CN213261223U - Construction rubbish compressor arrangement - Google Patents

Construction rubbish compressor arrangement Download PDF

Info

Publication number
CN213261223U
CN213261223U CN202020816855.2U CN202020816855U CN213261223U CN 213261223 U CN213261223 U CN 213261223U CN 202020816855 U CN202020816855 U CN 202020816855U CN 213261223 U CN213261223 U CN 213261223U
Authority
CN
China
Prior art keywords
box body
pressing
pushing
box
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020816855.2U
Other languages
Chinese (zh)
Inventor
魏乐通
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020816855.2U priority Critical patent/CN213261223U/en
Application granted granted Critical
Publication of CN213261223U publication Critical patent/CN213261223U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The utility model belongs to the technical field of building construction, in particular to a building construction garbage compression device, which comprises a third box body, wherein a pushing and pressing component is arranged in the third box body; the multi-hole sliding plate type refrigerator is characterized by also comprising a first box body and a second box body, wherein a multi-hole sliding plate is fixed in the second box body; two first pressing roller pairs which are distributed in parallel are supported and installed in the first box body through bearings, and two second pressing roller pairs which are distributed in parallel are supported and installed in the second box body through bearings; a discharge hole is formed in one end of the third box body, and a movable sealing door plate is mounted outside the end opening of the discharge hole; the utility model discloses a construction rubbish compressor arrangement utilizes a pressure material pair roller and No. two to press the material pair roller to roll in construction rubbish, utilizes to bulldoze the subassembly and bulldoze, has improved the compression efficiency to construction rubbish greatly to a pressure material pair roller has and beats the piece, can carry out the breakage to the great rubbish of volume, is convenient for adapt to the compression to the rubbish of volume variation in size.

Description

Construction rubbish compressor arrangement
Technical Field
The utility model belongs to the technical field of the construction, concretely relates to construction waste compressor arrangement.
Background
The construction is a production activity in the construction implementation stage of engineering, is a construction process of various buildings, and can also be a process of changing various lines on a design drawing into a real object at a specified place.
Original construction rubbish compressor arrangement uses inconveniently, and compression efficiency is low, is difficult to effectively compress the rubbish of volume size difference.
SUMMERY OF THE UTILITY MODEL
For solving the above-mentioned problem that exists among the prior art, the utility model provides a construction rubbish compressor arrangement has convenient to use and the efficient characteristics of compression.
In order to achieve the above object, the utility model provides a following technical scheme: a construction waste compression device comprises a third box body, wherein a pushing and pressing assembly is arranged in the third box body; the feeding device comprises a first box body and a second box body, wherein the first box body is fixed at the top of the second box body and is communicated with the second box body, and a feeding hole is formed in the top end of the first box body; a porous sliding plate is fixed in the second box body, the third box body is arranged on the front surface of the second box body, and the third box body is communicated with the second box body by the porous sliding plate; two first pressing roller pairs which are distributed in parallel are supported and installed in the first box body through bearings, and two second pressing roller pairs which are distributed in parallel are supported and installed in the second box body through bearings; supporting legs are fixed on the bottom surfaces of the second box body and the third box body; and one end of the third box body is provided with a discharge hole, and a movable sealing door plate is arranged outside the port of the discharge hole.
As an optimal technical scheme of the utility model, driving motor is installed to the outer wall of a box, driving motor drive press the material pair roller with press the material pair roller rotation No. two.
As an optimal technical scheme of the utility model, No. two press the material pair roller to be in directly over porous slide, just No. two the box inner bottom surface has been placed and is in the collection liquid box under the porous slide No. two the box lateral wall is articulated to have the cleanness to run from opposite directions corresponding to the position department of collecting the liquid box.
As the utility model discloses a preferred technical scheme, bulldoze the subassembly including bulldozing the cylinder and bulldozing the board, bulldoze the cylinder and install No. three box outer walls, bulldoze the board and fix bulldoze on the piston rod of cylinder and be in No. three boxes are internal.
As a preferred technical scheme of the utility model, the device also comprises a sealing cylinder, two guide rails which are symmetrically distributed are fixed on the outer wall of the port of the discharging hole, the transverse section of each guide rail is of an L-shaped structure, and the sealing door plate can be embedded into the inner sides of the two guide rails; a horizontally distributed connecting frame is fixed on the first box body, the sealing air cylinder is installed on the bottom surface of the connecting frame, and a piston rod of the sealing air cylinder is fixedly connected with the sealing door plate.
As an optimized technical scheme of the utility model, the outer wall of a pressure material pair roller is evenly fixed with strikes the piece.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses a construction rubbish compressor arrangement utilizes a pressure material pair roller and No. two to press the material pair roller to roll in construction rubbish, utilizes to bulldoze the subassembly and bulldoze, has improved the compression efficiency to construction rubbish greatly to a pressure material pair roller has and beats the piece, can carry out the breakage to the great rubbish of volume, is convenient for adapt to the compression to the rubbish of volume variation in size.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic front view of the present invention;
FIG. 3 is a schematic side sectional view of the present invention;
fig. 4 is a schematic top sectional view of a third box of the present invention;
in the figure: 1. a first box body; 2. a second box body; 3. a third box body; 4. a feeding port; 5. supporting legs; 6. a connecting frame; 7. sealing the cylinder; 8. a sealing door panel; 9. a guide rail; 10. a pushing cylinder; 11. a drive motor; 12. a push plate; 13. a porous slide plate; 14. a liquid collecting box; 15. a first material pressing pair roller; 16. pressing a pair of rollers; 17. a discharging port; 18. cleaning the split door; 19. and knocking the block.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides the following technical solutions: a construction waste compression device comprises a third box body 3, wherein a pushing and pressing assembly is arranged in the third box body 3; the feeding device also comprises a first box body 1 and a second box body 2, wherein the first box body 1 is fixed at the top of the second box body 2, the first box body 1 is communicated with the second box body 2, and a feeding port 4 is arranged at the top end of the first box body 1; a porous sliding plate 13 is fixed in the second box body 2, the third box body 3 is arranged on the front surface of the second box body 2, and the third box body 3 is communicated with the second box body 2 by the porous sliding plate 13; two first pressing roller pairs 15 which are distributed in parallel are supported and installed in the first box body 1 through bearings, and two second pressing roller pairs 16 which are distributed in parallel are supported and installed in the second box body 2 through bearings; the bottom surfaces of the second box body 2 and the third box body 3 are both fixed with supporting legs 5; no. three box 3's one end is equipped with drain hole 17, and there is mobilizable sealed door plant 8 at this drain hole 17 port externally mounted, when using, close sealed door plant 8, treat that the construction waste of compression presses material pair roller 15 to roll-in rubbish from feeding port 4 feeding box 1 No. one in box 1, later rubbish gets into No. two boxes 2 under the dead weight, press material pair roller 16 to carry out the secondary roll-in to rubbish through No. two in No. 2 boxes, later rubbish passes through porous slide 13 landing to No. three boxes 3, bulldoze the subassembly through bulldozing in No. three boxes 3, later open sealed door plant 8, the utilization bulldozes the subassembly and promotes rubbish and remove, carry out the unloading.
Specifically, as shown in fig. 1, fig. 2 and fig. 3, in this embodiment, a driving motor 11 is installed on an outer wall of a first box 1, the driving motor 11 drives a first pressing pair roller 15 and a second pressing pair roller 16 to rotate, actually, the driving motor 11 drives one of the first pressing pair rollers 15 to rotate, the two first pressing pair rollers 15 are in transmission connection by virtue of a meshing relationship of gears, the first pressing pair roller 15 and the second pressing pair roller 16 are in transmission connection by virtue of a belt, and meanwhile, the two second pressing pair rollers 16 are also in transmission connection by virtue of a meshing relationship of gears.
Specifically, as shown in the attached drawing 3, in this embodiment, the pressing roller pair 16 is located directly above the porous sliding plate 13, the liquid collecting box 14 located directly below the porous sliding plate 13 is placed on the bottom surface in the box 2, the cleaning side-by-side door 18 is hinged to the position, corresponding to the liquid collecting box 14, of the side wall of the box 2, the cleaning side-by-side door 18 is hinged to the side wall of the box 2, in the compression process of the construction waste, if the waste contains sewage, the sewage can flow into the liquid collecting box 14 through the porous sliding plate 13, the cleaning side-by-side door 18 is opened in the later stage, the liquid collecting box 14 can be taken out for cleaning, and in addition, in order to ensure that the waste normally slides down, the hole of.
Specifically, according to fig. 2 and fig. 4, in this embodiment, the pushing and pressing assembly includes a pushing and pressing cylinder 10 and a pushing and pressing plate 12, the pushing and pressing cylinder 10 is installed on the outer wall of the third box 3, the pushing and pressing plate 12 is fixed on the piston rod of the pushing and pressing cylinder 10 and located in the third box 3, the pushing and pressing plate 12 is pushed by the pushing and pressing cylinder 10 to move, and then the pushing and pressing of the garbage or the blanking of the garbage can be performed, wherein the pushing and pressing cylinder 10 is an SC series, and can be purchased directly on the market, and needs to be connected with an electrical power supply.
Specifically, as shown in fig. 1, fig. 2 and fig. 3, in this embodiment, the sealing device further includes a sealing cylinder 7, two guide rails 9 are fixed on an outer wall of a port of the discharging port 17, a transverse section of each guide rail 9 is an "L" shaped structure, and a sealing door panel 8 can be embedded into inner sides of the two guide rails 9; be fixed with horizontally distributed's link 6 on box 1, sealed cylinder 7 installs in 6 bottom surfaces of this link, and sealed cylinder 7's piston rod and sealed door plant 8 fixed connection, drives sealed door plant 8 through sealed cylinder 7 and removes along guide rail 9, can realize sealed door plant 8 to the shutoff or the deblocking of drain hole 17, and wherein, sealed cylinder 7 is SC series, can directly purchase on the market, need connect electric power during the use.
Specifically, according to the illustration in fig. 3, in this embodiment, the knocking blocks 19 are uniformly fixed on the outer walls of the first pressing pair rollers 15, and when the first pressing pair rollers 15 rotate to press, the knocking blocks 19 crush garbage with a large volume.
The utility model discloses a theory of operation and use flow: the utility model discloses a construction rubbish compression device, when using, guarantee earlier that sealing door panel 8 is in the shutoff state to drain hole 17, the construction rubbish of waiting to compress is from feeding mouth 4 feeding box 1 No. one, roll-in rubbish through pressing material pair roller 15 in box 1 No. one, later rubbish gets into box 2 No. two under the dead weight, roll-in rubbish for the second time through pressing material pair roller 16 in box 2 No. two, later rubbish slides to box 3 No. three through porous slide 13, bulldoze through the bulldozing subassembly in box 3 No. three, later open sealing door panel 8, utilize the bulldozing subassembly to promote rubbish to move, carry out the unloading;
if contain sewage in the rubbish, sewage can flow through porous slide 13 and fall to album liquid box 14 in, the clean door 18 that runs from opposite directions is opened to the later stage, takes out album liquid box 14 and can clear up, and is very convenient.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a construction rubbish compressor arrangement, includes No. three box (3), its characterized in that: a pushing and pressing assembly is arranged in the third box body (3); the feeding device is characterized by further comprising a first box body (1) and a second box body (2), wherein the first box body (1) is fixed to the top of the second box body (2), the first box body (1) is communicated with the second box body (2), and a feeding opening (4) is arranged at the top end of the first box body (1); a porous sliding plate (13) is fixed in the second box body (2), the third box body (3) is installed on the front surface of the second box body (2), and the third box body (3) is communicated with the second box body (2) through the porous sliding plate (13); two first pressing roller pairs (15) which are distributed in parallel are supported and installed in the first box body (1) through bearings, and two second pressing roller pairs (16) which are distributed in parallel are supported and installed in the second box body (2) through bearings; supporting legs (5) are fixed on the bottom surfaces of the second box body (2) and the third box body (3); one end of the third box body (3) is provided with a discharge hole (17), and a movable sealing door plate (8) is arranged outside the port of the discharge hole (17).
2. The construction waste compressing apparatus as claimed in claim 1, wherein: a driving motor (11) is installed on the outer wall of the first box body (1), and the driving motor (11) drives the first pressing roller pair (15) and the second pressing roller pair (16) to rotate.
3. The construction waste compressing apparatus as claimed in claim 1, wherein: the second pressing roller pair (16) is located right above the porous sliding plate (13), a liquid collecting box (14) located right below the porous sliding plate (13) is placed on the inner bottom surface of the second box body (2), and a cleaning split door (18) is hinged to the position, corresponding to the liquid collecting box (14), of the side wall of the second box body (2).
4. The construction waste compressing apparatus as claimed in claim 1, wherein: the pushing and pressing assembly comprises a pushing and pressing cylinder (10) and a pushing and pressing plate (12), the pushing and pressing cylinder (10) is installed on the outer wall of the third box body (3), and the pushing and pressing plate (12) is fixed on a piston rod of the pushing and pressing cylinder (10) and located in the third box body (3).
5. The construction waste compressing apparatus as claimed in claim 1, wherein: the device is characterized by further comprising a sealing cylinder (7), two guide rails (9) which are symmetrically distributed are fixed on the outer wall of the end opening of the discharging opening (17), the transverse section of each guide rail (9) is of an L-shaped structure, and the sealing door plate (8) can be embedded into the inner sides of the two guide rails (9); a horizontally distributed connecting frame (6) is fixed on the first box body (1), the sealing cylinder (7) is installed on the bottom surface of the connecting frame (6), and a piston rod of the sealing cylinder (7) is fixedly connected with the sealing door plate (8).
6. The construction waste compressing apparatus as claimed in claim 1, wherein: knocking blocks (19) are uniformly fixed on the outer wall of the first pressing pair roller (15).
CN202020816855.2U 2020-05-17 2020-05-17 Construction rubbish compressor arrangement Expired - Fee Related CN213261223U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020816855.2U CN213261223U (en) 2020-05-17 2020-05-17 Construction rubbish compressor arrangement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020816855.2U CN213261223U (en) 2020-05-17 2020-05-17 Construction rubbish compressor arrangement

Publications (1)

Publication Number Publication Date
CN213261223U true CN213261223U (en) 2021-05-25

Family

ID=75936016

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020816855.2U Expired - Fee Related CN213261223U (en) 2020-05-17 2020-05-17 Construction rubbish compressor arrangement

Country Status (1)

Country Link
CN (1) CN213261223U (en)

Similar Documents

Publication Publication Date Title
CN213261223U (en) Construction rubbish compressor arrangement
CN210911258U (en) Compression environment-friendly device for garbage disposal
CN210474114U (en) Movable fallen leaf crushing compressor
CN112623550A (en) Compression mechanism of environment-friendly garbage storage device and working method thereof
CN110641063A (en) Intelligent sorting and packaging device for solid wastes
CN217247059U (en) Environment-friendly equipment for treating and utilizing hogwash
CN216096075U (en) Automatic press recovery mechanism of cross cutting waste material
CN217298846U (en) Water surface garbage fishing device capable of compressing and collecting
CN209599926U (en) A kind of new energy cell house refuse cleaning device
CN211917811U (en) Scraped car flattens device
CN211761309U (en) Household electrical appliances dismantle platform
CN210669046U (en) Interim electric power cabinet is used in electric power construction place
CN209775621U (en) slag remover is used in biodiesel production
CN213678373U (en) Movable garbage disposer
CN219170299U (en) Waste collection device with material pressing structure
CN214952159U (en) Novel all-round testing platform of automobile engine security performance
CN214497435U (en) Hydropower station river course suspended solid filters intercepting device
CN207857525U (en) A kind of urban resource recycling refuse compressor
CN216911484U (en) Compression device for household garbage treatment
CN212468266U (en) Construction waste compressor arrangement
CN216259303U (en) Diaphragm filter press is used in zinc carbonate production
CN215556212U (en) Movable garbage compression device
CN212826996U (en) High-order compression rubbish compressor
CN211942233U (en) Garbage briquetting processing device
CN212575695U (en) Washing device for ternary lithium ion battery precursor

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210525