CN213265322U - Steel bar lifting frame for building construction - Google Patents

Steel bar lifting frame for building construction Download PDF

Info

Publication number
CN213265322U
CN213265322U CN202021216160.7U CN202021216160U CN213265322U CN 213265322 U CN213265322 U CN 213265322U CN 202021216160 U CN202021216160 U CN 202021216160U CN 213265322 U CN213265322 U CN 213265322U
Authority
CN
China
Prior art keywords
fixed plate
reinforcing bar
fixed
handling
lower extreme
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021216160.7U
Other languages
Chinese (zh)
Inventor
苏锡朋
其他发明人请求不公开姓名
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021216160.7U priority Critical patent/CN213265322U/en
Application granted granted Critical
Publication of CN213265322U publication Critical patent/CN213265322U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a reinforcing bar lifting frame for construction, including the handling post, the fixed handling board that is provided with of lower extreme of handling post, the fixed first fixed plate that is provided with of lower extreme of handling board, the fixed second fixed plate that is provided with of lower extreme of first fixed plate, the fixed third fixed plate that is provided with of lower extreme of second fixed plate, the lower extreme four corners department of handling board all fixes and is provided with the screw thread post, the position that first fixed plate, second fixed plate and third fixed plate correspond the screw thread post all runs through and sets up the through-hole. Through the cooperation that sets up handling post, handling board, first fixed plate, second fixed plate, third fixed plate, screw thread post, through-hole and lead to the groove and use, solved current reinforcing bar for construction and hung the unable convenient fixed reinforcing bar position of frame, all adopt both ends to bind or the multiple spot is binded the handling, toughness and self weight that reinforcing bar self has very easily cause independent reinforcing bar to drop, have the problem of great potential safety hazard.

Description

Steel bar lifting frame for building construction
Technical Field
The utility model belongs to the technical field of the building, especially, relate to a reinforcing bar lifting frame for construction.
Background
The building construction refers to production activities in the engineering construction implementation stage, is a construction process of various buildings, and can also be a process of changing various lines on a design drawing into a real object at a specified place, and comprises foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like, and the place of the construction operation is called a building construction site or a construction site.
Need use reinforcing bar overhead hoist to carry out the handling with the reinforcing bar in the building work progress, traditional hoist device, its clamping device's below is open, if the accident appears, the reinforcing bar will drop, the security is low, traditional hoist device structure is unstable in addition, when lifting by crane, rock easily, and current hoist device needs tower crane staff and ground staff's close cooperation, no matter which party is careless slightly, all probably cause very big incident, all adopt both ends to bind or the multiple spot to bind the handling during the handling, toughness and self weight that reinforcing bar self has, very easily cause independent reinforcing bar to drop, there is great potential safety hazard.
SUMMERY OF THE UTILITY MODEL
Problem to prior art exists, the utility model provides a reinforcing bar lifting frame for construction can a plurality of fixed plates of activity fixation through setting up, and sets up logical groove and rubber pad at the fixed plate, can carry out quick clamp with the reinforcing bar and press from both sides fixedly, can still have higher efficiency in order to guarantee the security of handling.
The utility model discloses a realize like this, including the handling post, the fixed handling board that is provided with of lower extreme of handling post, the fixed first fixed plate that is provided with of lower extreme of handling board, the fixed second fixed plate that is provided with of lower extreme of first fixed plate, the fixed third fixed plate that is provided with of lower extreme of second fixed plate, the lower extreme four corners department of handling board is the fixed screw thread post that is provided with all, the position that first fixed plate, second fixed plate and third fixed plate correspond the screw thread post all runs through and has seted up the through-hole, many logical grooves have all been seted up to the horizontal direction that the up end of first fixed plate, second fixed plate and third fixed plate is located between the screw thread post.
As the utility model discloses preferred, many it all adjacent the setting to lead to the groove, and many cross-sections that lead to the groove all are the arc form.
As the utility model discloses it is preferred, the horizontal position that the lower terminal surface of handling board, first fixed plate, second fixed plate and third fixed plate is located between the screw thread post all sets up flutedly, and is a plurality of the rubber pad, a plurality of all bonds in the inside of recess the degree of depth of recess all is greater than the degree of depth that leads to the groove.
As the utility model discloses it is preferred, lock nut has all been cup jointed to the outer wall that the lower extreme of the through-hole of first fixed plate, second fixed plate and third fixed plate is located the screw thread post.
As the utility model discloses preferred, the fixed ring of lifting that is provided with of handling post upper end central authorities department.
As the utility model discloses it is preferred, the size of first fixed plate, second fixed plate and third fixed plate all is the same with the handling size.
Compared with the prior art, the beneficial effects of the utility model are as follows:
1. the utility model discloses a set up handling post, handling board, first fixed plate, second fixed plate, third fixed plate, screw thread post, through-hole and lead to the cooperation use, solved the unable convenient fixed reinforcement position of current reinforcing bar lifting frame for construction, all adopt both ends to bind or the multiple spot is binded the handling, toughness and self weight that reinforcing bar self has very easily cause independent reinforcing bar to drop, have the problem of great potential safety hazard.
2. The utility model discloses a set up adjacent many logical grooves, and the cross-section that leads to the groove is the arc form, can be so that fixing that the reinforcing bar can be better lead to the inslot, and then fix with the rubber pad of upper end for the reinforcing bar is fixed more firmly, guarantees the security of handling.
3. The utility model discloses a set up recess and rubber pad, can be so that the reinforcing bar place logical inslot back, further with the fixed plate activity of making progress for reinforcing bar upper end and rubber pad contact, further chucking, the rubber pad has great frictional force, and the elasticity that has can be so that rubber pad and reinforcing bar surface laminating, and then the reinforcing bar that makes is fixed more firmly.
4. The utility model discloses a set up lock nut, can be so that through lock nut, can fix the fixed plate in the optional position of screw thread post upper end, the staff can be through will placing the lock nut of the fixed plate below behind the reinforcing bar and play soon, and then make the fixed plate rise, further make reinforcing bar and upper end rubber pad contact, and then screw lock nut, play the effect of fixed reinforcing bar.
5. The utility model discloses a set up the handling ring, can be so that whole handling frame can be convenient with the handling hook device high-speed joint of overhead hoist lower extreme, can be so that handling efficiency is higher.
6. The utility model discloses a set up the same handling board of size and a plurality of fixed plate, can be so that the joint reinforcing bar is more convenient between fixed plate and the handling board, and fixed more firm, the joint reinforcing bar is also more convenient firm between fixed plate and the fixed plate, has promoted the security of integrated device.
Drawings
Fig. 1 is a schematic view of an overall structure provided by an embodiment of the present invention;
fig. 2 is a schematic plan view of the overall structure provided by the embodiment of the present invention;
fig. 3 is a schematic cross-sectional view of a first fixing plate according to an embodiment of the present invention;
in the figure: 1. hoisting the column; 2. hoisting the plates; 3. a first fixing plate; 4. a second fixing plate; 5. a third fixing plate; 6. a threaded post; 7. a through hole; 8. locking the nut; 9. a through groove; 10. a groove; 11. a rubber pad; 12. and (5) hoisting the ring.
Detailed Description
In order to further understand the contents, features and effects of the present invention, the following embodiments are illustrated and described in detail with reference to the accompanying drawings.
The structure of the present invention will be described in detail with reference to the accompanying drawings.
As shown in fig. 1 to 3, the embodiment of the utility model provides a pair of reinforcing bar lifting frame for construction, including handling post 1, the fixed handling board 2 that is provided with of lower extreme of handling post 1, the fixed first fixed plate 3 that is provided with of lower extreme of handling board 2, the fixed second fixed plate 4 that is provided with of lower extreme of first fixed plate 3, the fixed third fixed plate 5 that is provided with of lower extreme of second fixed plate 4, the lower extreme four corners department of handling board 2 all fixes and is provided with screw thread post 6, first fixed plate 3, the position that second fixed plate 4 and third fixed plate 5 correspond screw thread post 6 all runs through and has seted up through-hole 7, first fixed plate 3, many logical grooves 9 have all been seted up to the horizontal direction that the up end face of second fixed plate 4 and third fixed plate 5 is located between screw thread post 6.
Referring to fig. 1 and 3, the plurality of through grooves 9 are all adjacently disposed, and the cross sections of the plurality of through grooves 9 are all arc-shaped.
Adopt above-mentioned scheme: through setting up adjacent many logical grooves 9, and the cross-section that leads to groove 9 is the arc form, can be so that the reinforcing bar can be better fix inside leading to groove 9, and then fix with rubber pad 11 of upper end for the reinforcing bar is fixed more firmly, guarantees the security of handling.
Referring to fig. 1 and 3, grooves 10 are formed in horizontal positions, located between the threaded columns 6, of the lower end faces of the lifting plate 2, the first fixing plate 3, the second fixing plate 4 and the third fixing plate 5, rubber pads 11 are bonded inside the grooves 10, and the depth of the grooves 10 is larger than that of the through grooves 9.
Adopt above-mentioned scheme: through setting up recess 10 and rubber pad 11, can be so that the reinforcing bar place logical inslot 9 back, further with the fixed plate activity of making progress for reinforcing bar upper end and the contact of rubber pad 11, further chucking, rubber pad 11 have great frictional force, and the elasticity that has can be so that rubber pad 11 and reinforcing bar surface laminating, and then the reinforcing bar that makes is fixed more firmly.
Referring to fig. 1 and 2, the lower ends of the through holes 7 of the first fixing plate 3, the second fixing plate 4 and the third fixing plate 5 are sleeved with lock nuts 8 on the outer walls of the threaded columns 6.
Adopt above-mentioned scheme: through setting up lock nut 8, can be so that through lock nut 8, can fix the fixed plate in the optional position of 6 upper ends of screw thread post, the staff can be through the lock nut 8 of the fixed plate below after will placing the reinforcing bar and play soon, and then make the fixed plate rise, further make reinforcing bar and 11 contacts of upper end rubber pad, and then screw lock nut 8, play the effect of fixed reinforcing bar.
Referring to fig. 1, 2 and 3, a lifting ring 12 is fixedly arranged at the center of the upper end of the lifting column 1.
Adopt above-mentioned scheme: through setting up the handling ring, can be so that whole handling frame can be convenient with the handling hook device high-speed joint of handling lower extreme of handling, can be so that handling efficiency is higher.
Referring to fig. 1, the first fixing plate 3, the second fixing plate 4 and the third fixing plate 5 are all the same size as the lifting plate 2.
Adopt above-mentioned scheme: through setting up the same handling board 2 of size and a plurality of fixed plate, can be so that the joint reinforcing bar is more convenient between fixed plate and the handling board 2, and fixed more firm, the joint reinforcing bar is also more convenient firm between fixed plate and the fixed plate, has promoted the security of integrated device.
The utility model discloses a theory of operation:
when using, at first the staff unscrews lock nut 8 of each fixed plate lower extreme, further place the reinforcing bar inside many logical grooves 9, then earlier with four lock nuts 8 of 3 lower extremes of first fixed plate spin up to locking, make reinforcing bar upper end and the laminating of the rubber pad 11 of 2 lower extremes of handling board fixed, rubber pad 11 produces great frictional force to the reinforcing bar, and then make the reinforcing bar fixed, can not drop at the handling process, then screw lock nut 8 of second fixed plate 4 and the 5 lower extremes of third fixed plate in proper order, the handling is to the position that needs to use after, the staff unscrews lock nut 8 of lower extreme in proper order, can take out the reinforcing bar.
In summary, the following steps: this reinforcing bar lifting frame for construction, through setting up handling post 1, handling board 2, first fixed plate 3, second fixed plate 4, third fixed plate 5, threaded post 6, through-hole 7, lock nut 8, lead to groove 9, recess 10, the cooperation of rubber pad 11 and handling ring 12 is used, the unable convenient fixed reinforcing bar position of reinforcing bar lifting frame for construction has been solved, all adopt both ends to bind or the multiple spot is binded the handling, toughness and self weight that reinforcing bar self has, very easily cause independent reinforcing bar to drop, there is the problem of great potential safety hazard.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a reinforcing bar lifting frame for construction, includes handling post (1), its characterized in that: the lower extreme of handling post (1) is fixed and is provided with handling board (2), the fixed first fixed plate (3) that is provided with of lower extreme of handling board (2), the fixed second fixed plate (4) that is provided with of lower extreme of first fixed plate (3), the fixed third fixed plate (5) that is provided with of lower extreme of second fixed plate (4), the lower extreme four corners department of handling board (2) all fixes and is provided with screw thread post (6), the position that first fixed plate (3), second fixed plate (4) and third fixed plate (5) correspond screw thread post (6) all runs through and has seted up through-hole (7), many logical grooves (9) have all been seted up to the horizontal direction that the up end of first fixed plate (3), second fixed plate (4) and third fixed plate (5) is located between screw thread post (6).
2. A reinforcing bar lifting frame for construction according to claim 1, wherein: many lead to groove (9) all adjacent setting, and many the cross-section that leads to groove (9) all is the arc form.
3. A reinforcing bar lifting frame for construction according to claim 1, wherein: the horizontal position that the lower terminal surface of handling board (2), first fixed plate (3), second fixed plate (4) and third fixed plate (5) is located between screw post (6) all sets up fluted (10), and is a plurality of the inside of recess (10) all bonds and has rubber pad (11), and is a plurality of the degree of depth of recess (10) all is greater than the degree of depth that leads to groove (9).
4. A reinforcing bar lifting frame for construction according to claim 1, wherein: and the lower ends of the through holes (7) of the first fixing plate (3), the second fixing plate (4) and the third fixing plate (5) are positioned on the outer wall of the threaded column (6) and are all sleeved with locking nuts (8).
5. A reinforcing bar lifting frame for construction according to claim 1, wherein: and a hoisting ring (12) is fixedly arranged at the center of the upper end of the hoisting column (1).
6. A reinforcing bar lifting frame for construction according to claim 1, wherein: the sizes of the first fixing plate (3), the second fixing plate (4) and the third fixing plate (5) are the same as the size of the lifting plate (2).
CN202021216160.7U 2020-06-28 2020-06-28 Steel bar lifting frame for building construction Expired - Fee Related CN213265322U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021216160.7U CN213265322U (en) 2020-06-28 2020-06-28 Steel bar lifting frame for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021216160.7U CN213265322U (en) 2020-06-28 2020-06-28 Steel bar lifting frame for building construction

Publications (1)

Publication Number Publication Date
CN213265322U true CN213265322U (en) 2021-05-25

Family

ID=75957579

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021216160.7U Expired - Fee Related CN213265322U (en) 2020-06-28 2020-06-28 Steel bar lifting frame for building construction

Country Status (1)

Country Link
CN (1) CN213265322U (en)

Similar Documents

Publication Publication Date Title
CN107178203A (en) A kind of planar dimension and adjustable for height operating platform
CN210944509U (en) Plate hoisting clamping part for building construction
CN213265322U (en) Steel bar lifting frame for building construction
CN203889888U (en) Steel plate hoisting clamp
CN105952129A (en) Elevator shaft combined type integral lifting operation platform and construction method thereof
CN210263111U (en) Hollow pile body for civil engineering construction
CN211421834U (en) Composite wood formwork with good compression resistance
CN210684727U (en) Construction safety supporting construction
CN209988961U (en) Special lifting appliance for large I-shaped steel beam
CN217000456U (en) High strength concatenation formula prestressing force superimposed sheet
CN214755310U (en) Cable strutting arrangement for construction
CN212562432U (en) Connecting device of automatic lifting scaffold
CN210421872U (en) Laminated slab overhanging scaffold I-steel embedded pipe
CN208505594U (en) A kind of steel pipe column loading test device
CN113860189A (en) Pin shaft type climbing beam of non-turnover internal climbing tower crane and use method thereof
CN209976068U (en) Connectable steel cushion block for jacking and storey-adding
CN206428959U (en) A kind of scaffold upright rod base
CN214531840U (en) Pin-connected panel elevartor shaft hoisting frame
CN210263859U (en) Elevator shaft construction operation platform
CN215290248U (en) Super high-rise construction elevator foundation slab back-jacking device
CN219034077U (en) Can have enough to meet need vertical reinforcing bar stop device of assembled structural conversion layer
CN213569251U (en) Novel tower machine wall supporting frame
CN204738554U (en) Controllable off -load ware of formula of buryying
CN206625523U (en) Builder's jack rotation angle position regularization component
CN215760661U (en) Force-transferring top cap device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210525