CN213445485U - Formula of book material maintenance system - Google Patents

Formula of book material maintenance system Download PDF

Info

Publication number
CN213445485U
CN213445485U CN202022112957.9U CN202022112957U CN213445485U CN 213445485 U CN213445485 U CN 213445485U CN 202022112957 U CN202022112957 U CN 202022112957U CN 213445485 U CN213445485 U CN 213445485U
Authority
CN
China
Prior art keywords
controller
blanking
formula
feeding
maintenance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022112957.9U
Other languages
Chinese (zh)
Inventor
廖章安
罗炳军
曾令建
王有颖
陈东海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Jusen Intelligent Equipment Co ltd
Original Assignee
Guangdong Jusen Intelligent Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Jusen Intelligent Equipment Co ltd filed Critical Guangdong Jusen Intelligent Equipment Co ltd
Priority to CN202022112957.9U priority Critical patent/CN213445485U/en
Application granted granted Critical
Publication of CN213445485U publication Critical patent/CN213445485U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Controlling Rewinding, Feeding, Winding, Or Abnormalities Of Webs (AREA)

Abstract

The utility model relates to an overhaul equipment technical field discloses a formula of book material maintenance system, which comprises a controller, loading attachment, first conveyer, overhaul the device, second conveyer and unloader set gradually along the direction of transmission of a formula of book material, loading attachment includes the material loading installation axle, the formula of book material cover that waits to overhaul is established on the material loading installation axle, unloader includes unloading installation axle, material loading installation axle is connected with first drive arrangement, unloading installation axle is connected with second drive arrangement, first drive arrangement, second drive arrangement all is connected with the controller electricity. Adopt the utility model discloses technical scheme's formula of book material maintenance system can realize a formula of book material and roll back the function, can provide invariable tension for entire system, avoids a formula of book material to be pulled out of shape, the material collapses, corrugates or splits, influences the performance of a formula of book material.

Description

Formula of book material maintenance system
Technical Field
The utility model relates to an overhaul technical field, especially relate to a formula of book material overhauls system.
Background
The rolled materials are favored due to the excellent properties of light weight, thin thickness, self-bending and folding and the like, most of the examination and repair of the rolled materials are carried out manually, the manual examination cost is high, and the efficiency is low; scratch and wrinkle are easily caused to the circuit board in the manual detection process, and the structure and the service performance of the circuit board are damaged.
The automatic overhaul system that has now can't realize returning back the function and guarantee that a formula material is received neatly, traditional old equipment book formula material can only advance and guarantee the precision of the regularity of receiving the material through deviation correcting system, the regularity of a formula material need not be followed in the new arrangement to convenient next process ability automatic feeding, along with the improvement of industrialization intelligent degree, many piece defects of FPC book formula material are 0, the yield is high, the customer end is all the selective examination in order to can improve production efficiency a lot of FPC book formula materials, so can realize that a formula material is backed and guarantee to receive the material regularity and be imperative. Furthermore, the traditional equipment adopts a step wheel form, a round roller drives the roller to float freely up and down through a rolling material, constant tension cannot be provided, the constant tension of the rolling material depends on the weight of the roller, and the rolling materials at a plurality of client sides are thin, easy to wrinkle and easy to pull and deform, so that the work of the next process is influenced.
SUMMERY OF THE UTILITY MODEL
The utility model aims at: the utility model provides a formula of book material overhauls system, this formula of book material overhauls system can realize a formula of book material and roll back the function, the material that need not to wait whole roll overhauls and takes out again, the selective examination is accomplished, the formula of book material that detects can directly return to loading attachment on, take away, save time, improve maintenance efficiency, can provide invariable tension for entire system, solve the difficult even tension of control of traditional segment difference wheel structure and lead to a formula of book material by the tensile deformation, the material collapses, corrugate or fracture, the performance of the formula of book material is influenced.
In order to achieve the purpose, the utility model provides a formula of book material overhauls system, including controller, loading attachment, first conveyer, maintenance device, second conveyer and unloader, loading attachment first conveyer overhaul the device second conveyer reaches unloader sets gradually along the direction of transmission of a formula of book material, loading attachment includes the material loading installation axle, and the formula of book material cover that waits to overhaul is established material loading installation epaxial, unloader includes unloading installation axle, the material loading installation axle is connected with first drive arrangement, unloading installation axle is connected with second drive arrangement, first drive arrangement second drive arrangement all with the controller electricity is connected.
Preferably, the feeding installation shaft is arranged below the first conveying device, and the discharging installation shaft is arranged below the second conveying device.
As a preferred scheme, a protective film winding shaft for winding the protective film on the surface of the rolled material is arranged on one side of the feeding installation shaft, and a protective film feeding shaft for covering the protective film on the feeding installation shaft is arranged on one side of the feeding installation shaft.
Preferably, the first conveying device comprises a plurality of feeding conveying rollers and a feeding tension controller for adjusting tension of the feeding conveying rollers, the feeding tension controller is electrically connected with the controller, and a first conveying surface is defined on the upper surfaces of the feeding conveying rollers.
Preferably, a connection platform is arranged above the first conveying surface.
As a preferred scheme, a first maintenance guide roller is arranged between the first conveying device and the maintenance device, a feeding ultrasonic deviation correction controller is arranged between the first conveying device and the first maintenance guide roller, and the feeding ultrasonic deviation correction controller is electrically connected with the controller.
As preferred scheme, overhaul the device including overhauing platform, scanner and optical identifier, the scanner reaches optical identifier slides and sets up overhaul the top of platform, the scanner reaches optical identifier all is connected with the controller electricity, overhaul the platform with be equipped with the second between the first maintenance guide roller and overhaul the guide roller.
As preferred scheme, the end of overhauing the platform is equipped with the third and overhauls the direction roller, unloader with overhaul and be equipped with the fourth and overhaul the direction roller between the device, unloader includes a plurality of unloading conveying rollers and is used for adjusting the tensile unloading tension controller of unloading conveying roller, unloading tension controller with the controller electricity is connected, and is a plurality of the second conveying surface is injectd to the upper surface of unloading conveying roller.
Preferably, a blanking guide roller is arranged between the second conveying device and the blanking device.
As a preferred scheme, a blanking ultrasonic deviation-rectifying controller is arranged at the tail end of the second conveying device and arranged between the blanking conveying roller and the blanking guide roller, and the blanking ultrasonic deviation-rectifying controller is electrically connected with the controller.
The embodiment of the utility model provides a formula of book material maintenance system, compared with the prior art, its beneficial effect lies in:
the utility model discloses a formula of book material maintenance system overhauls a formula material through setting up consecutive loading attachment, first conveyer, maintenance device, second conveyer and unloader, uses automatic material loading, detection, has avoided prior art to lean on the manual work to detect, and is inefficient, causes circuit board fish tail and fold easily among the manual work testing process, destroys the structure and the performance scheduling problem of circuit board. Further, the yields when a roll of formula material is higher, only need carry out the first half spot check to the thing of lapping, first drive arrangement of accessible controller control and second drive arrangement, reversal material loading installation axle and unloading installation axle, thereby realize a roll of formula material and roll back the function, the material that need not wait whole roll overhauls takes out again, the spot check is accomplished, the roll formula material that detects can directly return to on the loading attachment, take away, save time, the efficiency of overhaul is improved, the problem that just can take out a roll formula material after having avoided needing whole roll to detect among the prior art, the efficiency of overhaul has been improved.
Drawings
FIG. 1 is a schematic structural diagram of a roll material maintenance system according to an embodiment of the present invention;
FIG. 2 is a schematic diagram of a transmission structure of a roll material overhaul system according to an embodiment of the present invention;
in the figure, 1, a feeding device, 11, a feeding installation shaft, 12, a protective film furling shaft, 13, a feeding guide roller, 2, a first conveying device, 21, a feeding tension controller, 22, a first feeding roller, 23, a second feeding roller, 24, a third feeding roller, 25, a fourth feeding roller, 26, a feeding ultrasonic deviation correction controller, 27, a connection platform, 28, a first overhaul guide roller, 3, an overhaul device, 31, a second overhaul guide roller, 32, an overhaul platform, 33, a scanner, 34, an optical identifier, 35, a third overhaul guide roller, 4, a second conveying device, 41, a blanking tension controller, 42, a fourth overhaul guide roller, 43, a first blanking roller, 44, a second blanking roller, 45, a third blanking roller, 46, a blanking ultrasonic deviation correction controller, 47, a blanking guide roller, 5, a blanking device, 51. blanking installation shaft, 52, protective film feeding shaft, 6 and display.
Detailed Description
The following detailed description of the embodiments of the present invention is provided with reference to the accompanying drawings and examples. The following examples are intended to illustrate the invention, but are not intended to limit the scope of the invention. It is to be understood that the embodiments described are only some embodiments of the invention, and not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
It should be understood that the terms "first", "second", etc. are used herein to describe various information, but the information should not be limited to these terms, and these terms are only used to distinguish one type of information from another. For example, "first" information may also be referred to as "second" information, and similarly, "second" information may also be referred to as "first" information, without departing from the scope of the present invention.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "connected" and "connected" are to be interpreted broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
It should be noted that the arrow direction in the drawings is the moving direction of the rolled material in the maintenance state.
As shown in fig. 1 to 2, the utility model discloses a formula of book material overhauls system of preferred embodiment, including controller (not shown in the figure), loading attachment 1, first conveyer 2, overhaul device 3, second conveyer 4 and unloader 5 set gradually along the direction of transmission of formula of book material, loading attachment 1 includes material loading installation axle 11, the formula of book material cover that waits to overhaul is established on material loading installation axle 11, unloader 5 includes unloading installation axle 51, material loading installation axle 11 is connected with first drive arrangement (not shown in the figure), unloading installation axle 51 is connected with second drive arrangement (not shown in the figure), first drive arrangement, second drive arrangement all is connected with the controller electricity.
Based on above technical scheme, overhaul device 3, second conveyer 4 and unloader 5 through setting up consecutive loading attachment 1, first conveyer 2, maintenance device and examining and repairing the formula material of book, use automatic material loading, detect, avoided prior art to lean on the manual work to detect, it is inefficient, cause circuit board fish tail and fold easily among the manual work testing process, destroy the structure and performance scheduling problem of circuit board. Further, the yields when a roll of formula material is higher, only need carry out the first half spot check to the thing of lapping, accessible controller control first drive arrangement and second drive arrangement, reverse material loading installation axle 11 and unloading installation axle 51, thereby realize a roll of formula material and roll back the function, the material that need not to wait the whole book overhauls takes out again, the spot check is accomplished, the roll formula material that detects can directly return to loading attachment 1 on, take away, save time, improve maintenance efficiency, the problem that the formula material could be taken out after having avoided needing the whole roll to detect among the prior art, the efficiency of overhauing is improved.
Further, the feeding installation shaft 11 is arranged below the first conveying device 2, the discharging installation shaft 51 is arranged below the second conveying device 4, the feeding device 1 is arranged below the first conveying device 2, and the discharging device 5 is arranged below the second conveying device 4, so that the space is saved, and the arrangement of a rolled material maintenance system is facilitated.
Preferably, a protective film furling shaft 12 for rolling the protective film on the surface of the rolled material is arranged on one side of the feeding mounting shaft 11, and usually, some rolled materials are provided with copper wires, like a flexible circuit board, so that in order to avoid friction between copper and influence the use performance of the materials, a layer of film is added to play a role in protection; when unreeling and overhauling, the protective film furling shaft 12 is used for furling the protective film, the whole roll material is firstly sleeved on the feeding installation shaft 11, the end of the outmost layer of the roll material bypasses a plurality of feeding rollers and is connected onto the protective film furling shaft 12 through the overhauling device 3 and then bypasses a plurality of rollers. A protective film feeding shaft 52 for covering the protective film on the blanking mounting shaft 51 is provided on one side of the blanking mounting shaft 51. When the rolled material is rolled after being overhauled, a layer of interlayer paper needs to be added to protect the rolled material; the interlayer paper is sleeved on the protective film feeding shaft 52, and the end of the outermost layer of the interlayer paper and the overhauled roll-type material are connected on the blanking mounting shaft 51 to provide protection for the overhauled roll-type material.
Specifically, in this embodiment, the driving devices are motors, and the feeding device motor, the discharging device motor and the transmission mechanism motor are simultaneously started, the pneumatic shafts of the feeding device 1 and the discharging device 5 tension the rolled materials thereon and rotate, the rollers of the first conveying device 2 and the second conveying device 4 rotate, the rolled materials are pulled to move from front to back, the protective film is received on the protective film winding shaft 12, and therefore, the rolled materials are separated from the protective film.
In this embodiment, the feeding mounting shaft 11, the discharging mounting shaft 51, the protective film furling shaft 12 and the protective film feeding shaft 52 are all inflatable shafts, and the inflatable shafts are inflated by the rubber air bags to inflate the keybars on the inflatable shafts, so as to tension the material on the inflatable shafts, thereby avoiding the problem that the rolled material is easily damaged by using other positioning devices on the premise of ensuring the reliable installation of the rolled material and the protective film.
Further, the first conveying device 2 comprises a plurality of feeding conveying rollers and a feeding tension controller 21 used for adjusting tension of the feeding conveying rollers, the feeding tension controller 21 is electrically connected with the controller, and a first conveying surface is limited on the upper surfaces of the feeding conveying rollers.
Specifically, the feeding conveying rollers on the first conveying device 2 are marked as a first feeding roller 22, a second feeding roller 23, a third feeding roller 24 and a fourth feeding roller 25 in sequence, the discharging conveying rollers of the second conveying device 4 are marked as a first discharging roller 43, a second discharging roller 44 and a third discharging roller 45 in sequence, in this embodiment, the connection platform 27 is arranged above the middle of the first feeding roller 22 and the second feeding roller 23, the rolled material enters the first conveying device 2 through the feeding mounting shaft 11 and the feeding guide roller 13, then enters the lower part of the third feeding roller 24 through the first feeding roller 22, the connection platform 27 and the upper part of the second feeding roller 23 in sequence, then winds from the upper part of the fourth feeding roller 25 to the lower part of the first maintenance guide roller 28, then winds to the second maintenance guide roller 31 and enters the maintenance device 3, then, the steel wire is conveyed from the upper part of the third maintenance guide roller 35 to the lower part of the second blanking roller 44, then wound above the first blanking roller 43, wound below the second blanking roller 44, wound above the third blanking roller 45, and wound to the blanking mounting shaft 51 through the blanking guide roller 47 to be wound.
Preferably, a connection platform 27 is arranged above the first conveying surface, and the rolled materials slide over the connection platform 27, so that the rolled materials are smooth. Further, the next roll material can be manually connected to the roll material on the current equipment at the connection platform, so that continuous operation is realized.
In this embodiment, a first maintenance guide roller 28 is arranged between the first conveying device 2 and the maintenance platform 32, a feeding ultrasonic deviation correction controller 26 is arranged between the first conveying device 2 and the first maintenance guide roller 28, and the feeding ultrasonic deviation correction controller 26 is electrically connected with the controller.
Specifically, the feeding ultrasonic deviation rectifying controller 26 is installed at the front end of the first conveying device 2, the feeding ultrasonic deviation rectifying controller 26 comprises a first ultrasonic deviation rectifying sensor located on the front side of the conveying direction of the rolled material and a second ultrasonic deviation rectifying sensor located on the rear side of the conveying direction of the rolled material, when the rolled material deviates from a correct rolling route, the feeding ultrasonic deviation rectifying controller 26 automatically corrects the position of the rolled material, the first ultrasonic deviation rectifying sensor controls the advancing direction, and the second ultrasonic deviation rectifying sensor controls the retreating direction, so that the rolled material can be collected neatly whether the rolled material advances or retreats; the first ultrasonic deviation-rectifying sensor and the second ultrasonic deviation-rectifying sensor detect the variation of the edge position of the rolled material and a set value, feed back the variation to the controller, and convert the variation into a proportional signal after the calculation of the controller program to correct the signal for the driving device, so that the material receiving is tidy.
Specifically, the maintenance device 3 comprises a maintenance platform 32, a scanner 33 and an optical identifier 34, wherein the scanner 33 and the optical identifier 34 are arranged above the maintenance platform 32 in a sliding manner, the scanner 33 and the optical identifier 34 are both electrically connected with the controller, and a second maintenance guide roller 31 is arranged between the maintenance platform 32 and the first maintenance guide roller 28, so that the conveying of the rolled materials is guided, when the rolled materials arrive at the maintenance device 3 first, the optical identifier 34 of the maintenance device 3 identifies images on the rolled materials and displays the images on the display 6; each piece of the rolled material is provided with a two-dimensional code, and the two-dimensional code scanner 33 records the serial number of each piece by scanning the two-dimensional code on the rolled material, so that defective materials can be accurately and quickly found out; two-dimensional code scanner 33 takes notes each two-dimensional code, jumps the material sequence number and also can not make mistakes, realizes preventing slow-witted function. The overhauled rolled material bypasses the second conveying device 4 on the other side of the overhauling device 3 and is rolled on the blanking mounting shaft 51 together with the interlayer paper of the blanking device 5.
Preferably, the end of the maintenance platform 32 is provided with a third maintenance guide roller 35, a fourth maintenance guide roller 42 is arranged between the blanking device 5 and the maintenance device 3, the blanking device 5 comprises a plurality of blanking conveying rollers and a blanking tension controller 41 used for adjusting the tension of the blanking conveying rollers, the blanking tension controller is electrically connected with the controller, and a second conveying surface is limited on the upper surfaces of the blanking conveying rollers.
In the embodiment, a blanking guide roller 47 is arranged between the second conveying device 4 and the blanking device 5, thereby further providing a better guiding function for conveying the rolled materials.
Further, the tail end of the second conveying device 4 is provided with a blanking ultrasonic deviation-rectifying controller 46, the blanking ultrasonic deviation-rectifying controller 46 is arranged between the blanking conveying roller and a blanking guide roller 47, and the blanking ultrasonic deviation-rectifying controller 46 is electrically connected with the controller.
Specifically, the blanking ultrasonic deviation rectifying controller 46 is installed at the rear end of the second conveying device 4, the blanking ultrasonic deviation rectifying controller 46 comprises a third ultrasonic deviation rectifying sensor located on the front side of the conveying direction of the rolled material and a fourth ultrasonic deviation rectifying sensor located on the rear side of the conveying direction of the rolled material, when the rolled material deviates from a correct rolling route, the feeding ultrasonic deviation rectifying controller 26 automatically corrects the position of the rolled material, the third ultrasonic deviation rectifying sensor controls the advancing direction, and the fourth ultrasonic deviation rectifying sensor controls the retreating direction, so that the rolled material can be received neatly whether the rolled material advances or retreats; the third ultrasonic deviation-rectifying sensor and the fourth ultrasonic deviation-rectifying sensor detect the variation of the edge position of the rolled material and a set value, feed back to the controller, and convert the variation into a proportional signal after program calculation of the controller to correct the signal to the driving device, so that the material receiving is tidy.
Preferably, the service device 3 further comprises a display 6, the display 6 is arranged at one side of the service platform 32, and the display 6 is electrically connected with the controller. The display 6 can facilitate the user to observe the maintenance result.
In this embodiment, a set of tension controllers are respectively installed on one side of the feeding device 1 and one side of the discharging device 5, so as to provide constant tension for the whole system, realize synchronization between rollers and uniform control of winding and unwinding, and avoid the phenomenon that the performance of a rolled material is influenced by tensile deformation, material collapse, wrinkling or fracture of the rolled material due to uneven tension; specifically, the tension controller sets a required tension value, the deviation between the tension value in the system and the set tension value is compared, the tension value is input to the PID module and fed back to the servo motor, the servo motor changes the torsion size by changing the output voltage, and the torsion is constant, so that the tension of the whole system is constant.
The utility model discloses a working process does: the whole roll type material is firstly sleeved on the feeding mounting shaft 11 of the feeding device 1, and the end head of the outmost layer of the roll type material bypasses a plurality of transmission rollers, passes through the maintenance device 3, and then bypasses a plurality of transmission rollers to be connected on the discharging mounting shaft 51 of the discharging device 5; the end of the outermost layer of the protective film is connected to the protective film furling shaft 12 to furl the protective film; simultaneously starting a motor of the feeding device 1, a motor of the discharging device 5 and a motor of the transmission mechanism, wherein air expansion shafts of the feeding device 1 and the discharging device 5 tension the rolled materials on the air expansion shafts and rotate, rollers of the transmission mechanism rotate to pull the rolled materials to move forwards, the protective film is received on a protective film rolling shaft 12, and the rolled materials are separated from the protective film; the rolled material firstly reaches the maintenance device 3; the optical identifier 34 of the service device 3 identifies the image on the roll material and displays it on the display 6; each piece of the rolled material is provided with a two-dimensional code, and the two-dimensional code scanner 33 records the serial number of each piece by scanning the two-dimensional code on the rolled material, so that defective materials can be accurately and quickly found out; the two-dimensional code scanner 33 records each two-dimensional code, and the material jumping time sequence number cannot make mistakes, so that the fool-proof function is realized; the overhauled roll-type material bypasses the second conveying device 4 on the other side of the overhauling device 3 and is received on the blanking mounting shaft 51 together with interlayer paper of the protective film feeding mounting shaft 11 of the blanking device 5. The two transmission mechanisms are respectively provided with an ultrasonic deviation correction controller, when the rolled material deviates a correct rolling route, the ultrasonic deviation correction controllers automatically correct the position of the rolled material, and the feeding device 1 and the discharging device 5 are respectively provided with a set of tension controllers to provide constant tension for the whole system, so that the synchronization between the rollers and the uniform control of rolling and unwinding are realized, and the phenomenon that the rolled material is pulled to deform, collapse, wrinkle or fracture due to uneven tension and the performance of the rolled material is influenced is avoided; in the transmission mechanism of the unreeling side, a connection platform is installed, and a next roll of material can be manually connected to the roll of material on the current equipment at the connection platform, so that continuous operation is realized.
To sum up, the embodiment of the utility model provides a formula of book material overhauls system, its formula of book material overhauls system overhauls a formula of book material through setting up consecutive loading attachment 1, first conveyor 2, maintenance device 3, second conveyor 4 and unloader 5, uses automatic material loading, detection, has avoided prior art to lean on the manual work to detect, and is inefficient, causes circuit board fish tail and fold easily among the manual work testing process, destroys the structure and the performance scheduling problem of circuit board. Further, the yields when a roll of formula material is higher, only need carry out the first half spot check to the thing of lapping, accessible controller control first drive arrangement and second drive arrangement, reverse material loading installation axle 11 and unloading installation axle 51, thereby realize a roll of formula material and roll back the function, the material that need not to wait the whole book overhauls takes out again, the spot check is accomplished, the roll formula material that detects can directly return to loading attachment 1 on, take away, save time, improve maintenance efficiency, the problem that the formula material could be taken out after having avoided needing the whole roll to detect among the prior art, the efficiency of overhauing is improved.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "left", "right", "top", "bottom", and the like indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus should not be construed as limiting the present invention.
The foregoing is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, a plurality of modifications and replacements can be made without departing from the technical principle of the present invention, and these modifications and replacements should also be regarded as the protection scope of the present invention.

Claims (10)

1. The utility model provides a formula of book material maintenance system, its characterized in that, includes controller, loading attachment, first conveyer, overhauls device, second conveyer and unloader, loading attachment the first conveyer overhaul the device the second conveyer reaches unloader sets gradually along the transmission direction of a formula of book material, loading attachment includes the material loading installation axle, and the formula of book material cover that treats to overhaul is established on the material loading installation axle, unloader includes the unloading installation axle, the material loading installation axle is connected with first drive arrangement, the unloading installation axle is connected with second drive arrangement, first drive arrangement second drive arrangement all with the controller electricity is connected.
2. The roll material servicing system of claim 1, wherein the load mounting shaft is disposed below the first conveyor and the discharge mounting shaft is disposed below the second conveyor.
3. The roll type material overhauling system according to claim 2, wherein a protective film furling shaft for furling the protective film on the surface of the roll type material is arranged at one side of the feeding installation shaft, and a protective film feeding shaft for covering the protective film on the discharging installation shaft is arranged at one side of the discharging installation shaft.
4. The roll material servicing system of claim 1, wherein the first conveyor comprises a plurality of feed conveyor rollers and a feed tension controller for adjusting tension of the feed conveyor rollers, the feed tension controller electrically connected to the controller, an upper surface of the plurality of conveyor rollers defining a first conveying surface.
5. The roll material servicing system of claim 4, wherein a docking platform is disposed above the first conveying surface.
6. The roll type material overhauling system according to claim 1, wherein a first overhauling guide roller is arranged between the first conveying device and the overhauling device, a feeding ultrasonic deviation rectifying controller is arranged between the first conveying device and the first overhauling guide roller, and the feeding ultrasonic deviation rectifying controller is electrically connected with the controller.
7. The roll material maintenance system according to claim 6, characterized in that said maintenance device comprises a maintenance platform, a scanner and an optical identifier, said scanner and said optical identifier are slidably disposed above said maintenance platform, said scanner and said optical identifier are both electrically connected to a controller, and a second maintenance guide roller is disposed between said maintenance platform and said first maintenance guide roller.
8. The roll type material overhauling system according to claim 7, wherein a third overhauling guide roller is arranged at the end of the overhauling platform, a fourth overhauling guide roller is arranged between the blanking device and the overhauling device, the blanking device comprises a plurality of blanking conveying rollers and a blanking tension controller used for adjusting the tension of the blanking conveying rollers, the blanking tension controller is electrically connected with the controller, and a second conveying surface is defined on the upper surface of the plurality of blanking conveying rollers.
9. The roll material servicing system of claim 8, wherein a blanking guide roller is disposed between the second conveyor and the blanking device.
10. The roll type material overhaul system according to claim 9 wherein the end of the second conveyor is provided with a blanking ultrasonic deviation controller, the blanking ultrasonic deviation controller is disposed between the blanking conveyor roller and the blanking guide roller, and the blanking ultrasonic deviation controller is electrically connected to the controller.
CN202022112957.9U 2020-09-23 2020-09-23 Formula of book material maintenance system Active CN213445485U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022112957.9U CN213445485U (en) 2020-09-23 2020-09-23 Formula of book material maintenance system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022112957.9U CN213445485U (en) 2020-09-23 2020-09-23 Formula of book material maintenance system

Publications (1)

Publication Number Publication Date
CN213445485U true CN213445485U (en) 2021-06-15

Family

ID=76327201

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022112957.9U Active CN213445485U (en) 2020-09-23 2020-09-23 Formula of book material maintenance system

Country Status (1)

Country Link
CN (1) CN213445485U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114044386A (en) * 2021-11-15 2022-02-15 佛山市坦斯盯科技有限公司 Flexible circuit board AOI unreels check out test set
CN115385255A (en) * 2022-09-13 2022-11-25 江阴市福达船舶配件制造有限公司 Control device for reel based on four-reel electric cable reel

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114044386A (en) * 2021-11-15 2022-02-15 佛山市坦斯盯科技有限公司 Flexible circuit board AOI unreels check out test set
CN115385255A (en) * 2022-09-13 2022-11-25 江阴市福达船舶配件制造有限公司 Control device for reel based on four-reel electric cable reel
CN115385255B (en) * 2022-09-13 2024-01-09 江阴市福达船舶配件制造有限公司 Control device for winding drum based on four-winding-drum electric cable winding vehicle

Similar Documents

Publication Publication Date Title
CN213445485U (en) Formula of book material maintenance system
CN110167269B (en) Automatic feeding flying machine
CN110861949A (en) Automatic lifting unreeling quality inspection machine
CN114295627B (en) Full-automatic detection device and detection method for flexible circuit board
CN113320175B (en) Oblique cutting adhesive tape joint device
CN111017600A (en) Membrane class product charging equipment
CN110267436A (en) Automatic feeding
CN218841225U (en) Coil stock loading attachment with rectify and connect material function
CN117485957A (en) Die cutting and discharging device for power battery protection sheet
CN210709947U (en) Full-automatic silica gel protection film production line
CN114709466B (en) Rubberizing equipment
CN215101017U (en) Printed label intelligent detection platform based on artificial intelligence
CN102709584A (en) Battery coiler
CN215620140U (en) Direct-cutting film reverse-pasting device
CN216926609U (en) Detection equipment for electronic tag
CN217691289U (en) Utmost point ear plastic equipment and electric core system of processing
CN112247011B (en) A assembly line for new forms of energy license plate is made
CN213474861U (en) Winding equipment
CN211687511U (en) Unwinding mechanism and quality control machine
CN114243124A (en) Lug shaping method, lug shaping equipment and battery cell processing system
CN111634737A (en) Bidirectional deviation rectifying device
CN110404828B (en) Detection equipment
CN202721230U (en) Battery winding machine
CN221396354U (en) Full-automatic dividing and cutting machine
CN220390315U (en) Online corona device