CN213653078U - Disconnect-type cable brick - Google Patents

Disconnect-type cable brick Download PDF

Info

Publication number
CN213653078U
CN213653078U CN202021650085.5U CN202021650085U CN213653078U CN 213653078 U CN213653078 U CN 213653078U CN 202021650085 U CN202021650085 U CN 202021650085U CN 213653078 U CN213653078 U CN 213653078U
Authority
CN
China
Prior art keywords
brick body
cable
notch
brick
laying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021650085.5U
Other languages
Chinese (zh)
Inventor
封信超
陈正强
丁黎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zunyi Hanfeng Decoration Material Co ltd
Original Assignee
Zunyi Hanfeng Decoration Material Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zunyi Hanfeng Decoration Material Co ltd filed Critical Zunyi Hanfeng Decoration Material Co ltd
Priority to CN202021650085.5U priority Critical patent/CN213653078U/en
Application granted granted Critical
Publication of CN213653078U publication Critical patent/CN213653078U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model discloses a disconnect-type cable is laid bricks, it is with the technical field of laying bricks to belong to the town road. This brick of laying bricks includes the brick body and the lower brick body, and the top of the lower brick body is equipped with two bosss along vertically side by side, and the top of the lower brick body is equipped with notch A between two bosss, goes up the brick body and places under on the brick body, and the bottom of going up the brick body is equipped with two recess B with the corresponding position of two bosss, and the bottom of going up the brick body is equipped with notch B with the corresponding position of notch A. After the lower brick body and the cable are laid firstly, the laying work of the upper brick body is finished, the cable laying operation is convenient, and the laying efficiency is high. When the cable is overhauled or replaced, the upper brick body is taken out from the lower brick body by lifting the handle, so that the cable can be exposed, and the overhaul by workers is facilitated.

Description

Disconnect-type cable brick
Technical Field
The utility model relates to a disconnect-type cable is laid bricks, it is with the technical field of laying bricks to belong to the town road.
Background
Generally, municipal roads have many consumers of electricity, such as street lamps, traffic lights and speed measuring camera lamps, and these consumers of electricity connect the power plant through pre-buried underground multichannel cable and supply power and transmit signal. When the cable is pre-buried, a plurality of pipes are buried firstly, the pipes form a pipeline, and then the cable penetrates through the pipeline to finish pre-burying of the cable. In order to prevent the pipe from being crushed by vehicles, a deep ditch needs to be dug for burying the pipe, and the pipe is difficult to bury, namely the pipe is difficult to install. The pipe is generally 5-10 meters long and heavy, so at least more than two workers are needed to move the pipe to complete the burying work of the pipe, the requirement on the number of workers is high, and the labor intensity of the workers is high due to the heavy pipe. When buried pipes are damaged, workers need to dig out the pipes from the ground and then maintain the pipes, and the maintenance is difficult. Therefore, the existing pipe used for pre-embedding the municipal road cable has the defects of difficult installation, high requirement on the number of workers, high labor intensity of the workers and difficult maintenance.
Therefore, Chinese patent document with publication number CN208685370U discloses a brick with a built-in spool, which comprises a brick body, wherein I-shaped steel is arranged in the brick body, through holes are arranged on both sides of the I-shaped steel and are respectively positioned in grooves on both sides of the I-shaped steel, the spool is arranged in the through holes, one end of the spool extends out of the brick body to form a plug, an annular groove positioned on the plug is arranged at the joint of the plug and the brick body, a horn-shaped sealing pipe is arranged at the other end of the spool and is positioned in the through holes, and the large end of the sealing pipe faces the outer side of the brick body. Has the advantages of low requirement on the number of workers, low labor intensity of the workers and easier maintenance.
However, when the cable is laid, the cable needs to sequentially pass through each brick, and when the cable is overhauled, the cable needs to be drawn out of the bricks, so that the operation is inconvenient, the cable laying efficiency is low, and the labor intensity is high.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, the utility model provides a disconnect-type cable brick.
The utility model discloses a following technical scheme can realize:
the utility model provides a disconnect-type cable brick of laying bricks, includes the brick body and the lower brick body, and the top of the lower brick body is equipped with two bosss along vertically side by side, and the top of the lower brick body is equipped with notch A between two bosss, goes up the brick body and places under on the brick body, and the bottom of going up the brick body is equipped with two recess B with the corresponding position of two bosss, and the bottom of going up the brick body is equipped with notch B with the corresponding position of notch A.
The notch A and the notch B are both semicircular notches.
The inboard of notch A and notch B all is equipped with semi-circular spool.
The top of going up the brick body is equipped with two recess A side by side, all swing joint has the handle in two recess A.
And the edge of the top surface of the boss is chamfered.
And the edge of the opening end of the groove B is chamfered.
The beneficial effects of the utility model reside in that: after the lower brick body and the cable are laid firstly, the laying work of the upper brick body is finished, the cable laying operation is convenient, and the laying efficiency is high. When the cable is overhauled or replaced, the upper brick body is taken out from the lower brick body by lifting the handle, so that the cable can be exposed, and the overhaul by workers is facilitated.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of the upper brick body of the present invention;
fig. 3 is a schematic structural view of the lower brick body of the present invention.
In the figure: 1-upper brick body, 10-groove A, 11-groove B, 2-lower brick body, 20-boss, 3-handle and 4-semicircular line pipe.
Detailed Description
The technical solution of the present invention is further described below, but the scope of the claimed invention is not limited to the described.
As shown in fig. 1 to 3, a disconnect-type cable brick, including last brick body 1 and lower brick body 2, the top of lower brick body 2 is along vertically being equipped with two bosss 20 side by side, the top of lower brick body 2 is equipped with notch A between two bosss 20, go up brick body 1 and place on brick body 2 down, the bottom of going up brick body 1 is equipped with two recess B11 with the corresponding position of two bosss 20, the bottom of going up brick body 1 is equipped with notch B with the corresponding position of notch A.
The notch A and the notch B are both semicircular notches.
The inboard of notch A and notch B all is equipped with semicircular spool 4.
The top of going up the brick body 1 is equipped with two recess A10 side by side, all swing joint has handle 3 in two recess A10. The upper brick body 1 is convenient to lift from the lower brick body 2.
The edge of the top surface of the boss 20 is chamfered. Conveniently snapping into the groove B11.
The open end edge of the groove B11 is chamfered. Facilitating snap-fitting of the boss 20 into the recess B11.
When using, excavate one at the roadside of town road with build brick width and high assorted irrigation canals and ditches, the bottom surface of irrigation canals and ditches of making level, lay the lower brick body 2 of each building brick in the bottom of irrigation canals and ditches, then lay the cable in the semi-circular spool 4 of the lower brick body 2, after the cable is laid, will go up brick body 1 in proper order and cover under on brick body 2, the boss 20 card at lower brick body 2 top goes into in the recess B11 of the brick body 1 bottom, transversely carry on spacingly to building brick.
In conclusion, after the lower brick body 2 and the cable are laid, the laying work of the upper brick body 1 is completed, the cable laying operation is convenient, and the laying efficiency is high. When overhauing or changing the cable, lift 3 on and take out the brick body 1 from the brick body 2 down, can make the cable expose, make things convenient for the staff to overhaul.

Claims (6)

1. The utility model provides a disconnect-type cable brickwork which characterized in that: including the brick body (1) and the lower brick body (2), the top of the lower brick body (2) is equipped with two boss (20) along vertically side by side, the top of the lower brick body (2) is equipped with notch A between two boss (20), go up the brick body (1) and place on the lower brick body (2), the bottom of going up the brick body (1) is equipped with two recess B (11) with the corresponding position of two boss (20), the bottom of going up the brick body (1) is equipped with notch B with the corresponding position of notch A.
2. The discrete cable brickwork of claim 1, wherein: the notch A and the notch B are both semicircular notches.
3. The discrete cable brickwork of claim 2, wherein: the insides of the notch A and the notch B are respectively provided with a semicircular line pipe (4).
4. The discrete cable brickwork of claim 1, wherein: the top of the upper brick body (1) is provided with two grooves A (10) side by side, and handles (3) are movably connected in the two grooves A (10).
5. The discrete cable brickwork of claim 1, wherein: the edge of the top surface of the boss (20) is chamfered.
6. The discrete cable brickwork of claim 1, wherein: the edge of the opening end of the groove B (11) is chamfered.
CN202021650085.5U 2020-08-10 2020-08-10 Disconnect-type cable brick Active CN213653078U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021650085.5U CN213653078U (en) 2020-08-10 2020-08-10 Disconnect-type cable brick

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021650085.5U CN213653078U (en) 2020-08-10 2020-08-10 Disconnect-type cable brick

Publications (1)

Publication Number Publication Date
CN213653078U true CN213653078U (en) 2021-07-09

Family

ID=76692960

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021650085.5U Active CN213653078U (en) 2020-08-10 2020-08-10 Disconnect-type cable brick

Country Status (1)

Country Link
CN (1) CN213653078U (en)

Similar Documents

Publication Publication Date Title
CN105113543B (en) 0815 type underground pipe gallery assembling combination cabin concrete structure of shallow embedding
CN102359123B (en) Cast-in-place concrete cable conduit construction method
CN105951876A (en) Cover plate type precast concrete urban comprehensive pipe gallery and construction method thereof
CN107630500A (en) A kind of water supply and drainage construction method
CN213653078U (en) Disconnect-type cable brick
CN103669400A (en) Typical construction method for prefabricated tube bank
CN213653957U (en) Brick for laying cable
CN101141054A (en) Compaction grouting method for preventing land subsidence after non-digging horizontal drilling
CN208072456U (en) A kind of underground pipe gallery and underground garage connecting taxiway structure based on road
CN106368211B (en) Rectangular concrete pile for building piping lane side wall
CN206157768U (en) Street piping lane is crossed to underground
CN112177006B (en) Construction method for protecting municipal pipeline
CN204098066U (en) The square underground pipe gallery of assembling
CN211922702U (en) Prefabricated cable utility tunnel
CN211579545U (en) Protection structure for pipeline passing through
CN113108123A (en) Multi-purpose tool pipe for artificial jacking pipe
CN202543759U (en) Concrete block for road construction
CN102852063B (en) concrete block and construction method for road construction
CN207003605U (en) Reinforced buried concrete pumping equipment
CN211689741U (en) Novel synthesize curb structure
CN110635436A (en) Compound cable pit
CN204163099U (en) Street lamp prefabricated well basis
CN219604375U (en) Pipeline foundation pit supporting structure
CN217734268U (en) Existing sewer line's of oblique crossing difference in height water level structure of plugging into
CN214697177U (en) Town road lighting apparatus convenient to change and repair

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant