting holes 10 about and is equipped with same one first pair of screw rod 11 that draws, and first pair of screw rod 11 passes through the setting of through hole 8, and threaded connection has two first tensioning nuts 12 on the first pair of screw rod 11.
It should be noted that, the purpose of connecting the left and right formworks 1 is achieved by the first tie screw 11 and the first tightening nut 12, and the sealing performance between the first sealing groove 2 and the first insert 17 is enhanced by the pressure effect.
The second tensioning mechanism comprises a second fixing block 13 fixedly mounted on the template 1, a second mounting hole 14 is formed in the second fixing block 13, the same second counter pull screw 15 is slidably arranged in the upper second mounting hole 14 and the lower second mounting hole 14, and a second tensioning nut 16 is connected to the second counter pull screw 15 in a threaded mode.
It should be noted that, the purpose of connecting the upper and lower formworks 1 is achieved by the second tie screw 15 and the second tightening nut 16, and meanwhile, the sealing performance among the second seal groove 3, the third seal groove 5 and the second insert block 18 is enhanced by the pressure effect.
The utility model discloses in, at first connect two left and right sides template 1, insert respectively in the first seal groove 2 of both sides through the first inserted block 17 with the 4 both sides of first sealed piece, the purpose of the 1 initial joint of template of the left and right sides at first, make the first fixed block 9 on two templates 1 correspond the setting, make first mounting hole 10 and through hole 8 on two first fixed plates 9 correspond, later pass two first mounting holes 10 and through hole 8 with first lag screw 11, locate first lag screw 11's both sides with two first lag nuts 12 difference thread bush, make two first lag nuts 12 compress tightly the first fixed block 9 of both sides respectively, realize the fixed connection purpose of left and right sides template 1, realize the purpose of the leakproofness between the enhancement left and right sides template 1 through pressure simultaneously.
Further, a second insert block 18 on a second sealing block 6 is inserted into two second sealing grooves 3 and a third sealing groove 5, then a next formwork 1 is placed on the second sealing block 6, the second sealing groove 3 is connected with the second insert block 18, the operations are repeated, the left formwork 1 and the right formwork 1 are connected firstly, after the two formworks 1 above the second sealing block 6 are connected, the upper second fixing block 13 and the lower second fixing block 13 are in a corresponding state at the moment, a second counter-pull screw 15 penetrates through two second mounting holes 14, two second tightening nuts 16 are respectively sleeved on two sides of the second counter-pull screw 15 in a threaded manner, the purpose of compressing the upper second fixing block 13 and the lower second fixing block 13 is achieved, and the sealing performance and the connection strength between the upper formwork 1 and the lower formwork 1 are enhanced.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.
Claims (6)
1. The building engineering construction formwork device comprises formworks (1) and is characterized in that first sealing grooves (2) are formed in the left side wall and the right side wall of each formwork (1), second sealing grooves (3) are formed in the top and the bottom of each formwork (1), first sealing blocks (4) are connected to the two first sealing grooves (2) in a sliding mode, third sealing grooves (5) are formed in the top and the bottom of each first sealing block (4), the third sealing grooves (5) are communicated with the second sealing grooves (3), the second sealing grooves (3) and the third sealing grooves (5) are connected with the same second sealing block (6) in a sliding mode, limit blocks (7) are fixedly installed on the first sealing blocks (4), the same first tensioning mechanism is fixedly installed between the left formwork (1) and the right formwork (1), and penetrates through the limit blocks (7) in a sliding mode, and the same second tensioning mechanism is fixedly arranged between the upper template (1) and the lower template (1).
2. The construction formwork device according to claim 1, wherein the limiting block (7) is provided with a through hole (8), and the first tensioning mechanism is arranged through the through hole (8).
3. The building engineering construction formwork device according to claim 2, wherein the first tensioning mechanism comprises a first fixing block (9) fixedly mounted on the formwork (1), a first mounting hole (10) is formed in the first fixing block (9), a same first pair of pulling screws (11) are slidably arranged in the left and right first mounting holes (10), the first pair of pulling screws (11) pass through the through holes (8), and two first tensioning nuts (12) are in threaded connection with the first pair of pulling screws (11).
4. The building engineering construction formwork device according to claim 1, wherein the second tensioning mechanism comprises a second fixing block (13) fixedly mounted on the formwork (1), a second mounting hole (14) is formed in the second fixing block (13), a same second counter-pulling screw (15) is slidably arranged in the upper and lower second mounting holes (14), and a second tensioning nut (16) is in threaded connection with the second counter-pulling screw (15).
5. The construction formwork device according to claim 1, wherein the side walls of the left end and the right end of the first sealing block (4) are fixedly provided with first inserting blocks (17), the first inserting blocks (17) are slidably arranged in the first sealing groove (2), and the first inserting blocks (17) and the first sealing groove (2) are arranged in a dovetail shape.
6. The construction formwork device according to claim 1, wherein a second insert block (18) is fixedly installed at the top and the bottom of the second sealing block (6), and the second insert block (18) is slidably arranged in the second sealing groove (3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022313332.9U CN213654239U (en) | 2020-10-17 | 2020-10-17 | Building engineering construction template device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022313332.9U CN213654239U (en) | 2020-10-17 | 2020-10-17 | Building engineering construction template device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213654239U true CN213654239U (en) | 2021-07-09 |
Family
ID=76701712
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202022313332.9U Expired - Fee Related CN213654239U (en) | 2020-10-17 | 2020-10-17 | Building engineering construction template device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213654239U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113550583A (en) * | 2021-07-30 | 2021-10-26 | 陕西忠信建筑安装有限责任公司 | Building plank sheathing connection structure |
-
2020
- 2020-10-17 CN CN202022313332.9U patent/CN213654239U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113550583A (en) * | 2021-07-30 | 2021-10-26 | 陕西忠信建筑安装有限责任公司 | Building plank sheathing connection structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN213654239U (en) | Building engineering construction template device | |
CN203769062U (en) | Structural frame and connection structure of lapping position of beam column frame | |
CN204402030U (en) | A kind of oval door opening concrete wall template | |
CN111980162A (en) | Mounting structure of building assembled wall body | |
CN116657792A (en) | Assembled double-layer steel plate combined shear wall capable of realizing double-sided compression | |
CN203756198U (en) | Tunnel buried type rubber waterstop linear control device | |
CN213330004U (en) | Large steel formwork and combined formwork formed by same | |
CN204311725U (en) | Putlock Combined fixing device | |
CN211369168U (en) | Whole light partition wall system in superelevation space | |
CN207776184U (en) | A kind of flat jam-packed controller of precast facade hanging plate perps folder | |
CN205976558U (en) | Two -way handle negative and positive angle floater | |
CN213115518U (en) | Construction structures is consolidated to aluminium membrane board single face | |
CN213766337U (en) | Concrete protection pier construction steel form with rapid Assembly function | |
CN209855204U (en) | Outer scaffold frame connection structure of shear force wall | |
CN218758744U (en) | Horizontal hoop reinforcing apparatus of cylinder template design | |
CN216690377U (en) | Reinforcing member for construction of internal and external corners of wall | |
CN220184725U (en) | Waterproof structure of opposite-pulling screw hole | |
CN211775707U (en) | Splicing structure-containing convenient-to-combine anti-expansion die aluminum template | |
CN218815207U (en) | Corner structure column template structure | |
CN209653175U (en) | A kind of aluminium Baogang curtain wall corner window construction | |
CN215290287U (en) | Novel stagnant water steel sheet | |
CN214658804U (en) | Aluminum alloy building templates splayed readily removable reentrant corner device | |
CN220621055U (en) | Reinforced structure of back edge of building aluminum template | |
CN210767849U (en) | Hole shutoff template is reserved to aluminum alloy template | |
CN217379382U (en) | Side plate projection welded assembled perforated steel plate shear wall structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210709 |