CN213329942U - Engineering construction scaffold - Google Patents
Engineering construction scaffold Download PDFInfo
- Publication number
- CN213329942U CN213329942U CN202022087935.1U CN202022087935U CN213329942U CN 213329942 U CN213329942 U CN 213329942U CN 202022087935 U CN202022087935 U CN 202022087935U CN 213329942 U CN213329942 U CN 213329942U
- Authority
- CN
- China
- Prior art keywords
- groups
- base
- sides
- movable
- screw rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 19
- 238000004804 winding Methods 0.000 claims description 2
- 230000000694 effects Effects 0.000 abstract description 6
- 230000006978 adaptation Effects 0.000 abstract description 2
- 230000006872 improvement Effects 0.000 description 4
- 230000009471 action Effects 0.000 description 2
- 230000003044 adaptive effect Effects 0.000 description 1
- 230000001174 ascending effect Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000008569 process Effects 0.000 description 1
Images
Landscapes
- Movable Scaffolding (AREA)
Abstract
The utility model discloses an engineering construction scaffold, including base and workstation, the both sides at base top all are equipped with the bearing, and two sets of all rotate in the bearing and install the screw rod, and the screw rod bottom passes the base, and the top of two sets of screw rod all is equipped with the looks adaptation knob, the screw rod top position department all is equipped with the fixed block inside the base, and the both sides of two sets of fixed block all are equipped with the connecting rod, and the connecting rod passes the base, and the intermediate position department of the below connecting rod of two sets of screw rod all movable mounting has the movable rod, and two sets of all install three sets of movable blocks on the movable rod; the utility model discloses a twist and move the knob, drive the screw rod and rotate to drive the quick downward movement of activity, utilize multiunit staple to insert ground and fix, when needs are dismantled, twist and move the knob, drive the screw rod and rotate, thereby drive movable block rebound, the staple leaves ground, this kind of mode, fixed effectual, easy dismantlement, easy operation.
Description
Technical Field
The utility model relates to a construction technical field especially relates to engineering construction scaffold.
Background
As is well known, with the rapid development of society, more and more engineering buildings are needed in cities, and in the construction process of the engineering buildings, a scaffold is an indispensable tool and can well help workers to work;
among the prior art, the scaffold is generally directly placed subaerial, maintains the stability of scaffold or adopts the dead structure of lock to fix through weight on the scaffold, and the fixed effect of this kind of mode is poor, and difficult dismantlement moreover, the operation is complicated, and simultaneously, scaffold among the prior art, the workman generally adopts to pull the material with the hand or throw the scaffold with the material through the mode of hand throwing, the extravagant manpower of this kind of mode, work efficiency is low, consequently, the utility model provides an engineering construction scaffold is in order to solve the problem that exists among the prior art.
SUMMERY OF THE UTILITY MODEL
To the above problem, the utility model aims to provide an engineering construction scaffold, this engineering construction scaffold moves the knob through twisting, drives the screw rod and rotates to the quick downstream of drive activity utilizes multiunit staple to insert ground and fixes, and is fixed effectual, dismantles easily easy operation.
For realizing the purpose of the utility model, the utility model discloses a following technical scheme realizes: engineering construction scaffold, including base and workstation, the both sides at base top all are equipped with the bearing, and are two sets of all rotate in the bearing and install the screw rod, and the screw rod bottom passes the base, the top of screw rod is equipped with the knob of looks adaptation, be equipped with the fixed block on the screw rod, the both sides of fixed block all are equipped with the connecting rod, and the connecting rod passes the base, and adjacent two sets of movable mounting has the movable rod on the connecting rod, it is fast to install the activity on the movable rod, and the movable block is equipped with three groups, three groups the movable block is installed respectively on screw rod and connecting rod, the staple is all installed to the both sides of movable block, the support is all installed to two of base top, and is two sets of the top of support all is equipped with electric putter, the.
The further improvement lies in that: the improved sliding pipe device is characterized in that a sliding pipe is arranged in the workbench, a motor is arranged on one side of the workbench, the output end of the motor is connected with the sliding pipe through a rotating shaft, rope locking blocks are arranged on two sides of the sliding pipe, ropes are wound on two sides of the sliding pipe, and one end of each rope is connected to one side of each rope locking block.
The further improvement lies in that: the rope conveying device comprises two groups of supports and is characterized in that a baffle is arranged between the two groups of supports, conveying plates are arranged at the tops of the baffle, supporting plates are arranged on two sides of each conveying plate, rope holes are formed in the tops of the two groups of supporting plates, and the two groups of rope holes are connected with ropes.
The further improvement lies in that: and a guardrail is arranged at the top of the workbench.
The further improvement lies in that: the fixing plates are arranged between the two groups of the brackets in a crossed mode and are arranged in two groups, and the fixing plates are fixed in a staggered mode.
The utility model has the advantages that: the utility model drives the screw rod to rotate by twisting the knob, thereby driving the movable screw rod to move downwards quickly, and utilizes the plurality of groups of fixing nails to be inserted into the ground for fixing, when needing to be disassembled, the knob is twisted to drive the screw rod to rotate, thereby driving the movable block to move upwards, the fixing nail leaves the ground, the mode has good fixing effect, easy disassembly and simple operation, simultaneously, the material is placed on the conveying plate and rotates through the screw pipe, thereby driving the conveying plate under the rope to move, and conveying the material to the workbench, the mode well saves manpower, greatly improves working efficiency, in addition, the guard bar on the workbench well protects the working personnel, and finally, through the pushing action of the electric push rod, the lifting and descending of the workbench can be completed, the buildings with different heights can be constructed, the operation is convenient, and the functions are diversified.
Drawings
Fig. 1 is a front view of the present invention;
FIG. 2 is a schematic view of the internal structure of the present invention;
fig. 3 is an enlarged schematic view of the position a of the present invention.
Wherein: 1. a base; 2. a work table; 3. a bearing; 4. a screw; 5. a knob; 6. a fixed block; 7. a connecting rod; 8. a movable rod; 9. a movable block; 10. fixing nails; 11. a support; 12. an electric push rod; 13. a slide pipe; 14. a motor; 15. a rope locking block; 16. a rope; 17. a baffle plate; 18. a transport plate; 19. a support plate; 20. a rope hole; 21. a guardrail; 22. and (7) fixing the plate.
Detailed Description
In order to deepen the understanding of the present invention, the following embodiments will be combined to make the present invention do further details, and the present embodiment is only used for explaining the present invention, and does not constitute the limitation of the protection scope of the present invention.
According to fig. 1, 2 and 3, the embodiment provides an engineering construction scaffold, which comprises a base 1 and a workbench 2, wherein bearings 3 are arranged on two sides of the top of the base 1, two groups of bearings 3 are internally and rotatably provided with screw rods 4, the bottoms of the screw rods 4 penetrate through the base 1, the tops of the screw rods 4 are provided with adaptive knobs 5, fixed blocks 6 are arranged on the screw rods, connecting rods 7 are arranged on two sides of the fixed blocks 6, the connecting rods 7 penetrate through the base 1, movable rods 8 are movably arranged on two adjacent groups of the connecting rods 7, movable blocks 9 are arranged on the movable rods 8, three groups of the movable blocks 9 are respectively arranged on the screw rods 4 and the connecting rods 7, fixing nails 10 are arranged on two sides of the movable blocks 9, supports 11 are respectively arranged on two sides above the base 1, and electric push rods 12 are arranged above the two groups of the supports 11, the workbench 2 is arranged at the output end of the electric push rod 12, and the knob 5 is screwed to drive the screw rod 4 to rotate, so that the movable block 9 is driven to move downwards, and the plurality of groups of fixing nails 10 are inserted into the ground for fixing.
Be equipped with slide pipe 13 in the workstation 2, one side of workstation 2 is equipped with motor 14, and motor 14's output connects slide pipe 13 through the pivot, slide pipe 13's both sides all are equipped with locking rope piece 15, rope 16 is installed in the equal winding of slide pipe 13's both sides, and the one end of rope 16 is connected in one side of locking rope piece 15, conveniently drives rope 16 through slide pipe 13 and removes.
The material conveying device comprises two groups of supports 11, a baffle 17 is arranged between the two groups of supports 11, a conveying plate 18 is arranged at the top of the baffle 17, supporting plates 19 are arranged on two sides of the conveying plate 18, rope holes 20 are formed in the tops of the two groups of supporting plates 19, the two groups of rope holes 20 are connected with ropes 16, materials can be conveyed to the workbench 2, manpower is saved well in the mode, and working efficiency is improved greatly.
The top of the working table 2 is provided with a guardrail 21, so that workers are well protected.
Two sets of alternately be equipped with fixed plate 22 between the support 11, and fixed plate 22 is equipped with two sets ofly, two sets of fixed plate 22 is crisscross fixed, lets the scaffold more stable.
During the use, twist knob 5, it is rotatory to drive screw rod 4, it moves down on connecting rod 7 to drive movable rod 8, thereby drive movable block 9 and move down, multiunit staple 10 inserts ground and fixes, when needs are dismantled, twist knob 5, it is rotatory to drive screw rod 4, it moves up on connecting rod 7 to drive movable rod 8, thereby drive movable block 9 and move up, multiunit staple 10 leaves ground, simultaneously, drive slide pipe 13 through motor 14 and rotate, it moves up to drive transport board 18 under 16 connections of rope, transport the material to workstation 2, promote through electric putter 12, drive workstation 2 and reciprocate.
The engineering construction scaffold drives the screw rod 4 to rotate by screwing the knob 5, so as to drive the movable block 9 to move downwards, and the plurality of groups of fixing nails 10 are inserted into the ground for fixing, when the engineering construction scaffold needs to be disassembled, the knob 5 is screwed, the screw rod 4 is driven to rotate, so as to drive the movable block 9 to move upwards, the fixing nails 10 leave the ground, the fixing effect is good, the disassembly is easy, the operation is simple, meanwhile, the material is placed on the transport plate 18, the material is rotated by the sliding pipe 13, so as to drive the transport plate 18 under the rope 16 to move, so that the material can be transported onto the workbench 2, the manpower is well saved, the working efficiency is greatly improved, in addition, the working personnel are well protected by the guardrail 21 on the workbench 2, finally, the ascending and descending of the workbench 2 can be completed by the pushing action of the electric push rod 12, the construction of different heights can be carried out, convenient operation and diversified functions.
The foregoing illustrates and describes the principles, general features, and advantages of the present invention. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.
Claims (5)
1. Engineering construction scaffold, including base (1) and workstation (2), its characterized in that: the two sides of the top of the base (1) are provided with bearings (3), two groups of bearings (3) are internally provided with screw rods (4) in a rotating manner, the bottoms of the screw rods (4) penetrate through the base (1), the tops of the screw rods (4) are provided with knobs (5) matched with each other, the screw rods are provided with fixed blocks (6), the two sides of each fixed block (6) are provided with connecting rods (7), the connecting rods (7) penetrate through the base (1), two adjacent groups of connecting rods (7) are movably provided with movable rods (8), the movable rods (8) are provided with movable blocks (9), the movable blocks (9) are provided with three groups, the movable blocks (9) are respectively arranged on the screw rods (4) and the connecting rods (7), the two sides of the movable blocks (9) are provided with fixing nails (10), and two sides above the base (1) are provided with brackets (11), two sets of the top of support (11) all is equipped with electric putter (12), the output at electric putter (12) is installed in workstation (2).
2. An engineering construction scaffold according to claim 1, wherein: be equipped with slide pipe (13) in workstation (2), one side of workstation (2) is equipped with motor (14), and the output of motor (14) connects slide pipe (13) through the pivot, the both sides of slide pipe (13) all are equipped with lock rope piece (15), rope (16) are all installed in the equal winding of both sides of slide pipe (13), and the one end of rope (16) is connected in one side of lock rope piece (15).
3. An engineering construction scaffold according to claim 2, wherein: a baffle (17) is arranged between the two groups of supports (11), a conveying plate (18) is arranged at the top of the baffle (17), supporting plates (19) are arranged on two sides of the conveying plate (18), rope holes (20) are arranged at the tops of the two groups of supporting plates (19), and the two groups of rope holes (20) are connected with ropes (16).
4. An engineering construction scaffold according to claim 1, wherein: and a guardrail (21) is arranged at the top of the workbench (2).
5. An engineering construction scaffold according to claim 1, wherein: fixing plates (22) are arranged between the two groups of brackets (11) in a crossed mode, two groups of fixing plates (22) are arranged on the fixing plates (22), and the two groups of fixing plates (22) are fixed in a staggered mode.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022087935.1U CN213329942U (en) | 2020-09-22 | 2020-09-22 | Engineering construction scaffold |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202022087935.1U CN213329942U (en) | 2020-09-22 | 2020-09-22 | Engineering construction scaffold |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213329942U true CN213329942U (en) | 2021-06-01 |
Family
ID=76065451
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202022087935.1U Expired - Fee Related CN213329942U (en) | 2020-09-22 | 2020-09-22 | Engineering construction scaffold |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213329942U (en) |
-
2020
- 2020-09-22 CN CN202022087935.1U patent/CN213329942U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110978118B (en) | Building material perforating device | |
CN210918166U (en) | Scaffold for elevator shaft | |
CN206782622U (en) | One kind building brick clamp | |
CN209364949U (en) | It is a kind of for processing the blank remedying device of porcelain tube | |
CN203171225U (en) | Carbon brush holder torsional spring automatic assembling machine | |
CN108162073A (en) | A kind of cutter device of the wooden finishing material of interior decoration | |
CN213329942U (en) | Engineering construction scaffold | |
CN106185313A (en) | Clamping device | |
CN111977532A (en) | Be used for construction machinery and construction synchronous elevation structure | |
CN201838934U (en) | Novel portable adjustable rod upper platform | |
CN113818690A (en) | Novel special buckle connecting piece for building formwork support and using method thereof | |
CN209620624U (en) | A kind of mobile frame body of side wall reinforcing bar binding | |
CN214739838U (en) | Dish knot formula scaffold frame based on BIM | |
CN205949972U (en) | Panel follow -up cutting device | |
CN208163566U (en) | A kind of maintenance platform for entertaining overhead falling sphere loop wheel machine | |
CN210523678U (en) | High efficiency reinforcing bar cutting device for building | |
CN212218469U (en) | Reinforcing bar letter sorting manipulator | |
CN216030035U (en) | Complete set of rust removal device for oil field pipeline | |
CN218950952U (en) | A dalle hoisting device for fork truck | |
CN213915806U (en) | Feeding mechanism for straightener | |
CN213801592U (en) | Novel construction is with defeated material device | |
CN219543664U (en) | Building outer wall perforating device for building engineering | |
CN108979119A (en) | A kind of construction coherent-wall scaffolding cantilever arrangement easy to use | |
CN212147041U (en) | Inflatable brick cutting device | |
CN215626033U (en) | Liftable support for construction engineering construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210601 |