CN213265493U - A quick convenient transport means for large-scale piping lane piping erection - Google Patents

A quick convenient transport means for large-scale piping lane piping erection Download PDF

Info

Publication number
CN213265493U
CN213265493U CN202021366932.5U CN202021366932U CN213265493U CN 213265493 U CN213265493 U CN 213265493U CN 202021366932 U CN202021366932 U CN 202021366932U CN 213265493 U CN213265493 U CN 213265493U
Authority
CN
China
Prior art keywords
pipe gallery
rope
support
pipe rack
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021366932.5U
Other languages
Chinese (zh)
Inventor
魏雄伟
黄廷毅
巩瑞红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Engineering Group Co Ltd
Sinopec Fifth Construction Co Ltd
Original Assignee
Sinopec Engineering Group Co Ltd
Sinopec Fifth Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinopec Engineering Group Co Ltd, Sinopec Fifth Construction Co Ltd filed Critical Sinopec Engineering Group Co Ltd
Priority to CN202021366932.5U priority Critical patent/CN213265493U/en
Application granted granted Critical
Publication of CN213265493U publication Critical patent/CN213265493U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a quick and convenient transportation tool for large-scale pipe gallery pipeline installation, which is used for transporting large-scale pipe gallery pipeline sections to the installation position on a pipe gallery support of the large-scale pipe gallery, the pipe gallery support is provided with a multilayer pipe gallery extending along the X direction, the X direction is the direction from the head end to the tail end of the pipe gallery support, and the installation position is positioned at the bottom of one layer of pipe gallery of the pipe gallery support; the method is characterized in that: the rapid and convenient transportation tool comprises a roller mechanism, a winding mechanism, a first pulley, a second pulley and a traction rope. The utility model discloses can realize the rapid transit to large-scale piping lane pipeline section under the very long and limited condition in space of piping lane length to, through the swing of connecting the rope in the transportation, can ensure the smooth and easy nature of haulage rope pulling large-scale piping lane pipeline section, have that the conveying efficiency is high, can cyclic utilization, with low costs, the equipment is simple and convenient swift, artifical intensity of labour is little, the high advantage of security.

Description

A quick convenient transport means for large-scale piping lane piping erection
Technical Field
The utility model relates to a petroleum, chemical engineering piping erection, specific quick convenient transport means for large-scale piping lane piping erection that says so.
Background
When petrochemical device piping lane piping erection, the installation that needs the straight tube section usually, because piping lane interlamellar spacing is little, the number of piles is more, and the piping lane is longer (generally reach more than 100 meters), and the space is less. Traditional piping lane piping erection adopts crane or artifical chain block poling usually, often the poling occupies a large amount of resources, and the crane constantly shifts, consumes a large amount of machinery machine shifts and manpower and time, and installation intensity of labour is big, and efficiency of construction is not high, directly influences the whole pipeline construction progress of device. And the safety is not high.
SUMMERY OF THE UTILITY MODEL
The utility model discloses the technical problem that will solve is: the utility model provides a quick convenient transport means for large-scale piping lane piping erection to because of the very long and space of piping lane length is limited among the solution prior art, cause to have construction difficulty, inefficiency, the poor problem of security with large-scale piping lane pipeline transportation to its mounted position in the piping lane.
Solve above-mentioned technical problem, the utility model discloses the technical scheme who adopts as follows:
a quick and convenient transportation tool for large pipe gallery pipeline installation is used for transporting large pipe gallery pipeline sections to installation positions on a pipe gallery support of the large pipe gallery support, the pipe gallery support is provided with a plurality of layers of pipe galleries extending along an X direction, the X direction is a direction from a head end to a tail end of the pipe gallery support, and the installation positions are located at the bottom of one layer of pipe gallery of the pipe gallery support;
the method is characterized in that:
the rapid and convenient transportation tool comprises a rolling shaft mechanism, a winding mechanism, a first pulley, a second pulley and a traction rope;
the pipe gallery support is arranged at the bottom of a pipe gallery where the mounting position is located, a plurality of roller mechanisms are arranged from the head end of the pipe gallery support to the mounting position at intervals along the X direction, the axes of the roller mechanisms are perpendicular to the X direction, and the distance between any two adjacent roller mechanisms is smaller than the length of the large pipe gallery pipeline section;
the hoisting mechanism is fixed on the ground, the first pulley is connected with the upright post component of the pipe gallery support at the tail end of the pipe gallery support through a connecting rope, and the second pulley is fixedly installed on the cross beam component of the pipe gallery support at the tail end and at the height of the installation position; the first end of the hauling rope is connected with the hoisting mechanism, and the second end of the hauling rope sequentially bypasses the first pulley and the second pulley and then is connected with and placed at the end part of the large pipe gallery pipeline section on the roller mechanism.
Therefore, during use, a large-scale pipe gallery pipeline section is firstly hoisted to the roller mechanism at the head end of the pipe gallery support, then the second end of the traction rope is connected with the end part of the large-scale pipe gallery pipeline section, the hoisting mechanism is started to reel the traction rope, so that the large-scale pipe gallery pipeline section is driven to slide along the X direction on each roller mechanism until the large-scale pipe gallery pipeline section reaches the installation position, the hoisting mechanism is stopped, and the transportation of the large-scale pipe gallery pipeline section is completed.
Therefore, the utility model discloses can realize the rapid transit to large-scale piping lane pipeline section under the very long and limited condition in space of piping lane length to, through the swing of connecting the rope in the transportation, can ensure the smooth and easy nature of haulage rope pulling large-scale piping lane pipeline section, have that the conveying efficiency is high, but cyclic utilization, with low costs, equipment is simple and efficient, artifical intensity of labour is little, the high advantage of security.
Preferably: the roller mechanism comprises a roller support fixed on the pipe gallery support, and a roller is rotatably arranged on the roller support.
Preferably: the hauling rope and the connecting rope are both steel wire ropes so as to improve the durability of the hauling rope and the connecting rope.
As a preferred embodiment of the present invention: the second end of haulage rope divide into two strands of branch rope sections, and these two strands of branch rope sections are respectively through a kayser mechanism fixed connection in the tip of large-scale piping lane pipeline section.
Preferably: the clamping and locking mechanism comprises a U-shaped lock body and two bolts, a rope tying hole is formed in the end part of the U-shaped lock body, and the branch rope section is fastened and fixed in the rope tying hole of the U-shaped lock body; the pipe wall card of large-scale piping lane pipeline section in the U type breach of U font lock body, U font lock body is equipped with two coaxial and all communicates the screw hole of U type breach, two bolts respectively with two screw hole threaded connection of U font lock body, and one of them bolt supports to push up and compresses tightly the pipe wall medial surface of large-scale piping lane pipeline section, another bolt supports to push up and compresses tightly the pipe wall lateral surface of large-scale piping lane pipeline section.
As a preferred embodiment of the present invention: the winding mechanism comprises a motor, a winding drum and a bearing, wherein a machine body of the motor and an outer ring of the bearing are relatively fixed, and the winding drum is coaxially connected between a motor shaft of the motor and an inner ring of the bearing; the first end of the hauling cable is fixedly connected to the winding drum.
Preferably: the winding mechanism further comprises a control device for controlling the motor to work.
Compared with the prior art, the utility model discloses following beneficial effect has:
the utility model discloses can realize the rapid transit to large-scale piping lane pipeline section under the very long and limited condition in space of piping lane length to, through the swing of connecting the rope in the transportation, can ensure the smooth and easy nature of haulage rope pulling large-scale piping lane pipeline section, have that the conveying efficiency is high, can cyclic utilization, with low costs, the equipment is simple and convenient swift, artifical intensity of labour is little, the high advantage of security.
Drawings
The invention will be described in further detail with reference to the following drawings and specific embodiments:
fig. 1 is a schematic structural view of the rapid and convenient transportation tool of the present invention;
FIG. 2 is a schematic structural view of the middle pulling rope connecting the large pipe gallery pipe section;
fig. 3 is a schematic structural view of the latch mechanism of the present invention;
fig. 4 is a schematic structural diagram of the middle hoisting mechanism of the present invention.
Detailed Description
The present invention will be described in detail with reference to the following embodiments and the accompanying drawings to help those skilled in the art to better understand the concept of the present invention, but the scope of the claims of the present invention is not limited to the following embodiments, and all other embodiments obtained without creative work for those skilled in the art will fall within the scope of the present invention without departing from the scope of the present invention.
Example one
As shown in fig. 1 to 4, the utility model discloses a quick and convenient transportation tool for large pipe gallery pipeline installation, which is used for transporting a large pipe gallery pipeline section 1 to a mounting position P on a pipe gallery bracket 2, wherein the pipe gallery bracket 2 is provided with a plurality of layers of pipe galleries extending along the X direction, the X direction is from the head end to the tail end of the pipe gallery bracket 2, and the mounting position P is positioned at the bottom of one layer of pipe gallery of the pipe gallery bracket 2;
the rapid and convenient transportation tool comprises a roller mechanism 3, a winding mechanism 4, a first pulley 5, a second pulley 6 and a traction rope 7;
the pipe gallery support 2 is arranged at the bottom of a pipe gallery where the installation position P is located, a plurality of roller mechanisms 3 are arranged from the head end of the pipe gallery support 2 to the installation position P at intervals along the X direction, the axes of the roller mechanisms 3 are perpendicular to the X direction, and the distance between any two adjacent roller mechanisms 3 is smaller than the length of the large pipe gallery pipeline section 1;
the hoisting mechanism 4 is fixed on the ground, the first pulley 5 is connected with the column member 2-1 at the tail end of the pipe rack support 2 through a connecting rope 8, and the second pulley 6 is fixedly installed on the beam member 2-2 at the tail end of the pipe rack support 2 and at the height of the installation position P; the first end of the hauling rope 7 is connected with the hoisting mechanism 4, and the second end of the hauling rope sequentially bypasses the first pulley 5 and the second pulley 6 and then is connected with and placed at the end part of the large pipe gallery pipeline section 1 on the roller mechanism 3.
Therefore, during use, firstly, the large-scale pipe gallery pipeline section 1 is hoisted to the roller mechanism 3 at the head end of the pipe gallery support 2, then the second end of the traction rope 7 is connected with the end part of the large-scale pipe gallery pipeline section 1, the hoisting mechanism 4 is started to wind the traction rope 7, so that the large-scale pipe gallery pipeline section 1 is driven to slide along the X direction on each roller mechanism 3 until the large-scale pipe gallery pipeline section 1 reaches the installation position P, the hoisting mechanism 4 is stopped, and the transportation of the large-scale pipe gallery pipeline section 1 is completed.
Therefore, the utility model discloses can realize the rapid transit to large-scale piping lane pipeline section 1 under the very long and limited condition in space of piping lane length to, through the swing of connecting rope 8 in the transportation, can ensure the smooth and easy nature of haulage rope 7 pulling large-scale piping lane pipeline section 1, have that the conveying efficiency is high, can cyclic utilization, with low costs, the equipment is simple and efficient, artifical intensity of labour is little, the high advantage of security.
The above is a basic implementation manner of the first embodiment, and further optimization, improvement and limitation may be performed on the basis of the basic implementation manner:
preferably: the roller mechanism 3 comprises a roller support fixed on the pipe gallery support 2, and a roller is rotatably arranged on the roller support.
Preferably: the hauling rope 7 and the connecting rope 8 are both steel wire ropes so as to improve the durability of the hauling rope and the connecting rope.
Example two
On the basis of the first embodiment, the second embodiment further adopts the following preferred structure:
as shown in fig. 2, the second end of the pulling rope 7 is divided into two branch rope segments 7-1, and the two branch rope segments 7-1 are fixedly connected to the end of the large pipe rack pipe segment 1 through a locking mechanism 9.
The above is the basic implementation manner of the second embodiment, and further optimization, improvement and limitation can be made on the basis of the basic implementation manner:
preferably: as shown in fig. 3, the locking mechanism 9 comprises a U-shaped lock body 9-1 and two bolts 9-2, the end of the U-shaped lock body 9-1 is provided with a rope tying hole 9-1a, and the branch rope section 7-1 is fastened and fixed in the rope tying hole 9-1a of the U-shaped lock body 9-1; the pipe wall of the large pipe gallery pipeline section 1 is clamped in the U-shaped notch 9-1b of the U-shaped lock body 9-1, the U-shaped lock body 9-1 is provided with two coaxial threaded holes 9-1c which are communicated with the U-shaped notch 9-1b, the two bolts 9-2 are in threaded connection with the two threaded holes 9-1c of the U-shaped lock body 9-1 respectively, one bolt 9-2 abuts against and is pressed on the inner side surface of the pipe wall of the large pipe gallery pipeline section 1, and the other bolt 9-2 abuts against and is pressed on the outer side surface of the pipe wall of the large pipe gallery pipeline section 1.
EXAMPLE III
On the basis of the first embodiment or the second embodiment, the third embodiment further adopts the following preferable structure:
as shown in fig. 4, the hoisting mechanism 4 comprises a motor 4-1, a winding drum 4-2 and a bearing 4-3, wherein the body of the motor 4-1 and the outer ring of the bearing 4-3 are relatively fixed, and the winding drum 4-2 is coaxially connected between the motor shaft of the motor 4-1 and the inner ring of the bearing 4-3; the first end of the traction rope 7 is fixedly connected to the winding drum 4-2.
The above is the basic implementation of the third embodiment, and further optimization, improvement and limitation can be made on the basis of the basic implementation:
preferably: the winding mechanism 4 further comprises a control device 4-4 for controlling the motor 4-1 to work.
The present invention is not limited to the above-mentioned embodiments, and according to the above-mentioned contents, according to the common technical knowledge and conventional means in the field, without departing from the basic technical idea of the present invention, the present invention can also make other equivalent modifications, replacements or changes in various forms, all falling within the protection scope of the present invention.

Claims (7)

1. A quick and convenient transport means for large pipe rack piping erection for transporting large pipe rack pipe sections (1) to a mounting location (P) on its pipe rack support (2), the pipe rack support (2) having a multi-layer pipe rack extending in the X-direction, the X-direction being the direction from the head end to the tail end of the pipe rack support (2), the mounting location (P) being located at the bottom of one of the layers of pipe racks of the pipe rack support (2);
the method is characterized in that:
the rapid and convenient transportation tool comprises a rolling shaft mechanism (3), a winding mechanism (4), a first pulley (5), a second pulley (6) and a traction rope (7);
the pipe rack support (2) is arranged at the bottom of a pipe rack where the mounting position (P) is located, a plurality of roller mechanisms (3) are arranged from the head end of the pipe rack support (2) to the mounting position (P) at intervals along the X direction, the axis of each roller mechanism (3) is perpendicular to the X direction, and the distance between any two adjacent roller mechanisms (3) is smaller than the length of the large pipe rack pipeline section (1);
the hoisting mechanism (4) is fixed on the ground, the first pulley (5) is connected with the column member (2-1) of the pipe gallery support (2) at the tail end thereof through a connecting rope (8), and the second pulley (6) is fixedly installed on the beam member (2-2) of the pipe gallery support (2) at the tail end thereof and at the height of the installation position (P); the first end of the hauling rope (7) is connected with the hoisting mechanism (4), and the second end of the hauling rope (7) sequentially bypasses the first pulley (5) and the second pulley (6) and then is connected with the end part of the large pipe gallery pipeline section (1) on the roller mechanism (3).
2. A quick and convenient transport means for large pipe rack piping erection according to claim 1 characterized in that: the roller mechanism (3) comprises a roller support fixed on the pipe gallery support (2), and a roller is rotatably arranged on the roller support.
3. A quick and convenient transport means for large pipe rack piping erection according to claim 1 characterized in that: the traction rope (7) and the connecting rope (8) are both steel wire ropes.
4. A quick and convenient transport means for large pipe rack piping installation according to any of claims 1 to 3, characterized in that: the second end of the traction rope (7) is divided into two branch rope sections (7-1), and the two branch rope sections (7-1) are fixedly connected to the end of the large pipe gallery pipeline section (1) through a locking mechanism (9).
5. A quick and convenient transport means for large pipe rack piping erection according to claim 4 characterized in that: the clamping and locking mechanism (9) comprises a U-shaped lock body (9-1) and two bolts (9-2), a rope tying hole (9-1a) is formed in the end part of the U-shaped lock body (9-1), and the branch rope section (7-1) is fastened and fixed in the rope tying hole (9-1a) of the U-shaped lock body (9-1); the pipe wall of the large pipe gallery pipeline section (1) is clamped in a U-shaped notch (9-1b) of the U-shaped lock body (9-1), the U-shaped lock body (9-1) is provided with two coaxial threaded holes (9-1c) which are communicated with the U-shaped notch (9-1b), the two bolts (9-2) are in threaded connection with the two threaded holes (9-1c) of the U-shaped lock body (9-1) respectively, one bolt (9-2) abuts against and is pressed against the inner side face of the pipe wall of the large pipe gallery pipeline section (1), and the other bolt (9-2) abuts against and is pressed against the outer side face of the pipe wall of the large pipe gallery pipeline section (1).
6. A quick and convenient transport means for large pipe rack piping installation according to any of claims 1 to 3, characterized in that: the hoisting mechanism (4) comprises a motor (4-1), a winding drum (4-2) and a bearing (4-3), the body of the motor (4-1) and the outer ring of the bearing (4-3) are relatively fixed, and the winding drum (4-2) is coaxially connected between the motor shaft of the motor (4-1) and the inner ring of the bearing (4-3); the first end of the traction rope (7) is fixedly connected to the winding drum (4-2).
7. A quick and convenient transport means for large pipe rack piping erection according to claim 6 characterized in that: the winding mechanism (4) further comprises a control device (4-4) used for controlling the motor (4-1) to work.
CN202021366932.5U 2020-07-13 2020-07-13 A quick convenient transport means for large-scale piping lane piping erection Active CN213265493U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021366932.5U CN213265493U (en) 2020-07-13 2020-07-13 A quick convenient transport means for large-scale piping lane piping erection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021366932.5U CN213265493U (en) 2020-07-13 2020-07-13 A quick convenient transport means for large-scale piping lane piping erection

Publications (1)

Publication Number Publication Date
CN213265493U true CN213265493U (en) 2021-05-25

Family

ID=75959533

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021366932.5U Active CN213265493U (en) 2020-07-13 2020-07-13 A quick convenient transport means for large-scale piping lane piping erection

Country Status (1)

Country Link
CN (1) CN213265493U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960926A (en) * 2022-05-16 2022-08-30 中国化学工程第四建设有限公司 Chemical pipe gallery structure and pipeline replacement method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960926A (en) * 2022-05-16 2022-08-30 中国化学工程第四建设有限公司 Chemical pipe gallery structure and pipeline replacement method
CN114960926B (en) * 2022-05-16 2023-05-02 中国化学工程第四建设有限公司 Chemical pipe gallery structure and pipe replacement method

Similar Documents

Publication Publication Date Title
CN213265493U (en) A quick convenient transport means for large-scale piping lane piping erection
CN203284084U (en) Suspension type transporter at cave top
CN212475874U (en) Bridge cable crane system
CN211142840U (en) Suspension bridge main push-towing rope erects system
CN106594387A (en) Pipe gallery group pipe transportation device
CN213475219U (en) Roof concrete lifting and sliding conveying system
CN112482227B (en) Low-tower cable-stayed bridge cable penetrating system and method thereof
CN213738242U (en) Horizontal installation utility tool for internal parts of large tower
CN114645619A (en) Construction method for integrally drawing Gamma steel bundle stranded wire of containment vessel of nuclear power station
CN213950432U (en) Jacket stretching type impressed current cable winding device
CN207761689U (en) A kind of material transport system for small space inside development machine
CN217756658U (en) Inclined shaft steel pipe conveyer
CN202626985U (en) Hoist traction anchor cable penetration device
CN216472107U (en) Tunnel cloth hanging trolley lifter
CN220975474U (en) Tube plate chain transporting device
CN214425261U (en) Device for transporting equipment in pipe jacking pipeline
CN219449103U (en) Secondary beam lifting device
CN213838549U (en) Hoisting and moving device for prefabricating pipelines of ocean module drilling machine
CN213125552U (en) Monorail crane device for shuttle car cable
CN113578981B (en) Method for threading steel wire rope in loop of cold rolling pickling section and special winch fixing frame
CN218754206U (en) Large-section cable recovery device
CN220596778U (en) Pipeline vertical transportation fixing device
CN210103273U (en) Steel rail hoisting device
CN220336479U (en) Concrete spreader
CN215355355U (en) Cold rolling pickling section loop internal winding machine fixing frame

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant