CN213457204U - Reality-augmented high-voltage test preview device for main equipment of transformer substation - Google Patents

Reality-augmented high-voltage test preview device for main equipment of transformer substation Download PDF

Info

Publication number
CN213457204U
CN213457204U CN202022028949.6U CN202022028949U CN213457204U CN 213457204 U CN213457204 U CN 213457204U CN 202022028949 U CN202022028949 U CN 202022028949U CN 213457204 U CN213457204 U CN 213457204U
Authority
CN
China
Prior art keywords
camera
display screen
voltage test
transformer substation
main equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022028949.6U
Other languages
Chinese (zh)
Inventor
魏秋累
李自怀
戴兵
王文琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Ruihuan Electric Power Technology Co ltd
Original Assignee
Wuhan Ruihuan Electric Power Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Ruihuan Electric Power Technology Co ltd filed Critical Wuhan Ruihuan Electric Power Technology Co ltd
Priority to CN202022028949.6U priority Critical patent/CN213457204U/en
Application granted granted Critical
Publication of CN213457204U publication Critical patent/CN213457204U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The utility model relates to a high-voltage test rehearsal technical field just discloses a reality-augmented high-voltage test rehearsal device for main equipment of transformer substation, including display screen and host computer, host computer one side is provided with the USB interface, the installation is provided with body in the middle of the display screen upper portion and feels the camera, body feels the camera and includes camera main part, camera support and support mounting hole, the installation of host computer bottom is provided with the chassis, the installation of chassis bottom is provided with the universal wheel, the fixed controller support that is provided with in chassis top one side, the controller has been placed to controller support inside. This augmented reality's high-voltage testing rehearsal device for main equipment of transformer substation feels camera and controller through setting up body for personnel can show various equipment scenes in the transformer substation through the software simulation program and the display screen that set up in the host computer, thereby simulate various equipment of actual operation transformer substation in the reality, and then strengthened the reality sense of high-voltage testing rehearsal.

Description

Reality-augmented high-voltage test preview device for main equipment of transformer substation
Technical Field
The utility model relates to a high-voltage test rehearsal technical field specifically is a reality-enhanced high-voltage test rehearsal device for main equipment of transformer substation.
Background
For a transformer substation, high-voltage electrical equipment is required to be detected timely so as to ensure safe and stable operation of the high-voltage electrical equipment. The high-voltage test is a work with high technology and high danger degree, and needs to be planned and prepared in an early stage, compile a corresponding implementation scheme, determine a test object, define a working range, plan a power failure area and make a safeguard measure to ensure that a work task is completed on time according to quality and quantity and ensure the safety in work. How to ensure that the work is consistent with the actual situation on site needs to carry out reasonable live-action preview by means of corresponding technical means.
However, the prior high-voltage test preview only uses preview software to edit a preview flow, simulates the preview in a computer, has low personnel participation and insufficient reality sense, and is not enough to truly reflect the conditions.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides an augmented reality's transformer substation is high-voltage test preview device for main equipment possesses advantages such as analog operation, outdoor scene show, has solved the problem of proposing among the above-mentioned background art.
(II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a reality-augmented high-voltage test preview device for main equipment of transformer substation, includes the display screen, the installation of display screen rear portion is provided with the host computer, the through-hole installation has been seted up to host computer one side and has been provided with the USB interface, the rear side is seted up in the middle of the display screen upper portion and is provided with body and feels the camera, body feels the camera and includes camera main part, camera support and support mounting hole, the installation of host computer bottom is provided with the chassis, the installation of chassis bottom is provided with the universal wheel, the fixed controller support that is provided with in chassis top one side, the controller has been placed to controller support inside.
Preferably, the rear side of the display screen is connected with the front side of the host machine into a whole through screws, and the display screen is connected with the host machine through an HDMI data line.
Preferably, the number of the USB interfaces is multiple, and one of the USB interfaces is connected with the somatosensory camera through a data line.
Preferably, the camera main body is connected with the display screen top shell through a screw through a support mounting hole formed in the surface of the camera support.
Preferably, the number of the universal wheels is four, and the four universal wheels are respectively arranged at the front end and the rear end of the cross rods on the two sides of the underframe.
Compared with the prior art, the utility model provides an augmented reality's high-voltage testing preview device for main equipment of transformer substation possesses following beneficial effect: this augmented reality's high-voltage testing rehearsal device for main equipment of transformer substation feels camera and controller through setting up body for personnel can show various equipment scenes in the transformer substation through the software simulation program and the display screen that set up in the host computer, thereby simulate various equipment of actual operation transformer substation in the reality, and then strengthened the reality sense of high-voltage testing rehearsal.
Drawings
FIG. 1 is a perspective view of the present invention;
FIG. 2 is a side view of the structure of the present invention;
fig. 3 is the utility model discloses the camera schematic diagram is felt to the structure body.
Wherein: 1. a display screen; 2. a host; 3. a motion sensing camera; 301. a camera body; 302. a camera head bracket; 303. a bracket mounting hole; 4. a chassis; 5. a universal wheel; 6. a controller bracket; 7. a controller; 8. and a USB interface.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, a high-voltage test preview device for augmented reality substation main equipment comprises a display screen 1, a main unit 2 is installed at the rear part of the display screen 1, the rear side of the display screen 1 and the front side of the main unit 2 are connected into a whole through screws, the display screen 1 and the main unit 2 are connected through an HDMI data line, a plurality of USB interfaces 8 are installed at one side of the main unit 2, one of the USB interfaces 8 is connected with a motion sensing camera 3 through a data line, a motion sensing camera 3 is installed at the rear side of the middle of the upper part of the display screen 1 through a screw hole, the motion sensing camera 3 comprises a camera main body 301, a camera support 302 and a support installation hole 303, the camera main body 301 is connected with a top shell of the display screen 1 through a support installation hole 303 formed on the surface of the camera support 302 through screws, a bottom frame 4 is installed at the bottom of the main unit 2, and a universal wheel 5 is installed, the universal wheels 5 are four in number and are respectively arranged at the front end and the rear end of the cross rods at the two sides of the bottom frame 4, a controller support 6 is fixedly arranged on one side of the top of the bottom frame 4, and a controller 7 is placed inside the controller support 6.
When using, this augmented reality's high-voltage testing rehearsal device for main equipment of transformer substation, 5 universal wheels through 4 bottoms of chassis set up remove to the rehearsal position, rehearsal operating personnel takes out controller 7 from controller support 6 and holds in the hand, shoot response operating personnel operation controller 7 and button through setting up body sensing camera 3 and carry out corresponding motion, make operating personnel can show various equipment scenes in the transformer substation through the software simulation program that sets up in the host computer 2 and display screen 1, thereby simulate various equipment at actual operation transformer substation in reality, and then strengthened the realistic sensation of high-voltage testing rehearsal.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides an augmented reality's high-voltage test rehearsal device for main equipment of transformer substation, includes display screen (1), its characterized in that: display screen (1) rear portion installation is provided with host computer (2), host computer (2) one side has been seted up the through-hole installation and has been provided with USB interface (8), the rear side is opened to establish screw hole installation in the middle of display screen (1) upper portion and is provided with body and feels camera (3), body feels camera (3) and includes camera main part (301), camera support (302) and support mounting hole (303), host computer (2) bottom installation is provided with chassis (4), chassis (4) bottom installation is provided with universal wheel (5), chassis (4) top one side is fixed and is provided with controller support (6), controller (7) have been placed to controller support (6) inside.
2. The high-voltage test rehearsal device for the main equipment of augmented reality of claim 1, characterized in that: the rear side of the display screen (1) is connected with the front side of the host (2) into a whole through screws, and the display screen (1) is connected with the host (2) through an HDMI data line.
3. The high-voltage test rehearsal device for the main equipment of augmented reality of claim 1, characterized in that: USB interface (8) quantity is a plurality of, and one of them is connected through the data line with body and feels camera (3).
4. The high-voltage test rehearsal device for the main equipment of augmented reality of claim 1, characterized in that: the camera body (301) is connected with a shell at the top of the display screen (1) through screws through a support mounting hole (303) formed in the surface of the camera support (302).
5. The high-voltage test rehearsal device for the main equipment of augmented reality of claim 1, characterized in that: the number of the universal wheels (5) is four, and the four universal wheels are respectively arranged at the front end and the rear end of the cross rods on the two sides of the bottom frame (4).
CN202022028949.6U 2020-09-16 2020-09-16 Reality-augmented high-voltage test preview device for main equipment of transformer substation Active CN213457204U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022028949.6U CN213457204U (en) 2020-09-16 2020-09-16 Reality-augmented high-voltage test preview device for main equipment of transformer substation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022028949.6U CN213457204U (en) 2020-09-16 2020-09-16 Reality-augmented high-voltage test preview device for main equipment of transformer substation

Publications (1)

Publication Number Publication Date
CN213457204U true CN213457204U (en) 2021-06-15

Family

ID=76325178

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022028949.6U Active CN213457204U (en) 2020-09-16 2020-09-16 Reality-augmented high-voltage test preview device for main equipment of transformer substation

Country Status (1)

Country Link
CN (1) CN213457204U (en)

Similar Documents

Publication Publication Date Title
CN102798802A (en) Cable fault locating visual simulation experimental method
CN202855106U (en) Multi-screen simulator for simulating standby hard panel combination of nuclear power station
CN111210696B (en) Teaching control end simulator, student end simulator and radar equipment comprehensive training simulation system
CN101635106A (en) Simulation training system of centralized control station
CN213457204U (en) Reality-augmented high-voltage test preview device for main equipment of transformer substation
CN110444073A (en) A kind of remote online teaching and training operating platform
CN211555173U (en) Intelligent low-voltage distribution network operation and maintenance comprehensive simulation system
CN201378367Y (en) Electronic experimental box
CN206249032U (en) A kind of man-machine interactive system based on emulation aircraft
CN205486883U (en) Power cable fault tests teaching system
Dong et al. Research on overhead crane training system and its construction based on virtual reality
CN205753023U (en) Machine room power distribution cabinet
CN201765712U (en) Simulated training device for smoke vehicle
CN210515727U (en) Interactive installation is used in animation design teaching
CN104849885B (en) The integrated apparatus and method of liquid crystal module test are realized based on industrial computer
CN208861495U (en) A kind of computer teaching multifunctional assisting device
CN209471574U (en) A kind of marketing sand table
CN211555171U (en) Novel Cube-Box virtual simulation all-in-one machine
CN206312403U (en) A kind of science and engineering science and education analog machine based on virtual reality technology
CN112578684A (en) Intelligent Internet of things terminal simulation device
CN218513075U (en) Simulation training and examining device for cable head manufacturing
CN204791768U (en) Device is instructed to multi -functional reality that area is little
CN220085516U (en) Intelligent substation simulation training system
CN219418322U (en) Fill electric pile dress and transfer teaching equipment
CN215341055U (en) PCB hardware test equipment based on computer

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant