CN213597998U - Stoping roadway support - Google Patents

Stoping roadway support Download PDF

Info

Publication number
CN213597998U
CN213597998U CN202022340824.7U CN202022340824U CN213597998U CN 213597998 U CN213597998 U CN 213597998U CN 202022340824 U CN202022340824 U CN 202022340824U CN 213597998 U CN213597998 U CN 213597998U
Authority
CN
China
Prior art keywords
left upper
support
jack
right upper
pushing jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022340824.7U
Other languages
Chinese (zh)
Inventor
邓月华
雷刚
王斌
蔡华林
许维武
蒲伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yibin University
Original Assignee
Yibin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yibin University filed Critical Yibin University
Priority to CN202022340824.7U priority Critical patent/CN213597998U/en
Application granted granted Critical
Publication of CN213597998U publication Critical patent/CN213597998U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model relates to a stoping tunnel support uses in groups, and the stoping tunnel about 20 meters is strutted to every group. When the support needs to be moved, workers can safely work in the space below a top plate for supporting and protecting the support, and can start the two-side pushing jacks to move the whole support by respectively lifting the two-side stand columns, so that the labor intensity of the workers is greatly reduced. The utility model relates to a supporting bracket structural design is compact, reasonable, supporting intensity is big, effectual, wholly moves the frame, advancing speed is fast, easy and simple to handle, and safe and reliable is the mining tunnel support equipment of the mine advance coal face of ten minutes ideal.

Description

Stoping roadway support
Technical Field
The utility model relates to a stoping tunnel support is applicable to the advance support in two roadways of colliery coal face stoping in-process.
Background
The advance working face of the stoping roadway of the mine coal face is advanced by about 20 meters to carry out advanced reinforcement support, most of the advance working face supports of the stoping roadway of the mine in the south at present adopt a support form that a single hydraulic prop is matched with a steel beam or a shed to carry out reinforcement support, and workers are required to manually disassemble and carry forward support supports of props along with the advance of the coal face in the support process.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a solve above-mentioned problem, provide the stoping tunnel support to solve the advance working face of mine stoping tunnel and strut the problem, reduce workman intensity of labour, increase the stability and the operation security in stoping tunnel, reduce the roof country rock destruction that adopts the monomer pillar to arouse to the repeated supporting of tunnel roof.
The utility model discloses the stoping tunnel support uses in groups, and the stoping tunnel about 20 meters is strutted to every group. The purpose of each bracket is realized as follows: the back mining roadway support comprises a left upper support column, a left upper middle beam, a left upper top beam, a right upper support column, a right upper middle beam, a right upper top beam, a left upper oblique vertical jack, a right upper oblique vertical jack, a left upper pushing jack, a left upper middle pushing jack, a left upper lower pushing jack, a right upper middle pushing jack and a right upper lower pushing jack; the left upper pillar and the left upper top beam are respectively hinged through a left upper middle beam and are respectively connected with a left upper inclined vertical jack, and the right upper pillar and the right upper top beam are respectively hinged through a right upper middle beam and are respectively connected with a right upper inclined vertical jack.
On the stoping roadway support, the left upper top beam and the right upper top beam are connected in an embedded mode.
On the stoping roadway support, a pushing jack at the upper part of the left upper is connected with the middle beam of the left upper, and a pushing jack at the middle part of the left upper and a pushing jack at the lower part of the left upper are connected with the left upper support; the upper pushing jack of the right upper is connected with the middle beam of the right upper, and the middle pushing jack of the right upper and the lower pushing jack of the right upper are connected with the pillar of the right upper.
The utility model provides a back production tunnel support, when using, the workman can be in the space safety operation of the roof below of strutting the support maintenance, when the support need move the frame, the workman promotes two group's stands respectively through promoting two, impels two groups and passes the jack and remove whole support, greatly reduced workman intensity of labour. The utility model relates to a supporting bracket structural design is compact, reasonable, supporting intensity is big, effectual, wholly moves the frame, advancing speed is fast, easy and simple to handle, and safe and reliable is the mining tunnel support equipment of the mine advance coal face of ten minutes ideal.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a sectional view of the present invention.
In the figure, 1-left upper strut, 2-left upper middle beam, 3-left upper top beam, 4-right upper strut, 5-right upper middle beam, 6-right upper top beam, 7-left upper oblique lifting jack, 8-right upper oblique lifting jack, 9-left upper pushing jack, 10-left upper middle pushing jack, 11-left upper lower lifting jack, 12-right upper pushing jack, 13-right upper middle pushing jack, 14-right upper lower pushing jack.
Detailed Description
In order to make the purpose and technical solution of the present invention clearer, the following describes the present invention further with reference to the accompanying drawings and embodiments:
fig. 1 is a schematic view of the structure of the present invention, fig. 2 is a sectional view of the present invention, which is a group of roadway support, including a left upper pillar 1, a left upper middle beam 2, a left upper top beam 3, a right upper pillar 4, a right upper middle beam 5, a right upper top beam 6, a left upper inclined jack 7, a right upper inclined jack 8, a left upper pushing jack 9, a left upper middle pushing jack 10, a left upper lower pushing jack 11, a right upper pushing jack 12, a right upper middle pushing jack 13, and a right upper lower pushing jack 14; the left upper pillar 1 and the left upper top beam 3 are respectively hinged through a left upper middle beam 2 and are respectively connected with a left upper inclined vertical jack 7, the right upper pillar 4 and the right upper top beam 6 are respectively hinged through a right upper middle beam 5 and are respectively connected with a right upper inclined vertical jack 8.
On the stoping roadway support, the left upper top beam 3 and the right upper top beam 6 are connected in an embedded mode.
On the stoping roadway support, a left upper part pushing jack 9 is connected with the left upper middle beam 2, and a left upper middle part pushing jack 10 and a left upper lower part pushing jack 11 are connected with the left upper support 1; the right upper part pushing jack 12 is connected with the right upper middle beam 5, and the right upper middle part pushing jack 13 and the right upper lower part pushing jack 14 are connected with the right upper strut 4.
When the mining roadway works, a left upper supporting column 1, a left upper middle beam 2, a right upper supporting column 4 and a right upper middle beam 5 are respectively hinged and supported by a left upper top beam 3 and a right upper top beam 6 to maintain a roadway top plate, the left upper supporting column 1 and the right upper supporting column 4 respectively support two sides of the mining roadway, and a worker safety operation space of the mining roadway is maintained; when the support is walking, a left upper pillar 1 at one end of the support keeps a supporting state, a right upper pillar 4 and a right upper oblique jack 8 contract simultaneously to lower the support, when the right upper pillar 4 can not move downwards any more, the foot of the right upper pillar 4 is operated to lift and separate from a roadway bottom plate, then a right upper part pushing jack 12, a right upper middle pushing jack 13 and a right upper lower part pushing jack 14 are pushed, the right upper pillar 4 and a right upper middle beam 5 are pushed forwards, after the pushing stroke is in place, the right upper pillar 4 is lifted, a right upper beam 6 is contacted with a top plate through the right upper middle beam 5, the left upper pillar 1 and the left upper oblique jack 7 at one end contract simultaneously to lower the support, the left upper pillar 1 is operated to lift and separate from the roadway bottom plate, then the left upper part pushing jack 9, the left upper middle pushing jack 10 and the left upper lower part pushing jack 11 are pushed forwards, after the pushing stroke is in place, the left upper strut 1 is lifted, the left upper top beam 3 is contacted with the top plate through the left upper middle beam 2, and the circular propelling of the support is completed.
In the working process of the support, a left upper pillar 1 and a left upper middle beam 2, and a right upper pillar 4 and a right upper middle beam 5 of each support are respectively in movable hinge joint, a left upper top beam 3 and a right upper top beam 6 are in embedded connection, when the support is lowered and moved, sufficient movable space and range exist in the left upper top beam 3 and the right upper top beam 6, and the integral moving of the support and the maintenance of surrounding rocks of a top plate cannot be influenced.
The utility model discloses compare with the background art and have obvious superiority, the overall structure design propulsion has been adopted, left and right two group stands adopt tertiary flexible hydro-cylinder power mode, left group back timber and right group roof beam adopt two-way embedded connection to maintain the back production tunnel roof, two group respectively adopt oblique upright jack to shrink and fix a position, about two group, in, the lower part all adopts to pass the whole propulsion frame of jack, maintain the roof country rock in the back production tunnel of leading coal face, but this support several recycles, the back production tunnel of about 20 meters is strutted to leading working face. The support has compact and reasonable structural design, high supporting strength, good effect, high integral support moving and pushing speed, simple and convenient operation, safety and reliability, and is very ideal mining roadway support equipment for the advanced coal face of the mine.

Claims (1)

1. A stoping roadway support is characterized in that: a group of supporting 20m roadways comprises a left upper pillar (1), a left upper middle beam (2), a left upper top beam (3), a right upper pillar (4), a right upper middle beam (5), a right upper top beam (6), a left upper oblique lifting jack (7), a right upper oblique lifting jack (8), a left upper pushing jack (9), a left upper middle pushing jack (10), a left upper lower pushing jack (11), a right upper pushing jack (12), a right upper middle pushing jack (13) and a right upper lower pushing jack (14); the left upper pillar (1) and the left upper top beam (3) are respectively hinged through a left upper middle beam (2) and are respectively connected with a left upper inclined vertical jack (7), the right upper pillar (4) and the right upper top beam (6) are respectively hinged through a right upper middle beam (5) and are respectively connected with a right upper inclined vertical jack (8);
the left upper top beam (3) and the right upper top beam (6) are connected in an embedded manner;
the left upper part pushing jack (9) is connected with the left upper middle beam (2), and the left upper middle part pushing jack (10) and the left upper lower part pushing jack (11) are connected with the left upper strut (1); the upper right side pushing jack (12) is connected with the right side middle beam (5), and the middle right side pushing jack (13) and the lower right side pushing jack (14) are connected with the right side support column (4).
CN202022340824.7U 2020-10-20 2020-10-20 Stoping roadway support Expired - Fee Related CN213597998U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022340824.7U CN213597998U (en) 2020-10-20 2020-10-20 Stoping roadway support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022340824.7U CN213597998U (en) 2020-10-20 2020-10-20 Stoping roadway support

Publications (1)

Publication Number Publication Date
CN213597998U true CN213597998U (en) 2021-07-02

Family

ID=76591836

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022340824.7U Expired - Fee Related CN213597998U (en) 2020-10-20 2020-10-20 Stoping roadway support

Country Status (1)

Country Link
CN (1) CN213597998U (en)

Similar Documents

Publication Publication Date Title
CN102128040B (en) Hydraulic striding-type advanced-support equipment
CN110130965B (en) Advanced support bracket for comprehensive mechanized excavation and use method
CN110080811B (en) Adjustable type advanced support bracket for rapid comprehensive mechanized excavation and use method
CN104047627A (en) Mining roadway frame style advanced support bracket
CN110985084B (en) Coal roadway full-section self-moving advanced temporary support device and support method
CN103032091A (en) Self-moving hydraulic support
CN203223239U (en) Roadway advance timbering support used for assisting machine to move
CN204646284U (en) A kind of roadway support equipment of gob side entry retaining
CN103216252B (en) Roadway advanced supporting supports capable of assisting machinery to move
CN201953390U (en) Hydraulic walking advance support equipment
CN213597998U (en) Stoping roadway support
CN110219681B (en) Movable temporary supporting device and construction method thereof
CN210068218U (en) Multipurpose roadway advance support hydraulic support
CN210396782U (en) Single-beam temporary supporting structure
CN211549734U (en) Fully-mechanized mining working face roadway advance support hydraulic support
CN203962017U (en) Stope drift active workings frame type advance support rack
CN210564602U (en) Split type hydraulic support for ultra-thin coal seam
CN203223238U (en) Mechanical arm for moving racks in roadway
CN212406774U (en) Combined hydraulic support for gob-side entry retaining
CN202125305U (en) Hydraulic bracket for roadway support
CN206448831U (en) Without support gib equipment repeatedly
CN103216251B (en) Support moving mechanical arm for roadway
CN110159333B (en) Comprehensive mechanized tunneling quick advance support unit and use method thereof
CN216714433U (en) Underground coal mine roadway driving face advance support
CN209875194U (en) Single column support vehicle

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210702

CF01 Termination of patent right due to non-payment of annual fee