CN213450490U CN202021882375.2U CN202021882375U CN213450490U CN 213450490 U CN213450490 U CN 213450490U CN 202021882375 U CN202021882375 U CN 202021882375U CN 213450490 U CN213450490 U CN 213450490U
Authority
CN
China
Prior art keywords
drainage
tunnel
temporary
lining
lateral
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021882375.2U
Other languages
Chinese (zh)
Inventor
徐冲
何永旺
李国良
陈霄汉
许宇
杨木高
李宁
徐亚峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN202021882375.2U priority Critical patent/CN213450490U/en
Application granted granted Critical
Publication of CN213450490U publication Critical patent/CN213450490U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a sewage-cleaning and diversion system for TBM tunnel downslope drainage, which comprises a longitudinal central drainage ditch at the inverted arch of the tunnel and longitudinal lateral drainage ditches or temporary drainage pipes at the two sides of the tunnel in two lining sections, wherein the outer sides of the lateral drainage ditches or the temporary drainage pipes are communicated with longitudinal blind pipes at the arch feet through transverse drainage pipes; construction sewage in the tunnel is scattered and collected and flows to the tunnel opening along the slope through the central drainage ditch; the clean water seeped out of the surrounding rock behind the lining of the two lining sections automatically flows out of the hole through the lateral drainage ditch or the temporary drainage pipe. The utility model has the characteristics of the pipeline overall arrangement is clear, and the reposition of redundant personnel route of decontaminating is clear and definite, and on-the-spot installation and management are convenient etc, to the percolating water and gush the big TBM tunnel construction of water yield, can effectively utilize the function of the prefabricated inverted arch piece central escape canal of TBM in the construction period to leave out processing procedure such as the outer separation of sewage hole, sediment, realized clear water and sewage at the effective separation of source and reduce the sewage treatment cost.

Description

A diversion system that decontaminates for TBM tunnel is along with slope drainage
Technical Field
The utility model relates to a tunnel construction engineering technical field, concretely relates to a reposition of redundant personnel system of decontaminating for TBM tunnel is along with slope drainage.
Background
In recent years, railway construction projects are developed rapidly, railway tunnels often pass through environment-friendly and water source protection areas of different levels, railway engineering construction and ecological environment protection are increasingly concerned by people, wherein sewage generated by tunnel construction is mixed with surrounding rock seepage and gushing water to form sewage which is an important pollution source in tunnel construction, and the ecological environment and underground water environment of an area are seriously affected by improper treatment of the sewage. The separation of decontaminating is often neglected to traditional tunnel work progress, or does not do the direct drainage of handling outside the hole, causes very big destruction to ecological environment, or all carries out sewage treatment, causes great economic input and waste.
Disclosure of Invention
The utility model aims at providing a reposition of redundant personnel system of decontaminating for TBM tunnel cisdocks drainage, the reposition of redundant personnel effect of decontaminating is showing, can possess effectively to reduce the sewage treatment cost, has important engineering application and spreading value.
The utility model discloses the technical scheme who adopts does:
the utility model provides a clean up reposition of redundant personnel system for TBM tunnel downslope drainage which characterized in that:
the system comprises a longitudinal central drainage ditch at the inverted arch of the tunnel and longitudinal lateral drainage ditches or temporary drainage pipes at two sides of the tunnel in the two lining sections, wherein the outer sides of the lateral drainage ditches or the temporary drainage pipes are communicated with longitudinal blind pipes at the arch springing through transverse drainage pipes;
construction sewage in the tunnel is scattered and collected and flows to the tunnel opening along the slope through the central drainage ditch;
the clean water seeped out of the surrounding rock behind the lining of the two lining sections automatically flows out of the hole through the lateral drainage ditch or the temporary drainage pipe.
The secondary lining section comprises a lateral drainage ditch unfinished part and a lateral drainage ditch finished part, wherein a temporary drainage pipe is arranged at the lateral drainage ditch position of the lateral drainage ditch unfinished part and is longitudinally connected into the lateral drainage ditch.
The front of the two lining sections is a tunneling section and a primary lining section of the tunnel in sequence, and a transverse temporary water retaining wall is arranged between the primary lining section and the two lining sections.
The temporary water retaining wall is a mortar concrete wall.
The temporary drain pipe is supported by the fixing frame.
The fixing frame is a longitudinal angle steel, is positioned on the inner wall of the lining and forms a supporting groove of the temporary drainage pipe together with the inner wall of the lining.
The utility model has the advantages of it is following:
the utility model has the characteristics of the pipeline overall arrangement is clear, and the reposition of redundant personnel route of decontaminating is clear and definite, and on-the-spot installation and management are convenient etc, to the percolating water and the big TBM tunnel construction of gushing the water yield, can effectively utilize the function of the prefabricated inverted arch piece central escape canal of TBM in the construction period to having left out the sewage hole and having separated outward, processing procedure such as deposit, realized clear water and sewage and reduce the sewage treatment cost at the effective separation of source, guarantee engineering construction and ecological environment protection harmonious and go on one's hand.
Drawings
FIG. 1 is a plan view of the utility model of the TBM clean-up and diversion for the construction along the slope;
FIG. 2 is a schematic sectional view taken along line A-A in FIG. 1;
FIG. 3 is a schematic cross-sectional view B-B of FIG. 1;
FIG. 4 is a schematic cross-sectional view of C-C in FIG. 1
In the figure: 1-central drainage ditch, 2-tunnel portal, 3-temporary drainage pipe, 4-lateral drainage ditch, 5-temporary water retaining wall, 6-longitudinal blind pipe, 7-transverse drainage pipe, 8-fixed frame, 9-tunnel face, 10-rock stratum, 11-tunneling section, 12-primary lining section, 13-unfinished secondary lining section of lateral drainage ditch, 14-finished secondary lining section of lateral drainage ditch, 15-clear water discharge, 16-sewage discharge, 17-top surface of inner rail, and 18-primary support.
Detailed Description
The present invention will be described in detail with reference to the following embodiments.
The utility model relates to a sewage-cleaning and diversion system for TBM tunnel downslope drainage, which comprises a longitudinal central drainage ditch 1 at the inverted arch of the tunnel, and longitudinal lateral drainage ditches 4 or temporary drainage pipes 3 at the two sides of the tunnel in two lining sections, wherein the outer sides of the lateral drainage ditches 4 or the temporary drainage pipes 3 are communicated with longitudinal blind pipes 6 at the arch feet through transverse drainage pipes 7; construction sewage in the tunnel is scattered and collected and flows to a tunnel opening 2 along the slope through a central drainage ditch 1; the clean water seeped out of the surrounding rock behind the lining of the two lining sections flows out of the hole through the lateral drainage ditch 4 or the temporary drainage pipe 3.
The secondary lining section includes a side drain unfinished portion and a side drain finished portion, and a temporary drain pipe 3 is provided at a side drain position of the side drain unfinished portion to be longitudinally accessed to a side drain 4.
The front of the second lining section is a tunneling section 11 and a primary lining section 12 of the tunnel in sequence, and a transverse temporary water retaining wall 5 is arranged between the primary lining section 12 and the second lining section. The temporary water retaining wall 5 is a mortar concrete wall body, is arranged at the end part of the temporary drain pipe 3 and plays a role in plugging, and prevents sewage collected by the tunneling section 11 and the primary lining section 12 from flowing into the temporary drain pipe.
The temporary drain pipe 3 is supported by a fixing frame 8. The fixing frame 8 is a longitudinal angle steel, is positioned on the inner wall of the lining, and forms a supporting groove of the temporary drain pipe 3 together with the inner wall of the lining.
The invention will be described in further detail with reference to the accompanying drawings:
the tunnel face and the water gushing, water seepage and construction sewage which are already applied as the primary lining section are scattered and collected and automatically flow to the tunnel portal 2 along the slope through the central drainage ditch 1; the clean water seeped out of the surrounding rocks behind the lining which is constructed into the two lining sections flows to the outside of the hole by the temporary drainage pipe 3 arranged in the side drainage ditch 4.
The central drainage ditch 1 is reserved in advance by TBM prefabricated inverted arch blocks. The temporary drain pipes 3 and the side drains 4 are symmetrically arranged on both sides of the tunnel.
The TBM tunnel construction section comprises a tunneling section, a primary lining section and a secondary lining section, and the distance between the tunnel face of the tunneling section and the temporary waterproof wall 5 is not less than 500 m; the two lining sections comprise an unfinished lateral drainage ditch section and a finished lateral drainage ditch section.
A temporary water-stop wall 5 is arranged between the primary lining section and the secondary lining section to separate sewage and clean water. The temporary diaphragm wall 5 may be constructed using mortar concrete.
And the water seepage of the surrounding rocks of the two lining sections is guided and drained through a longitudinal blind pipe 6 and a transverse drain pipe 7. At the second lining section where the lateral drainage ditch 4 is not constructed, the transverse drainage pipe 7 is communicated with the temporary drainage pipe 3; and the transverse drain pipe 7 is communicated with the side drains 4 and the central drain 1 at the two lining sections of the constructed side drains 4.
The temporary drain pipe 3 is fixed by a fixing frame 8, and the drain pipe can be made of PVC plastic, cast iron, steel pipes and other materials or composite pipes; the fixing frame 8 can be made of simple angle steel materials.
The pipe diameter of the temporary drain pipe 3 must not be larger than the width of the side drain 4 and ensures easy installation.
The content of the present invention is not limited to the examples, and any equivalent transformation adopted by the technical solution of the present invention is covered by the claims of the present invention by those skilled in the art through reading the present invention.

Claims (6)

1. The utility model provides a clean up reposition of redundant personnel system for TBM tunnel downslope drainage which characterized in that:
the system comprises a longitudinal central drainage ditch (1) at the inverted arch of the tunnel, and longitudinal lateral drainage ditches (4) or temporary drainage pipes (3) at two sides of the tunnel in the two lining sections, wherein the outer sides of the lateral drainage ditches (4) or the temporary drainage pipes (3) are communicated with longitudinal blind pipes (6) at the arch feet through transverse drainage pipes (7);
construction sewage in the tunnel is scattered and collected and flows to the tunnel opening (2) along the slope through the central drainage ditch (1);
the clean water seeped out from the surrounding rock behind the lining of the two lining sections automatically flows out of the hole through the lateral drainage ditch (4) or the temporary drainage pipe (3).
2. The cleaning and distributing system for draining water along the slope of the TBM tunnel according to claim 1, wherein:
the secondary lining section comprises a lateral ditch unfinished part and a lateral ditch finished part, and a temporary drain pipe (3) is arranged at the lateral ditch position of the lateral ditch unfinished part and longitudinally accesses the lateral ditch (4).
3. The cleaning and distributing system for draining water along the slope of the TBM tunnel according to claim 2, wherein:
the front of the second lining section is provided with a tunneling section (11) and a primary lining section (12) of the tunnel in sequence, and a transverse temporary water retaining wall (5) is arranged between the primary lining section (12) and the second lining section.
4. The cleaning and distributing system for draining water along the slope of the TBM tunnel according to claim 3, wherein:
the temporary water retaining wall (5) is a mortar concrete wall.
5. The cleaning and distributing system for draining water along the slope of the TBM tunnel according to claim 4, wherein:
the temporary drain pipe (3) is supported by a fixing frame (8).
6. The cleaning and distributing system for draining water along the slope of the TBM tunnel according to claim 5, wherein:
the fixing frame (8) is a longitudinal angle steel, is positioned on the inner wall of the lining, and forms a supporting groove of the temporary drain pipe (3) together with the inner wall of the lining.
CN202021882375.2U 2020-09-02 2020-09-02 A diversion system that decontaminates for TBM tunnel is along with slope drainage Active CN213450490U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021882375.2U CN213450490U (en) 2020-09-02 2020-09-02 A diversion system that decontaminates for TBM tunnel is along with slope drainage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021882375.2U CN213450490U (en) 2020-09-02 2020-09-02 A diversion system that decontaminates for TBM tunnel is along with slope drainage

Publications (1)

Publication Number Publication Date
CN213450490U true CN213450490U (en) 2021-06-15

Family

ID=76319658

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021882375.2U Active CN213450490U (en) 2020-09-02 2020-09-02 A diversion system that decontaminates for TBM tunnel is along with slope drainage

Country Status (1)

Country Link
CN (1) CN213450490U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482714A (en) * 2021-08-17 2021-10-08 中铁隧道局集团有限公司 Long-distance high-permeability tunnel large reverse slope construction sewage disposal and diversion system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482714A (en) * 2021-08-17 2021-10-08 中铁隧道局集团有限公司 Long-distance high-permeability tunnel large reverse slope construction sewage disposal and diversion system
CN113482714B (en) * 2021-08-17 2023-07-07 中铁隧道局集团有限公司 Sewage-cleaning and shunting system for large-counter-slope construction of long-distance high-permeability tunnel

Similar Documents

Publication Publication Date Title
CN206386134U (en) A kind of Underground Subway Station guarded drainage construction
CN107131001B (en) High-speed railway tunnel with water delivery and traffic functions
CN206386150U (en) A kind of Underground Subway Station draining and examination and repair system
CN111005759A (en) Super long tunnel separation drainage structures of decontaminating suitable for cold areas
KR101039316B1 (en) Drainage structure for tunnel
JP2016173003A (en) Water leakage countermeasure construction method for tunnel constructed using natm construction method
CN109611148B (en) Method for removing dirt and shunting tunnel construction wastewater of single-track railway crosshole
CN213450490U (en) A diversion system that decontaminates for TBM tunnel is along with slope drainage
CN108757027A (en) Multi-functional lobby water system in a kind of tunnel
CN105888693A (en) Treating construction method for water burst of small underground river of highway tunnel
CN207568626U (en) A kind of tunnel structure for expansive stratum
CN205654378U (en) Novel visual operation highway tunnel side wall foot of a wall drainage system
CN108571342A (en) A kind of Middle Wall of Multi-Arch Highway Tunnel top waterproof/drainage structure and its construction method
CN107761763A (en) A kind of pipe gallery and its application method
CN108590752A (en) Draining repair system and its construction method after a kind of underdrain formula tunnel-liner
CN204646253U (en) A kind of small interval Four-Lane Road Shallow-buried Large-span Tunnel structure
CN105275001A (en) Novel replaceable hard and rigid combined double-layer curved-grain net-shaped pervious pipe for slope
CN206903689U (en) A kind of and water delivery and the Railway Tunnel of communication function
CN212359860U (en) Urban tunnel sewage-cleaning shunting drainage system
CN207362974U (en) A kind of urban road rain water collecting system
CN208473932U (en) Multi-functional lobby water system in a kind of tunnel
CN207760681U (en) A kind of discharge structure of municipal road pavement
CN205062825U (en) Novel removable hard netted pipe that permeates water of double -deck bent line of tough combination of side slope
CN212248659U (en) Cleaning system of dark culvert sewage intercepting pipe
CN219932241U (en) Tunnel drainage structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant