CN213359247U - Toilet overhead layer structure used in temporary building - Google Patents

Toilet overhead layer structure used in temporary building Download PDF

Info

Publication number
CN213359247U
CN213359247U CN202021115725.2U CN202021115725U CN213359247U CN 213359247 U CN213359247 U CN 213359247U CN 202021115725 U CN202021115725 U CN 202021115725U CN 213359247 U CN213359247 U CN 213359247U
Authority
CN
China
Prior art keywords
crossbeam
rectangular frame
layer structure
steel nail
toilet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021115725.2U
Other languages
Chinese (zh)
Inventor
贾瑞华
肖安
王静
高俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ccteb Infrastructure Construction Investment Co ltd
China Construction Third Engineering Bureau Co Ltd
Original Assignee
Ccteb Infrastructure Construction Investment Co ltd
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ccteb Infrastructure Construction Investment Co ltd, China Construction Third Engineering Bureau Co Ltd filed Critical Ccteb Infrastructure Construction Investment Co ltd
Priority to CN202021115725.2U priority Critical patent/CN213359247U/en
Application granted granted Critical
Publication of CN213359247U publication Critical patent/CN213359247U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sink And Installation For Waste Water (AREA)

Abstract

The utility model discloses a bathroom built on stilts layer structure for in interim building, including stand, crossbeam, connecting rod and set-square, the crossbeam connects into a rectangular frame structure through the steel nail, and the stand passes through the steel nail to be connected the rectangular frame structure's that the crossbeam is constituteed lower extreme, connecting rod pass through steel nail fixed connection in rectangular frame structure's inside, consolidate the crossbeam, and the hookup location of stand and crossbeam has been increased the set-square and has consolidated, and the outer coating of whole built on stilts layer structure is brushed and is had fire prevention anticorrosive coating. The utility model discloses simple structure fills original grit material and changes into modular built on stilts layer structure, and the module can be processed in the major structure construction, then with the synchronous installation of bathroom waterproof layer construction, reduction of erection time, modular structure can be according to bathroom plane arrangement, water and electricity pipeline finely tune, convenient and the cooperation of water and electricity specialty.

Description

Toilet overhead layer structure used in temporary building
Technical Field
The utility model belongs to the technical field of the connecting elements, concretely relates to bathroom built on stilts layer structure for in temporary building.
Background
The temporary building toilet can be installed for convenient water and electricity and can be lifted up the whole toilet or the local part of a squatting pan area, the traditional method is to fill the toilet by adopting a sand stone material, the self weight of the toilet is large, the requirement on the bearing capacity of a foundation is high, and the investment of the foundation part of the temporary building is large. According to the traditional method, gravel filling can be carried out after the waterproof layer of the toilet and the water and electricity pipeline are installed, and the construction period is long.
Disclosure of Invention
In order to overcome technical defect among the prior art, the utility model provides a bathroom built on stilts layer structure for in the temporary building can greatly alleviate its dead weight through modular design, can carry out modular structure processing when the major structure construction simultaneously, then with the synchronous installation of bathroom waterproof layer construction, shorten the construction time. And the quality of the product is guaranteed by off-site processing, and when a certain part is damaged, the corresponding module is replaced, so that the technical problem is solved by later-stage maintenance.
The utility model discloses a following technical scheme realizes above-mentioned purpose, a bathroom built on stilts layer structure for in temporary building, including stand, crossbeam, connecting rod and set-square, the crossbeam connects into a rectangular frame structure through the steel nail, and the stand passes through the steel nail to be connected the lower extreme of the rectangular frame structure that the crossbeam is constituteed, the connecting rod passes through steel nail fixed connection in rectangular frame structure's inside, consolidates the crossbeam, and the hookup location of stand and crossbeam has been increased the set-square and consolidates, and the outer coating of whole built on stilts layer structure is brushed and is had fire prevention anticorrosive coating.
In the above toilet overhead layer structure for use in the temporary building, the upright posts, the cross beams and the connecting rods are wood purlin with a cross-sectional dimension of 80mm × 40 mm.
The above toilet overhead layer structure used in the temporary building is characterized in that the triangular plate is a wood plate with the thickness of 15 mm.
When the overhead layer structure is arranged at the position of the squatting pan, a gap is reserved on a cross beam at one side of the rectangular frame structure and is used as an installation reserved position of a water inlet pipe.
Generally, through the utility model discloses above technical scheme who conceives compares with prior art, can reach following beneficial effect:
1. the utility model relates to a bathroom built on stilts layer structure for in interim building fills original grit material and changes into modular built on stilts layer structure, has alleviateed the dead weight, divide into two kinds of standardized modules to the inner structure of bathroom to through the mode of off-site centralized processing, make its quality can obtain effectual guarantee.
2. The utility model discloses when using, the module can be processed in the major structure construction, then with the synchronous installation of bathroom waterproof layer construction, the reduction of erection time can finely tune according to bathroom planar arrangement, water and electricity pipeline, convenient and water and electricity professional cooperation, removable corresponding module when certain region takes place to damage, the maintenance in the later stage of being convenient for.
Drawings
The following detailed description of embodiments of the present invention is provided with reference to the accompanying drawings, in which:
FIG. 1 is a schematic diagram of a functional division of a toilet;
fig. 2 is a schematic structural diagram of a first toilet overhead floor structural module used in a temporary building according to the present invention;
fig. 3 is a schematic structural view of a second toilet overhead layer structure module used in a temporary building according to the present invention;
in the figure: 1-upright column, 2-cross beam, 3-connecting rod and 4-triangular plate.
Detailed Description
As shown in fig. 1, the layout schematic diagram of the toilet according to the function division is respectively a door, a gateway, a storage cabinet, a wash basin, a squatting pan and a shower room, and each function area is independently provided with a module. The door, the crossing, the storage cabinet, the wash basin and the shower room adopt a first module form according to the trend of pipelines, and the squatting pan adopts a second module form.
As shown in fig. 2, for the utility model discloses module one's structural schematic diagram mainly comprises stand 1, crossbeam 2, tie-beam 3 and set-square 4, at first adopt the steel nail to connect into a rectangular frame with 4 crossbeams 2, secondly adopt the steel nail to be connected the frame that eight stands 1 and four crossbeams 2 are constituteed, adopt the steel nail to be connected two tie-beams 3 again with two of them crossbeams 2, consolidate with set-square 4 between stand 1 and crossbeam 2 at last, the module processing is accomplished the back and is unified to apply paint fire prevention anticorrosive paint with a brush.
As shown in fig. 3, for the utility model discloses the structural schematic diagram of module two, mainly by stand 1, crossbeam 2, tie-beam 3 and set-square 4 are constituteed, at first adopt the steel nail to connect into a rectangular frame with five crossbeams 2 (water inlet one end is because of needing to reserve inlet tube position and need adopt two crossbeams), secondly adopt the steel nail to be connected four stands 1 and the frame that five crossbeams 2 are constituteed, the tie-beam 3 that supports the squatting pan effect with four plays adopts two liang of steel nails to meet the back and is connected with two among them crossbeams 2, adopt the steel nail to be connected two stands 1 and tie-beam 3 again, consolidate with set-square 4 between stand 1 and crossbeam 2 at last, module processing accomplishes the back unified fireproof anticorrosion coating of applying paint with a brush.
After the modules are processed outside the field, the modules are assembled during the construction of a waterproof layer of a toilet, the positions of the modules need to be paid attention to during the assembly of the modules, and gaps of 10mm-20mm are reserved among the modules, so that the modules are convenient to install and replace at the later stage.
It will be understood by those skilled in the art that the foregoing is merely a preferred embodiment of the present invention, and is not intended to limit the invention, and that any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included within the scope of the present invention.

Claims (4)

1. The utility model provides a bathroom built on stilts layer structure for in interim building, includes stand (1), crossbeam (2), connecting rod (3) and set-square (4), its characterized in that, crossbeam (2) connect into a rectangular frame structure through the steel nail, stand (1) is connected through the steel nail the lower extreme of the rectangular frame structure that crossbeam (2) are constituteed, connecting rod (3) are consolidated crossbeam (2) through steel nail fixed connection in rectangular frame structure's inside, the hookup location of stand (1) and crossbeam (2) has been increased set-square (4) and has been consolidated, and the outer brush of whole built on stilts layer structure has fire prevention anticorrosive paint.
2. The toilet hangar structure for use in temporary buildings according to claim 1, characterized in that the columns (1), beams (2) and connecting rods (3) are wood purlins with cross-sectional dimensions of 80mm x 40 mm.
3. A toilet elevated floor structure for use in temporary buildings according to claim 2, wherein: the triangular plate (4) is a wood plate with the thickness of 15 mm.
4. A toilet elevated floor structure for use in temporary buildings according to claim 3, wherein: when the overhead layer structure is arranged at the position of the squatting pan, a gap is reserved on a cross beam (2) at one side of the rectangular frame structure and is used as an installation reserved position of the water inlet pipe.
CN202021115725.2U 2020-06-16 2020-06-16 Toilet overhead layer structure used in temporary building Active CN213359247U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021115725.2U CN213359247U (en) 2020-06-16 2020-06-16 Toilet overhead layer structure used in temporary building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021115725.2U CN213359247U (en) 2020-06-16 2020-06-16 Toilet overhead layer structure used in temporary building

Publications (1)

Publication Number Publication Date
CN213359247U true CN213359247U (en) 2021-06-04

Family

ID=76125939

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021115725.2U Active CN213359247U (en) 2020-06-16 2020-06-16 Toilet overhead layer structure used in temporary building

Country Status (1)

Country Link
CN (1) CN213359247U (en)

Similar Documents

Publication Publication Date Title
WO2017076070A1 (en) Integrated-assembly steel structure building
CN203866966U (en) Novel assembly type frame core tube steel structure residential housing system
CN112443043B (en) Multilayer through-height large-space cantilever truss structure with embedded small orthotropic truss and application
CN207553289U (en) A kind of assembled steel and concrete frame space modular structure and system
CN210152069U (en) Assembled high-rise steel structure residential system
CN203487676U (en) Honeycomb steel hidden beam composite floor system
CN213359247U (en) Toilet overhead layer structure used in temporary building
CN109138523A (en) The removable assembling type steel structure of corner post builds single open-door toilette modules
WO2003048469A1 (en) Method for constructing tier building and special jack equipment thereof
CN109505225B (en) Safe and stable suspension bridge and construction process thereof
CN108756038A (en) Assembly concrete shear wall and floor support plate rigid connection node and construction method
CN107313551A (en) A kind of concrete prefabricated wallboard of steel bar girder and structural system and its construction method
CN210969335U (en) A curing means for concrete member prefabrication field
CN216920788U (en) Building construction of assembled light steel structure house in coastal region
CN208056513U (en) A kind of structural system of assembly concrete stair
CN201133089Y (en) Loading transferring device for roof beam changing to floor joist
CN103352579A (en) Reinforcement and reconstruction masonry structure using externally-added gallery bridge and externally-added elevator and construction method
CN203270775U (en) House assembled by light steel composite construction modules
CN203394094U (en) Reinforced and reconstructed masonry structure using external gallery bridge and external elevator
CN209011400U (en) Assembly concrete shear wall and floor support plate rigid connection node
CN211229646U (en) Prefabricated assembled high-rise dwelling cylinder formwork multi-ribbed prestressed floor structure system
CN209339662U (en) The removable assembling type steel structure of corner post builds single open-door toilette modules
CN112962823A (en) Double-steel-plate shear wall with replaceable inclined struts and construction method thereof
CN109469351A (en) A kind of terminal, which is not suspended, reconstructs modular construction guard fender and its construction method
CN207647233U (en) A kind of assembling type steel structure public lavatory

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant