CN213356618U - Construction elevator - Google Patents
Construction elevator Download PDFInfo
- Publication number
- CN213356618U CN213356618U CN202021646047.2U CN202021646047U CN213356618U CN 213356618 U CN213356618 U CN 213356618U CN 202021646047 U CN202021646047 U CN 202021646047U CN 213356618 U CN213356618 U CN 213356618U
- Authority
- CN
- China
- Prior art keywords
- wire rope
- steel wire
- cage
- top beam
- counterweight
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model discloses a construction elevator. The construction elevator comprises a top beam, a power mechanism, a suspension cage, a counterweight, a control cabinet and a steel wire rope reel, wherein the top beam is arranged on a hoistway; the height of the top beam is adjustable, the control cabinet and the steel wire rope winding drum are arranged outside the well, and the suspension cage is connected with the steel wire rope winding drum through the steel wire rope. The utility model provides a construction elevator makes it can not receive interference and damage that building debris in heavy weather such as heavy rain fall and the well fall through setting up switch board and partial wire rope in the outside of well to avoided causing harmful effects to the work and the use of lift, improved the security of lift, ensured staff's personal safety.
Description
Technical Field
The utility model relates to a lift field, in particular to construction elevator.
Background
An elevator is a device which uses a power mechanism such as a motor, a tractor or a hydraulic cylinder to control a load bearing mechanism such as a suspension cage or a platform to ascend, and each mechanism needs to be controlled and operated by corresponding control equipment, and generally, each control equipment is integrated into an independent control cabinet to be controlled. In addition, a plurality of steel wire ropes are arranged in the elevator for connecting and lifting. In a conventional elevator, a control cabinet, a wire rope, and the like are installed in a hoistway.
Some elevators that need open air setting, for example the elevator that construction used often can meet bad weather such as heavy rain, and the rainwater falls into the well, probably floods the switch board to cause the condition of control device damage. In addition, in the construction, often have in the well that building debris (such as cement, stone, steel pipe, ironware etc.) fall, also probably cause damage to switch board and wire rope etc. to cause harmful effects to the work and the use of lift, probably appear leaking electricity and phenomenon such as out of control even, threaten staff's personal safety.
SUMMERY OF THE UTILITY MODEL
In order to solve the problem, the utility model provides a construction elevator.
According to one aspect of the utility model, a construction elevator is provided, comprising a top beam, a power mechanism, a suspension cage, a counterweight, a control cabinet and a wire rope reel, wherein the top beam is arranged on a well, the power mechanism is arranged on the top beam, and the suspension cage and the counterweight are both arranged below the top beam and are connected with the power mechanism through a wire rope; the height of the top beam is adjustable, the control cabinet and the steel wire rope winding drum are arranged outside the well, and the suspension cage is connected with the steel wire rope winding drum through the steel wire rope.
The utility model provides a construction elevator makes it can not receive interference and damage that building debris in heavy weather such as heavy rain fall and the well fall through setting up switch board and partial wire rope in the outside of well to avoided causing harmful effects to the work and the use of lift, improved the security of lift, ensured staff's personal safety.
In some embodiments, two rope pulleys are installed on the top of the suspension cage side by side, the steel wire rope is wound around the two rope pulleys from the bottom, and two ends of the steel wire rope are respectively connected with the power mechanism and the steel wire rope winding drum. Therefore, a specific connection mode of the suspension cage, the top beam and the steel wire rope reel is set.
In some embodiments, a head connector is mounted on the top beam, and the wire rope is connected to the wire rope drum after passing through the head connector. Therefore, the steel wire rope can be turned by the rope head connecting piece, and the steel wire rope can be smoothly connected to the steel wire rope drum and used for being matched with the lifting of the suspension cage.
In some embodiments, there are more than two of the wire rope drums, each of the wire rope drums being mounted on a stand or placed on the ground. Wherein, in order to connect respectively and pull many wire rope through a plurality of wire rope reels.
In some embodiments, a cage buffer is centrally disposed at the bottom of the hoistway, the cage buffer being located directly below the cage. Thus, when the cage moves to the bottom of the hoistway, the cage bumpers can contact the bottom of the cage, thereby cushioning the cage.
In some embodiments, a counterweight buffer is disposed about a bottom of the hoistway, the counterweight buffer being located directly below the counterweight. Thus, when the counterweight moves to the bottom of the hoistway, the counterweight buffer can contact the bottom of the counterweight to buffer the counterweight.
Drawings
Fig. 1 is a schematic structural view of a construction hoist according to an embodiment of the present invention;
FIG. 2 is a first schematic view of a portion of the construction hoist of FIG. 1;
fig. 3 is a schematic view of a part of the construction hoist shown in fig. 1.
In the figure: the device comprises a top beam 1, a power mechanism 2, a suspension cage 3, a counterweight 4, a control cabinet 5, a steel wire rope reel 6, a well 7, a steel wire rope 8, a rope pulley 9, a rope head connecting piece 11, a suspension cage buffer 12, a counterweight buffer 13 and a passage opening 14.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Fig. 1 schematically shows a construction hoist according to an embodiment of the present invention, and fig. 2 shows a part of the construction hoist of fig. 1; fig. 3 shows another partial structure of a construction hoist of fig. 1. As shown in fig. 1-3, the construction hoist is installed in a hoistway for construction, and mainly comprises a top beam 1, a power mechanism 2, a suspension cage 3, a counterweight 4, a control cabinet 5 and other structures, wherein the top beam 1 is installed on the hoistway 7, the power mechanism 2 is installed on the top beam 1, and the suspension cage 3 and the counterweight 4 are both arranged inside the hoistway 7 below the top beam 1 and are also connected with the power mechanism 2 through a steel wire rope 8. The power mechanism 2 can be selected from a tractor or an electric winch. In addition, the shaft 7 is provided with an access opening 14 for access at a certain height.
The proper height can be selected according to actual needs to install the top beam 1 so as to adjust the height of the top beam 1; furthermore, the top sill 1 can also be arranged to be directly adjustable up and down.
The control cabinet 5 is provided with control equipment for controlling the power mechanism 2 and the like, the control cabinet 5 is arranged outside the hoistway 7, and meanwhile, a plurality of cables can be reasonably arranged according to needs to be connected with mechanisms controlled by the control cabinet.
In addition, a wire rope reel 6 is arranged outside the well 7, the wire rope reel 6 is generally positioned at the same height with the top beam 1, and the suspension cage 3 is also connected with the wire rope reel 6 through a wire rope 8. Connect through wire rope reel 6 and receive wire rope 8, can go up and down to the pulling of cage 3 and cooperate supplementaryly.
Preferably, a rope pulley is installed on the top of the suspension cage 3, the middle part of the steel wire rope 8 is wound around the rope pulley 9 from the bottom, and the two ends of the steel wire rope 8 are respectively connected with the power mechanism 2 and the steel wire rope winding drum 6 after extending to the upper part. Further preferably, the sheave may be provided in one or a plurality side by side.
Preferably, a rope end connecting piece 11 is arranged on the top beam 1, and one end of the steel wire rope 8 is connected to the steel wire rope reel 6 through the rope end connecting piece 11. Rope end connecting piece 11 can carry out the diversion to wire rope 8, makes the one end that wire rope 8 is close to cage 3 here can be partial to perpendicularly, makes cage 3 can stimulate smoothly and go up and down.
Preferably, since the steel wire ropes 8 are generally used in a plurality of numbers at the same time, a plurality of steel wire rope reels 6 may be provided for connecting with a plurality of steel wire ropes 8, respectively. Wherein, a plurality of wire rope reels 6 act on jointly can improve for the power way and the stability of cage 3 provided pulling force.
Further preferably, the plurality of wire reels 6 are fixedly mounted, and may be selectively mounted on a bracket or placed on the ground, etc., depending on the case.
Preferably, at least one cage buffer 12 is provided at the bottom of the hoistway 7, wherein the cage buffer 12 is located directly below the cage 3, and when the cage 3 moves to the bottom of the hoistway 7, the cage buffer 12 can contact the bottom of the cage 3 to buffer the descending motion of the cage 3.
Preferably, at least one counterweight buffer 13 is further provided at the bottom of the hoistway 7, wherein the counterweight buffer 13 is located directly below the counterweight 4, and when the counterweight 4 moves to the bottom of the hoistway 7, the counterweight buffer 13 can contact the bottom of the counterweight 4, thereby buffering the downward movement of the counterweight 4.
The utility model provides a construction elevator is because set up switch board 5 in the outside of well 7, still set up one of them part wire rope 8 in the outside of well 7 through setting up wire rope reel 6, then controlgear and this part wire rope 8 in the switch board 5 can not receive heavy rain and lead to ponding and submerged in well 7, also can not be fallen and damaged by the building debris in well 7 (such as cement, the stone, the steel pipe, ironware etc.), thereby avoided causing harmful effects to the work and the use of elevator, the security of elevator has been improved, staff's personal safety has been ensured.
What has been described above are only some embodiments of the invention. For those skilled in the art, without departing from the inventive concept, several modifications and improvements can be made, which are within the scope of the invention.
Claims (6)
1. A construction elevator characterized in that: the lifting device comprises a top beam (1), a power mechanism (2), a lifting cage (3), a counterweight (4), a control cabinet (5) and a steel wire rope reel (6), wherein the top beam (1) is installed on a hoistway (7), the power mechanism (2) is installed on the top beam (1), and the lifting cage (3) and the counterweight (4) are both positioned below the top beam (1) and are connected with the power mechanism (2) through a steel wire rope (8); the height of the top beam (1) is adjustable, the control cabinet (5) and the steel wire rope reel (6) are arranged outside the well (7), and the suspension cage (3) is connected with the steel wire rope reel (6) through the steel wire rope (8).
2. A construction hoist according to claim 1, characterized in that: rope sheave (9) is installed at the top of cage (3), wire rope (8) are walked around rope sheave (9) and its both ends respectively with power unit (2) with wire rope reel (6) are connected.
3. A construction hoist according to claim 1, characterized in that: a rope head connecting piece (11) is installed on the top beam (1), and the steel wire rope (8) is connected to the steel wire rope winding drum (6) after passing through the rope head connecting piece (11).
4. A construction hoist according to claim 1, characterized in that: the number of the wire rope reels (6) is more than two, and each wire rope reel (6) is installed on a support or placed on the ground.
5. A construction hoist according to claim 1, characterized in that: the bottom of well (7) is provided with cage buffer (12), cage buffer (12) are located under cage (3).
6. A construction hoist according to claim 1, characterized in that: a counterweight buffer (13) is arranged around the bottom of the hoistway (7), and the counterweight buffer (13) is located right below the counterweight (4).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021646047.2U CN213356618U (en) | 2020-08-10 | 2020-08-10 | Construction elevator |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021646047.2U CN213356618U (en) | 2020-08-10 | 2020-08-10 | Construction elevator |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213356618U true CN213356618U (en) | 2021-06-04 |
Family
ID=76143781
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021646047.2U Active CN213356618U (en) | 2020-08-10 | 2020-08-10 | Construction elevator |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213356618U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111960213A (en) * | 2020-09-08 | 2020-11-20 | 歌拉瑞电梯股份有限公司 | Construction elevator |
-
2020
- 2020-08-10 CN CN202021646047.2U patent/CN213356618U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111960213A (en) * | 2020-09-08 | 2020-11-20 | 歌拉瑞电梯股份有限公司 | Construction elevator |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110023229B (en) | Elevator installation and method for building an elevator installation | |
US7635049B2 (en) | Method and apparatus for installing an elevator during the construction of a building | |
US8028393B2 (en) | Elevator arrangement | |
EP1583710B1 (en) | Method and apparatus for installing an elevator during construction of a building | |
AU745619B2 (en) | Elevator system | |
KR101245570B1 (en) | Method for installing an elevator, and elevator | |
US9415974B2 (en) | Method and arrangement for moving a heavy load | |
WO2010061265A1 (en) | Method of installing an elevator | |
EP0415218B1 (en) | Placement of a drive unit for an elevator | |
JP2004504239A (en) | Elevator equipment using the smallest building space | |
CN213356618U (en) | Construction elevator | |
CN112585077B (en) | Lift extension type elevator for construction | |
CN115038660A (en) | Construction elevator device | |
CN218841490U (en) | Building material hoist and mount direction hawser mechanism | |
KR20010096838A (en) | Installation structure and the method for winch of a lower part driving elevator with machine roomless | |
CN111960213A (en) | Construction elevator | |
CN214192153U (en) | Closed loop elevator | |
EP1016616A1 (en) | Lift cage guidance system | |
CN112678653A (en) | Transmission method of closed loop type lifter and closed loop type lifter | |
CN1511778A (en) | Lift system without machine room | |
CN219885403U (en) | Counterweight rope winding device | |
KR100728419B1 (en) | Elevator equipment | |
CN215248923U (en) | Elevator machine | |
WO2023084721A1 (en) | Construction elevator and method of extending compensating rope for construction elevator | |
CN212334326U (en) | Construction elevator prevents sitting end device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address | ||
CP03 | Change of name, title or address |
Address after: 215000 No.122 Yong'an Road, high tech Zone, Suzhou City, Jiangsu Province Patentee after: Suzhou kelairui Intelligent Equipment Co.,Ltd. Address before: 215000 Hushuguan Guanzhen Huqing Road, Suzhou High-tech Zone, Jiangsu Province Patentee before: Suzhou kelairui Electromechanical Technology Co.,Ltd. |